Production Facility for Singer Bangladesh Limited. Construction of RCC Boundary Wall
Rev.0
2-Jun-22
Month May June July August September October
Week 1W 2W 3W 4W 1W 2W 3W 4W 1W 2W 3W 4W 1W 2W 3W 4W 1W 2W 3W 4W 1W 2W 3W 4W
Issuance of LOI (May-22)
Issuance of Contract agreement (May-26) Handover
Commencement of construction (May-31) Oct-22
Overall Project Schedule
Construction schedule
Survey work, Site preparation
Boundary Wall Type-1, 1a
Area A (approx. 240m)
Earth Work
Foundation
Grade Beam
Brick, Drain pipe & Lintel beam
Column, Conduit pipe & Capping
Plastering
Painting
Steel Fence Installation
Area B (approx. 240m)
Earth Work
Foundation
Grade Beam
Brick, Drain pipe & Lintel beam
Column, Conduit pipe & Capping
Plastering
Painting
Steel Fence Installation
Area C (approx. 316m)
Earth Work
Foundation
Grade Beam
Brick, Drain pipe & Lintel beam
Column, Conduit pipe & Capping
Plastering
Painting
Steel Fence Installation
Area D (approx. 360m)
Earth Work
Foundation
Grade Beam
Brick, Drain pipe & Lintel beam
Column, Conduit pipe & Capping
Plastering
Painting
Steel Fence Installation
Boundary Wall Type-2
Foundation & Post Installation
Steel Mesh Fence Installation
Inspection & Handover Handover
Inspection
Bensito A. Castillo
Project manager
TOA CORPORATION