Professional Documents
Culture Documents
Updated PDG Ind Ohsmsm 1304 Permit To Work
Updated PDG Ind Ohsmsm 1304 Permit To Work
Updated PDG Ind Ohsmsm 1304 Permit To Work
Permit To Work
1.0 PURPOSE
The purpose of this procedure is to protect every individual on site by means of a permit-to-work system in
conjunction with specific work procedures and safe practices. All work which is under the control of the permit-
to-work system shall be carried out strictly in accordance with the requirements and conditions included in
the specific work permits.
Work permit system is dovetailed around custodian concept. The DC Head is custodian of the project and all
work in that functional area shall have authorization.
This standard is applicable across PDG DC projects in India. Permit to work shall be applicable to (but not
limited to) all works that are required to be carried out within PDG DC project works carried out by vendors/
contractors under PDG supervision etc. based on the following guidelines:
• The “permit-to-work” system will in principle cover all on-site routine and non-routine work
which may create potential hazards.
• All activities shall necessarily need to have work permit unless and otherwise it is stated
and approved by Issuer.
• A list of activities where general work permit is not required will be prepared and approved
from Issuer.
• It is cautioned that permit-to-work is not permission to carry out a dangerous job. The permit-
to-work system should not be regarded as a way of avoiding the need to eliminate hazards
and reduce risks.
• The issue of work permits does not, by itself, make a job safe or guarantee safety. The
conditions and safety precautions stipulated in a work permit are normally addressing those
foreseeable risks or hazards and they are by no means exhaustive. Safety can only be
achieved by those preparing for the work and those carrying out work in accordance with
the work procedure, methods, use of right tools, and use the right judgment for which they
have been trained and made responsible.
Permit To Work
3.0 DEFINITIONS
3.1 Permit-to-work System is a formal written system used to control certain types of work
which are potentially hazardous. It is also a means of communication among site
personnel to ensure all necessary safety precautions are taken before commencing such
work. The types of work permits are:
3.2 General Work Permit it is the first level permit issued for jobs of general nature not
involving any special activities like Confined Space entry, Work at height, Excavation, Electrical
works, uses of cranes and hoist, Hot work, Lockout & Tagout & Scaffolding.
3.3 Custodian
Custodian is generally the Project Head of the particular DC construction project. Custodian is generally
the person responsible for implementing this PTW effectively in their respective projects. He will
primarily be accountable to ensure that all hazardous energy sources are isolated and conditions to
provide safe work environment for persons executing the job.
3.4 Issuer
Issuer is an employee designated by custodian with relevant job experience & authorized by custodian
who will issue work permit for respective area. Issuer should be knowledgeable of the hazards and
safety requirements for the equipment and process. He should be trained in this Work Permit procedure
and shall be responsible to get physical isolation of all hazardous energy sources to provide safe work
environment to the work initiator. The criteria for selecting Issuer should include educational background
and total experience within the DC.
Authorized isolator is a person identified and authorized by Custodian as per the requirements in the
LOTO standard. Authorized isolator shall be different for different discipline like Electrical &
Instrumentation, Mechanical and any other facility/process.
Permit To Work
Co-permittee means the person or the supervisor of a work group who is/are carrying out the job at site.
Hazardous energy sources are defined as any source of electrical, mechanical, hydraulic, pneumatic,
chemical, thermal, radiation or any other energy that, if not controlled, could cause injury to personnel
or damage to property and/or environment.
4.0 PROCEDURE
4.1.1 Initiator will raise the General work permit in triplicate, by entering details in clause “A” of the work
permit (with the help of Issuer) after taking consent from custodian. He shall mention work
description in detail, date, time, duration and mention the list of equipment. Initiator will not start
the job while permit is under approval but can do the preparatory job till permit gets approved
from custodian. The Initiator shall ensure that the persons engaged are thoroughly briefed
through TBT about the relevant job steps, associated hazards & control measures (JSA) as per
the risk assessment. He will also ensure that relevant PPEs are provided. He will sign the permit.
4.1.2 The custodian will check & ensure that all Hazardous energy sources which are to be isolated
have been identified by initiator. If any additional isolation is required, Custodian shall identify it
and mention in Permit. He shall nominate an issuer and direct him to get isolation physically
completed and give clearance to start the job. He will sign the permit.
4.1.3 Issuer shall note isolations be done including those have been identified by custodian and carry
out isolation along with respective authorized isolator. Authorized isolators shall mention
equipment details, Equipment no and type of isolation made, LOTO Tag no in respective column
in clause “C” and shall mention his name and sign.
4.1.4 The Issuer shall visit site and ensure isolation of all Hazardous energy sources are completed by
respective authorized isolators. He shall ensure Checks mentioned in clause “D”. He shall give
clearance to start the work and sign the permit.
4.1.5 Initiator shall note Clause “D”, ensure and explain to the work group about issuer’s check list and
control measures stated in the permit clauses A, B, C & D for safe execution of the job. Initiator
together with the Co-permittee shall jointly inspect the site to confirm that all preparation work is
completed, and the permit conditions have been maintained on work site. He shall sign in clause
“E” of the permit and obtain signature of co-permittee in clause “F” & hand over the 1st copy of
permit (white) to the workgroup for display at job site. The 2nd copy (yellow) will be displayed at
the designated location (office / site) by the Issuer. The 3rd copy (pink) will be retained in the
book for records.
4.1.6 Duly signed & approved work permit along with associated permits, JSA & TBT shall be kept at
site where work group is performing the job.
Permit To Work
4.1.7 Initiator is responsible to maintain the status quo for control measures stated in the JSA/ work
permit during execution of work safely.
4.1.8 Co-permittee is equally responsible to maintain the control measures stated in the JSA/ work
permit during execution of work safely.
IMPORTANT: ANY CHANGES IN THE WORK PERMIT MUST REFLECT ON ALL THE THREE COPIES
Additional respective special work permit needs to be taken along with the General work permit. For
special work permit, respective standard shall be referred.
4.3.1 When the job is completed, the Initiator shall ensure that all men and material is removed
from the site and ensure that isolations made, can be restored. He shall obtain signature of
the co - permittee and sign in clause “G”. He shall hand over the Permit copy (First copy)
to Issuer to close the permit.
4.3.2 The Issuer shall direct authorized isolators to carry out restoration of isolation as per clause
“C” and sign in clause “H”.
4.3.3 Respective authorized isolators shall carry out restoration of respective isolations as per
clause “C” and shall mention respective equipment tag no. in both copies of the permit and
sign in clause “I”.
4.3.4 Issuer shall ensure restoration of all isolation mentioned in clause “C” are completed and
shall sign the permit in clause “J”. He shall declare equipment ready to start and shall inform
the custodian.
4.4.1 First copy (white) of the work permit and any attached permit(s) shall be with initiator / co-
permittee and shall be at job site.
Permit To Work
4.4.2 The second copy (yellow) shall be with issuer and shall be displayed at issuer’s designated
area. (Office/site).
4.4.3 The third copy (pink) will remain in the permit book and shall be available with custodian for
office record.
4.4.4 On completion of the work, all the three copies shall be signed by the concerned persons (as
detailed in section above).
4.4.5 The completed copy of the permit shall be retained at respective projects for office record
purpose along with all associated permits/documents for 1 year.
Permit shall remain valid for one shift, including General Shift. New work permits shall be issued
whenever Initiator or Co-Permittee is changed for any reason (even before completion of the shift),
A permit is valid for a specific scope of works, on specific locations with same team within a
specified period of time – it is valid till the end of the shift in which it is issued. If the work extends
beyond the shift it is issued, permit must be revalidated or renewed.
4.5.1 Issuer shall inform the custodian regarding the job being continued and the need for Permit
renewal. He will make a site visit if the work permit is to be renewed.
4.5.2 Initiator shall brief the work group regarding the hazards and the risk control plan/
safeguards and obtain signature of Co-permittee.
4.5.3 Issuer, Initiator and Co-Permittee shall sign all the three copies of permit and shall hand-
over the 1st copy to initiator.
4.5.5 In the event of change in work group members, the Initiator shall inform the Issuer about
the change. He shall also explain the hazards and safety measures to new person(s) in the
work group. Undertaking of new members shall be obtained on TBT.
Deviations from this procedure must be reviewed as per Annexure -IV by the Project Head of a
particular DC project in consultation with OHS Manager. Deviations must be documented (as per
Annexure-4) and documentation must include the relevant facts supporting the deviation decision.
Deviation authorization must be renewed periodically as necessary as and not later than one
year.
Permit To Work
7.1 Project Head for the DC Construction work are responsible to ensure that
7.2 Permit Initiator shall be responsible to obtain permit for the job he or she is executing.
Multiple permits for multiple work groups working on the same equipment will be required,
A permit is valid for a specific scope of works, on specific locations with same team within a specified
period of time – it is valid till the end of the shift in which it is issued. If the wok extends beyond the shift,
it is issued permit must be revalidated or renewed.
7.3 All individuals of the work groups working within the site have the responsibility to -
a. Have a good understanding of the permit-to-work systems and follow the PDG Safety
Standards SOP / HIRA / JSA briefed to them before commencing the job.
b. Ensure that they do not start work on any job requiring a work permit. Always wait till a work
permit has been authorized and issued, including a briefing at the work location.
c. Follow all the precautions and safety measures stipulated in the work permits and strictly
comply with the requirements and procedures of the permit-to-work system;
d. Stop work and get advice immediately from initiator when in doubt or in case there is any
change in circumstances or change of conditions which makes the work area unsafe.
e. Should not adopt any short cut while performing the job.
Permit To Work
8 Annexures
Permit To Work
Annexure I
Flow Chart to obtain General Work Permit
Stop permittee
Follows the instructions
given by initiator & carries
out job.
Permit To Work
Annexure II
Flow Chart to Close General Work Permit
Asks Authorized
Isolators to
Issuer restore Isolation
as per clause “C”
Auth.
Isolator
Initiator retains
Stop Initiator permit copy for 7
days as record.
Permit To Work
Annexure – 3
Job Safety Analysis Form
□ Area barricaded, cordoned off □ Manpower deployed is trained □All PPEs, Tools and Equipment inspected
(esp. electrical, height work)
□ Isolations done as per LOTO (If □ Special Work Permits being □ This JSA explained to the workers during
applicable). deployed (if applicable) TOOLBOX TALKs
PPE Checklist:
□ Safety Helmet □ Safety Helmet with Welders mask □ Safety Helmet with Face Shield
□ Safety Shoes □ Safety Shoes (Electrical work) □ Safety Glass - Cutting, grinding etc.
□ Safety Goggles (for Chemicals) □ Dust Mask, Cartridge Mask □ Supplied Breathing Air, SCBA
□ Ear Plugs, Earmuffs □ Gloves – Ordinary, Cut Resistant, □ Protective suit – Hot Work, Chemical,
Chemical, Hot Work, Electrical Electrical (etc.)
Fire Safety checklist:
□ Area free of Flammables and □ Fire Hose laid out and ready □ Fire Extinguisher (Type, Size and
Combustibles, Gas Tests done (Quantity), Fire Water available Quantity)
□ Fire Blankets □ Sand Buckets (Quantity) □ Sprinkler/ detectors in area working?
Safeguard / controls to be put
Sequence of Basic Job Steps Potential Hazards Responsibility
in place
Permit To Work
Annexure – 3
Permit To Work
Annexure – 4
Description of Works:
Description of Deviation:
Permit To Work
Annexure - 5
Duration: hrs
Name of Initiator: Agency / Company Name: Initiator’s Contact No.: Initiator’s Signature:
Ensure the equipment isolated as listed in section C & ensure checklist as Clause D & also
additional isolation is also required.
JSA S/No. ____________________ HOT WORK S/No. _______________ LOTO S/No. _________ EXCAVATION S/No. _________
TBT S/No. HEIGHT WORK S/No. ____________ ELECTRICAL S/No. ______ LIFTING S/No. _____________
HIRA S/No. ____________________ CONFINED SPACE S/No. ________ SCAFFOLDING S/No. ____ OTHERS S/No. _____________
S. No. Description of Isolation Equipment Tag No. Isolation Details LOTO Tag No. Name of Auth. Isolator Signature
1.
2.
3.
4.
5.
(D) Checks to be filled & ensured by issuer Y N NA
1. Work area is free from any obstruction / hazards?
2. Sufficient illumination is maintained?
3. Is the area cordon off/ barricaded with required warning signs?
4. Have the vessel/equipment/line been positively isolated from all the energy sources?
5. Equipment / Tools inspected and tagged?
6. IS PPE provided and being used?
7. Are the person conducting work, suitably trained & competent?
Comment by Issuer: I have ensured that all required control measures as per clause C & D are Issuer’s Name: Issuer’s Signature:
completed. Identified workplace hazards, associated risk & adequate control measures as
determined & mentioned in the preliminary job safety analysis have been implemented & verified
onsite, also the same has been briefed to the job execution team through toolbox talks. I declare
the site is now ready for work execution. Date: / / Time: A.M / P.M
(F) Co-permittee: I am briefed and understood. I shall maintain site as per the work-
(E) Initiator: I have understood & verified clause D. Work can be started now. permit & associated checklist.
(G) To be filled by initiator: The Job is completed, all the men & materials removed from the site. Safe to restore the isolations (if any) as stated in clause C.
(H) I have restored isolation for following equipment’s from list (if any) stated in clause (c)
Copy Distribution: 1st Copy (White) to be displayed at worksite. 2nd Copy (Yellow) to be kept for display & records (control room). 3rd Copy (Pink) for records with site.
Permit To Work
Annexure 6 – (a)
A. Permit Application (To be filled and ensured by initiator with the help of issuer)
HIRA S/No. CONFINED SPACE S/No. SCAFFOLDING S/No. ____ OTHERS S/No.
Comment by Initiator: I certify that the above have been checked and found satisfactory.
Comment by Issuer: I certify that the above have been checked and found satisfactory. The permit is hereby approved and work at height is allowed subject to compliance
of all safety precautions and requirements stipulated in this permit and associated permits and work procedures.
We have inspected at the work site and confirm that the permit conditions have been complied.
Work completed and all personnel and material have been removed.
Inspected site and confirmed that the permit conditions have been complied with and the work is now completed.
Copy Distribution: 1st Copy (White) to be displayed at worksite. 2nd Copy (Yellow) to be kept for display & records (control room). 3rd Copy with user for records.
Permit To Work
Annexure 6 – (b)
PDG-IND-OHSMSM-1304 Electrical Work Permit Sr. No.
A. Permit Application (To be filled and ensured by initiator with the help of issuer)
HIRA S/No. ____ CONFINED SPACE S/No. ________ SCAFFOLDING S/No. ___________
Rings, watch, chain, bracelets etc have been Is welding machine & all the connections were
4. 10.
removed before start of work. routed through RCCB/RCBO with tripping
sensitivity of 30 mA
5. All portable electrical equipment’s are having proper 11. All cables been routed above the head level or
plug with earthing. cable manager has been installed at the ground?
Comment by Issuer: I certify that the above have been checked and ensured in place and JSA has been carried out. JSA form attached with work permit.
We have inspected at the work site and confirm that the permit conditions have been complied & safe to carry out Electrical Work in the area.
Work completed and all personnel and material have been removed and site is clear.
Inspected site and confirmed that the permit conditions have been complied with and the work is now completed.
Copy Distribution: 1st Copy (White) to be displayed at worksite. 2nd Copy (Yellow) to be kept for display & records (control room). 3rd Copy with user for records.
Permit To Work
Annexure 6 – (c)
CONFINED SPACE ENTRY PERMIT
A. PERMIT APPLICATION (INITIATOR)
Associated Permit(s): Cold Work Permit (S/No. ) Hot Work Permit (S/No. )
Work at Height Permit (S/No. ) Electrical Work Permit (S/No. )
Name: Signed:
Date: Time
B. PERMIT APPROVAL (APPROVER)
GENERAL SAFETY CHECKS
The vessel *contained/did not contain hazardous material The vessel has been depressurized, drained, purged
Type of hazardous material: and cleared of hazardous material and positively
Gas tests to be carried out at following interval: every _hr isolated/blinded from all process/utility/electrical
Gas tests have been carried out in the vessel/confined space systems.
Lock, Tag & Try completed (Key Control Box No. )
All employees involved are trained for the Job Appropriate controls put in Place as per JSA
Ensure Sufficient Illumination Ensure Equipment grounding in case of Static charge
SAFETY REQUIREMENTS
Respiratory Protection Other PPE
Respiratory protective equipment Chemical suit. Type:
Air-Line Respirator Chemical gloves and boots
Self-contained Breathing Apparatus (SCBA) Lifeline Other
Gas Monitoring Equipment
I certify that the above have been checked and found satisfactory. The permit is hereby approved, and vessel
entry is allowed subject to compliance of all safety precautions and requirements stipulated in this permit and
associated permits and work procedures.
Name: Signed:
Date: Time:
C. CONFIRMATION & ACCEPTANCE
We have inspected the work site on (Date) at (Time) and confirm that the permit
conditions have been complied with and it is safe to enter the vessel/confined space. Initial gas test has been
carried out. Subsequent gas test must be carried out every 2 hours interval and results to be recorded.
INITIATOR (CSE SUPERVISOR) APPROVER ISSUER
Name: Name: Name:
Company:
Signed: Signed: Signed:
Permit To Work
D. PERMIT RENEWAL
The vessel/confined space has been re-surveyed, and conditions have not changed as per Annex—1 & 2
The renewal of permit is granted from at hrs, to at hrs
Name: Signed:
Date: Time:
Permit To Work
Annexure 6 – (d)
A. Permit Application (To be filled and ensured by initiator with the help of issuer)
HIRA S/No. CONFINED SPACE S/No. SCAFFOLDING S/No. ____ OTHERS S/No.
6. Welding cable joints must be with lugs and insulated. 14. Others (specify)
Comment by Issuer: I certify that the above have been checked and ensured in place and JSA has been carried out. JSA form attached with work permit.
We have inspected at the work site and confirm that the permit conditions have been complied & safe to carry out Hot Work in the area.
E. Work completed and all personnel and material have been removed and site is clear.
Inspected site and confirmed that the permit conditions have been complied with and the work is now completed.
Copy Distribution: 1st Copy (White) to be displayed at worksite. 2nd Copy (Yellow) to be kept for display & records (control room). 3rd Copy with user for records.
Permit To Work
Annexure 6 – (e)
PDG-IND-OHSMSM-1304 Excavation Permit Sr. No.
A. Permit Application (To be filled and ensured by initiator with the help of issuer)
Comment by Initiator: I certify that the above have been checked and found satisfactory.
Before commencing the excavation, clearance should be taken from underground pipes and cables.
I certify the above has been checked and found satisfactory. The permit is hereby approved, and excavation is allowed subject to compliance of all safety precautions
and requirements stipulated in this permit, associated permit and work procedures.
We have inspected the worksite and confirm that the permit conditions have been complied with and it is safe to excavate the space.
Inspected site and confirmed that all the personnel’s and material have been removed and site is clear.
Copy Distribution: 1st Copy (White) to be displayed at worksite. 2nd Copy (Yellow) to be kept for display & records (control room). 3rd Copy with user for records.
Permit To Work
Annexure 6 – (f)
PDG-IND-OHSMSM-1304 Lifting Permit Sr. No.
A. Permit Application (To be filled and ensured by initiator with the help of issuer)
TBT S/No. GENERAL PERMIT S/No. ELECTRICAL S/No. HEIGHT WORK S/No.
HIRA S/No. CONFINED SPACE S/No. SCAFFOLDING S/No. ____ OTHERS S/No.
1. Is suitable sling /'D' shackle selected and its healthiness Lifting plan, SWMS & HIRA attached with
8. this permit?
is being inspected?
2. Are U clamps saddle grips seated on live ends of wire Crane fitness is being checked. More than 10 years
ropes? And min. 9.
old crane is being engaged?
3. Min 3 U clamps in Dx6 distance formula has been All safety devices such as ASLI and limit switches
provided? 10.
with auto cut off is functioning?
4. Dedicated signal man has been provided with Is SWL fall under 75% as per the crane
signaling device such as whistle, walky-talky? 11. load chart?
5. Are all height workers were provided with full body safety Emergency response team & Medical
12. facilities available?
harness?
6. Access and egress marked and without obstruction? 13. Lifting sling / belt is protected against sharp edges?
Comment by Initiator: I certify that the above have been checked and found satisfactory.
Comment by Issuer: I certify that the above have been checked and found satisfactory. The permit is hereby approved and the lifting work is allowed subject to compliance
of all safety precautions and requirements stipulated in this permit and associated permits and work procedures.
We have inspected at the work site and confirm that the permit conditions have been complied.
Work completed and all personnel and material have been removed.
Inspected site and confirmed that the permit conditions have been complied with and the work is now completed.
Copy Distribution: 1st Copy (White) to be displayed at worksite. 2nd Copy (Yellow) to be kept for display & records (control room). 3rd Copy with user for records.
Permit To Work
Annexure 6 – (g)
PDG-IND-OHSMSM-1304 Scaffolding Permit Sr. No.
A. Permit Application (To be filled and ensured by initiator with the help of issuer)
HIRA S/No. CONFINED SPACE S/No. HEIGHT WORK S/No. ____ OTHERS S/No.
5. Are outriggers used for scaffold stability when point no. 2 13. Is the working area of the scaffold extending
is not complied. outside the scaffold base dimensions
Are mobile scaffolds used on a firm & level surface Area below the job is properly cordoned off and
6. 14.
and all bracings in place display cautionary sign board?
Comment by Initiator: I certify that the above have been checked and found satisfactory.
Comment by Issuer: I certify that the above have been checked and found satisfactory. The permit is hereby approved and work at height is allowed subject to compliance
of all safety precautions and requirements stipulated in this permit and associated permits and work procedures.
We have inspected at the work site and confirm that the permit conditions have been complied.
Work completed and all personnel and material have been removed.
Inspected site and confirmed that the permit conditions have been complied with and the work is now completed.
Copy Distribution: 1st Copy (White) to be displayed at worksite. 2nd Copy (Yellow) to be kept for display & records (control room). 3rd Copy with user for records.
Permit To Work
Annexure 6 – (h)
PDG-IND-OHSMSM-1304 LOTO Permit Sr. No.
A. Permit Application (To be filled and ensured by initiator with the help of issuer)
JSA S/No. ____ HOT WORK S/No. ____________________ SCAFFOLDING PERMIT S/No.
TBT S/ No. _________________________ GENERAL PERMIT S/No. ___________________ LIFTING PERMIT S/No.
HIRA S/No. ____ CONFINED SPACE PERMIT S/No. ________ HEIGHT WORK S/No. ___________
S. No. Description of Isolation Equipment Tag No. Isolation Details LOTO Tag No. Name of Auth. Isolator Signature
8.
2. Is equipment/machine is required to be locked out and tag out to Have you checked that no personnel are exposed
perform the servicing or maintenance? to hazardous energy/sources?
Whether the energy isolating device(s) is deactivated to 11. Have you verified the isolation of the equipment by
5. operating the push button or other normal operating
isolate from the primary energy source(s)?
control?
Comment by Issuer: I certify that the above have been checked and ensured in place and JSA has been carried out. JSA form attached with work permit.
We have inspected at the work site and confirm that the permit conditions have been complied & safe to carry out Electrical Work in the area.
4. Work Completed (Initiator) The Job is completed, all the men & materials removed from the site. Safe to restore the isolations (if any) as stated in clause C.
(H) I have restored isolation for following equipment’s from list (if any) stated in clause (c)
Permit To Work
Inspected site and confirmed that the permit conditions have been complied with and the work is now completed.
Permit To Work
Annexure 6 – (i)
PDG-IND-OHSMSM-1304 Night Work Permit Sr. No.
A. Permit Application (To be filled and ensured by initiator with the help of issuer)
JSA S/No. ____ HOT WORK S/No. ____________________ SCAFFOLDING PERMIT S/No.
HIRA S/No. ____ CONFINED SPACE S/No. ________ HEIGHT WORK S/No. ___________
C. To be filled by initiator who is carrying out night work and verified by issuer
S. No. Name of the worker Gate Pass / ID Workman Signature Name of the worker Gate Pass / ID Workman Signature
Number Number
S. No Checklist Y N N/A
1 Adequate illumination as per lighting standard SOP ref. PDG-IND-OHSMSM-2111 has been provided?
Comment by Issuer: I certify that the above have been checked and ensured in place and JSA has been carried out. JSA form attached with work permit.
F. Work Completed (Initiator) The Job is completed, all the men & materials removed from the site.
Inspected site and confirmed that the permit conditions have been complied with and the work is now completed.