Checklist No/ Revision No.

CL-ENG-EXE-029-R0

Page Number 1 of 1

EXE-029-Checklist For Painting Issue date 10/7/2015

Project Name: Dated:

Unique No. / Reference on the drawing : Time :

Sl.no Description Yes No N/A Remarks

1 Check whether the quality and shade is as per specification

2 Check for the brand & manufacturing date

Check whether the surface to be painted are free from dust,


3
loose materials, grease, algae, dirt etc.

4 Check for brand of brush used

5 Check for adequate light provision during painting

6 Check whether the wall is scrapped

7 Check for the primer application

8 Check whether proper time interval is given between the coats

9 Check whether the paint is applied uniformly

10 Check the quality of the putty blade, brush and roller

11 Check whether the paint is mixed properly

12 Check for the shade variation / pigmentation

13 Check whether the floors are protected before painting

Check whether the hardware and CP items are covered with


14
masking tape

15 Check for the brush marks / unevenness

Contractor's Site Personnel Project Engr. AGM/Project Mngr.


Sign & Date

Initial sign off by QA/QC Representative Signed by consultant [ if applicable]

Sl No Corrective Actions Proposed : Corrective Actions undertaken Report :

Confirmed by
Site Engr. Project Engr. Project Mngr.

Sign & Date


Final sign off by QA/QC Representative Signed by consultant [ if applicable]