Professional Documents
Culture Documents
Ch.8-Examples 2
Ch.8-Examples 2
3m
W.T.
figure, estimate the ultimate carrying capacity in
(tension and compression). The pile will filled
5m
with concrete. O.D. = 45.72 cm, wall thickness =
ϕ = 20 ᵒ
0.792 cm, pipe weight = 0.861 kN/m. Use Clayey sand c = 25 kPa
10 m
γ = 19 kN/m3
Meyerhof’s method in estimating the point
bearing capacity and the API method in ϕ = 35 ᵒ
Dense sand γt = 19.6 kN/m3
10 m
estimating the adhesion factor.
Solution
( i ) Point bearing capacity
Qb = Ab . ̅. ́
̅ = (19 ‒ 9.8) × 10 + (19.6 ‒ 9.8) × 10 = 190 kPa
Ab = = 0.164 m2
R1 = = = 21.87 > R2
Since, ˃ ; then
Qb Ab (50 tan ϕ ). ́
0.164 (50 tan 35) × 150 = 861.3 kN
Limiting value controls;
⸫ Qb = 861.3 kN
From Table (8.3); for steel pile and clayey sand soil; k1 = 0.5 and δ1 = 20
̅ = (19 ‒ 9.8) × 5 = 46 kPa
From Fig. (8.9); for c1 = 25 kPa ; α1 = 1.0
fs1 = 1.0 × 25 + 0.5 × 46 × tan 20 = 33.37 kPa < 100 kPA o.k.
As1 = π × 0.4572 × 10 = 14.363 m2
Qs1 = 14.363 × 33.37 = 479.3 kN
For the second soil layer (bottom)
Qs2 = As2 . fs2
fs2 = α2 . c2 + k2 . ̅ . tanδ2 ≤ 100 kPa
For sand; α2 . c2 = 0
From table (8.3); For steel pile and dense sand, k2 = 1 , and δ2 = 20
̅ = (19 ‒ 9.8) × 10 + (19.6 ‒ 9.8) × 5 = 141 kPa
fs2 = 1 × 141 × tan 20 = 51.3 kPa < 100 kPa O.k.
As2 = π × 0.4572 × 10 = 14.363 m2
Qs2 = 14.363 × 51.3 = 736.8 kN
Qs = Qs1 + Qs2 = 479.3 + 736.8 = 1216.1 kN
Qu = Qb + Qs = 861.3 + 1216.1 = 2077.4 kN
Tu = W + Qs
W = Wsteel + Wconc.
Wsteel = 28 × 0.861 = 24.108 kN
10 m
ultimate load Qu = 5000 kN. γ = 17.5 kN/m3
ks = 0.7
Sand
ϕ = 35 ᵒ
L
γ = 19.5 kN/m3
20 m
ks = 1.0
Concrete pile
(0.4 m × 0.4 m)
Solution
( i ) Point bearing capacity
Qb = Ab ( ̅. ́ ) ≤ Ab (11000) kN
Assume the limiting value controls;
Qb = Ab (11000) = (0.4)2 × 11000 = 1760 kN
+ 110
N.C.clay
Example (3-H.W.): Find the Allowable cu = 70 kPa W.T. +108
axial load for the driven pile shown taking γt = 17 kN/m3
α=1
Fs = 2.0. The elevation of W.T. ranged
between the two levels (105-108) during + 102
the year.
O. C. clay. γt = 20 kN/m3
Pile diameter = 0.5 m α = 0.45
cu = 180 kPa + 98
Pile length = 20 m
Deep sandy layer 𝑁́𝑞 = 23.18
γt = 19 kN/m3 ks = 1.5
= 32ᵒ tan δ = 0.5
Solution
( i ) Point bearing capacity
Qb = Ab ( ̅. ́ ) ≤ Ab (11000) kN
̅ = 17 × 2 + (17 ‒ 9.8) × 6 + (20 ‒ 9.8) × 4 + (19 ‒ 9.8) × 8 = 191.6 kPa
̅. ́ = 191.6 × 23.18 = 4441.3 kPa < 11000 kPa o.k.
Qa = = = 1758.6 kN
Foundation Engineering 7
10 m
c = 20 kPa
Fs = 2.7 . 𝛾 = 8.8 kN/m3
b- The allowable compressive load for the same
value of safety factor. Stiff clay
L
c = 80 kPa
Solution
𝛾 = 9.8 kN/m3
( a ) Tu = Wp + Qs
0.3 m × 0.3 m
(Tu)net = Qs
(Ta)net = = = 160 kN
Qs = 2.7 × 160 = 432 kN
Qs = Qs1 + Qs2
For the first layer (Soft clay)
Qs1 = As1 . fs1
α1 = 1 (soft clay)
fs1 = 1 × 20 = 20 kPa ≤ 100 kPa
Qs1 = (0.3 × 4 × 10) × 20 = 240 kN
⸫ Qs2 = Qs ‒ Qs1 = 432 ‒ 240 = 192 kN
( b ) Qu = Qb + Qs
Qb = Ab ( c ́ + ̅. ́ )
Qa = = = 184.0 kN
Example (5): Estimate the allowable carrying capacity of a concrete pile for the
following data;
L = 18 m , Wp = 3.5 kN/m , pile cap wt. = 7.6 kN
Double acting hammer; Wr = 60 kN , s = 0.5m/25 blows
Eh = 33.14 kN.m
Solution
S= = 20 mm/blow
a. ENR formula
Pu = = = 245 kN
b. BBC formula
Pu = = = 211.8 kN
√ √