Professional Documents
Culture Documents
CoP 03 Organisation Resources and Capability Final 07 - 12 - 2017
CoP 03 Organisation Resources and Capability Final 07 - 12 - 2017
CoP 03 Organisation Resources and Capability Final 07 - 12 - 2017
Date of Revision: 5th December 2017 Effective from: 1st January 2018
This document shall not to be reproduced without written permission from the FOIZ CEO.
Note: Printed copies shall be considered as uncontrolled unless otherwise stamped “CONTROLLED COPY” in red ink and numbered.
Code of Practice-03 HSEQ-COP-03
Document Authorisation
Revision Record
Revision Date of Reason for Revision / Description of Prepared by Reviewed by Approved by
Number Revision Changes (Title) (Title) (Title)
This document shall not to be reproduced without written permission from the FOIZ CEO.
Note: Printed copies shall be considered as uncontrolled unless otherwise stamped “CONTROLLED COPY” in red ink and numbered.
Code of Practice-03 HSEQ-COP-03
Document Control
Deviations and deferments from the requirements specified in this document are permitted only if
approved in writing by the FOIZ Chief Executive Officer (CEO). Any such deviations and deferments shall be
approved for only a limited and specified time, and shall be supported by a risk assessment and control.
Before referring to this document, it is the user's responsibility to use the latest version (hard or electronic
copy).
Copy Control
The electronic version of the document is available on the FOIZ website and shall be considered as the
“Controlled Document”. Printed copies shall be considered as uncontrolled unless otherwise stamped
“CONTROLLED COPY” in red ink and numbered on the front page.
Controlled copies can only be issued by the Document Controller (Executive Secretary) and it is the
responsibility of the Document Controller to maintain a record of all controlled copies issued and to ensure
that all controlled copies are recalled and reissued whenever the document is revised.
FOIZ employees, operators, investors, stakeholders and authorised contractors may maintain uncontrolled
printed copies of this document for their personal use. They are however responsible for ensuring that only
the up to date version of this document is used at any time.
Review Cycle
This document shall be reviewed and revised as necessary at least once in 3 years by the Document
Authority. In addition, this code of practice must be reviewed and revised as necessary whenever there are
any significant changes in FOIZ’s HSEQ MS Manual affecting the Code of Practice (CoP). Such changes may
include changes to the HSEQ MS policies, organization structure, roles and responsibilities and any
management or control procedure directly linked to this CoP. What constitutes a “significant” change must
be determined by the CEO and the HSEQ Coordinator in line with the criteria specified in the Management
of Change (Ref. 01).
Feedback
All FOIZ employees, operators, investors, stakeholders, authorised contractors and any other users of this
document are encouraged to provide their feedback to the CEO that could result in an improvement. This
feedback could be on matters relating to the structure, format and / or content of this manual and such
feedback can be provided by email or any other means.
Terminology
The terminology used in this document has very specific and clear meaning within the context of FOIZ. The
verbs “should”, “shall” and “must” used throughout this document denote that the action is a mandatory
requirement. These terms are used interchangeably with no specific difference in the intent.
Throughout the HSEQ MS documentation, the term “Plant” refers to the companies that are already
operating and those who have signed agreements to become operational within the FOIZ area.
This document shall not to be reproduced without written permission from the FOIZ CEO.
Note: Printed copies shall be considered as uncontrolled unless otherwise stamped “CONTROLLED COPY” in red ink and numbered.
Code of Practice-03 HSEQ-COP-03
This document shall not to be reproduced without written permission from the FOIZ CEO.
Note: Printed copies shall be considered as uncontrolled unless otherwise stamped “CONTROLLED COPY” in red ink and numbered.
Code of Practice-03 HSEQ-COP-03
Table of Contents
List of Abbreviations and Definitions: ...................................................................................... 4
3 Introduction ....................................................................................................................... 7
3.1 HSE Organisation, Roles and Responsibilities ....................................................................................... 7
3.1.1 HSE Organisation in Projects ........................................................................................................... 7
3.1.2 HSE Roles and Responsibilities in Major Projects .......................................................................... 8
3.1.3 Quality .............................................................................................................................................. 9
3.1.4 Management of Change .................................................................................................................. 9
3.1.5 HSEQ Organisation in Operational Plants ....................................................................................... 9
3.2 HSE Competence and Training ..........................................................................................................10
3.2.1 HSE Competency in Plants ............................................................................................................ 10
3.2.2 HSE Training .................................................................................................................................... 12
3.2.3 Training Process Overview ............................................................................................................. 12
3.2.4 HSE Training Needs Identification ................................................................................................. 13
3.2.5 HSE Training Plan ............................................................................................................................14
3.3 Contractor HSEQ Management ......................................................................................................... 15
3.3.1 Criteria for Determining HSE Involvement in Contracts .............................................................. 16
3.3.2 Contractor Pre-Qualification .......................................................................................................... 17
3.3.3 Tendering and Award of Contract ................................................................................................. 17
3.3.4 Contractor Mobilisation ................................................................................................................ 18
3.3.5 Contract Close-out ......................................................................................................................... 19
3.4 HSEQ Communication ........................................................................................................................ 19
3.4.1 Shift Handover ............................................................................................................................... 20
3.4.2 Toolbox Talks ................................................................................................................................. 20
3.4.3 HSE Meetings ................................................................................................................................. 20
3.4.4 HSE Alerts ....................................................................................................................................... 20
3.4.5 Management Tour Outputs ........................................................................................................... 21
3.4.6 Promotional Campaigns ................................................................................................................. 21
3.4.7 HSE Climate Surveys ....................................................................................................................... 21
3.5 HSEQ Documents, Data and Records Management ......................................................................... 21
3.6 List of References .............................................................................................................................. 23
This document shall not to be reproduced without written permission from the FOIZ CEO.
Note: Printed copies shall be considered as uncontrolled unless otherwise stamped “CONTROLLED COPY” in red ink and numbered.
Code of Practice-03 HSEQ-COP-03
List of Tables
Table 1: HSE Competence Framework ................................................................................................................. 11
Table 2 HSE Involvement Criteria ........................................................................................................................ 16
List of Figures
Figure 1: Principles of HSE Competence Framework ......................................................................................... 10
Figure 2: HSEQ Training Process Overview ......................................................................................................... 13
Figure 3: Training Needs Identification................................................................................................................14
Figure 4: Overall HSEQ Contractor Management Process ................................................................................ 16
This document shall not to be reproduced without written permission from the FOIZ CEO.
Note: Printed copies shall be considered as uncontrolled unless otherwise stamped “CONTROLLED COPY” in red ink and numbered.
Code of Practice-03 HSEQ-COP-03
3 Introduction
Adequate and competent human resources are required, in addition to the hardware and software systems,
for delivering the HSEQ Management System (HSEQ MS) within FOIZ and the Plants.
Within this CoP, FOIZ sets out the requirements to ensure the specifics of HSEQ management are duly
considered within the Plants to provide adequate personnel who will implement and sustain the HSEQ MS.
To ensure that HSEQ is continually improved, the Plant management will annually develop a HSEQ Plan to
be implemented during the following year.
Within the following section the term HSE is used regarding competence and capabilities. The Quality
aspect is considered in 3.1.4.
HSE competence and capability is not only a requirement for FOIZ or the Plant HSE team, it is applied to all
personnel who are involved in safe systems of work and those who carry out activities on HSE critical
equipment and systems. In some instances, Contractor personnel are also involved in HSE critical activities
and it is the responsibility of the Plant management to ensure (through the contracting process and
monitoring) these people have the necessary skills, experience and knowledge to perform the work tasks
safely.
Training of personnel in HSE activities will be structured to meet the requirements identified within this
CoP. Training is just one element of a development process for employees within FOIZ or the Plants, there
is also a requirement to assess competency before a person can be fully conversant with an HSE critical
process or activity. Competency assessments are required at the Plants to give assurance to the
management that the designated people have the capability to perform the work tasks in a safe manner.
The creation and control of HSEQ information is an essential process for both FOIZ and Plant management
to have assurance on the HESQ MS process. The documentation, in either paper or electronic format is
required so that HSEQ activities are carried out at the Plant in a consistent manner.
This Code of Practice contains 5 sub-elements. The FOIZ requirements under each sub-element are
specified in the following sub-sections.HSE Organisation, Roles and Responsibilities
The Plant management will develop the required documents that provide guidance on the approach taken
to implement and sustain the HSE organisational structure, how it functions and determines the roles and
responsibilities for HSE activities.
There are 2 main aspects for the HSE Organisation, Roles and Responsibilities within this CoP. These are for
a Project and for an operational Plant. The following are the requirements set out by FOIZ for the resource
requirements for both Projects and operational Plants.
This document shall not to be reproduced without written permission from the FOIZ CEO.
Note: Printed copies shall be considered as uncontrolled unless otherwise stamped “CONTROLLED COPY” in red ink and numbered.
Code of Practice-03 HSEQ-COP-03
The term Project Manager is the person appointed by the Contractor or the Plant with the relevant
experience and knowledge to have the overall accountability to provide and manage the internal and
external resources to deliver all the agreed components for HSE within the HSE MS.
Dependent upon the scale and complexity of a major new project, a full time (or part time) HSE Manager
will be appointed by the Contractor or the Plant. Justification for not appointing a HSE Manager within the
project must be given to the FOIZ CEO (who has oversight of HSE compliance) for the approval to proceed
with regards to HSE aspects. The HSE Manager will report to the Project Manager or Senior Plant Manager
and will be responsible for the safety, health and environmental aspects of the project. For expansion
projects the Plant must determine if their internal HSE resources are sufficient to manage all HSE aspects
of the project. If so, then the requirements stated within this CoP that refer to the HSE Manager within a
project will be applied to the designated Plant employee with responsibility for HSE.
HSE Engineers will be appointed within the project based upon the specific requirements set out in the
Project HSE Plan. All the HSE Engineers will have sufficient knowledge and understanding of HSE systems
that are required for the specific project. The number of HSE Engineers will vary during the project lifecycle
and it is the responsibility of the HSE Manager to ensure adequate personnel are available during the
project.
For an operational Plant, the HSE resources will be determined by the size and complexity of the facility.
The HSE function shall be independent of other functions and will report to the Senior Plant Manager.
This document shall not to be reproduced without written permission from the FOIZ CEO.
Note: Printed copies shall be considered as uncontrolled unless otherwise stamped “CONTROLLED COPY” in red ink and numbered.
Code of Practice-03 HSEQ-COP-03
agencies (Ministry of Environment, Civil Defence, FOIZ etc.), reviewed, and approved by the
concerned regulatory authorities and other external stakeholders.
3.1.3 Quality
All Plants and Projects shall have a process in place to ensure that the incoming goods (materials and
equipment) are inspected and verified at the time of delivery, to ensure they fully comply with the
specifications and the delivery requirements shown on the purchase order. This responsibility shall lie with
the project Procurement team for the goods delivered at the site.
If any goods received are found to be substandard (damaged or off-spec), they shall be either returned to
the supplier or quarantined until they are replaced or remediated. It shall be ensured that substandard
goods are not put into use. The quarantining items of may require a physical location that cannot be
accessed unless an authorised person from the Plant or project allows the release of the items.
For all equipment received, the equipment datasheets provided by the manufacturer / vendor shall be
saved in the data management system, and communicated to the end users.
For all hazardous goods received, the Material Safety Data Sheets (MSDS) provided by the supplier shall be
saved in the project data management system, and communicated to the end users.
This document shall not to be reproduced without written permission from the FOIZ CEO.
Note: Printed copies shall be considered as uncontrolled unless otherwise stamped “CONTROLLED COPY” in red ink and numbered.
Code of Practice-03 HSEQ-COP-03
All the following criteria are to be applied by the Plant management to give an assurance that the HSE
critical activities are being carried out by competent personnel:
All HSE critical activities have defined competency requirements which are periodically reviewed
and improved, as appropriate,
All personnel performing HSE critical activities are appropriately experienced / qualified and
trained to ensure they are competent to undertake and implement the risk control measures,
An HSE competency assurance process is in place for all personnel who perform HSE critical
activities. Competency shall be reassessed at intervals that are appropriate to their criticality.
Shortfalls will be documented and addressed as part of the training needs analysis,
A comprehensive and structured training system to develop competency for all staff involved in
managing HSE critical activities is in place,
Recruitment, deployment and succession plans are in place to enable the correct level of subject
matter expertise within HSE critical activities to be applied.
Manpower development
HSE critical activities
Human Resources
HSE policies and procedures
Recruitment, promotion and
HSE management system
succession planning
IDENTIFICATION INTEGRATION
REVIEW IMPLEMENTATION
This document shall not to be reproduced without written permission from the FOIZ CEO.
Note: Printed copies shall be considered as uncontrolled unless otherwise stamped “CONTROLLED COPY” in red ink and numbered.
Code of Practice-03 HSEQ-COP-03
Stage Description
Identification Documentation of HSE policies & procedures are applied and controlled
All HSE critical activities are defined
Competency levels are recorded and are periodically reviewed and
improved as appropriate
The HSE Management System is linked with the HSE competence
framework
Plants shall assess the HSE competency of each relevant employee (or directly supervised contract worker)
through a process that includes an informal day-to-day job evaluation by the immediate line supervisor and
the annual formal performance appraisal by the department manager. The day-to-day evaluation is based
upon the way an employee carries out the specific tasks that support HSE critical equipment and systems.
This document shall not to be reproduced without written permission from the FOIZ CEO.
Note: Printed copies shall be considered as uncontrolled unless otherwise stamped “CONTROLLED COPY” in red ink and numbered.
Code of Practice-03 HSEQ-COP-03
The HSE competency and appraisal of contract personnel is the responsibility of the Contractor. The Plant
management are accountable to ensure the competency and appraisal of individuals working at the Plant is
carried out through the contracting process as shown in Section 3.3.
1Contractors
are considered for HSE critical activities and for those who are directly supervised by the Plant
management.
This document shall not to be reproduced without written permission from the FOIZ CEO.
Note: Printed copies shall be considered as uncontrolled unless otherwise stamped “CONTROLLED COPY” in red ink and numbered.
Code of Practice-03 HSEQ-COP-03
Regulator
Legal Requirements Industry Best Practice
Requirements
Training Objectives
Teaching methods
Lesson plans
Method of delivery
Training frequency
Certification Levels
Competency Assessment
Performance Review
This document shall not to be reproduced without written permission from the FOIZ CEO.
Note: Printed copies shall be considered as uncontrolled unless otherwise stamped “CONTROLLED COPY” in red ink and numbered.
Code of Practice-03 HSEQ-COP-03
Needs Assessment
Training Requirements
This document shall not to be reproduced without written permission from the FOIZ CEO.
Note: Printed copies shall be considered as uncontrolled unless otherwise stamped “CONTROLLED COPY” in red ink and numbered.
Code of Practice-03 HSEQ-COP-03
This document shall not to be reproduced without written permission from the FOIZ CEO.
Note: Printed copies shall be considered as uncontrolled unless otherwise stamped “CONTROLLED COPY” in red ink and numbered.
Code of Practice-03 HSEQ-COP-03
This document shall not to be reproduced without written permission from the FOIZ CEO.
Note: Printed copies shall be considered as uncontrolled unless otherwise stamped “CONTROLLED COPY” in red ink and numbered.
Code of Practice-03 HSEQ-COP-03
Once the involvement of the HSE Lead / Team within a contract has been established, the implementation
of this CoP is then aimed at ensuring the principle that for the effective management of a Contractor’s HSE
performance is based on the level of risk and the application of control measures to mitigate the risk to an
acceptable level (ALARP).
2FOIZ is seeking to improve the HSEQ performance of contractors within the Plants and the move towards
accreditation will support this initiative.
This document shall not to be reproduced without written permission from the FOIZ CEO.
Note: Printed copies shall be considered as uncontrolled unless otherwise stamped “CONTROLLED COPY” in red ink and numbered.
Code of Practice-03 HSEQ-COP-03
given to include incentive schemes to encourage and reward the Contractor to achieve better than
the minimum expectations
This document shall not to be reproduced without written permission from the FOIZ CEO.
Note: Printed copies shall be considered as uncontrolled unless otherwise stamped “CONTROLLED COPY” in red ink and numbered.
Code of Practice-03 HSEQ-COP-03
Review and approve change requests - If the Contractor requests any changes to the HSE Plan or any of
the supporting HSE procedures and programmes, review the consequence of the proposed changes on
the HSE performance of the contract.
Review and analyse Contractor’s HSE performance monitoring (long duration projects) - Ensure that the
Contractor prepares and submits a monthly HSE performance monitoring reports for review. These
reports should be prepared in the format approved by FOIZ or the Plant management. The reports may
contain the following:
HSE Inspection reports,
Observations (positive and negative performance),
HSE audits, and
Accident / Incident / Near Miss statistics.
Perform periodic HSE inspections and audits - Perform routine HSE inspections or audits of the
Contractor’s activities. The frequency is determined by the risks associated with the project activities e.g.
erecting scaffolding.
This document shall not to be reproduced without written permission from the FOIZ CEO.
Note: Printed copies shall be considered as uncontrolled unless otherwise stamped “CONTROLLED COPY” in red ink and numbered.
Code of Practice-03 HSEQ-COP-03
The requirements within this CoP provide guidance on the methods of communication that could be
applied within the Plant as part of the overall communication process in absence of internal
communication processes.
There are occasions when additional HSE communications are necessary and should be scaled up
accordingly e.g. prior to major repair.
HSEQ communication is a two-way process and the information flowing upwards in the Plants is equally as
important as the downward communication. The requirements to communicate and report to FOIZ are
stated within the relevant CoPs.
Internal HSE communication shall cover, when applicable and required, the following topics:
Updates on the Plant HSE policy and the relevant topics from the HSEQ MS Manual / CoPs,
Annual HSEQ objectives and performance targets,
Compliance with Life savings rules,
Status of HSE plan and programs,
Lessons learned from HSE events / non-compliances, and
Periodic HSE performance results.
The Plant internal HSE communication channels can include, as appropriate, the following methods.
This document shall not to be reproduced without written permission from the FOIZ CEO.
Note: Printed copies shall be considered as uncontrolled unless otherwise stamped “CONTROLLED COPY” in red ink and numbered.
Code of Practice-03 HSEQ-COP-03
the contents of the alert are cascaded to the relevant personnel and contractors. FOIZ may remove the
origin of the alert if it sensitive to a Plant within the FOIZ area.
Alerts can also be displayed on noticeboards in Control Rooms and Offices to ensure employees see and
read them to understand the context and what to apply to prevent a reoccurrence within the Plant. Alerts
can be sent electronically as emails or on the opening screen on the Plant IT systems.
This document shall not to be reproduced without written permission from the FOIZ CEO.
Note: Printed copies shall be considered as uncontrolled unless otherwise stamped “CONTROLLED COPY” in red ink and numbered.
Code of Practice-03 HSEQ-COP-03
against unauthorised access, unauthorised alterations, and any other abuse / misuse by individuals / groups
internal or external.
As a reference, the IT system should include arrangements for:
Routine information back-up to a safe location,
Physical access control to IT servers,
Uninterrupted power supply,
Control of removal data storage devices,
Virus and malicious software protection,
System performance monitoring, and
Security of teleworking and mobile computing.
As a reference, the IT system access controls should include:
User registration and access rights,
Password for log-on and log-off,
Access to internet, and
Data transfer (downloads and uploads).
The IT Administrator should review the adequacy and effectiveness of the IT system:
At regular intervals based on a pre-defined schedule, and
Following a security lapse.
Based on the review, corrective / preventive actions shall be identified and implemented as part of the IT
work plan.
This document shall not to be reproduced without written permission from the FOIZ CEO.
Note: Printed copies shall be considered as uncontrolled unless otherwise stamped “CONTROLLED COPY” in red ink and numbered.
Code of Practice-03 HSEQ-COP-03
This document shall not to be reproduced without written permission from the FOIZ CEO.
Note: Printed copies shall be considered as uncontrolled unless otherwise stamped “CONTROLLED COPY” in red ink and numbered.