METHOD STATEMENT
PROJECT:
PROPOSSED MODIFICATION WORKS AT MAPEI AT
DIP 1, DUBAI – UAE.
METHOD STATEMENT
CONTENTS
1. PRELIMINARY NOTE
2. PURPOSE OF WORK
3. RESPONSIBILITIES
4. SAFETY REQUIREMENTS
5. PERSONAL PROTECTIVE APPAREL AND SAFETY EQUIPMENT
(PPE)METHODOLOGY
6. EQUIPMENT & MANPOWER
6.1 EQUIPMENT
6.2 MANPOWER
6.3 MATERIAL
7. SCOPE OF WORK
8. Methodology
8.1 PREPARATION WORK
8.2 GYPSUM WALL CLADING JOINT FILLING AND SANDING
8.3 FIXING WALL MDF ACEESS DOOR
8.4 DOUBLE SKIN PLYWOOD FIXING ON THE WOODEN STRUCTURE
8.5 PVC FLOOR TILE FIXING ON THE WOODEN STEPS.
8.6 FIXING OF EXISTING WINDOW PAINTED WOODEN ARCHITRAVE.
8.7 WOODEN CAPPING FIXING
9. Clear work area
10. Dismantle Aluminium scaffold
11. Rubbish arising
12. Health and Safety Management Provisions
LOYAL BUILDING CONTRACTING L.L.C.
1. PRELIMINARY NOTE:
LOYAL BIUILDING CONTRACTING LLC reserves the right to adapt the
methods used according to site needs and configuration. In the case of major
changes to the methods intended to be used, this method statement will be
resubmitted for approval. The Work shall be commenced upon approval of the
MS and RS by Client.
2. PURPOSE OF WORK:
This document defines the procedures to be used during the initial stage starting
from making for fixing the gypsum wall cladding, filling and sanding and
fixing of the 30X30 MDF on the wall.
3. SCOPE OF WORK:
The scope of work includes as follows,
4. Responsibilities:
Project Mr.Senthil – 0526404814
Manager Leads and execute timely completion of work and oversee
the safety of the site.
4. Safety Requirements:
Worker involved must be inducted by Safety officer.
Worker involved must wear complete and proper PPE requirements at all
times.
Worker involved must be MS/RA briefed and recorded.
All workers must be briefed with emergency procedure, Evacuation drill
procedure and general site rules that are followed at Mapei Site.
Material Handling.
Induction and training shall be based on this safety program and shall
include but shall not be limited to:
LOYAL BUILDING CONTRACTING L.L.C.
Persons working at height (i.e on the scaffold) shall be provided with Full
body harness system. Prior to use, make sure that the harness and the
Lanyards are Safe for use.
All persons exposed to operations which subject the eye (OR) face to dust
or flying particles shall use Safety Goggles and Face shield.
6.1EQUIPMENT:
Gypsum Filler
Stainless Steel joint knife
Kraft Tools
6.2 MANPOWER:
Engineer 1 Nos
Workers 3 Nos
6.3 MATERIALS:
7. SCOPE OF WORK:
LOYAL BUILDING CONTRACTING L.L.C.
The scope work involved in fixing of the Gypsum wall joints, Fixing on the
wall MDF access door, double skin plywood fixing on the wooden structure,
and wooden capping fixing.
As an initial step, provide safe access for the site operatives to reach to the work
area.
Obtaining the work permit from the Mapei Client representative and
ensure the work area is safe.
Tool box talk training must be given to the workers about the scope of
work and the risk that are associated with the work must be
communicated.
Job specific instruction must be given by the onsite supervisor.
Providing proper access to the work execution area.
Listed modification works shall be done by complying with the on site
safety rules..
All site rubbish that arises during the modification work shall be stored in
the black cover and at the end of each shift, the waste debris shall be
disposed in the designated area.
8 Methodology:
8.1 Preparation Work:
PPE must be worn at all times.
Aluminium Scaffold shall be provided for all the height work activities.
Ensure that the existing services drawing shall be identified before the
commencement of the work.
All equipment shall be inspected, and all personnel shall be inducted
and trained before the commencement of work on site.
Loyal Engineer shall ensure that prior to commencing work the area of
the gypsum cladding filling shall be established, marked, agreed, and
recorded.
Peel off the paper at the square edge of the boards.
Apply joint filler compound in all the joints to fill the gaps.
Apply joint filler over the mesh and screw positions in level of the boards
and leave it to get dry.
The ceiling shall be finished with the client approved paint, Minimum
two coats of paint must be used.
Up on completion of paint on the filling area, Loyal Engineer will review
the surface preparation before start of final finishing and painting work
Provide the required holes on the wall for fixing of the MDF sheet.
Hang the vertical part of the MDF support to the wall.
Hang the horizontal part of the MDF Support to back of the veneer
panel.
Follow the same procedure for all the rest of the panels.
The initial portion of the plywood shall be fixed with the help of the
screws and it shall be followed for other portions also.
Ensure that the clearance are obtained from the client before fixing the
PVC floor tiles.
Restrict the work area by providing the barricade with warning tapes and
signage’s to indicate the work is under process.
Ensure that the of the floor Tile shall be as per the direction and pattern
agreed with the client.
Tiling should be started from the start point as mentioned by the client.
All the wooden capping that are highlighted by the client shall be
attended by the trained / competent team.
Client approved silicon shall be used for fixing of the capping.
The Team will undertake safety induction /Pre job safety briefings.