CABLE TRAY & CABLE LAYING INSTALLATION CHECKLIST

RFI No : Date of Inspection :


Location :

Sl.No Description Checked Checked


Remarks
Contractor Consultant
Confirm all the Electrical/Instrumentation equipments are complaince with the
1
project specification requirements

2 Confirm the material receiving inspection & FAT reports.

Cables trays/ladders are to be installed as detailed in the Approved cable tray /


3
Ladder layouts.

4 Location of installation as per approved drawings.

Verify the size and type of electrodes/ rods & other accessories. Ensure span between
5 each threaded rods.

6 Depth of trench and conductors protection as per drawings.

7 Avoid sharp bends and narrow loops.

8 Size as per approved cable schedule.

9
Color identification for all cables/ wires is as per AFC Drawings (Cable schedule &
9 Wiring diagrams)

10 Confirm minimum trench depth as per approved layout drawings.

11 The segregation between cable as per layout drawings & project speciation’s.

12 Check minimum recommended Bending Radius. ID tags on the both ends.

13 Cable gland size and type as approved.

Verify the cable protection cover like sand cover, warning tape and protection tiles for
14
direct buried cables in the trench.

15 Cable entry sealed with approved compound.

Verify all cable accessories and termination material is used in the panel/ junction
16
box/ terminal box is approved by client.

17 IR and continuity test with megger as per voltage rating of cables.

Consultant's Comment :

Name /Signature

Contractor Representative Consultant Representative

N.B:
· The Check on above structure does not relieve the Contractor of his contractual obligations under the Contract.