CADANGAN MEREKABENTUK, MEMBINA, MENYIAPKAN DAN MENTAULIAH LOJI RAWATAN AIR (LRA) MINI MERANTI

BAHARU, JAJAHAN PASIR MAS, KELANTAN


NO. KONTRAK : AKSB/UKPK/LJ/22/2

As Awarded
Item No. Description Unit Qty. Rate
Amount (RM)
WORK BELOW LOWEST FLOOR FINISH

PILING
A Piling of pump house foundation (29 nos) m 832 50.00 41,600.00

EXCAVATING
B Excavation of pump house foundtaion L.Sum 9,010.00

C For removal of unsuitable material beyond nominal m3 100 21.25 2,125.00


limits of incidential excavation as ordered by the
S.O. Rate to include refilling the excavation with
compacted approved granular material.

STRUCTURAL FRAME AND UPPER FLOOR


PLAIN IN-SITU CONCRETE

Mass Concrete Grade 15


D In tank and chamber blinding layers. Rate to include m2 12 182.75 2,193.00
all necessary formwork.

Mass Concrete Grade 20


E In pipe and valve support, concrete surround to m3 0 233.75 -
pipes, benching and screed to floor, roof and etc.
Rate to include all necessary formwork.

Mass Concrete Grade 25


F In chambers, plinths, pipe supports, trenches, ramp m3 0 246.50 -
and etc.

Reinforced Concrete Grade 30


G In footing, chamber and sump. Rate to include all m3 68 195.50 13,294.00
necessary formwork

Reinforced Concrete Grade 35A


H Supply concrete Grade 35A for contact tank , m3 0 259.25 -
backwash tank and suction tank and all water
retaining structures.

FORMWORKS
Formwork rate shall include providing,
transporting to site, cutting, fixing,
forming shape for concrete casting, etc.

Vertical class F1 formwork to all below ground level


I Generally m2 50 29.75 1,487.50

Vertical class F2 formwork to all above ground


J Generally m2 125 46.75 5,843.75

Total Carried to Collection Page 75,553.25

FORMWORKS (Cont'd)
Vertical class F3 formwork to all internal water
contact faces.
A Generally m2 0 46.75 -

Soffit class F2 formwork


B Generally m2 125 21.25 2,656.25

Soffit class F3 formwork


C Generally m2 185 29.75 5,503.75

REINFORCEMENT
Rate of reinforcement shall include supply,
deliver, cutting, fixing, tying wires,
saddles, spacers, rolling margin, wastage and
etc.

Mild Steel
D 12mm dia. Mild steel bars and below. kg 3,500.00 3.57 12,495.00

High Yield Steel


E T 10mm,12mm dia. High yield steel bars and below. kg 18,000.00 3.57 64,260.00

F T 16mm,20mm,25mm dia. High yield steel bars and kg 25,000.00 3.57 89,250.00
above.

BRICKWORKS
G Supply and fix 230mm brickwall in common cement m2 610 42.50 25,925.00
and sand brick, joint raked in on both sides.

H Supply and fix 115mm brickwall in common cement m2 166 25.50 4,233.00
and sand bricks, joint raked in on both sides.

J Plastering to internal face of brickwall and concrete. m2 776 25.50 19,788.00

K Rendering to external face of brickwall and concrete m2 610 25.50 15,555.00


L Supply and lay damp proof course to brickwall m 65 8.50 552.50

INTERNAL WALL FINISHES

M Supply and paint internal brickwall and concrete m2 776 6.80 5,276.80
faces with two coats of approved emulsion paint.
Rate to include one coat of primer and undercoat as
specified.

EXTERNAL WALL FINISHES


N Supply and paint external faces of concrete walls m2 610 12.75 7,777.50
and brickwall with two coats of approved weather
shield paint. Rate to include one coat of primer and
undercoat as specified.

Total Carried to Collection Page 253,272.80

DOORS
Supply, erect, built in and paint as specified
doors complete with frames, internal and
external locks, ironmongery, door furnitures
etc. as shown in the drawing

A Hardwood flush door, door type D1. Rate to include no 6 365.50 2,193.00
painting with two coats or preservative and fixed
with one layer of 2mm thick SS304 (hairline finish)
plate at external face and all ironmongeries

B Ditto. type D2A.Ditto no 1 620.50 620.50

Aluminium Roller Shutter Doors


C Supply deliver and fix complete motorised no 2 2,737.00 5,474.00
aluminium roller shutter door type RS1 opening
complete with rollers, guide plummet and lock as
shown on drawing. Rate to include push button
mechanism and all fixing accessories to
manufacturer's details.

WINDOWS
Supply, deliver and fix all windows, glass
panels and louvers complete with all aluminium
frame fixed, accessories and glazing as shown
in the drawing.
D Window type L2. no 1 365.50 365.50
E Window type L3. no 8 450.50 3,604.00
F Window type L4. no 2 535.50 1,071.00
G Window type L6. no 5 620.50 3,102.50
H Window type SW2. no 0 620.50 -
J Window type SW3. no 1 620.50 620.50
K Window type SW4. no 5 705.50 3,527.50
FLOOR FINISHES
L Supply and lay as specified hardener finish at m2 75 46.75 3,506.25
pumps area, control room, vsd room, msb/mcc
room, chemical rooms, loading bay including all
cement rendering.

M Supply and lay ceramic tiles for office room m2 25.5 55.25 1,408.88
including all cement rendering.

N Supply and lay none slip resistance ceramic tiles for m2 4.83 63.75 307.91
toilet and laboratory including all cement rendering.

ROOFING
Design and construct complete light weight
roofing system and trusses. Rate to include
50mm thick glass wool on double sided woven
aluminium foil insulation, gutter, 100mm uPVC
class B rain water down pipe (measure
separately), column support, roof truss, etc.

P Roofing m2 450 119.00 53,550.00

Total Carried to Collection Page 79,351.54

ROOFING (Cont'd)

A Supply and build/fix in 100mm dia. uPVC class B m 115 46.75 5,376.25
rainwater downpipe complete with bends and leaf
trap at entrance and outlet specials. Rate to include
galvanized M.S. bracket at 1000mm C/C.

CEILING FINISHES
B Supply and fix 1200mm x 600mm x 13mm thk. m2 25.5 17.00 433.50
Approved mineral fibre board ceiling (class 'O'
rated, set out symmetrically from centre room. Rate
to include one coat of alkali resisting primer, sealer,
one under coat and two finishing coats emulsion
paint, aluminium grid suspension system comprising
main tees, cross tees, wall angles and all
accessories as per manufacturer's detail.

STAIRCASE HANDRAILING

C Supply, paint and fix MS handrailing complete as m 150 97.75 14,662.50


detailed in the drawing. Rate to include all
necessary works.

PLUMBING AND SANITARYWARE


Supply,and install all the piping works and saniatry
pipe including bends, fittings and all other
accessories.
D Toilet LS 425.00
E Sanitaryware LS 1,262.25

Total Carried to Collection Page 22,159.50

Collection Page : Building Work

Page 3.1.3/ 1 75,553.25

Page 3.1.3/ 2 253,272.80

Page 3.1.3/ 3 79,351.54

Page 3.1.3/ 4 22,159.50


Total Amount Carried to Summary (CSA 3.1) 430,337.09