This document is a civil budget summary for an effluent treatment plant construction project by U.S Apparel and Textile Unit 1(US-1R) (Pvt) Limited. It outlines the total approved budget of PKR 61.5 million and payments made to date of PKR 21.7 million, leaving a remaining budget of PKR 39.7 million. It requests an additional budget of PKR 10.16 million to account for inflation and extra civil works required due to rainy season conditions.
This document is a civil budget summary for an effluent treatment plant construction project by U.S Apparel and Textile Unit 1(US-1R) (Pvt) Limited. It outlines the total approved budget of PKR 61.5 million and payments made to date of PKR 21.7 million, leaving a remaining budget of PKR 39.7 million. It requests an additional budget of PKR 10.16 million to account for inflation and extra civil works required due to rainy season conditions.
This document is a civil budget summary for an effluent treatment plant construction project by U.S Apparel and Textile Unit 1(US-1R) (Pvt) Limited. It outlines the total approved budget of PKR 61.5 million and payments made to date of PKR 21.7 million, leaving a remaining budget of PKR 39.7 million. It requests an additional budget of PKR 10.16 million to account for inflation and extra civil works required due to rainy season conditions.
This document is a civil budget summary for an effluent treatment plant construction project by U.S Apparel and Textile Unit 1(US-1R) (Pvt) Limited. It outlines the total approved budget of PKR 61.5 million and payments made to date of PKR 21.7 million, leaving a remaining budget of PKR 39.7 million. It requests an additional budget of PKR 10.16 million to account for inflation and extra civil works required due to rainy season conditions.
Effluent Treatment Plant Civil Budget Summary Plot 729-730-735-736 Sr # Detail Value (PKR)
1 Total approved budget 61,500,000
2 1st running bill Paid 9,235,264
3 2nd running bill paid 12,544,228
4 Paid till date 21,779,492
5 Remaining budget 39,720,508
Inflation adjustment 6 (Cement Steel) 1,805,570 additional Budget required for extra civil work due to rainy season 7 (Earth work, None BOQ work ) 8,354,502