Shoe Crane Readyness Check
Shoe Crane Readyness Check
SL.
Parameter Status Remark
No.
OK NOT OK
Discharge chute area ( Skirt rubber and
1 OK
Sealing belt)
6 Grab Condition OK
15 LT lubrication status OK
16 Structure Status OK
18 Any Third party certification due or not OK All thirdparty certification are available
Check for any previous observation of coal PAC point attend by EPC. It will check during coal discharge
19
Leakage operation.
30 Grab Condition OK
39 LT lubrication status OK
40 Structure Status OK
42 Any Third party certification due or not OK All thirdparty certification are available
Check for any previous observation of coal PAC point attend by EPC. It will check during coal discharge
43
Leakage operation.
During trail run we noticed limitswitch for Discharge chute
44 Check the all-limit switches healthiness OK divertor gate found faulty. The same was rectified on 10-02-
2023 & found ok.
Sign Sign