Checklist for Booster/circulation/submersible pump Installation

Ref. : ITP REF.ATR/261/ITP/MEP-06 DATE:23/04/2016


The Client:ABDULLA SAEED AMER AL NEYADI MEP Contractor: AIRTECHNIC
CONSULTANT:ECG REV.0
CONTRACTOR: ARABTEC Checklist No. 1
Drawing(s):2BASEMENT&ROOF WATER SUPPLY DRAWINGS
Work Location:INSIDE BUILDING
Status
S/N Description of Checking to be carried out Remarks
Done Partially done Not Done

1 Check the installed pumps and accessories have approved


submittals

2
Ensure drawings used for installation are latest and approved.

3 Verify the pumps and accessories ,flow and head are as per
approved submittals.

4 Check the installation equipments and accessories are as per


the approved drawing.
5
Ensure installation complies with manufacturer's instructions.
6
Check all nuts, bolts, clamps, etc are tightly fixed and secure.
7 Check the installation of piping and supports are completed as
per the approved shop drawings.

8 Check the control panel are installed as per the approved shop
drawing.

9
Check all the cabling and wiring are completed and terminated.

10 Check and ensure adequate access is available for


maintenance and service including removal of components.
11 Check the identification labels/tags are provided as per the
requirement.
12
Chek foot valves are installed in suction line for booster pump
13 Chek stainer and flexible connectors are installed in suction
line for pumps
Check that all the control panel components are labelled
14 properly.
Ensure the equipments is cleaned and free from dust/debris.
15

REMARKS:
TESTED BY WITNESSED BY APPROVED BY
MEP CONTRACTOR ( AIRTECHNIC ) MAIN CONTRACTOR ( ARABTECH ) CONSULTANT ( ECG )
Name : Name : Name :
Designation : Designation : Designation :

Signature : Signature : Signature :

Date : Date : Date :