Professional Documents
Culture Documents
PE M3 02 ConfigurePhasing
PE M3 02 ConfigurePhasing
PE M3 02 ConfigurePhasing
Learning objectives:
Page | 2
4. Repeat steps 2 and 3 until the
following views are created by
duplicating the Level 1 – Existing view:
a. Level 1 – Demo
b. Level 1 – Existing
c. Level 1 - New
Page | 3
6. In the Level 1 – Existing view, in the
Properties palette, change the Phase to
Existing.
Page | 4
8. In the Level 1 – New view, activate the
Wall tool and create a vertical wall in
the center of the basic building.
Page | 5
10. In the Level 1 – Demo view, change the
Phase Filter in the Properties palette to
Show Previous + Demo.
Page | 6