Report (30-4) - (1-5) - 2023

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 5

MASAR AWCS

SITE REPORT
DATE: (30 - 4) - (1 - 5) - 2023
CODE MASR-KAS-PA-DCR-CIV-(30 - 4) - (1 - 5) - 2023

1-Staff of Main Contractor " Marimatic "


STAFF DAY Shift NIGHT Shift TOTAL REMARKS
Project Manager 1 0 1
Site Engineer 1 0 1
Site Supervisor 0 0 0
Project Forman 0 0 0
Safety Officer 0 0 0
Surveyor 0 0 0
Design (finland) 2 0 2
Electrician 0 0 0
TOTAL 4 0 4
2- Al wagehat Al gharbiya Contracting (WGCC)
2.1-"Man power" Al wagehat Al gharbiya Contracting "
Man power DAY Shift NIGHT Shift TOTAL REMARKS
Mobile Crane operator 2 0 2
Driver 2 0 2
Welders 8 0 8
Pipe fitter 4 0 4
Welders Groups
Fabricator 8 0 8
Helpers 16 0 16
Labor 55 0 55
Rigger 5 0 5
TOTAL 100 0 100

2.2-Staff
2.2-STAFF DAY Shift NIGHT Shift TOTAL REMARKS
Project Manager 1 0 1
Site Engineer 2 0 2
Site Supervisor 1 0 1
Project Forman 1 0 1
Safety Officer 2 0 2
Safety supervisor 3 0 3
Surveyor Engineer 1 0 1
Surveyor helpers 3 0 3
Technical Engineer 1 0 1
Electrician Engineer 2 0 2
Electrician supervisor 1 0 1
Mechanical supervisor 1 0 1
Site logistic Manager 1 0 1
Purchases official 1 0 1
Store keeper 1 0 1
TOTAL 22 0 22

2.3-Main Equipments
Main Equipments DAY Shift NIGHT Shift TOTAL REMARKS
Mobile Crane 2 0 2
Welding Machine 9 0 9
Cutting Machine 10 0 10
Generator 2 0 2
Compressor 2 0 2
Cars 4 0 4
Fork lift 1 0 1
Boom Truck 1 0 1
TOTAL 31 0 31
3-Description of The Main Activities BY QTYS
SER LOCATION Excavation -MTR WELDED Pipes-MTR Installed Pipes-MTR No.WELDED of joints-ONE No. of tested joints (approved) -ONE Installed Conduit -MTR Installed Detectable - Warning TapeInstalled Litter Bin Backfill By-MTR
1 ZONE 02 664 661 661 180 180 1879 502 12 502
2 ZONE 03 314 312.24 300 64 64 925
3 ZONE 04 1025 1396.7 748 284 278 2083 981 981
4 ZONE 05 545 545 545 147 147 1208 266 3 266
BOULEVARD
5 ZONE 06 314.1503 314.1503 314.1503 77 77 1215 100 7 100
6 ZONE 07 567.3574 567.3574 567.3574 156 156 1487 300 15 300
7 ST05-BOULEVARD 282.6432 208 208 91 86 773 7
8 ST04-BOULEVARD 140.8 140.8 135 40 40 17 17 17
1 ST03-NORTH AREA 190 190 190 44 44 310 37 37
2 ST03-SOUTH AREA 143 12 12
3 STO4-NORTH AREA 113.3657 112 113.3657 25 25 250
INTERFACES AREAS
4 STO4-SOUTH AREA 112 112 112 48 48 308 34 34
5 ST05-NORTH AREA 236 236 236 58 58 472
6 ST-05-SOUTH AREA 198 198 198 66 66 208 92 92
1 Z1 130 130 130 42 42 227
2 Z2
3 Z3 - TERMINAL STATION 578 578 578 46 46
South and North Roads-
4 Z4
DIRECT BURRIED
5 Z5-SOUTH ROAD 341 341 298 70 70 699 192 192
6 Z6
7 Z7
TOTAL 5751.3166 6185.2477 5333.8734 1450 1439 12061 2521 44 2521

4-BOULIVARD INCLUDING INTERFACES AREAS PROGRESS PER ZONE (Percentage (%)


PIPES - PROGRESS % LITTER BIN CHAMBERS
SER ACTIVITY DESCRIPTION QTY Description Installed Pipes- TOTAL QTY OF
Percentage (%) LITTER BIN CHAMBER INSTALLED TOTAL QTY OF LITTER BIN CHAMBERS INSTALLATION - Percentage (%)
MTR PIPES

1 ZONE-02-INCLUDE ST03 BY MTR 851 1078.5 78.90588781 12 18 66.66666667

2 ZONE - 03 BY MTR 300 732.7 40.94445203 0 21 0

3 ZONE - 04 BY MTR 748 1215 61.56378601 0 15 0

4 ZONE -05 INCLUDE ST04 BY ONE 770.3657 938.2 82.11103176 3 20 15

5 ZONE-06-INCLUDE ST05 BY ONE 956.1503 989.5 96.62964123 7 15 46.66666667

6 ZONE - 07 BY MTR 567.3574 942 60.22902335 15 19 78.94736842

SER ACTIVITY DESCRIPTION QTY Description DONE OVERALL Percentage (%)


5-DIRECT BURRIED BOULEVARD Progress (%)
1 Excavation BY MTR 3852.9509 4854 79.37682118

2 Installed Pipes BY MTR 3478.5077 4854 71.66270499

3 Welded Pipes BY MTR 4145.2477 4854 85.39859291 =

4 No. of joints welded BY ONE 1039 1933 53.75064666

5 No. of Tested joints (approved) BY ONE 1028 1933 53.18158303

6 Installed Conduit BY MTR 9587 13663 70.16760594

7 Installed Detectable - Warning Tape BY MTR 2166 4854 44.62299135

8 Installed Litter bin BY ONE 44 108 40.74074074

9 Backfill By Al Dahry BY MTR 2166 4854 44.62299135


6- INTERFACE Areas Progress (%)
1 Excavation BY MTR 849.3657 1021 83.18958864
2 Installed Pipes BY MTR 849.3657 1021 83.18958864
3 Welded Pipes BY MTR 991 1021 97.06170421
4 No. of joints welded BY ONE 253 373 67.82841823
5 No. of Tested joints (approved) BY ONE 253 373 67.82841823
6 Installed Conduit BY MTR 1548 1911 81.00470958
7 Installed Detectable - Warning Tape BY MTR 163 1021 15.96474045
8 Installed Litter bin BY ONE 0 0 0
9 Backfill By Al Dahry BY MTR 163 1021 15.96474045

7-South and North Roads-DIRECT BURRIED (%)


1 Excavation BY MTR 1049 4051 25.89484078
2 Installed Pipes BY MTR 1006 4051 24.83337448
3 Welded Pipes BY MTR 1049 4051 25.89484078
4 No. of joints welded BY ONE 158 700 22.57142857
5 No. of Tested joints (approved) BY ONE 158 700 22.57142857
6 Installed Conduit BY MTR 926 6957 13.31033491
7 Installed Detectable - Warning Tape BY MTR 192 4051 4.739570476
8 Installed Litter bin BY ONE 0 2 0
9 Backfill By Al Dahry BY MTR 192 4051 4.739570476

8-South and North Roads- inside UG (%)


1 Installed Pipes BY MTR 0 12000 0
2 Welded Pipes BY MTR 0 12000 0
3 No. of joints welded BY ONE 0 2000 0
4 No. of Tested joints (approved) BY ONE 0 2000 0
5 Installed Conduit BY MTR 0 23820 0
6 Installed Litter bin BY ONE 0 77 0

9-Overall progress for whole project (%)


1 Excavation BY MTR 5751.3166 9926 57.94193633
2 Installed Pipes BY MTR 5333.8734 21926 24.32670528
3 Welded Pipes BY MTR 6185.2477 21926 28.20964927
4 No. of joints welded BY ONE 1450 5006 28.96524171
5 No. of Tested joints (approved) BY ONE 1439 5006 28.74550539
6 Installed Conduit BY MTR 12061 46351 26.02101357
7 Installed Detectable - Warning Tape BY MTR 2521 9926 25.39794479
8 Installed Litter bin BY ONE 44 187 23.52941176
9 Backfill By Al Dahry BY MTR 2521 9926 25.39794479

10-Open Front Areas


1 ZONE 07&ZONE 06&ZONE 02&ZONE 03
2 UGLS LITTER BINS
3

11-MAIN ISSUES
1 ST05 NORTH NORTH WEST NEED CORE
2 UGLS LITTER BINS EXCAVATION STILL NO ACTION
3
12-PHOTOS OF ACTIVITIES

12.1-ZONE - 05, DIRECT BURIED BOULEVARD, INSTALLATION

12.2- ZONE - 06, ST - 05, DIRECT BURIED BOULEVARD, INSTALLATION


12.3-ZONE - 07, UTILITY GALLERY NORTH NORTH ROAD, PIPE SUPPORT INSTALLATION

You might also like