WAKACHIKU PUTRA-JOINT OPERATION Rev.

0 Date 23/05/22
CW PIPE INSTALLATION COAL FIRED 2 x 1.000 MW
CENTRAL JAVA PROJECT Doc Ref. WKC/TR/ERP/002
EMERGENCY STOP DURING CW PUMP RUNNING
DRILL

Drill scenario at barges:


1. Date : Saturday, 28 May 2022
2. Time : SWI Lampung : 09.00 AM – 09.30 AM
Palu Utama : 09.45 AM – 10.15 AM
3. Location : SWI Lampung & Palu Utama Barge
4. Emergency Response Team
 Dive Supervisor SWI Lampung : Alexander Arnold
 Dive Supervisor Palu Utama : Dedi Kusuma
 HSE Department : Sugita, Fariz, Veri, Ridwan Abdul & Ridwan Emen
 CCR Operator : Rudy
5. Tools and Equipment
 Divecom
 Handy Talkie
 Mobile Phone
6. Personal Protective Equipment (PPE)
 Safety Helmet
 Lifejacket
 Safety Shoes
 Eyeglasses
 Dive Equipment

pg. 1
WAKACHIKU PUTRA-JOINT OPERATION Rev. 0 Date 23/05/22
CW PIPE INSTALLATION COAL FIRED 2 x 1.000 MW
CENTRAL JAVA PROJECT Doc Ref. WKC/TR/ERP/002
EMERGENCY STOP DURING CW PUMP RUNNING
DRILL

Drill Scenario Details at SWI Lampung


Time (AM) Action Comment
09.00 Short Briefing & Start Drill – CW Pump running
and Diving activity doing the transfer gravel
(backfilling work) at Intake Head A
09.10 Dive Supervisor unable to contact with the diver
no. 1 then dive supervisor inform to dive tender
to instruct diver no.2 to rescue the diver
09.11 Dive Supervisor calls and informs CCR Operator
(Mr. Rudy) to stop CW Pump

09.14 Dive Supervisor calls and informs CCR Operator


(Mr. Rudy) that diver can contact and return to
the barge
09.18 Dive Supervisor calls and informs CCR Operator
(Mr. Rudy) that diver has return to the barge
safely
09.20 Closing drill & evaluation

09.30 Drill finished

Assessment Yes No Yes No


1. Was drill conducted as per drill guideline ? 5. Was diligence, in general, satisfactory ?
2. Were emergency responses as per 6. Did all equipment function adequately ?
standard procedures ?
3. Were all personnel familiar with their 7. Was a briefing conducted ?
assigned duties ?
4. Was drill conducted safely ? Observer Name : Sign :

Additional Comment / Suggestion:

*Notes: Please put an (X) mark on each assessment poin


pg. 2
WAKACHIKU PUTRA-JOINT OPERATION Rev. 0 Date 23/05/22
CW PIPE INSTALLATION COAL FIRED 2 x 1.000 MW
CENTRAL JAVA PROJECT Doc Ref. WKC/TR/ERP/002
EMERGENCY STOP DURING CW PUMP RUNNING
DRILL

Drill Scenario Details at Palu Utama Barge


Time (AM) Action Comment
09.45 Short Briefing & Start Drill – CW Pump running
and Diving activity doing the transfer gravel
(backfilling work) at Intake Head A
09.55 Dive Supervisor unable to contact with the diver
no. 1 then dive supervisor inform to dive tender
to instruct diver no.2 to rescue the diver
09.56 Dive Supervisor calls and informs CCR Operator
(Mr. Rudy) to stop CW Pump

09.59 Dive Supervisor calls and informs CCR Operator


(Mr. Rudy) that diver can contact and return to
the barge
10.03 Dive Supervisor calls and informs CCR Operator
(Mr. Rudy) that diver has return to the barge
safely
10.05 Closing drill & evaluation

10.15 Drill finished

Assessment Yes No Yes No


1. Was drill conducted as per drill guideline ? 5. Was diligence, in general, satisfactory ?
2. Were emergency responses as per 6. Did all equipment function adequately ?
standard procedures ?
3. Were all personnel familiar with their 7. Was a briefing conducted ?
assigned duties ?
4. Was drill conducted safely ? Observer Name : Sign :

Additional Comment / Suggestion:

*Notes: Please put an (X) mark on each assessment poin


pg. 3
EMERGENCY FLOWCHART DURING CW PUMP RUNNING
LAMPUNG
KLIWON
BARGE CAPTAIN
0813 6840 0066

CW PUMP DAY SHIFT


DIVE SUPERVISOR ALEX
0813 8703 4719

EMERGENCY STOP NIGHT SHIFT


DIVE SUPERVISOR MUZAKKIR
0812 9356 4112

TTM
IIDA
0821 3679 2623
OFFICE
KANEKO
0813 7834 5568
CENTRAL CONTROL ROOM (CCR)
WAKACHIKU
FARIZ
0812 9590 2812
VERI
PERSON IN CHARGE BPI OPERATION DIVISION (RUDY)
0812 5001 1413
HSE ABDUL
TELEPHONE : 1) 0811 1300 3000 0812 2736 1022
: 2) 0813 2962 0055 EMEN
VHF CHANNEL : 164.750 0857 1511 7372
VHF CHANNEL 152.650

SWIJETTY
DHANU
0812 1221 5171
RIKI
HSE 0852 5849 3282
VHF CHANNEL
156.900
EMERGENCY FLOWCHART DURING CW PUMP RUNNING
PALU UTAMA
M. ZAKARUDDIN
BARGE CAPTAIN
0853 7667 1522

CW PUMP DIVE STATION


DIVE SUPERVISOR DEDI KUSUMA
0812 1548 8283

EMERGENCY STOP
JASALINDO
FAHMI
PROJECT COORDINATOR
0812 3900 4301

CENTRAL CONTROL ROOM (CCR)


WAKACHIKU
FARIZ
0812 9590 2812
VERI
PERSON IN CHARGE BPI OPERATION DIVISION (RUDY)
0812 5001 1413
HSE ABDUL
TELEPHONE : 1) 0811 1300 3000 0812 2736 1022
: 2) 0813 2962 0055 EMEN
VHF CHANNEL : 164.750 0857 1511 7372
VHF CHANNEL 152.650