Professional Documents
Culture Documents
Complete Notes of Project Management
Complete Notes of Project Management
Complete Notes of Project Management
Project
Manager have to handle various projects during their careers’ software consultant may need to implement a
database management project, a construction engineering may have to handle the construction project of a
building, a scientist in the research and development department of an organization may be given a research
project and simply, for an entrepreneur, starting a new business or a manufacturing unit is a project, A
project requires manpower, money, material, machine etc.
Example of project
A project is a group of unique, interrelated activities that are planned and executed in a certain sequence to
create a unique product or service within a specific time frame, budget and the client specifications.
or
A project is a set of activities which are networked in an order and aimed towards achieving the goal of a
project. Upon the completion of all the activities the goal of the project would have been achieved. A project
is undertaken to achieve a purpose.
or
A project is a temporary and one time exercise which vary in duration. It is undertaken to address a specific
need in an organization, which may be to create a product or service or to change a business process. This is
in direct contrast to how an organization generally works on a permanent basis to produce their goods or
service.
or
A project may be defined as a series of related jobs usually directed towards some major output and
requiring a significant period of time to perform.
or
A project is a set of activities which are networked in an order and aimed towards achieving the goal of a
project. Upon the completion of all the activities the goal of the project would have been achieved.
Education
Construction
Event
Finance
Human recourses
Software
Research
Management
Management is the techniques of understanding the problem, needs and controlling the use of resources such
as cost, time, management and materials. Management is an optimum use of all the recourses used in the
project.
Management of all activities related to particular project like Time Management, Marketing Management,
Operation Management, Human Resource Management, Finance Management etc.
Project Management
Project Management is planning, organizing, monitoring and controlling of all aspects of a project and
motivation of all involved to achieve project objective of safety and within a defined time, cost and
performance.
or
It is the art of planning, directing controlling recourses like people, equipment, material to meet the cost,
time,, manpower, hardware and software resources involved in a project.
Objective of Project
Other objective of Project – proper safety of people, machine, material and other recourses
Project life cycle/ Process of Project management/ functions of project management/ phases of project
management life cycle
Project life cycle refer to a logical sequence of activities that are performed to achieve project goal of
objective. It can also be termed as project cycle. The life cycle of every major project include seven steps
like
Identification – It refer to selection of one most feasible project idea out of several alternative.
Preparation – It refer to developing the identified and selected ideas.
Appraisal – Perform systematic and comprehensive evaluation of every aspect of the select ideas to
prepare the final project plan. Project appraisal deals with market appraisal, technical appraisal,
financial appraisal, economic appraisal, managerial appraisal, environmental appraisal.
Planning and organizing – It refer to designing the course of actions required to achieve the
objectives of the project like organization structure, manpower, schedule and budget, licensing and
government clearance, infrastructure of project, finance, site preparation, selecting vendors
Presentation – Involve creative a detail plan to send it to appropriate entities
Implementation – It refer to a stage in which the approved project plan is executed. Major bulk of
work (80 – 85%) project is done in this phase like preparation of equipment and machinery, civil
construction, placing orders for recourses, commissioning of plant.
Monitoring – It involve assessing and monitoring the progress of the project at every stage to
identifying the loopholes and take corrective action if required.
Closing – It refer to the formal closure of project. It involve handling over of the facilities built to the
customer ( project accounts are closed, outstanding payment is made, dues are collected, manual and
catalogued are handed over, The employee and other resources are released to be used for other
activities)
Evaluation – Calls for the re assessment of the efficiency and performance of the project after the
completion of project.
Type of projects
Budget of project
Time of project
Risk related to project
Technology used in project
Quality or performance of project
Recourses management
Stakeholder management
Profitability of project
Role and responsibility of Project Manager
The project manager must determine the purpose, goal and constraints of the project.
The project manager must establish basic project management controls.
Project planning puts together are the details of how to meet the project goals, given the constraints.
Managing the time by planning and meeting schedule.
Manage quality so that the project result is satisfactory
Manage cost to see that project is performed at the minimum possible cost within the budge,
Managing communication to see that appropriate parties are informed and have sufficient
information to keep the project coordinated.
Mange the human resource involved in a project effectively.
Mange the project scope of to define the goals and the work o be done in sufficient detail to facility
understanding and correct performance by participants.
To take corrective action.
There is various cause of failure of project failure which are given below
quality of project
duration of project
coordination among various activities
overlapping of activities
customer satisfaction of project
budget of project
managing conflicts among various stakeholders
It is the responsibility of a project manager to manage all stakeholder associated with the project like
Win win situation of all stakeholders
Minimize conflicts among member
No communication gaps with stakeholders
Act as mentor / guide stakeholders
Develop long term relationship with stakeholder
Try to solve their problem / issue of stakeholder
Project Identification
The first steps towards establishing a venture is the search for project ideas that are unique and appear
worthwhile for implementing. The ideas should be sound and workable so that it may exploited.
Identification of business opportunities requires imagination, sensitivity to environmental changes and
realistic assessment of what the firm can do. The world of business offers lots of opportunities but
everybody cannot identify a business opportunity.
Project identification is concerned with the collection, complication and analysis of economic data for the
eventual purpose of locating possible opportunity for investment and with the development of the
characteristic of such opportunities
Searching for idea which is profitable. There should be perfect balanced between demand and skill of
project.
Identifying a new worthwhile project is a complex problem. It involves careful study from many different
angles. Following are some of the sources from which new project ideas may emerges.
Identification process is concerned with conscious identification of a viable product idea that logically
addresses an opportunity. An opportunity is defined as the identification of a gap in need and the
likelihood that if a product was developed to fill the need it would also be wanted. The essential steps for
project identification related to studying the following
An entrepreneur has to screen all the generated project ideas on the basis of well defined criteria so as to
select the best ideas. While selecting the project ideas, the following points need to be considered.
The ideas should match the recourses, knowledge, skills and capabilities of the entrepreneur
It should require such capital, technical knowhow, power, raw material and other inputs which the
entrepreneur can mobilize.
The cost structure of project must ensure a reasonable return on the investment
The project should be compatible with the government policies, environmental regulation, state of
the economy, technological changes and other factors in the external environment
There must be sufficient demand for the proposed product or service.
Capital Budgeting is an important technique of management which is widely used for the evaluation of
various capital investment proposals and for choosing the appropriate source of finance and for
implementation of chosen investment proposal.
Investment decision related to long term assets are called capital budgeting. It involves planning and control
of capital expenditure. The term capital expenditure means the expenditure which is intended to benefit
future period’s i.e. in more than one year as opposed to revenue expenditure, the benefit of which is
supposed to be exhausted within the year concerned.
The payback period is defined as the number of years required for the proposal cumulative cash inflows to
be equal to its cash outflow. In other word, the payback period is the length of time required to recover the
initial cost of the project. The payback period therefore can be looked upon as the length of time required for
a proposal to break even on its net investment. The project should be selected in which payback period is
very less.
According to this method, the capital investment proposals are judge on the basis of their relative
profitability. For this purpose, capital employed and relative income is determined according to commonly
accepted accounting principle and practice over the entire economic life of the project and then the average
yield is calculated. Such a rate is termed is the accounting rate of return. The ARR is also known as Return
on Investment (ROI).It is the ratio of average after tax profit to average investment. The project should be
selected in which there is high accounting rate of return.
ARR = Average annual profit after tax / Average initial investment * 100 or average inflow / original
investment / 2 *100
3-Net Present Value (NPV) –The cash inflow in different year are discounted (reduced ) to their present
value by applying the appropriate discount factor or rate and the gross or total present value of cash flows of
different years are ascertained. The total present value of cash inflow are compared with present value of
cash outflow (cost of project) and the net present value or the excess present value of the project and the
difference between total present value of cash inflow and present value of cash outflow is ascertained. The
project should be selected which have positive NPV and should be rejected when NPV is negative.
4-Profability Index (PI) Method –Profitability index refers to the ratio of discounted benefit over the
discounted costs. It is an evaluation of profitability of an agreement of an investment can be compared with
the profitability of other similar elements which are under consideration. The probability index is also
referred to as benefit – cost ratio, cost benefit ratio or even capital rationing. The project should be selected
if NPV is greater than 1 and should be rejected when NPV is less than one.
The second discounted cash flow or time adjusted method for appraising capital investment decision is the
internal rate of return method. This techniques is also known as yield on investment, marginal efficiency of
capital, marginal productivity of capital, rate of return and the time adjusted rate of return and so on. The
internal rate of return is usually the rate of return that a project earns. It is defined as the discount rate which
equals the aggregate present value of the net cash inflow with the aggregate present value of cash outflow of
a project. In other word, it is that rate which gives the project NPV of zero.
IRR = lower rate + positive NPV / positive NPV –negative NPV * Higher rate – lower rate
Numerical
Future Value = Present Value (1+rate)n and Present Value = Future Value/(1+rate)n
1. The expected cash flow of a project are as follows:
Year 0 1 2 3 4 5
cash flow 100000 20000 30000 40000 50000 30000
The cost of capital is 12%. Calculate the following using (i) PB (ii) NPV (iii) PI (iv) ARR (v) IRR
Solution – (i) PB 20000+30000+40000+ 10000 / 50000 = 3.20 years
(ii) NPV = 17860+23910+28480+31800+17010 – 100000 = 19060
(iii) PI = 119060 / 100000 = 1.19
(iv) ARR = 20000+30000+40000+50000+30000 / 5 / 100000 /2 * 100 = 68%
(v) IRR NPV at 18% = 16940+21540+24360+25800+13110 – 100000 =1750
NPV at 19% = 16800+21180+23720+24950+12570 – 100000= -780
IRR = 18 + 1750 / 1750 – (-780) * (19 -18) = 18.69
2. The expected cash flow of a project are as follows:
Year 0 1 2 3 4
cash flow 10000 1000 1000 2000 10000
The cost of capital is 14%. Calculate the following using (i) PB (ii) NPV (iii) PI (iv) ARR (v) IRR
(Ans – (i) 2.85 (ii) NVP (iii) PI (iv) ARR (v) 10.22% )
3.The expected cash flow of a project are as follows:
Year 0 1 2 3 4 5
cash flow 50000 10000 10692 12769 13462 20385
The cost of capital is 10%. Calculate the following using (i) PB (ii) NPV (iii) PI (iv) ARR (v) IRR
(Ans (i) 4.32 (ii) -4648 (iii) 0.90 (iv) 34.6% (v) ARR
4.The expected cash flow of a project are as follows:
Year 0 1 2 3 4 5
cash flow 56225 3375 5375 7375 9375 11,374
Total
=36,875
(i) ARR =average income / average investment * 100 = 7375 / 28112*100 = 26% (here 36875/5
=7375 and 56225 /2 =28112)
(ii) PB = 3375+5375+7375+9375+11,375 = 3 year and 6364/20620 month
(iii) NPV =present value of all cash inflow – outflow
(iv) IRR rate at which NPV =0
(v) PI =present value of all inflow / outflow
Quality
Generally, it can be said that a product is of satisfactory quality, if it satisfies the customer. The customer
will buy product a product or service, only if it meets his or her minimum needs. Thus customer satisfaction
is the main criteria for determining whether a product possesses the required quality or not. Therefore
customer wants are first assessed by marketing people and then quality decision is taken on the basis of such
information. In order to define quality, therefore, we have to think of it in term of some use. The term
quality can be defined as the sum totals of feature of a product which influences its ability to satisfy a given
demand. It is also known as “fitness for use”. It is decided by customer. It is also considered as the sum total
of the attributes or properties that describe a product. A product quality should control at every stage of
transformation like input (material, machine), transformation (process) and output.
Design Quality
The design of a product or service must incorporate that feature and attributes that would satisfy the
customer need. While designing product or service, there are various characteristic should be considered.
The characteristics for product or service may be different.
Project Evaluation
Project evaluation is a systematic process of recording and analyzing project performance and output and
controlling them with pre determine standards .It is the process of analyzing and comparing the end result of
the project with pre-determined result. Project evaluation aim to identify the weakness of a project and
improve them. Project evaluation is a systematic process of recording and analyzing project performance
and output and comparing them with pre-determined standard
Objective of project evaluation
Identifying the progress of the project
Completing the project within allocated time and recourses
Responding to the demand of customer
Justifying the employment of team member to achieve goal of the project
Compare the actual performance with planned one
Locating the resource of the organization effectively.
Technical analysis
Type of technology
Cost of technology
Benefits of technology
Avaibility of technology
Risk in technology
Source of technology
Economic Analysis
National income
Inflation
Stock market
Employment
Infrastructure
Banking sector
Per capita income
Financial Analysis
Sources of fund
Use of fund
Cost of project
Probability of project
Financial risk
Social Analysis
Benefits of project
Cost of project
Impact of project
Nature of pollution
Institutional Analysis
Organization structure
Value system
Organization policy
Skills available in organization
Network Analysis
A network diagram is a model that uses small circles (nodes) connected by lines or branches to represent
precedence relationship. Networks are frequently used to show the precedence relationship among the
activities. CPM & PERT are network technique for analysing a system in term of activities and events that
must be completed in a specific sequence in order to achieve a goal.
Limitation of PERT
The basic difference comes in the way of time estimates for the completion of activities because
activities are of non – repetitive.
This technique does not consider recourses required at various stages of the project.
Use of these techniques for active control of a project requires frequent updating and receiving the
PERT calculations and this proves quite a costly affairs.
Limitation of CPM
CPM fails to incorporate statistical analysis in determining the time estimates
It operates on the assumption that there is a precise known time that each activity in the project will
take but this may not be true in actual life.
It is difficult to use CPM as a controlling device for the simple reason that one must repeat the entire
evaluation for the reason that one must repeat the entire evaluation of the project each time when
changes are introduced into the network. It may be remembered that CPM was initially developed as
a static planning as a static planning model and not as a dynamic controlling devices.
Crashing of Network
Crashing is employed to reduce the project completion time by spending extra resource cost. However,
beyond point a cost increase more quickly when time is reduced. Similarly, beyond point B, the time
increase whiles the cost decrease. Since for technical reasons, time may not be reduced in definitely point.
Therefore we call this limit crash point. There is also a most cost efficient duration called normal point.
Thus extending the activity duration beyond normal point may increase costs. It is clear that, one must be
interested in the critical region of the curve contained between point A and B to establish a trade off between
time and cost, the direct cost of completing an activity per unit time is completed as follows:
Cost slope = crash cost – normal cost / normal time – crash time.
Numerical of networking analysis
Total float – The amount of time by which completion of an activity could be delayed. It can be calculated
as LST –EST
Free float – The time by which the completion of an activity can be delayed beyond the earliest finish time.
It can be calculated as Total float – Head slack
Independent float – The amount of time by which the start of an activity can be delayed. It can be calculated
as Free float – Tail slack
Independent float < Free float < Total float
Slack vs Float – The basic difference between slack and float times is that slack is used for events only
whereas float is applied for activities.
Average = a+4m+b / 6
Variance = square of b-a / 6
The critical path is 1-6-7-8 and the project length is given by 6+11+27 = 44 day
Variance = 4+16+16 = 36
Standard Deviation = 6
The probability of completing the project within 31 days is given by Z = 31 – 44 / 6 = 2.16 = 0.48 (using
table)
Hence required probability is 0.50 – 0.48 = 0.0114 or 1.14%.
3. Draw network diagram, Critical path, total float, free float and independent float.
Activity: A B C D E F G H I J K L
Predecessor Activity: - A A B B C C F D G,H E I
Time: 10 9 7 6 12 6 8 8 4 14 5 7
(Critical path is A-C-F-H-J = 42)
4. Draw network diagram, Critical path, total float, free float and independent float.
Activity: A B C D E F G H I J K
Predecessor Activity: - A B C B E D,F E H G,I J
Time: 13 8 10 9 11 10 8 6 7 14 18
(Critical path is A-B-E-F-G-J-K = 82)
5. Draw network diagram, Critical path, total float, free float and independent float. Find the probability that
project is complete in 31 days
Job: 1–2 1–6 2–3 2–4 3–5 4–5 5–8 6–7 7-8
a: 3 2 6 2 5 3 1 3 4
m: 6 5 12 5 11 6 4 9 19
b: 15 14 30 8 17 15 7 27 28
6. Draw network diagram, Critical path, total float, free float and independent float. Find the probability that
project is complete in 60 days
Job: 1-2 1-3 2-3 2-4 3-4 4-5
a: 3 8 1 2 8 14
m 4 12 2 3 10 22
b: 54 16 3 5 12 25
(Critical path 1-2-3-4-5 = 76.5 and probability is 60 – 76.5 / square root of 19.92 = 3.69 = 0.011
7 Network diagram, Critical Path. Find EST, EFT, LFE, LST, Total Float, Free Float and Independent Float
Find the probability that the project is completed in 11 days.
Activity :A B C D E F G
Predecessor Activity :- - A A B C D,E
a : 2 2 1 4 4 3 1
m : 3 3 2 6 5 4 1
b : 10 4 3 14 12 5 7
(Critical path is 13 days and probability is 11-13 / 2.3 = .30 and required probability is 0.5 – 0.3 =19%
8. Network diagram, Critical Path. Find EST, EFT, LFE, LST, Total Float, Free Float and Independent Float
Find the probability that the project is completed in 35 days.
Activity :A B C D E F G H I J
Predecessor Activity :- - - A A A B,C C D E,F
a : 4 1 2 1 1 1 1 4 2 6
m : 4 2 5 4 2 5 2 4 2 7
b : 10 9 14 7 3 9 9 4 8 8
(Critical path is C-D-G-J =16 days and probability is 35-16 / 2.4)
Project team development / team building process / stages in deploying high performance project
team
The different stages of the project team
Forming stage (orientation – grouping of activities)
Storming stage(dissatisfaction – conflicts among members)
Norming stage(resolution – conflict resolution through negotiation)
Performing stage (production – implementation, team commitment to work)
Project Monitoring
Project monitoring refers to the process of evaluating the progress of project activities. It is a continuous
process of determine the actual status of a project in relation to the estimated time and cost. The main
objective of monitoring is to improve the performance of project by assessing the potential risk involved in
the project and identify the main cause of error in the project.
The project manager monitors project activities to
Assess the risks involved in a project
Identify the main cause of delay in the completion of the project
Recognize the factors that affect the progress of the project
Measure the actual performance of the project
Project controlling
Controlling involves the measurement of actual performance; comparing it with the planned performance
and correcting deviation to ensure attainment of predetermine project objectives. Thus controlling ensuring
that actual performance conforms to planned performance as closely as possible. There is a close inter
relationship between planning and control function. Planning serves as basis of control. The plan act as the
standard for evaluating actual. Planning can achieve nothing without control of actual observation. The
control can be related to like finance control, budgetary control, quality control, marketing control, human
recourse control, information technology control etc. Project control serves two major functions
It ensure regular monitoring of performance
It motivate project employee to strive for achieving project objectives.
Project controlling aim at reducing the gap between the actual performance of a project and the
expected performance activities such as planning, organizing and controlling
Purposes of controlling
Creating better quality
Coping with changes
Creating faster cycles
Adding value
Facilitating delegation and teamwork
Type of control
(i) Feed forward - It is preventive control that attempt to identified and prevent deviation in the
slandered before their occurrence
(ii) Concurrent control – It is performed when a project activity is in progress. It regulate ongoing
activities and ensure that they must follow the organizational standards
(iii) Feedback control – It focus on the output after project is completed. It is applied to check
whether the actual information is per the set standard.
Project appraisal is carried out by the financing agencies to ensure the viability of the project. The various
factors to be considered by the institution for project appraisal.
Risk can be defined as the chance that the actual outcome from an investment differs from the expected
outcome. Within the context of project, risk is commonly associated with an uncertain event or condition
that if it occurs has a positive or a negative effect on a project objective.
Risk management is the discipline of identifying monitoring and limiting risk. Risk can come accident,
natural cause and disaster as well as deliberate attracts from an adversely. In business risk management
contains organized activity to manage uncertainty and threats.
Risk Response
(a) Project specific risk – It is the first sources’ of risk in which an individual project may have higher or
lower cash flow than expected,either because the firm misestimated the cash flow for that project or
because of factor specific to that project. When firm take a large large number of similar projects, it
can be argued the much of the risk should be diversified way in the normal course of business.
(b) Competitive risk – It is the second source of risk, herby the earnings and cash flow on a project are
affected (positively or negatively) by the action of competitor. While a good project analysis will
build in the expected reaction of competitor into estimates of profit margin and growth, the actual
action taken by competitor may differ from this expectation. In must case this component of risk will
affect more than one project, making it more difficult to diversify away in the normal course of
business by the firms
(c) Industry specific risk – It is the third source of risk – those factor that impact the earnings and cash
flow of a specific industry. These are three source of industry – specific risk, which are as follows
(i) Technological risk
(ii) Legal risk
(iii) Commodity risk
(d) International risk – It is the fourth risk. firm faces this risk when it generate revenue or has costs
outside its domestic market. In such case ,the earnings and cash flow will be affected by unexpected
exchange rate movement or by political development
(e) Market risk – it is the final sources’ of risk. Macroeconomic factor that effect essentially all
companies and all project to varying degree.
There are various techniques to handle risk which are stated below
(a) Sensitivity analysis – It is a technique that measure the change in the profitability of a project caused
by the change in the profitability of a project caused by changes in the factors that affect the cash
inflow of the project. If a small change in one factors leads to a major changes in the profitability of
the proposed investment, the project is considered more sensitive to that factors. In other word, the
project is more risky, other thing being equal, a project that is less sensitive is preferalable of any
measure of profitability 9NPV,BEP or any other measure ) to change in critical factors. Sensitivity
analysis provides the management the much needed information as to which are the critical factors
that is prone to effect the profitability of the project.
(b) Scenario analysis – In sensitivity analysis, typically one variable is vested at a time. If variable are
interested as they are most likely to be, it will be helpful to look at some scenario, each scenario
representing a consistent combination of variables.
(c) Monte Carlo simulation analysis – Monte –Carlo method of simulation is a technique in which
statistical distribution functions are created by using a series of random numbers. This method of
simulation is generally used to solve problems which cannot be adequately represented by
mathematical models or where solution of the model is not possible by analytical method. This
method of simulation yields a solution that converges to the optimal or correct solution as the
number of simulated traits leads to infinity.
(d) Decision tree analysis – decision tree approaches is a graphical technique that can be used for
analyzing the pros and cons of alternative decision and choosing the best possible courses of action.
In real situation decision are taken condition of uncertinity.In project project management this is
more so in view of the multiplicity of factors involved. A decision tree is a diagrammatic
representation of the logical relationship and the possible outcomes of different decisions
Benefits to society
Generate employment
Increased feeder service
Living standard of people
Developmement of infrastructure
Resources’ utilization
Cost to society
Air pollution
Noise pollution
Land pollution
Water pollution
Deforestation
Group
A group is an aggregate of person with close inter relationship or a group is any number of people who
interact with one another are psychologically aware of one another and perceive themselves to be a group.
Two or more interacting and interdependent individuals who come together to achieve particular objectives.
Group Dynamics
The term dynamics implies changes taking place within the group as a result in any part of the group.
Reason for formation of group
Desire to socialize with each other
Common interest
Sense of identity
Sense of security
Sources of information
Monotones jobs
Communication device
Group development
Forming – work group is born and group members try to comprehend
Storming – once the formal group is created, internal subgroup arises.
Norming – during this stage dormant disagreement and power issues are worked out.
Performing – this stage is reached when collaboration among the group members is at highest
Type of group
Formal group –formal group are deliberately created to accomplish some common goals.
Informal group – within the conflicts of the formal organization structure there exist informal group of
people. Such group arises spontaneously through interaction among people who are in frequent contest with
one another.
What is a Team?
Formal group made up of interdependent individuals, responsible for attaining a goal.
Type of Team
(i) Functional team – A type of work team that is composed of a manager and his or her
subordinates from a particular functional areas
(ii) Self directed or self – managed team – A type of work team that operates without a manager and
is responsible for a complete work process or segment that deliver a product or service to an
extent or internal customer.
(iii) Cross –functional team – A type of work team in which a hybrid grouping of individual who are
expert in various specialist (or functional) work together on various organizational tasks.
Characteristic of Team
Less conflicts in team
More group cohesiveness
Company objective is more important than personal objective
Participating decision making
Respect for each other
Less politics or manipulation in group.
Clear goal
Mutual trust
Good communication
Internal and external support
Appropriate leadership
Small number of people
Complimentary skill
Common purposes and performance goal
Importance of team
Enhanced performance
Employee benefit
Reduced cost
Organization enhancement
Managing Team
Planning
Organizing
Leading
Controlling
Leadership
The ability to influence a group towards the achievement of goal or those who are able to influence others
and who posses’ managerial authority.
Manager vs Leadership
Manager Leader
Have authority may or may not have authority
Appointed by company may or may not appointed
Should have leadership quality may not have official authority
Significance of leadership
Setting goals
Motivating employees
Building moral
Creating confidence
Maintaining discipline
Developing team work
Facilitate change
Representing the group
Quality of a leadership
Physical qualities – sound health, vitality, endurance, physical and energy and enthusiasm
Intellectual qualilities – high intelligence, sound judgment, ability to teach, scientific approach,
decisiveness, self understanding
Moral qualities – integrality, fair play, moral courage, will power, sense of purposes,
achievement drive, objectivity
Social qualities – ability to inspire, tact, persuasiveness, self-confidence, empathy, initiative,
knowledge of human nature, human relations, attitude
Function of a leader
(i) Setting and achieving organizational goals
(a) Goal setter
(b) Planner
(c) Executive
Approaches of leadership
(i) Trait approach
Theory that sought personality, social, physical or intellectual traits that differentiated leader from
non leader or theories isolating characteristic that differentiate leader from non leader.
Six traits the differentiate leader from non leader like
Desired to lead
Drive
Honesty and integrity
Self confidence
Intelligence
Job relevant knowledge
(a) Initiating structure – The extent to which a leader is likely to define and structure his or
her role and role of subordinates in the search for goal attainment.
(b) Consideration – The extent to which a leader is likely is likely to have job relationship,
characterized by mutually trust, repeat for subordinates ideas and regards for their
feelings.
The Michigan group also comes up with two dimension of leadership behavior that they
labeled employee oriented and production oriented.
(a) Employed oriented leader – one who emphasis interpersonal relation.
(b) Production oriented leader – one who emphasis technical or task aspect of the job.
A two dimensional portrayal of leadership based on concern for people and for production.
A 9 by 9 matrix outline outline 81 different leadership styles. Blake and mountain proposed
a managerial grid based on the style of “concern for people” and “concern for production”.
Although there are 81 positions on the grid, the five key position identified by Black and
Mountain.
(a) 1.1 (improvershid) – the leader exerts a minimum of efforts to accomplish the work
(b) 9.1(Task) – the leader concentrate on task efficiency but show little concern for
development and morale of subordinated.
(c) 1.9 (country club) – the leader focus on being supportive and considerate of subordinates
to the exclusion of concern for task efficiency.
(d) 5.5(middle of the road) – the leader maintain adequate task efficiency and satisfactory
morale.
(e) 9.9 (team) – the leader facilitate task efficiency and high morale by coordinating and
integrating work related activities.
Likert and his associated of the University of Machigan conducted an extensive survey of management
styles and developed a continuum of four system of management which are given as
System 1 – Exploitative autocrats
The manager under this system make all work related decision and order their subordinates to carry out the
decision. The manager also define slandered and method of performance.
System 2 – Benevolent Autocrat
System 2 manager are also autocrats but they are not exploitative. They adopt a paternalistic approach
towards the subordinates. They allow some freedom to subordinates to carry out their tasks within the
prescribed limits.
System 3 – Consultative
Manager under this system set goals and issue order after discussing them with the subordinates. They take
major decision themselves and allow subordinates to make the routine decisions. Subordinates are free to
discuss the work related matters with the manager.
System 4 – democrative
Under this system, goal are set and work – related decision are taken by the subordinates manager are
friendly and supportive in their attitude towards the subordinates. Subordinates are permitted self appraisal
on the basis of mutually set goals.
(vii) Leadership Style
On the basis of how leader use their, leadership style can be classified into three broad categories
(a) Autocratic or Authootarian leadership
An autocratic leader exercise complete control over the subordinates. He centralized power in
himself and takes all decision without consulting the subordinates. He dominated and drives his
group through coercion and command. He loves power and never delegates authority. The leader
given order and expect the subordinates to follow them unquestioning. He uses rewards and hold and
threats of penalties to direct the subordinates. He does not delegate authority.