Professional Documents
Culture Documents
Construction Management Case Studies A Lifetime of Lessons
Construction Management Case Studies A Lifetime of Lessons
Case Studies
A lifetime of lessons-learned
examined over 275 practical
examples
by Len Holm
2022
Notes
Contents
Page
Preface v
List of figures xi
Chapter 1 Project owners and developers 1
Including discussions regarding owner’s representatives
and sustainability
16 case study examples
Chapter 2 Design teams: Architects and engineers 21
15 case study examples
Chapter 3 Construction company organizations 37
15 case study examples
Chapter 4 Preconstruction, Including
permits 51
15 case study examples
Chapter 5 Contracts 67
Including procurement, delivery, and pricing methods
14 case study examples
Chapter 6 Estimating and bidding 83
Including marketing, proposals, and interviews
18 case study examples
Chapter 7 Scheduling and schedule
control 105
Including liquidated damages
15 case study examples
Chapter 8 Jobsite operations 115
Including means and methods, jobsite organizations
and field personnel
15 case study examples
Chapter 9 Superintendents 131
17 case study examples
Page
Chapter 10 Subcontractors and material
suppliers 147
14 case study examples
Chapter 11 Communications 161
Including drawing reading
15 case study examples
Chapter 12 Construction controls 175
Including quality and safety controls,
and construction management tools such as submittals
15 case study examples
Chapter 13 Cost accounting and cost
control 189
Including pay requests, activity-based costing,
and lean construction techniques
16 case study examples
Chapter 14 Change orders and claims 201
Including negotiations
16 case study examples
Chapter 15 Construction completion 221
Including punch list, close-out, testing, and inspections
15 case study examples
Chapter 16 Leadership 237
Including ethics and careers
18 case study examples
Chapter 17 Advanced case studies 253
16 case study examples and potential advanced exercises
Chapter 18 Applied construction projects 295
12 case study projects
Appendices:
Abbreviations 307
References 315
Author background 316
Preface
I have been gathering real and interesting project experiences over the past
50 years. Some of those have been great, and others not so. But we can
learn from all of our experiences, regardless. I have been sharing a few of
those in my other books (see references in appendix) as short boxed-in
examples. With this book I have gathered over 275 case study examples or
stories all in one place. Writing the book was very fun. Exploring these
project experiences caused me to reflect on what happened, the good, the
bad, and the worse, and what I will do next time. I hope it will have the
same result with readers. The origins of the stories are primarily from the
hundreds of projects I have participated in. Some date as far back as when I
was only 10 years old working for my father’s company and others current
as of this writing. The experiences are not hypothetical, but they reflect
actual construction projects. My involvement has ranged from carpenter
and foreman through project manager and senior project manager,
construction company owner, estimating and scheduling consultant, and
now as owner’s representative and expert witness.
Most construction management textbooks use hypothetical examples. The
case study examples here outline activities and behaviors of actual project
owners, designers, general contractors, project managers, superintendents,
and also real craft workers, such as carpenters and electricians; and real
subcontractors, such as earthwork and drywall, etc. It takes people to build
buildings, and the examples included in this book explore the relations
among all these built environment participants. The actual names have all
been removed so any connection with real companies or individuals is
coincidental. After finishing the book the reader will have added many
important construction management tools to their toolbox.
There are many practical uses for the book. First of all, it is fun to read. One
finds themselves saying: “Did that really happen? Why did he or she do
that? This of course wouldn’t happen on my job.” But of course strange
things do happen, especially on construction projects. There is a lot of
money at stake, and money causes people to do some uncharacteristic
things. Some of their actions are unethical and others, unfortunately, may be
illegal. This book could work as a standalone course in a construction
management or construction engineering university program, especially at
the senior undergraduate level or at the master level. It would be perfect for
a course seminar. Complete project descriptions from Chapter 18 could be
combined with specific examples threaded throughout the book and
presented in a class or seminar, even debated. It would also be a good
accompany book for any construction management topic such as
estimating, scheduling, contracts, project management, claim resolution,
and others. The book would be a perfect fit for an industry seminar
conducted for construction professionals or internal training for a
contractor. If you could add only one construction management book to
your library, this one would be a good choice.
I have written two case study books prior, Who Done It, 101 Case Studies in
Construction Management, 2nd edition, published by Amazon and more
recently 101 Case Studies in Construction Management published by
Routledge. The second book added brief topic narratives and figures and
tables to the first book. Both books are written in more a “who done it” or
“Where’s Waldo?” fashion, forcing the reader to solve the problem or
debate (who is at fault?) in somewhat a mystery novel approach with no
clear villain. Although this new book asks questions of the reader as well,
the answers as to why something occurred and what is the right approach
are either readily apparent in the narrative or are resolved from logical
deductions and practical experience. Each of these stories provide a lesson
regarding the proper approach to numerous construction management
issues. As indicated, a handful of my boxed-in examples from my other
publications have provided seed topics for a few of these case studies. But
now those examples are expanded, with additional background, which
allow the reader to draw conclusions from these scenarios.
With this book I am intentionally staying away from excessive academic
jargon and not getting into the weeds with respect to complicated
terminology. This material was not developed as someone’s doctoral
dissertation; it is rather a practical and easy to read tool for students and
professionals alike to learn more about construction management. In
construction we use many abbreviations, acronyms, and slang, it is almost a
different language. I have included many interesting construction terms (but
no expletives!) in the body of the work; these also being applicable tools for
the construction student and professional. The focus of this book is
primarily on the construction contractor. These examples are geared for
construction management and construction engineering students and
construction professionals wanting to enhance their management
capabilities. The book’s focus is on practical construction management
tools learned through a lifetime in the industry. As presented, these lessons
should help contractors successfully build their projects.
The book includes 18 chapters organized along many popular construction
management topics; from owners and architects through estimating,
contracts, operations, and close-out. Each chapter includes a list of 15 or so
case study examples specific to that chapter topic. Many case studies
overlap with other topics. For example: “The owner and architect let
documents for bid and an estimate and schedule are prepared resulting in a
contract agreement. Over the course of construction many cost, schedule,
quality, and safety issues arise. Hopefully not too many safety issues! Pay
requests are developed monthly and change orders occur throughout. The
project is closed out and of course both good and bad construction
leadership examples happen on every project.” So this example could have
been included with many chapters, but I have placed it where the lessons
learned can be emphasized the most. These types of overlaps are outlined
with every chapter. Every chapter also includes photographs of actual case
study projects and other pertinent figures.
The 18 chapters each begin with a brief overview or introduction of the
topic and then the case study examples are examined in detail. There are
over 275 case studies and many have sub-parts (A, B, C), resulting in
approximately 100 additional examples. Every case study begins with an
introduction to the topic, such as contracts or change orders and their
applications to a specific example project. Then a unique project experience
is introduced and examined and often a conclusion is reached. Questions
are raised within the body of each case study and others are posed at the
end. All-in there are thousands of questions raised and if a facilitator
combined some of the advanced cases from Chapter 17, or the projects from
Chapter 18, with shorter detailed examples presented in earlier chapters, the
possibilities are limitless. A few blank lines have been included after each
case study allowing the reader to take notes and resolve some of the
questions posed. A separate long list of all the case study titles is available
from the author.
The chapters are presented in the relative order a true construction project
would experience. The project owner and architects are first introduced, and
then construction organizations are examined. The construction process
from preconstruction and contracts is followed through to project close-out.
The book can be read in the order introduced below, or the reader is
encouraged to dive into a topic that is of interest at that time, such as
scheduling. Because other case studies and chapters are referenced with the
introduction of each chapter and also within individual narratives, the
reader can follow that thread throughout the rest of the book, for example
from schedule to estimate and contract to claims and close-out.
Chapter 1 includes 16 case study examples focused on the individual or
company at the top of any project organization chart, the project owner or
client. Real estate developers in the private construction arena often take a
unique path, and these are also discussed. Ideally each client has a
designated owner’s representative and their role, along with owners’
outlook on sustainability goals, has been included. The next Chapter 2
examines the role of the design team and their relations to project owners
and general contractors (GCs). 15 different case study examples include the
roles of the project architect and design engineers. Construction company
organizations is the title of Chapter 3. These 15 different cases discuss GC
and construction management (CM) home office issues and how the home
office connects with project owners, architects, and most importantly, the
jobsite teams. Contractors hope to be contracted early in the design process
and negotiate preconstruction contracts with their clients. This affords them
an opportunity to influence the design and potentially reduce or eliminate
other prime contractors which may also be interested in the project. Chapter
4 includes 15 interesting examples of preconstruction services and permit
coordination. Just about every chapter and every case study have some
connection with construction contracts discussed in Chapter 5. The contract
is the most important document on any construction project and its
connection to estimating, organizations, scheduling, close-out, change
orders and others is paramount. There are 14 examples included here which
examine the contract agreement, or sometimes, the lack of a good
agreement.
Chapter 6 focuses on the important CM building block of estimating and
bidding. If a contractor cannot prepare accurate cost estimates and
successful bids, they will soon be out of business. There are 18 applicable
case studies in this chapter involving estimates, estimators, bids, marketing,
proposals, and interviews. Dozens of other cases in other chapters also
connect with this important building block. Chapter 7 includes the other
basic CM foundation building block, scheduling and schedule control.
These 15 interesting examples discuss the schedule as both a date and a
document and the role of schedulers. Liquidated damages are a risk every
contractor should consider when bidding or signing a contract and these are
explored as well. Jobsite operations is a very broad topic and is the focus of
Chapter 8. 15 case study examples have been included in that chapter which
cover the contractor’s choice of means and methods, the jobsite
organization or team, and field personnel. This discussion includes the
project superintendent (also the focus of the next chapter), project manager,
project engineers, foremen, and the most important team members,
construction craftsmen. The role of the contractor’s field general, field boss,
superintendent, and a lot of other well-deserved titles is then explored with
17 specific examples in Chapter 9.
Unfortunately many CM books focus solely on the role of the GC or CM
and lightly cover the role of the companies which perform 80% to 90% of
the work, subcontractors (or specialty contractors) and material suppliers. A
complete case study book could be written based on subcontractor
activities. 14 specific examples are included in this Chapter 10 but scores of
others in the book connect with specialty contractors. Construction
communication tools are the topic of chapter 11. Communication skills are
a valuable leadership trait and this applies to construction as much, if not
more, than any other industry. The 15 cases in this chapter are not the only
ones in the book which involve communications, essentially all 275
examples are about communications, or lack of effective communications.
Chapter 12 on construction controls builds on the jobsite operations
introduced in Chapter 8. Schedule control and cost control have their own
dedicated chapters, but quality control and safety control are case studied in
these 15 examples. Discussions of many CM tools including submittals are
evaluated here as well. Communication discussions from Chapter 11 and
this chapter on construction controls have many overlapping themes. The
‘control’ area which often gets the most CM focus is cost control. Chapter
13 combines cost control with cost accounting, pay requests, activity-based
costing, and lean construction techniques. These 16 case study examples
focus on all these important jobsite cost areas.
Many of the hundreds of examples in this book unfortunately (or
fortunately depending on your perspective) connect with change orders and
claims. Dispute resolution and negotiations have been added to the mix of
16 high-profile case study examples included with Chapter 14. Chapter 15
includes 15 examples discussing one of the most important, but arguably
the worst performed, contractor function – construction completion. There
are many physical and managerial activities necessary to successfully close
out a construction project. Many good and bad examples of these activities
are covered including punch list, testing, and inspection. If a contractor
wants to receive its retention, which often approximately equals its fee, it
needs to expeditiously close out the project. During the early organization
of these hundreds of case studies into chapters, at one time it appeared that
all would be included in Chapter 16 on leadership. Many cases included in
other chapters have a direct connection with this chapter. 18 specific
examples of ethics, career choices, and construction leadership are
examined here. The role of the construction leader is not covered in other
business leadership books and the reader will find these experiences as
valuable lessons learned.
Chapter 17 is the longest chapter in the book. 16 case study examples were
identified and separated from the previous chapters as they are more
advanced. These stories are complicated and invite a longer read and
potentially outside research. Some of these unfortunately ended up in post-
project claims and provide a direct connection with earlier Chapter 14.
Chapter 17 concludes with a long list of potential advanced exercise ideas.
Chapter 18 introduces an additional 12 unique projects. These project
descriptions include the project owner’s choice on procurement, delivery,
pricing, and contract formats. Interesting questions are posed regarding why
one of these choices might have been made and could there have been a
better alternative. Many of the hundreds of case examples discussed earlier
in the book are based on these 12 projects. If the reader finds one of the
longer and more involved case studies from Chapters 17 and 18 intriguing,
it is relatively easy to make a direct connection with another example or
two presented in the previous 16 chapters. Each of the 28 case studies in
these last two chapters could form the basis for an hour or a day-long
debate for students or industry practitioners in a workshop or training
seminar.
Appendices at the back material include a list of abbreviations for all of
those included in the book plus many others which are common in the
construction industry. The appendices also include a list of applicable
references and a brief background on the author. A glossary was not
included in this book due to space limitations but an extensive separate
construction management glossary is available pro gratis from the author if
the reader is interested.
My career has been blessed with many positive experiences. But the best
part of these 50 years has been working with so many talented construction
professionals and built environment participants, although some of them
were unconventional, and others may have been challenging. We did a lot
of things right; actually many things! I have worked with thousands of
knowledgeable project owners, architects, engineers, general contractors,
subcontractors, project managers, superintendents, and especially the
craftsmen. My thanks to all of you for providing me a lifetime of lessons
learned that I am able to share with others.
I have not provided answers to all the questions raised in the book, at least
not yet. In many cases the answers are implied or obvious, but there are also
many potential ‘suspect’ answers depending on the reader’s experiences.
Different companies approach construction management from different
angles as do different facets of the industry, residential versus commercial
versus heavy civil, for example. Also union versus merit shop labor
differences may result in alternative solutions, as would geographical
differences. The ‘opinions’ of the reader and therefore the correct ‘answers’
will vary; and this is healthy. I am happy to give you my take on a case
study or two if you send me a note. If you have any other questions about
the material, or recommendations for changes for future editions, please
feel free to contact me direct at holmcon@aol.com. Whether you label them
as stories or case studies or lessons learned or examples, I hope you enjoy
all these experiences.
Len Holm
Please respect the author’s copyright and not copy for distribution
individual case studies from the book. Thank you.
List of figures
The following figures represent actual case studies and examples described
in this book. Many of the photographs are from projects that are used in
more than one chapter. Many could also be connected with the advanced
examples in Chapter 17 or the project descriptions in Chapter 18. If the
reader was interested in a power point of these figures, or photographs of
other cases, please contact the author.
Book cover: Connects with case studies 5.3, 8.1, and 8.7, steel trusses
Figure 1: Connects with case studies 1.12 and 18.2, executive townhomes
Figure 2: Case study 2.12, apartment architect
Figure 3A: Case study 3.9, residential equipment
Figure 3B: Case studies 3.11, 8.4, 8.10, 13.3, and 16.7 nuclear power plant
Figure 4A: Preconstruction flow chart
Figure 4B: Case study 4.4, tile mockup
Figure 5A: Case study 5.6, campus research building, competitive GCs
Figure 5B: Case study 5.13, contract requirements
Figure 6: Case study 6.6, self-erecting tower crane estimate
Figure 7: Case study 7.14, school schedule
Figure 8A: Case studies 8.6 and 11.8, Alaska prefabrications, schedule
Figure 8B: Case study 8.13, post tension cables
Figure 9A: Case study 9.1, two superintendents, parking garage
Figure 9B: Case studies 9.7 and 8.15.A, superintendent, labor
Figure 9C: Case study 9.16, superintendent, messy site
Figure 10A: Case study 10.6.B, mechanical
Figure 10B: Case study 10.14, off-site water pipe tunnel
Figure 11: Case studies 11.11 and 7.10, power plant, dome hanger schedule
Figure 12A: Case study 12.4, plywood footballs
Figure 12B: Case study 12.11, five foot elevation problem
Figure 12C: Case study 12.12, concrete tilt-up
Figures 13A and 13B: Case study 13.15, timber frame
Figure 14A: Case studies 14.9, 6.1, and 8.3, steel truss miss-fits, painting
Figure 14B: Case study 14.16, bridge fire
Figure 15A: Case study 15.1, paint shop and louver damage
Figure 15.B: Case study 15.3, framing error
Figure 16A: Case study 16.3, Law of the Lid
Figure 16B, Case studies 16.12 and 8.9, clean rooms
Figure 17A: Case study 17, CM/GC organization chart
Figure 17B: Case study 17.14, dome ceiling tiles
Figure 18: Case study 18.12, brewery rendering
Notes
1
Project owners and developers
Including discussions involving owner’s
representatives and sustainability
Introduction
Most discussions of construction management focus on the contractor,
especially the general contractor (GC), and that is arguably warranted. Most
of the case study examples in this book, if not all, also include discussions
of the GC. But contractors would not have any work if it were not for their
clients, or project owners. Project owners include both private and public
entities. This chapter includes both of these ownership types and the
different ways they interface with their design and construction teams. Real
estate development involves improving property in the hope of making a
profit. Many real estate developers are interesting characters and there are
plenty of lessons to learn from our experiences on their projects, some good
and some bad. Because GCs need project owners, it is important for them to
understand their clients’ motivations and their businesses. Ideally each
owner organization has a single point of contact. It is difficult for a GC’s
project manager and superintendent to report to a building board,
committee, or board of directors. This single contact is known as an
owner’s representative, resident engineer (for public work), or an agency
construction manager. This chapter includes the following case studies
related to project owners, developers, sustainability, and owner’s
representatives:
1.1: Lucky developer
1.2: New owner’s representative
1.3: No loyalty
1.4: Black-listed PM
1.5: Team play
1.6: Multiple-multiple primes
1.7: Collaboration meeting
1.8: Green agent
1.9: New partner, new deal
1.10: Short pants
1.11: Users
1.12: Noisy furnace
1.13: Leverage
1.14: Mitigation fees
1.15: Sustainability trade-offs
1.16: Arm waving
Case studies throughout this book connect with multiple chapters. Case
studies in this Chapter #1 also connect with many other chapters including:
Case study #1.4.B – Chapter 16, leadership
Case studies #1.5 and 1.7 – Chapter 11, communications
Case study #1.10 – Chapter 12, construction controls, safety
Several case studies connect with Chapter 4 on preconstruction
_____________________________________________________________
_____________________________________________________________
_____________________________________________________________
_________________________________
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
On the current project the local architect, their engineers, the GC, and
mechanical and electrical subs banded together to protect each other’s
interests with respect to this owner’s rep. They didn’t partake in
anything illegal, but was this unethical? The GC’s project manager
would schedule a day-long meeting with these stakeholders a few days
before the out-of-town owner’s monthly visit. They would resolve as
many requests for information and submittals as they could. At the
monthly owner-architect-contractor meeting the owner’s rep would try
to stir the pot and pit one team member against the other; but they stood
strong. The owner’s rep was not pleased, yet this was the only project at
this site in the last 10 years that did not result in a lawsuit or a
bankruptcy. Was it successful?
B. In another project the owner was not the one who was excluded but
it was the contracted owner’s representative. The owner and GC
and architect all knew each other. They all lived and worked in the
same small town. But the current project was bigger than any of
them had participated prior so the owner and architect decided to
engage the services of a third-party owner’s rep. The owner’s chief
executive officer was also concerned about a need for transparency
and did not want any of the company’s board members thinking
there were any ‘sweetheart deals’ going on. The owner’s rep was
from out of town and would visit the jobsite once every other week.
The three primary parties would unofficially meet without the third-
party owner’s rep, often informally, and discussed the project and
made decisions. On one hand, the contracted owner’s rep was
offended. On the other hand, the project was running very smoothly.
Should he object? Should the three local parties who pass each
other in the grocery store or at their kid’s baseball game not be
allowed to say hello? Where do you draw a line between being
polite, social, and making business decisions?
How do you define successful teams? Who won with these examples?
_____________________________________________________________
_____________________________________________________________
_____________________________________________________________
_________________________________
How much do you think she saved with this multiple prime delivery? How
much of her time did it take to manage the project? Why would contractors
take just a piece of the project? Do you think they would resent their lost
fee potential? Who provides the overall warranty on a multiple prime
project? Did I forget to say she had two young children at home, another on
the way, and a full-time regular job?
Post script: The project was finished successfully, but with a few hic-cups:
The foundations did not fit with the shell structure.
The wall framing did not accommodate mechanical and electrical
rough-in.
The kitchen cabinets did not fit with the kitchen appliances. The
shell GC took pleasure in cutting the CVG fir cabinets down to
size.
There were numerous other change orders from all parties. Would it
surprise you to find out the final price was 10% over the original
GC’s quote?
_____________________________________________________________
_____________________________________________________________
_____________________________________________________________
_________________________________
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
C. How do large corporations with many divisions get anything done?
Imagine you are the general contractor (GC) project manager (PM)
or superintendent working on new a building for a publicly traded
client. The company does a lot of construction and your firm has
bid some of their projects and has negotiated others. Of course you
would prefer negotiated work, and need to take care of your client
to stay in their good-graces, but you need to make a profit as well.
The client has a designated in-house owner’s rep. This is a good
thing for a contractor so that you do not have to answer to a board
of directors or a task force or a corporate officer without a design or
construction background. Explain why this is. What sort of
companies try to manage their construction projects in-house with a
‘board’ or task force? This particular company has many divisions
and it should be the responsibility of the owner’s rep to coordinate
all of those interests but that doesn’t always happen. How do you
deal with eight different division heads taking daily project tours,
arm waving, challenging, and providing conflicting directions?
Wouldn’t it be great if they took their site tours all at the same time
and the tour was conducted by the owner’s rep, with you in
attendance? But it doesn’t always happen that way – maybe
intentionally on their part (experience). How do you deal with all of
these people? Don’t offend them. You don’t want to be black-listed
from future work.
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
What happens in the weekly OAC meeting if the GC’s PM and
superintendent disagree in front of the project owner? What happens when
the project architect and structural engineer disagree? What happens if two
members of the owner’s organization are not of the same mind?
_____________________________________________________________
_____________________________________________________________
_____________________________________________________________
_________________________________
If you were the agency CM, what actions should you take? Would you go
over the DA’s head and talk with the property owner direct? What risks
might you be taking? Should you quit?
_____________________________________________________________
_____________________________________________________________
_____________________________________________________________
_________________________________
Why would the new developer change out the whole team? Does a new
president keep his or her predecessor’s cabinet? What are the advantages
and disadvantages? They did retain the geotechnical engineer and the
surveyor, but why them? The project went through a complete redesign
with other targeted tenants. Three years later the ground has not been
broken. Did the property owner error?
_____________________________________________________________
_____________________________________________________________
_____________________________________________________________
_________________________________
The contractor and owner were getting along great. The project was
proceeding just fine with respect to quality, cost, schedule, and safety –
despite the owner’s visits. Payments were being made very promptly.
Should the new owner be banished form the site? How should the craftsmen
be instructed? They of course cannot be rude, but where do you draw the
line? If OSHA was to see the owner and his short pants and sneakers and no
hard hat, would the project be fined or red-tagged? If it was fined, who
would the fine be levied against?
_____________________________________________________________
_____________________________________________________________
_____________________________________________________________
_________________________________
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
B. Two young real estate developers (also cousins) inherited several
parcels of bare real estate from their fathers. One was an attorney
by trade and the other an accountant. That is a good combination!
They had dabbled in small tenant improvement projects prior but
were now considering a large downtown speculative office
building. What does ‘speculative’ mean with respect to real estate
development? The cousins engaged the services of an agency CM
to assist with designer and contractor selections. The CM also
reviewed and negotiated the construction price. After construction
started the CM’s participation dwindled. The developer was
inserting her (the agency CM’s) name on the bottom of all
correspondence with the architect and GC as being carbon copied,
but not actually forwarding any of the paperwork to her. Why were
they doing this? Is it ethical? Does the CM have any liability?
Should she be paid for this? The CM continued to support the
developer on a variety of other projects. Her role lessened with each
project. What was happening here? Was the CM being used?
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
C. A first time developer hired an architect and began design of a
mixed-use project. The architect suggested to the developer that he
hire an agency CM. He received two proposals, one from a large
CM firm for a lump sum of $2 mil and one from a sole proprietor
for a not-to-exceed $160,000, billable on an hourly basis. Why such
a big swing? Can you guess which one he hired? The sole
proprietor CM was very engaged early in the project with contractor
selection and start-up. The developer slowly began excluding the
CM from meetings with the architect and GC. Why would he do
that? The developer would engage the CM from time to time, all the
way through close-out. His final cost was only $80,000. What
happened to the $80,000 he did not invoice the developer for?
Should the CM require steady hours each week? If you were the
CM, why would you stay involved? The developer built several
other projects. The two maintained their friendship, with the
developer often calling (or emailing) for free advice. Was the CM
being used?
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
Figure 1
Case study #1.13: Leverage
A. Developer ‘A’ has $1,000,000 in cash. He buys a commercial
building for $800,000 and puts $200,000 worth of improvements in
it, all out of his own pocket. At the completion of the project he
sells the building for $1,200,000. This represents a $200,000 profit,
or 20%, which most of us would feel is a substantial return on our
investment (ROI). Was this a conservative approach? How much is
at-risk?
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
B. Developer ‘B’ also has $1,000,000 in cash. He buys 5 similar
buildings each costing $800,000 but only puts 25% down on each
project with his own money or $200,000 for each building and
borrows the balance of $600,000 for each building from the bank.
He now has $1,000,000 of his own money in these projects and has
borrowed $3,000,000. He then borrows an additional $1,000,000
against his equity in the buildings and puts $200,000 worth of
improvements in each project. This developer eventually also sells
each of his five improved properties for $1,200,000 for a total of
$6,000,000. He owes the bank a total of $4,000,000 for the 10
loans. This leaves him with $2,000,000. Based on his original
investment of $1,000,000 he has realized a $1,000,000 profit, or
100% ROI. This is leverage. Note that the interest cost of short-
term loans, were omitted from this scenario for simplicity.
Developers usually pay for the loan from the loan proceeds itself,
just as they would pay for building materials such as carpet. Was
this an aggressive approach? How much did he have at risk?
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
C. Now assume developer ‘C’ has the same investment to make but
buys 10 similar buildings and only puts 10% down for each one.
Assuming the same purchase cost, improvement cost, and sales
price, how much total did he make and what was the ROI? You
have heard of the risk-reward tradeoff. Do these three developers
match that comparison? How much would each have lost if they
didn’t sell, assuming they did not declare bankruptcy and honored
their obligations to the bank? But would they take that approach?
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
Notes
2
Design teams
Architects and engineers
Introduction
A great architect once said “There would be no built environment without
contractors.” And there would also be no built environment without
architects and designers. Project owners and contractors need their design
team members. Architectural organizations and their motives, contracts, and
fees are different than that for construction companies. It is relevant that
contractors understand these differences. There are many alternative ways
project owners contract with the prime architect and supporting engineers;
there is no one size fits all solution. There are also many variations with
how their fees are structured. Responsibilities of each of the design team
members affects their relations with the project owner and contractor. Case
study examples in this chapter help explain some of these relationships.
This chapter includes the following case studies related to designers,
architects, and engineers:
2.1: Architectural help
2.2: ADA advice
2.3: Leaking garage
2.4: Architectural fees
2.5: Give two to get one
2.6: Pay request signatures
2.7: Safety voice
2.8: GC’s architect is ‘low-value added’
2.9: Design QC
2.10: Come up with my estimate
2.11: Architect’s inspections
2.12: My architect
2.13: The intern
2.14: Design team
2.15: 700 sketches
Case studies throughout this book connect with multiple chapters. Case
studies in this Chapter #2 also connect with many other chapters including:
Case study #2.6 – Chapter 13, cost control, pay requests
Case studies #2.7, 2.9, and 2.11 – Chapter 12, construction controls,
safety and quality control
Case study #2.10 – Chapters 6 and 16, estimating and ethics
B. The garage walls leak all around the perimeter on all floors, where
the floor slabs meet the CIP concrete outside walls. An expansion
joint had been designed by the structural engineer to allow
movement. These were PT decks and because much of the garage
was below grade (only the top floor was visible at ground level)
there was not a great solution allowing for cable stressing and a
pour-back closure slab. Maybe you should draw a sketch. Over
time, as all of the slabs moved, the expansion joint experienced
wear and tear and that same cement-laden rain from above damaged
more cars.
C. The adjacent storm water control vault leaks. Every new building in
this city is responsible to handle its own storm water in what is
known as a ‘100 year storm’. How often do 100 year storms occur?
In the Pacific Northwest they occur about every other year, or so it
seems. All five levels of the garage collected rain water in a piping
system designed by the ME. That water was taken to this storm
water vault which was designed by the CE. Concrete usually
associated (in this case attached) to a building is customarily
designed by the SE but because of the vault’s use, it fell under the
CE’s jurisdiction. Water temporary held in the vault would
unfortunately travel horizontal through the vertical garage wall and
leak into the garage and damage more cars. The vault did not have
an internal liner on its sides or bottom. Typically these vaults are
stand-alone structures and evidently, if separated and isolated form
a new building, any leakage would find its way back into the
ground, which for some CEs, would be ideal.
D. Because the architect was a small company there was not a strong
design oversite present. Parking garages are customarily driven by
the structural engineer, but there are still several other design
elements including parking garage equipment, signage, striping,
paint, electrical embeds and others. Should the SE be the prime
designer in a concrete structure and should the architect be a sub
consultant to the engineer? Would the SE want that?
The developer and his attorney blamed the GC for all of these leaks and
design shortcomings and expected them to not only design and implement
repairs, but to pay for a couple of dozen car paint jobs. Will the developer
be successful? Since the contract has expired, do the dispute resolution
clauses in the contract still apply? Why doesn’t the developer file a claim
against his TI architect or the engineers? Does the developer have any
culpability here?
_____________________________________________________________
_____________________________________________________________
_____________________________________________________________
_________________________________
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
B. Would your answers to any of these questions related to an
architect’s fee change if you were aware that the project owner had
worked the proposed architect’s fee down when they executed a
contract? For example an architect proposed a fee of $1 mil but the
project owner was able to negotiate a fee of $800,000 in their
contract. Why would an owner do this (and they do!)? In in this
scenario, if the architect actually spent $900,000 and approached
the owner at the end of the project for an adjustment, would the
owner agree to a change? Owners negotiate construction contract
values down with architects and GCs, and GCs do the same with
subcontractors. If a GC or subcontractor (see drywall subcontractor
in case study #15.11) overspend and approach the owner after
construction for an adjustment, will the owner agree? Estimated
costs versus contracted values versus actual expenditures are often
the basis for after-the-fact construction claims. Some examples of
this are included with Chapter 14. Do architects ‘claim’ owners as
well?
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
B. Another architect on another project was on a site walk with her
structural engineer. She observed one drywall installer standing on
the top rail of a scissor lift 20 feet in the air and not tied off. The rail
is only one inch wide. This first guy was working with another
installer who was hanging out a window opening and was also not
tied off. Neither of the two had a spotter. If there was a spotter,
would their actions then be acceptable? The two designers observed
these safety violations and walked past. About 30 feet down the hall
the architect said to her engineer: “Wait, I cannot let that go.” She
returned to the drywall installers and read them the riot act. She
then went directly to the GC’s superintendent and shared her
observation. The two installers were removed from the site that day
and their company received a formal written reprimand from the
GC’s office. What are the proper procedures for:
Have you observed a safety violation? Did you do anything about it? If you
didn’t, and someone was injured, would you feel any responsibility? Do
you suppose the architect’s employer will reprimand her? I hope not.
_____________________________________________________________
_____________________________________________________________
_____________________________________________________________
_________________________________
The answers to these questions are ‘yes’. Do any of the design firms take
any responsibility for document errors? Do they pay for discrepancy change
orders? Is that the purpose of errors and omissions insurance? What do the
contracts say?
_____________________________________________________________
_____________________________________________________________
_____________________________________________________________
_________________________________
The architect who the developer hired was not the prime individual in the
original design and whose stamp was on the permit set of drawings. When
it came time to apply for a certificate of occupancy from the city, the city
only wanted to work with the original architect. Why is that? The developer
had to re-engage the architecture firm and have them buy-in to all the
changes he and his own architect had made. Do you suppose he had to pay
for this? You know the phrase, ‘what goes around comes around’.
Post script: After completion of this one project the architect, who had left
her firm, went back to work for them, now as a partner with a share of the
profits. The developer would continue to engage his original friendly
architecture firm for future projects.
_____________________________________________________________
_____________________________________________________________
_____________________________________________________________
_________________________________
Figure 3B
The CM will charge the same 7% fee they were to include in the GMP on
the total cost of the work. What is going on here? Is this a good deal for the
developer? Is this a good deal for the CM? Why were they proposing this
change of plans? Do you suppose they do this as a regular course of
business?
The construction consultant was not comfortable with this deal, especially
with a new developer. The developer’s architect did not offer an opinion on
this proposal. Why was that? Would a very experienced developer accept
this deal? This example is not the same situation as described in multiple
prime case #1.6. The construction consultant worked the CM over on this
proposal, in front of the developer. He challenged why the CM would still
need a 7% fee since they were no longer guaranteeing any of the typical
project controls including:
Cost control,
Schedule control,
Quality control, and
Safety control.
The CM’s chief executive officer claimed he was offended and indicated his
reputation was still at risk and that warranted the fee. What reputation?
What fee do you feel is justified by this revised arrangement? The
consultant’s fee proposal for the CM was very low. Who is now
contractually responsible for these controls? Would it be:
The architect?
The construction consultant?
The CM?
The developer?
Any or all of the 50 subs and suppliers?
4
Preconstruction
Including permits
Introduction
Everything we do in the built environment before construction occurs is
part of the preconstruction phase as depicted in this Figure 4A. This chapter
focuses on the general contractor preconstruction teams and processes that
interface with the project owner, architect and engineers, and
subcontractors. This discussion explores preconstruction services, contracts,
and fees, Preconstruction services includes everything from estimating and
scheduling to BIM, lean, and value engineering. Applying for and receipt of
building permits are critical to achieving project success and therefore the
owner-architect-contractor team’s interface with the city are also explored
in these examples. Although communication is the primary subject of
Chapter 11, many construction communication tools are part of the
preconstruction phase including early submittals, construction control plans,
mockups and others are discussed in these case studies as well.
Preconstruction Construction
Figure 4A
Figure 4B
Case study #4.4: Red and yellow tiles
Mockups are a valuable tool in construction as reflected in the previous
case study. This medical office building (MOB) included a complicated
exterior brick design. The architect had visited an old part of town and
desired to combine early 1900s brick, terracotta, and tile details with a new
building’s façade. Four-foot wide punch windows (pre-hung) were to be
framed in a small 8-foot wide by 12-foot high precast concrete panel that
was recessed into the brick wall. The panel would have bright glazed tiles
in all primary colors cemented to the concrete panels around the windows.
An extra precast concrete sill was included below the window and
additional brickwork returned the assembly to the outside brick wall. This
system also interfaced with waterproofing, metal studs, insulation, and
flashing. Take a shot now at drawing this feature.
The general contractor (GC) attempted on several occasions to value
engineer (VE) the complicated mix of materials and subcontractors and
suppliers out of the project. Even the project owner was skeptical about the
use of bright primary colored tiles, especially the red and yellow tiles. The
whole MOB was supposed to blend in with the naturally forested
neighborhood. The architect prevailed and the mockup was built on site.
When should mockups be built? How are they paid for? What
subcontractors and craftsmen should work on mockups?
All the preconstruction team met at the jobsite on a sunny day. The process
of building the mockup allowed the construction team to work out some of
its means and methods. They weren’t as negative as they had been when
early sketches were exchanged. The project owner said okay, but wanted
the red and yellow tiles replaced with earth tones. The blue tiles matched
the sky, especially that day, and the white tiles blended with the vinyl
window frames. What happened next appeared to be staged but was quite
impromptu. The architect walked 30 feet away and cut some scotch broom
and wild rhododendrons – both in full yellow and red bloom. Everyone
laughed and congratulated each other and the detail was approved. The GC
chose to cast the concrete panels on-site, stacking them, which saved
considerable cost. The project was a big success. List some of the different
subcontractors and suppliers who would be needed for this assembly.
Develop a short estimate and/or schedule for construction. Make whatever
assumptions as necessary. What other VE opportunities do you see?
Post script: The mockup stood for the duration of the project and was one of
the last things removed when the GC demobilized. Several trades used it as
a training and quality control tool when new craftsmen came to the job. A
photograph of the finished project is shown in Figure 4B.
_____________________________________________________________
_____________________________________________________________
_____________________________________________________________
_________________________________
Case study #4.5: BIM versus bid
Similar to other relatively new construction management concepts such as
lean and sustainability and activity-based costing, building information
modeling (BIM) has its place in the built environment. But the question is,
does it have a place on all projects? Consider some of these options when
analyzing the following two examples:
Public versus private projects,
Large projects (size and value) versus small projects,
Complex projects versus simple projects,
Sophisticated contractors,
Traditional design-bid-build versus other delivery methods such as
design-build or construction manager at-risk,
Lump sum versus cost plus or guaranteed maximum price (GMP)
projects, and
Bid versus negotiated projects.
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
B. What are GCs approaches to subcontractor (sub) VE? Do you
request it from subs? If subs offer unsolicited cost savings ideas, do
you consider them? How do you assure that you are getting good
value in return? Who owns the design responsibility for a value
engineered item? Should you give the sub some incentive to
propose these ideas? Is it acceptable to allow them to skim some of
the savings off? It is said that contractors return 50 cents on the
dollar for credits but charge two dollars for every dollar of added
scope. Do you agree with that premise? Is this true for VE?
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
Case study #4.14: Lean
Lean construction techniques have been adapted for construction in the last
20 years from the automobile industry. Lean basically means to build
construction projects as cost effectively as possible. Adopting a lean
approach to construction has been received well by some contractors and
resisted by others. Here are a couple of examples how different contractors
address lean.
A. This private developer has recently heard a lean presentation from a
college professor and is on the fence whether to require her open
book time and material project to be built by a lean contractor
advocate. She is interviewing two perspective general contractors
(GCs).
GC1: Argue why your company has always built in a lean fashion, even
it if was not labeled as such. Use concepts such as preconstruction
services, constructability reviews, value engineering, total quality
management, vetting best-value subcontractors, cost and schedule
controls, foreman work packages, earned value, zero punch list, zero
time-loss due to accidents, and others to pitch your company to this
client.
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
GC2: Your firm has sent all your superintendents, project engineers, and
project managers to construction industry sponsored lean training
classes. Everyone is lean certified, and your business cards and
letterhead have been modified accordingly. Your company’s goal is to be
the leanest contractor in your state. Prepare an argument why your firm
is now more cost-effective than your competition and you can validate
that lean construction projects are finished less expensive than those
which are not.
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
B. This large design-build mechanical subcontracting company
performs HVAC, processing piping, plumbing, mechanical controls
and fire protection all in-house. If they were a GC, they would be
the third largest in this metropolitan area. The company employs the
top mechanical engineers and has two hundred mechanics in their
fabrication shop. They sell fabricated ductwork and piping to many
of their smaller competitors. The vice president (VP) has just
attended a week-long lean construction technique seminar which
included topics such as activity-based costing, just in time planning,
pull planning, and supply chain material management. The VP is
tasked with transforming her company into the top lean mechanical
contractor in the state. She has hired you as an expert lean
consultant to help her phase in this transformation. You are to
prepare three lists of five actions each you would recommend she
implement. The first list is a group of easy to implement minor
changes which do not require buy-in or approval from any of her
other team members. The second list of five involves a pitch to the
project managers, superintendents, and project engineers. They will
have to devote some of their time and energy to incorporate these
suggestions into their project plans. The final list will have cost and
resource commitments needed from the subcontractor’s board of
directors. They will be the hardest to sell and will require the most
time to implement.
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
Case study #4.15: Church donors
A private religious high school houses their students on campus in
dormitories, similar to colleges. The school decided it needed a new girl’s
dormitory. The board of directors (board) included several members from
the built environment community. Is this typical? Church boards are
sometimes considered difficult clients. Why might that be? Although there
were church members with construction experience, they elected to contract
with a third-party owner’s representative, or agency construction manager
(CM). Why didn’t one of them step up and donate their time? The board
instructed the CM that he was to have this dorm built quickly, cost
efficiently, and meeting high quality standards. Why do some project
owners forget the fourth important CM control aspect, safety? The board
also instructed the contracted CM that everyone needed to be treated fairly
and they did not want any disputes or claims. All of this seemed to be
acceptable marching orders to the CM.
The school already had chosen an architect who was an Elder and major
donor of the church. They had also chosen a general contractor (GC) whose
chief executive officer (CEO) was a member in good standing of the
church. Owners of both of these companies agreed to perform the dormitory
work at zero fee, donating their own personal time, and be reimbursed for
other actual costs only. What might go wrong with this situation? It seemed
as if everyone will get along just fine.
The CM was the only individual on the team who was not integral with the
church. Even one board member was also a major commercial drywall
subcontractor (sub) in town. The drywall sub joined in and donated a whole
barn full of ‘rock’ to the project. Evidently he had bought it ten years earlier
but had not yet been able to use it on any of his projects. Why might that
have been?
The CM attempted to meet up with the architect and get the design phase
scheduled. The architect and school did not have a contract in place but the
CM felt one was necessary. Why did he insist on a contract? The architect
dodged that move and could not really commit to a design schedule. He
used the excuse that because he was donating his fee his firm would use the
job as fill-in. The architect even expected his employees to donate their
time and prepare the design off-shift. Would you do that? The first few
drawings were sketchy at best. The architect responded to the CM’s
complaint with: “I know the GC. He will know what to do.” Any
commitments made were subsequently missed. List five things wrong with
this scenario already. Won’t a set of permit drawings be needed to share
with the city? Do you know the adage ‘you get what you pay for’? That was
how the CM was feeling at this point.
The CM’s encounter with the GC’s CEO was a very similar experience. He
preferred to work on a time and material basis and was not interested in a
guaranteed maximum price. How could the CM assure the church board
that the project would comply with their cost and schedule goals? The
pricing the GC produced was at a high summary level at best and what
detail the CM could see, appeared over-priced. The GC did not provide any
written sub quotes and the CEO indicated because he was not being paid a
fee, he was going to recommend to the church that they contract with the
subs direct. He has lined up the subs and they all agreed to donate their fees
as well. What is happening here? If the subs work direct for the church,
who will be maintaining schedule and quality controls? What happens if
someone gets hurt?
The CM complained to the board about the architect and the GC but they
appeared not to listen and sent him back out to do his job. The CM began to
have doubts and worried that if there were ever any audits or repercussions,
the responsibility may be laid on his shoulders. Were his concerns founded?
Should he hammer on the architect and GC, write them formal letters, and
copy the church board? What would be everyone’s response if he proceeded
in that manner? The CM eventually quit the project before any significant
design or estimating had been produced. Are you surprised? Did he error?
_____________________________________________________________
_____________________________________________________________
_____________________________________________________________
_________________________________
5
Contracts
Including procurement, delivery, and pricing
methods
Introduction
The construction contract is arguably the most important document on the
project. The contract establishes relationships, rules, and vehicles of
coordination between the contracting parties. Before a contractor considers
executing a construction contract the project owner had to select the
project’s procurement options (bidding versus negotiating) and delivery
methods (traditional versus design build versus construction manager and
many others). The owner also decides on how the project is to be priced by
the contractors, either lump sum, cost plus, or a guaranteed maximum price
hybrid.
Contract documents can be generic documents copyrighted by the
American Institute of Architects, ConsensusDocs and other contractor
associations. Contracts can also be ‘home grown’ and written by project
owners and/or their attorneys. The five typical contract documents include
the prime agreement itself, supplemental or special conditions, general
conditions, drawings, and technical specifications. Additional contract
documents may include prevailing wage schedules, bid documents,
geotechnical reports, addenda, estimates, schedules, and many others. The
list is limitless and any document may be included in the contract as long as
it is referenced in the prime agreement. All contract exhibits should also be
physically attached to the agreement. Case study examples in this chapter
explore all of these documents and processes. This chapter includes the
following case studies related to contracts, procurement, project delivery,
and pricing methods:
5.1: No windfall allowed
5.2: Wet dirt
5.3: Epoxy floors
5.4: Not a GMP?
5.5: DB responsibility
5.6: Competitive general conditions
5.7: Master project agreement
5.8: Pick a GC, any GC
5.9: All-in
5.10: Unfair interview
5.11: Proposal preparation
5.12: Missing bakery ingredients
5.13: Are proposals contracts?
5.14: Man in the robe theory
Case studies throughout this book connect with multiple chapters. Case
studies in this Chapter #5 also connect with other chapters including:
Case studies #5.1, 5.2, and 5.9 – Chapter 6, estimating
Case study #5.3 – Chapter 10, subcontractors
Figure 5A
Was the GC taking advantage of the owner? Maybe a little bit (first-hand
experience). How could all these missing ingredients have been clarified
earlier? How should they
have been budgeted for? The discussion of owner’s subcontractors and
suppliers is threaded throughout this book. The problem with owner-
provided subcontractors did not show up first on this project, and this will
not be the last project it occurs.
_____________________________________________________________
_____________________________________________________________
_____________________________________________________________
_________________________________
Offer Acceptance
Conveyance
Figure 5B
Case study #5.14: Man in the robe theory
Fair is fair and that is important. Contractual inclusions and rules are
important. But which is MORE important? Can something be considered
‘fair’ but outside of the strict interpretation of the contract? And can
something be considered within the bounds of the contract, but might not be
fair? The answer to all of these is pretty much yes, considering other issues.
What is important for the construction professional is:
A. Cross your I’s and dot your T’s and complete the contract carefully.
Read all terms of the contract and do not sign up to anything you do
not agree with. Have your attorney and bonding company (surety)
read all prospective contract agreements before you submit a bid or
proposal. The court system considers that both parties have
thoroughly read and understood all conditions of the contract (even
the fine print) and they have mutually negotiated and agreed to all
terms. This is why the courts find it difficult to rule outside of the
contract. If the parties agreed to these terms, why would the court
overrule them?
But the parties cannot rely on just A or B above. They cannot ignore
contract language and just hope that fairness in the end will rule. They also
cannot rely strictly on contract language considering it might not be fair,
because at the end of the day, the ‘man in the robe’ (or woman), or in this
case the judge, may find in favor of fairness and over-rule contract
language. Consider the following example. This general contractor project
manager (PM) was tired of issuing detailed subcontracts (subs) and
purchase orders to his vendors only for them not to read the language and
then argue about it during the course of construction. He decided to teach
his electrical sub a lesson by inserting this language: “Electrical
subcontractor to supply all concrete reinforcement steel”. The sub signed
the agreement as the PM expected, without modification. One week into the
job the PM called the electrical owner and asked him when the rebar was
going to be delivered – they had foundations to pour. Can you imagine how
that conversation turned out? If the PM had attempted to enforce this
clause, would it have been considered ‘fair’? But it was in the contract,
right, and the contract rules? If you were the man, or the ‘person’ in the
robe, how would you rule?
_____________________________________________________________
_____________________________________________________________
_____________________________________________________________
_________________________________
Notes
6
Estimating and bidding
Including marketing, proposals, and interviews
Introduction
When is an estimate not an estimate? The answer is: When it is a bid or
budget or guaranteed maximum price or actual cost. The term ‘estimate’ is
generic. To-estimate is a process or procedure. The estimate itself can be a
document or a price. It is relevant for all members of the built environment
to be more specific regarding exactly what type of cost estimate they may
be referring to. Many disputes arise because the project owner thought they
had a ‘bid’ but the contractor proposed a ‘budget’. Bidding is one
procurement method available for project owners, the other being
negotiating. The bid itself is typically a lump sum price from a general
contractor. Heavy civil projects although often use a long list of materials
with stated quantities and the contractors apply their all-in (material, labor,
equipment, markups) unit prices to the government’s quantities. These are
known as unit price bids and unit price estimates.
Budget estimates are also known as rough-order of magnitude estimates and
are associated with preconstruction services (Chapter 4) and early design
phases such as conceptual and schematic design. Budget estimates are the
least accurate estimate type and often include substantial contingencies.
Lump sum estimates typically require complete construction documents,
including drawings and specifications. This is the most accurate type of
estimate but because contractors are assuming all pricing risks, they will
include higher fees. A guaranteed maximum price estimate is a hybrid of
budget and lump sum pricing and may occur at the completion of the design
development phase and is associated with a negotiated contract.
Estimates are prepared by many members of the built environment, not just
general contractors and subcontractors. Project owners, especially
developers, and architects also prepare estimates in-house or with the
assistance of contracted estimating consultants. Contractors prepare their
estimates in-house either with a staff estimator or estimates prepared by the
project manager who is slated to run the project if they are successful. Most
of the case studies in this book have money or estimates involved. We have
included 18 specific examples in this chapter which discuss all of these
estimating concepts and situations. This chapter includes the following case
studies related to estimating, bidding, marketing, proposals, and interviews:
6.1: Car painter
6.2: First, last, and only price
6.3: Choose a specialty
6.4: Tile shortage
6.5: Island prices
6.6: Tower crane or no tower crane?
6.7: Unverifiable
6.8: Push hard, but not too hard
6.9: Double burden
6.10: DFHW QTO
6.11: Pile cap QTO
6.12: Forklift purchase
6.13: It is for the kids!
6.14: Existing conditions
6.15: When is second the best?
6.16: Bad day for a sick day
6.17: Estimating strategies
6.18: Do what you know
Case studies throughout this book connect with multiple chapters. Case
studies in this Chapter #6 also connect with other chapters including:
Case study #6.1 – Chapter 10, subcontractors
Case studies #6.3, 6.7, and 6.9 – Chapter 16, leadership, careers,
and ethics
Case study #6.8 – Chapter 5, contracts
Case study #6.12 – Chapter 8, jobsite operations, means and
methods
Case study #6.14 – Chapter 14, change orders
Many case studies in this chapter also connect with Chapter 1
regarding the project owner and developers
I could continue but you get the picture. How did the estimator error? Is he
liable to his client for the budget bust? Can you think of any more creative
ways to reduce these costs? The lesson learned with this example is you
always visit the site before you prepare an estimate. Do your research!
_____________________________________________________________
_____________________________________________________________
_____________________________________________________________
_________________________________
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
B. The soils report for this bid project indicated the existing earth was
suitable for use as structural backfill. GCX was working on the site
adjacent to the project being bid. At the pre-bid meeting the
estimator for GCX asked this question of the owner: “Can we use
the on-site material for backfill as indicated in the soils report?”
The owner’s response: “Of course you can’t. You know that. You
are working on the adjacent site and all that mud had to be hauled
off and replaced, at considerable expense to us.” Why did the
estimator ask that question? It is customary that questions and
answers from pre-bid meetings are documented in meeting notes
and issued as an addendum. When do you ask a question at a pre-
bid meeting and when not? If you were the estimator for GCY, how
would you have figured the dirt before this meeting? Would you
have received a change order for the bad dirt? If the question had
not been raised, and GCX had been the low-bidder, could they have
successfully submitted a change order for the bad dirt on the new
site?
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
C. A GC’s estimator was going after this project very hard and had
figured all sorts of ways to combine sub bids on bid days and
separate other package bids out. Why might they do that? What are
some of the risks associated with splitting and packaging bids? The
estimator finished $25,000 out of low bid on a $25 mil project. That
is 1/10 of 1%, which is extremely tight bidding. Immediately after
submitting the bid the estimator realized a major error she had
made. She had included $150,000 for the fire protection system,
splitting it out from the mechanical bids, but the low bidding
mechanical price also had the fire protection included. She had
therefore doubled-up on the $150,000 and would have been the
clear low bidder without this error. She immediately called the
project owner and shared the error and asked to be able to revise
their bid. The bids had already been publicly opened. The owner
denied this request. Why would the owner not take a lower price? It
was a private company. If you had been the initial low bidder, and
the owner allowed this change, what would have been your
response? I often say we do not become first or second bidder based
on our count of anchor bolts, but it is the major mistakes such as
shown in this example, or slipping a digit, that define the low
bidder.
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
D. This bid project was similar to example C above. This was a
process piping facility and the GC’s PM was adept at understanding
mechanical systems. He decided the way to become low bidder was
by taking bids for all of the mechanical and electrical major
equipment direct, and taking bids from their smaller subcontractors
direct. The industry quickly became aware of his approach to this
complicated project. At the pre-bid meeting, one of the major
mechanical contractors who was working for the client on other
projects asked the following question: “Does the owner want the
mechanical subcontractor to be responsible for all the process
systems and equipment in one large package?” And the owner’s
response: “Yes, that is how we set up the specifications and the
drawings. We think that will provide us with complete operational
systems and no gaps.” Why did the mechanical subcontractor do
this? If you were the GC’s PM, would you still pursue busting all
these packages down to smaller bids? Is the owner’s opinion
correct? Can the owner enforce this?
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
E. A GC estimator/PM had worked in this pulp and paper mill several
times and knew most of the foremen in the plant. The purchasing
agent in charge of this new bid project was new to the company. He
included many construction procedural issues in the bid documents
such as parking, badging, work hours, and site access. The project
involved extensive process equipment revisions, but the equipment
was located on the opposite side of the mill from the designated
construction entrance. The estimator arrived at the pre-bid meeting
early and toured around the mill, chatting with many of the client’s
mechanics. He asked them if it would be okay on this new project if
he used the alley and back entrance to load materials and craftsmen,
rather than dragging all the construction materials across the very
active and very congested plant. Their response of course was
affirmative. They did not like the construction disruption and
keeping it out of their workspace was a benefit to all. Should the
GC estimator bring this up at the pre-bid meeting? Should he just
assume he can utilize this alternative approach? If so, it will save
considerable time and money. Should this plan be shared with all
the GC bidders? But if the estimator/PM cannot use this approach,
and has to use the designated construction entrance, he will be
short. What would you do?
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
F. A GC PM was sent across two states to attend a mandatory pre-bid
meeting at an industrial complex. He arrived one day early and set
himself up in a hotel room. He visited the campus and knew how
long it would take him to make the scheduled meeting at 9:00 am
the next day. He set his alarm for 7:00 and got up, took a shower,
treated himself to a nice breakfast, and read the local newspaper. He
had plenty of time. But when he arrived at the client’s facility at
9:00 he discovered the meeting was already completed. He had
missed it altogether. What he didn’t factor was the one hour time
zone difference between his home office and this potential site.
When he explained to the client’s procurement officer what had
happened, his response was sympathetic, but the GC was now
disqualified due to their strict bidding rules. Why might
corporations establish and follow strict procedures? The GC had
worked in this mill prior, but not this particular PM. Now what does
he do? If you were his boss, would you fire him?
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
There are many other examples of good and bad estimating experiences in
his book, including case #8.7 regarding the steel truss model with cranes,
case #6.15 justifying when it is good to be second bidder, and many others.
If all GCs take the same sub bids, use the same union labor, receive material
prices from all the local suppliers, how can they become low bidder? Sure
some contractors feel their craftsmen build it better and faster and safer, but
it often takes two carpenters a day to perform a task, regardless of the GC.
What are some other examples you have experienced with bidding success
and miscues?
_____________________________________________________________
_____________________________________________________________
_____________________________________________________________
_________________________________
Other than these few hiccups which the estimator felt she had under control,
the project seemed to be a slam dunk, right? The estimator briefly (very
briefly) discussed the project with her boss who said: “Sure, get started on
it, and we will touch base as the bid date draws near.” This all sounds
appropriate, except the boss then left for a one-month European cruise and
the bid date was three weeks away. The estimator was all in. She attended
the pre-bid meeting, visited the site, generated a lot of subcontractor and
supplier interest, and assembled her bid day team. The estimator and the
planned superintendent worked on the general conditions estimate together
and roughed out a construction schedule. It sounds as if she has followed all
the procedures to develop a competitive bid, right?
Two hours before the bid is to be submitted the only company officer
working that day (not many seem to be in the office on Fridays, why is
that?) came into the bid room. He was relatively new with the company and
had been hired as a vice president (VP) for hospitality work (hotels). The
estimator needed the VP’s input on a fee choice and his signature on the bid
form. This VP had previous public bid experience with another GC, and he
blew his top for all the bulleted reasons listed earlier, and a few more. He
might have even let a few expletives fly. He almost refused to sign the bid
form, but he did not want to offend his colleague who had given the
estimator a green light. Instead, he added $200,000 to the jobsite general
conditions estimate for subsistence associated with staffing the remote site
and finding qualified craftsmen. Is he correct to do this? He also chose a
10% fee. The estimator was devastated. The current market fees were 5%
and although this was a difficult project, she knew her three weeks of hard
work had just gone out the window. She could not possibly be competitive
at 10%. Why did the VP do this? Was he correct to do so? What is the
purpose of this increased fee? Can she just erase his modifications and go
with what she thinks will win the project? When should the estimator have
gotten the VP involved in this bid?
Guess what, no she was not low bidder, but she was a competitive second.
Evidently other GCs also felt this was a risky project. Her friendly architect
did everything he could to get her the contract. He tried to show the low
bidder had an error. He pitched to the client that our estimator’s bid was
complete, and she would not change order the job. Is a second bid always a
more complete estimate? Is there a guarantee the second bidder will not
change order a project? The low bidding GC was local to the jobsite but did
not have any laboratory experience. What would it take to disqualify a low
bidder and why might public project owners not do that? Can private
owners disqualify a bidder? The architect tried to convince the low GC it
had a bid error, and they should drop on their own, but they refused to do
so. Was the architect correct in doing all this? Was it legal? Was it ethical?
Why might the low bidder choose to proceed with the job? What wage rate
does a merit shop contractor pay on a prevailing wage project? What
recommendations do you have for this estimator for the next ‘perfect’
project she brings in the door?
_____________________________________________________________
_____________________________________________________________
_____________________________________________________________
_________________________________
7
Scheduling and schedule control
Including liquidated damages
Introduction
Just as many members of the built environment prepare estimates,
schedules also have many different authors. This chapter is about the
scheduling process, the schedule as a document, and the schedule as an end
date. But there would not be any schedules without ‘schedulers’ and
different types of schedulers, including staff schedulers, consulting
schedulers, and construction project managers and superintendents, are
examined in many of these case studies. Not everyone can read a schedule,
let alone create one. The schedule is an important communication tool and
ideally all members of a contractor’s team understand the schedule. After
development of the schedule, the control of the schedule, particularly at the
jobsite level, is often the responsibility of the general contractor’s project
superintendent. Many scheduling related topics will be included in these
examples including liquidated damages, strategy, subcontractors, schedule
formats, contracts, claims, and leadership. The important topics of schedule,
and scheduling, is woven throughout the over 275 cases in this book, as is
estimating. This chapter includes the following case studies related to
scheduling, schedule control, and liquidated damages:
7.1: Scheduling after the fact
7.2: Trusted scheduler
7.3: Subcontractor schedule revisions
7.4: Two schedules are less than one
7.5: Horse in the barnyard
7.6: To-do list
7.7: Cheap LDs
7.8: LDs versus bonus
7.9: Schedule critic
7.10: Young boss
7.11: Faster schedule
7.12: Staff scheduler
7.13: First schedule
7.14: Skipping school schedule
7.15: 10,000 activity schedule
Case studies throughout this book connect with multiple chapters. Case
studies in this Chapter #7 also connect with many other chapters including:
Case studies #7.1 and 7.3 – Chapter 10, subcontractors
Case studies #7.1 and 7.15 – Chapter 14, change orders and claims
Case study #7.11 – Chapter 6, estimating
Several case studies in this chapter also connect directly with
Chapter 9 on superintendents and Chapter 16, leadership.
8
Jobsite operations
Including means and methods, jobsite
organizations and field personnel
Introduction
General construction companies are typically organized in two different
fashions. The first is a staff organization where company specialists, such as
home office estimators and schedulers help, or potentially direct, jobsite
teams. The other is a project management or sole source organization where
the jobsite team, including the project manager and superintendent, perform
all management functions. Construction organizations were discussed in
Chapter 3. The choice of means and methods of construction is always the
contractor’s responsibility, especially the project superintendent. Many of
the case study examples included in this chapter evaluate these means and
methods choices. The most important people in a construction team are the
builders. This includes carpenters, laborers, electricians, plumbers, and
many others. It is the general contractor superintendent’s responsibility to
coordinate the activities of all these people and several examples in this
chapter describe the field team’s interactions. The jobsite team reports to
the home office. Many construction management communication tools are
used by the jobsite team including estimates, schedules, and contracts. The
jobsite general conditions estimate is an important guide the project
manager and superintendent rely on. This chapter includes the following
case studies related to jobsite operations and organizations including means
and methods and field personnel:
8.1: Super scaffold
8.2: Front loader
8.3: Steel truss misfits
8.4: Super general foremen
8.5: Nepotism?
8.6: Alaska prefabrications
8.7: 300 foot-long steel trusses
8.8: Zero laydown
8.9: Modular cleanrooms
8.10: Fearsome CM
8.11: Guaranteed OT
8.12: Selective OT
8.13: Stressful PT
8.14: Irrigation union?
8.15: Labor conflicts
This chapter connects and overlaps with many other chapters in this book.
Unique case studies in this Chapter #8 connect with other chapters,
including:
Case study #8.3 – Chapter 14, change orders and claims
Case studies #8.7 and 8.8 connect with Chapter 6, estimates and
presentations, and Chapter 9, superintendents
Case study #8.10 – Chapter 16, leadership
Case study #8.13 – Chapter 6, estimates
Case study #8.14 – Chapter 10, subcontractors
Figure 8B
The GC submitted its plan to the architect and structural engineer of record
for approval but they refused to comment. Why was that? That doesn’t feel
fair. The project was a success and although the GC had left $500,000 on
the table, they ended up doubling their bid fee and earned the respect from
the project owner and design team. Would the owner have spent less money
and evened the bidding playing field if they had fully-engineered the
project? Who would have been responsible then? Would you have bid on
this project? When they cut the first cable, where would you have been
standing?
_____________________________________________________________
_____________________________________________________________
_____________________________________________________________
_________________________________
All this seemed to work except when the developer began challenging
the GC on its choice to perform concrete with their own direct
craftsmen. The residential builder felt it would be more cost-effective to
subcontract that work out to concrete subcontractors who customarily
did residential work. The developer also recommended the GC use
merit-shop subcontractors for the earthwork and shoring. The GC said
they couldn’t do that for two reasons: (a) The project was too complex
and risky on this steep slope to trust these smaller inexperienced
subcontractors, and (b) they had union agreements they were going to
honor. Can the developer contractually require the use of their
subcontractors? The project proceeded along fine without any cost,
schedule, quality, or safety concerns. If the developer has their non-
union electrician onsite installing embeds in the garage slabs but the GC
does not have any electricians onsite and does not have a labor
agreement with the electricians’ union, is this a conflict? The GC will be
employing union carpenters to install the concrete formwork. Can the
developer mobilize its non-union carpenter framing crew to begin wall
layout when the first building is ready but others still under
construction? They did. See Figure 9B.
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
B. Most contracts include a provision that the project owner is allowed
to hire their own subcontractors and suppliers and the GC is
expected to work with them and be cooperative. Sometimes the
language will go so far as the GC is responsible for the owner’s
vendor’s schedule, site logistics, and even safety. Is this fair to the
GC if they do not also receive a markup on these companies and are
not involved in their selection? Some of the types of contractors and
suppliers that owners may employ include:
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
D. Can a project owner use their own people, their own employees (not
contractors), for installation of some items while the GC is on the
project? This is a union consideration as well. If the project is
complete, the owner is welcome to move in with their own people
and perform ‘fit up’. But if the GC is still on the project, and the
GC employs union craftsmen, can the owner do this? Does the
contract cover it? And even if the owner could, is it a good idea?
This brewery owner had several existing facilities and had their
own crew of mechanics. On this project, although the owner hired a
local union GC to build their building, they were not happy about
the GC’s use of all union subcontractors. The owner had a bias and
felt union plumbers and electricians were paid too much. Do you
agree? Unfortunately this owner was used to working without
permits and not necessarily building to code. Now how does this
affect its GC which needs to get along with the city for inspections,
especially if it hopes to receive the final certificate of occupancy?
How would you propose a contractor protect against this a) before
construction started, and b) during construction as the owner’s
mechanics show up with wrenches in hand?
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
E. Are union contractors (and craftsmen) necessarily more expensive
than non-union contractors? What happens when both union and
non-union craftsmen are working on the same jobsite? Does a two-
gate system work? Do these scenarios play out the same in a busy
versus a slow construction economy? Union craftsmen (and
contractors) will claim that because their people served an
apprenticeship, they are more qualified to do the same work and
will perform it faster, safer, and more economical. Is this
necessarily true? Doesn’t it take two people three days to do a task,
regardless of their union affiliations? Can either side prove their
point?
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
9
Superintendents
Introduction
The general contractor’s (GC’s) project superintendent is arguably the most
important single individual on a construction project. My apologies to our
clients, architects, and GC project managers (PM). The PM pushes the
paper on a construction project, or today, computer keys. The
superintendent pushes the field. In fact one nickname of the field boss is the
‘push’. This chapter includes many interesting examples of superintendents,
some good and some not so. There are many connections with other case
studies and chapters in this book from the material included here. In
particular, there is a direct correlation between the role of the field
superintendent with construction leadership (Chapter 16). The old school
superintendents were often gruff and not necessarily politically correct.
Today’s generation of superintendent often has a college background, is
well versed in technology, and understands the needs of all the built
environment team members, especially the craftsmen (and women!). Most
superintendents have traditionally come up through the field ranks, from
journeyman to foreman to assistant superintendent and beyond. The case
study examples in this chapter examine the communication tools of project
superintendents, including those necessary to deal with the project owner,
designers, and the city. Communications are discussed throughout the book,
including Chapter 11. Learning is a lifelong process, and achieving the role
of construction superintendent, especially today, is validation that we all
need to continue to learn, and to share our knowledge with others. This
chapter includes the following case studies related to construction
superintendents:
9.1: Conflicting superintendents
9.2: Underqualified PM and superintendent
9.3: Hand-drafted sketches
9.4: Two-trailer management team
9.5: From PE to teacher
9.6: Trailer superintendent
9.7: Structural engineer or superintendent?
9.8: Former superintendent
9.9: Different approaches to cost control
9.10: Super bear
9.11: Brand new tool belt
9.12: All the good superintendents are taken
9.13: Big job superintendent
9.14: Specialty superintendents
9.15: Off-shift superintendent
9.16: Superintendent of what?
9.17: Too nice of superintendent
Case studies throughout this book connect with multiple other chapters.
Case studies in this Chapter #9 also connect with cases in many chapters
including:
Case studies #9.6 and 9.10 – Chapter 11, communications
Case study #9.7 – Chapter 4, preconstruction
Case study #9.9 – Chapter 13, cost control
Case study #9.11, and all cases in this chapter to some degree
connect with Chapter 8, regarding jobsite operations, jobsite
personnel, and field labor
Case study #9.12 – Chapter 1, developers
Case study #9.13 – Chapter 3, construction organizations
Many cases in this chapter also connect with leadership Chapter 16
A retail client had just completed a large tenant improvement (TI) project
and was very happy with the general contractor’s (GC’s) superintendent. He
was a good communicator and was well mannered, which is important
when working in an occupied building. What are some other requirements
for a contractor to successfully work in an occupied retail building? The
client’s next project was a 2,000-stall cast-in-place (CIP) parking garage.
Their culture did not allow them to give work away to one GC – they had to
seek competitive proposals. Why might that be? The GC which had just
completed the TI also built CIP garages. They went after the project
aggressively and proposed the TI superintendent as their field boss, even
though he personally had little garage experience. Why did they do this?
Was it ethical? Do they plan a ‘bait and switch’? What does bait and switch
mean?
Figure 9A
The GC was successful with its proposal, but the experienced client was
wise to the bait and switch game and wrote their favorite superintendent
into the contract. They also included a $10,000 per day liquidated damages
(LDs) clause. The GC managed the LD risk with a second experienced
garage superintendent who knew how to achieve productivity out of his
direct craft workforce. They gave him a slightly different title so as not to
alert the owner. The two superintendents got along okay, but not great. One
ran the field and built the CIP garage, pushing his craftsmen and the subs
hard to avoid LDs. The TI superintendent represented the GC at all owner
meetings and meetings with the design team and permitting authorities.
Occasionally (once daily) one of the superintendents would step on the
other’s toes and voices would be raised. Did this system work? See Figure
9A for the result. Who do you suppose was the ultimate boss? If you could
be one or the other of these two superintendents, which would you choose?
How might this project organization have been improved upon? If you
could manage this project with one or the other superintendent, which
would you choose?
_____________________________________________________________
_____________________________________________________________
_____________________________________________________________
_________________________________
Figure 9B
_____________________________________________________________
_____________________________________________________________
_____________________________________________________________
_________________________________
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
So, put whatever hat you want on and analyze construction management
issues such as safety, insurance, cost, schedule, quality or claims. How can
success be achieved for each of the parties? If not success, how can they at
least come out even? Pick a party or two from this list and what
recommendations would you give them? Which would you rather be?
Ten development partners,
Lead development partner,
Original general contractor,
Financial owner’s rep, and/or
New builder/superintendent.
_____________________________________________________________
_____________________________________________________________
_____________________________________________________________
_________________________________
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
Figure 10A
B. The mechanical subcontractor also bid this project lump sum but
had extensive biotechnology experience. The PM took a big picture
approach. He did not charge for minor discrepancies. The client
eventually generated a very major change in scope, adding and
revising several pieces of mechanical equipment both on this
project and in an adjacent facility. Some of these can be seen in
Figure 10A. These changes amounted to over $600,000 worth of
mechanical work. Many of the equipment changes were performed
off-shift to minimize the impact to the client’s employees and
laboratory experiments. The client was very thankful. The
mechanical sub is still in the building doing time and material
(T&M) work, years later. If the client had not come through with
the big change order, how might this have worked out for the
mechanical sub? Should the GC be allowed to mark up this large
change order? What if the owner wanted to contract with the sub
outside of the GC for the change order? Should the GC be upset
they are not also involved in the long-term T&M work?
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
The GC’s project manager (PM) needs to make the same choice when it
comes time to draft subcontract agreements and purchase orders (POs). If
you choose the detailed approach, but you missed one item, is that item then
excluded? Some would say so. If you choose the generic approach but some
scope may be needed that is not clearly specified or shown on the drawings,
is that then excluded? GC estimators and PMs are always plugging holes in
sub and supplier scopes from lessons-learned on their past projects. It is
similar to plugging a hole in a dike that protects a city from a body of water.
Once you have that hole sufficiently plugged, another shows up. This does
not stop us from continuing with our mission as GCs - to make sub and
supplier scopes as tight as possible.
Scopes such as flashing, miscellaneous steel, rebar, blocking and backing,
and waterproofing are difficult to detail 100% in the RFQ or PO. One
common practice is for the GC to list every possible item they can find in
the documents (ask your superintendent for help here also) and add a phrase
such as: ‘Includes any and all additional work to make this a complete
system whether shown or called out for or not.’ Is that fair to the vendor? Is
it enforceable? This is often the preferred choice. What has been your
experience with successful and unsuccessful sub and supplier scopes? Other
than the material categories listed here, what systems require: a) a detailed
list, or conversely, b) a generic approach?
_____________________________________________________________
_____________________________________________________________
_____________________________________________________________
_________________________________
Notes
11
Communications
Includes drawing reading
Introduction
An attorney friend’s opening line in a dispute resolution conference given to
contractors was: “If contractors would learn to communicate, attorneys
would be out of a job.” Communication is unquestionably considered
among the top, if not THE top, construction leadership characteristic.
Communication skills include written, verbal, and maybe the most
important, listening skills. The ability to read and understand drawings and
specifications is a ‘given’ in the built environment, isn’t it? This chapter
includes a variety of case study examples where communications were used
positively and negatively on construction projects. All construction
management tools are essentially communication tools including:
Contracts, meeting notes, RFIs, submittals, schedules, estimates, inspection
reports, change orders and many others evaluated throughout this book.
Essentially each of the 275 case studies could have been included in this
chapter on communication to some degree. This chapter discusses the
following case studies related to all facets of construction communication
tools, including drawing reading:
11.1: Money can’t buy everything
11.2: Fear of the drawings
11.3: PM or PE?
11.4: Attorneys not allowed
11.5: No one is home
11.6: Follow the rules!
11.7: Shower curb detail
11.8: Ugly schedule
11.9: No schedule proof
11.10: Garage model
11.11: Dome hangers
11.12: Darryl’s footing
11.13: Broken water pipe
11.14: Thrown under the bus
11.15: Look the other way
Case studies throughout this book connect with multiple chapters. Many, if
not all, case studies in this Chapter #11 also connect with other chapters
including:
Case studies #11.1, 11.2, 11.3 and 11.14 – Chapter 16, leadership,
careers
Case study #11.5 – Chapter 1, project owners
Case studies #11.6 and 11.9 – Chapter 9, superintendents
Case studies #11.7 through 11.11, Chapter 7, scheduling
Case study #11.12 – Chapter 6, estimating
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
B. The young general contractor (GC) project manager (PM) working
on the adjacent apartment project witnessed and documented all
that happened with respect to the broken water pipe and subsequent
accident. His project had been complete for three years before he
received a phone call from an attorney. The attorney was very polite
and indicated he was looking into the laborer’s case and understood
the PM may have relevant documentation. Does it matter here
which party the attorney represented? The PM was so excited he
could contribute that he took the attorney to his company’s
basement and opened his file cabinet. Uh oh! When the PM’s boss
heard about this sharing he hit the roof. Why the concern? The GC
had not done anything wrong. How long are you are you required to
keep records? What would you do if an attorney asked to see your
files? What would legally be required for someone else to access
your documentation? Does your company have a policy about
speaking with or meeting with attorneys?
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
But other GC PMs look the other way, as do some project owners,
architects, and many agency owner’s representatives. Why do they let
things go? Is this ethical of them? Does this represent good project
leadership? Their projects get built and everyone seems to be happy in the
process at the end. Is the entire built environment industry messed up or is it
just me?
_____________________________________________________________
_____________________________________________________________
_____________________________________________________________
_________________________________
Notes
12
Construction controls
Including quality and safety controls, and
construction management tools such as submittals
Introduction
The term ‘construction control’ is common in both academia and in the
profession, but it is slightly misleading. We cannot actually ‘control’
someone or some event. What we can do is plan and manage to the best of
our ability. Some of the tools we use include adequate drawings and
specifications, clear contracts, sufficient time and budget, proper tools, and
a qualified workforce. There are typically five areas of construction controls
including schedule, documentation, cost, quality, and safety. The first three
of these have been assigned their own chapters in this book; 7, 11, and 13
respectively. This chapter is devoted to quality and safety controls. The
example case studies in this chapter include discussions of submittals,
inspections, and site security to reinforce these two important control areas.
But all five control areas interact. A project cannot be successful if the
contractor meets the expectations in four but falls short in one. For
example, a project which meets schedule and budget goals, is safe, has good
communications, but the quality of the installation is so poor that the project
owner will never use the contractor again, and the architect will not
recommend them to future clients, is a failure. This chapter includes the
following case studies related to construction controls, quality control,
safety control, and submittals:
12.1: Scaffold mishap
12.2: Dirty sanikans
12.3: Missing vapor barrier
12.4: Plywood footballs
12.5: Icemakers
12.6: Banned food truck
12.7: Aquarium trout
12.8: Utility inspector
12.9: No jerry-rigging here
12.10: No carpet submittal
12.11: Five-foot elevation snafu
12.12: Fix it, fix it quick
12.13: Lunch box contraband
12.14: Three-story fall
12.15: Who dropped the coupling?
Case studies throughout this book connect with multiple chapters. Case
studies in this Chapter #12 also connect with many other chapters,
including:
Case study #12.3 – Chapter 4, preconstruction
Case study #12.6 – Chapter 9, superintendents
Figure 12A
Case study #12.5: Icemakers
A general contractor (GC) does not want to be in the situation of receiving
100 kitchen refrigerators that lack icemakers when the contractual
documents required refrigerators equipped with this feature. The supplier
on this example project has offered to solve this issue by retrofitting the
refrigerators in the field, but this results in a two-week schedule delay
which will also affect the schedule of the plumber who has completed the
rough-in for the icemakers and is expected to connect them. Why doesn’t
the GC just reject the refrigerators and ship them back? The project
engineer (PE) in charge of coordinating this work apparently forgot to
review for this scope with the submittals. Does this relieve the supplier
from responsibility? What does a GC’s submittal stamp say? Who pays for
the plumber’s delay? Does the PE get fired because of this mistake?
_____________________________________________________________
_____________________________________________________________
_____________________________________________________________
_________________________________
Figure 12B
AHU 1 was set previously and most of the work had been
completed.
Apparently an electrician had left an errant two inch long conduit
coupling on the floor.
The plumber was making final connections internal to the AHU and
seemed to have accidently kicked the coupling.
The AHU supplier was responsible to provide the equipment with a
solid floor.
The mechanical subcontractor (sub) had plugged all penetrations in
the AHU floor but someone had left open a small gap to allow
condensate drainage during testing.
The conduit coupling rolled to the corner and found the only gap in
the AHU floor and fell to the roof.
The roofing sub was to flash and caulk around all equipment and
penetrations and make the complete system water tight, but they
had not yet finished.
The conduit then followed the roof slope for a few feet and fell
again through an un-flashed M&E opening.
The coupling now dropped through the truss interstitial space and
hit the solid scaffold deck, 12 feet below.
The conduit rolled again on what was supposed to be a flat surface
but found a slight slope and a small gap in the scaffold.
The coupling hit the safety net but the holes in the netting were too
large to retain it.
The two inch long conduit coupling fell an additional 50 feet and
hit an airplane fuselage which was on the assembly line near
completion.
Notes
13
Cost accounting and cost control
Including pay requests, activity-based costing, and
lean construction techniques
Introduction
There is much more to construction controls than just cost control, as
discussed in other chapters in this book, but cost is very important and often
receives most of the focus. Cost accounting includes assignment of the
original and modified estimate to cost codes, which allow effective cost
control tracking. Actual costs are recorded and input back into the
accounting system and form the basis for the contractor’s estimate database.
The accuracy of cost reporting is therefore crucial for future estimates. One
of the most important things a contractor does, if not the most important, is
receiving payment for work performed. Case study examples in this chapter
discuss both good and bad pay request and timely payment experiences.
Contractors must accurately report cost and monthly fee forecasts so the
company knows, at any given point of time, how each project and the
overall organization is doing financially. That accuracy depends on cost
control input from cost engineers, jobsite cost accountants, and project
managers. Understanding value-added activities and personnel is the
premise behind activity-based costing. Lean construction techniques
involve minimizing waste and building more cost efficiently. All these cost
control concepts are crucial to the long term financial viability of a
construction company and are discussed here. This chapter includes the
following case studies related to construction cost accounting and cost
control.
13.1: Pay request processing
13.2: T&M procedures
13.3: 10% cost forecast
13.4: Safety miss-code
13.5: Below cost home builder
13.6: Timesheets and cost codes
13.7: On-site accounting
13.8: Out-of-town accounting
13.9: Pipe hanger cobwebs
13.10: Medical fire
13.11: Equipment company controller
13.12: Activity-based costing
13.13: Warehouse staff
13.14: Surviving the recession
13.15: Timber-frame construction
13.16: Conservative cost forecast
Case studies throughout this book connect with multiple chapters. Case
studies in this Chapter #13 also connect with several other chapters
including:
Case study #13.4 – Chapters 9 and 12, superintendents and
controls, safety
Case study #13.5 – Chapter 1, developers
Case studies #13.7 and 13.8 – Chapter 5, contracts
Case studies #13.11 through 13.14 – Chapter 3, construction
organizations
Figure 13A
Figure 13B
Notes
14
Change orders and claims
Including negotiations
Introduction
Most projects have them. The key is to anticipate that change orders will
come, mitigate them, and manage the process once they occur. Good
communication skills and open book estimates and cost accounting help
facilitate expeditious resolutions. These tools were the topics of Chapters
11, 6, and 13 respectively. Many people use the terms change order
proposal, change order, and claim as the same thing, but they are different
as outlined here and explained in the case study examples in this chapter.
Change order proposal: An offer, a softer presentation of a cost for
a project change, whether requested by the project owner or
architect or the result of changed conditions.
Change order: Formal change to the contract incorporating one or
more approved change order proposals. The formal contract change
order should be a simple document and an accounting function,
assuming the change order proposals were mutually and amicably
negotiated.
Claim: The result of change order proposals or change orders which
are not accepted by both contracting parties. Claims often occur
after the fact or near project completion, as one or more parties
realize they did not achieve the financial outcome they had
anticipated.
_____________________________________________________________
_____________________________________________________________
_____________________________________________________________
_________________________________
The parties cannot bring a case to court (or litigation) without first
attempting an alternative dispute resolution process such as one or more of
these first three options. The DRB alternate has recently been added to
many copyrighted contracts as a viable choice. It involves the parties
selecting three neutral board members who participate in the project from
start to finish, rather than only showing up after a dispute has arisen. That
way they stay informed and often help deter the filing of a formal claim.
The DRB members are required to be impartial and not have worked with
either of the parties in the past 30 years. This requirement raises a series of
questions:
In a typical city, an experienced construction expert will have been
in a contract or associated with many built environment
participants. How do you find someone who is totally unknown to
all of the parties, including the design team? If they are totally
unknown, are they then an expert?
If you have to look outside of the area for an impartial expert, will
they have enough local knowledge to be a good judge on your
project?
If you hire from outside, are the contracting parties then responsible
for travel expenses and additional billable hours incurred for the
board member to travel, making this option uneconomical?
What has been your experience with claim preparation or defense? Have
you participated in negotiations, mediation, arbitration, litigation, or a
DRB? Was it satisfactory to you?
_____________________________________________________________
_____________________________________________________________
_____________________________________________________________
_________________________________
Does all this seem reasonable? It is a similar process that you may need to
follow if you have an automobile accident. But if the construction repairs
are deemed to be an emergency then the rules are slightly different. What
constitutes an emergency? Certainly repairs necessary to protect public
safety are an emergency. But are immediate repairs necessary to get a
business, such as retail, back up and running to minimize loss of sales?
Does insurance cover loss of business?
This sample client had its office and coffee manufacturing and distribution
in one of these historic brick buildings. They notified their insurance carrier
of the damage and the need to implement emergency repairs. The owner
employed their favorite architect and general contractor (GC) which both
mobilized immediately. These firms were told by their client that that they
were to proceed on a time and materials (T&M) basis. The insurance
adjuster also mobilized up and set up a jobsite trailer. But when the owner,
architect, and GC tried to engage the adjuster in the five-month repair
process he remained relatively silent. He was in an ‘observe and document’
mode. He was invited to all the meetings and copied with correspondence.
Did the owner’s team need to reach out like this? Why were they so
inclusive although they did not receive any help from the insurance agent in
return? When the adjuster was asked his opinion whether they should
pursue path A or path B with the repairs, he remained hands off.
Explain the strategy of the insurance company. What will they do in the end
and will they be successful? Explain the strategy of the property owner.
Will they be successful in the end? If the insurance company does not pay
100% of the cost of the repairs, is the project owner obligated to pay the GC
and architect? How would you proceed if you were the GC’s project
manager?
_____________________________________________________________
_____________________________________________________________
_____________________________________________________________
_________________________________
Likely most of us fall in the category 3-5 range. Where do you fit in?
Contractors negotiate every day, but most of those issues are not deal
breakers. Without thinking of them as negotiations, we attempt to get our
way with RFI responses, submittal approvals, acceptance of alternate
materials or methods, permit issuances, inspection approvals, pay request
approvals, timely receipt of payments, and many others. The two significant
negotiation topics for contractors are contract language and change order
approvals. Claim resolution is at another level. There are hundreds of
business school books and seminars on ‘how-to’ successfully negotiate.
There are few, if any, solely dedicated to construction. Several case studies
in this book have discussed negotiations including others in this chapter. In
addition to tactics discussed there, we include a few others to add to your
negotiation skills toolbox.
Do your research, be prepared, have backup.
No one wants to negotiate with another party that refuses to budge
or compromise on some point. This often results in walking away
and ultimately escalation.
Be willing to accept something other than what you are asking.
Ask for more than you want and be willing to settle for what you
need.
Find out what is the most important point for you. Don’t let the
other party know your position. Stand strong on that point and be
willing to give on other points.
Make it feel you suffered greatly by giving something up.
Conversely, find out what the other party truly needs.
Emotions can help or hurt. It is best to keep true emotions to
yourself – don’t let the other side read you. But playing a false or
exaggerated emotion may force a reaction from the other side.
Shake hands after. Don’t burn a bridge.
Figure 14A
We decided to visit the fabricator to make our case and flew to their
location. My boss advised me that a strategy the other side would use
against us was time. They would ask when our return flight was and use
that as a negotiating tactic, putting our back against the wall to force a
compromise. The owner of the fabrication facility was known simply as
Red. He was a very large man with a ruddy complexion. He was known to
have a wild temper, at which time his complexion would turn crimson. True
to form he used a loud voice throughout our meeting, pounded on the desk,
and let every expletive known to man fly, and even some new ones. My
boss remained very cool. When Red asked (as predicted) about our return
flight schedule, my boss replied “We haven’t booked a return flight and
plan on staying the night”, both of which were not true. Red had only an
internal design engineer with him during the meeting. No one from
production or estimating was in the room. After we calmly explained our
case, and the engineer confirmed our findings, Red turned pale and we split
the claim, 75% to us and 25% to them. We returned home exactly on the
flight we always had reserved. Did we win? Should I have resolved this
myself without my boss’ help? Did the fabricator lose? What negotiating
tactics would you recommend either party could have used to improve their
outcome? Why didn’t either party have their attorney present? Why did we
spend the money to meet in their shop since they were obviously the ones at
fault? Could all this have been avoided?
_____________________________________________________________
_____________________________________________________________
_____________________________________________________________
_________________________________
The owner’s rep put pressure on the GC and resolved items 1 and 2. Why
did he do that? Is that his responsibility? Is there anything the mechanical
sub should have been doing all along to avoid this uncomfortable situation?
Problem #3 was more difficult. When the GC PM finally submitted these to
the owner, they were all contractually too late. The agency owner’s rep felt
they had to stick to the contract terms and he rejected them all – even
though many were legitimate scope increases. Why did he do that? If he
had just agreed and processed the changes, and later payment, could he
have been found liable? If you bend the rules on one item, have you agreed
to bend the rules on others? The GC’s PM rejected group 3 change orders
back to the mechanical sub and blamed the owner. Since the sub processed
their requests for change timely, can the owner or the contractor then reject
them? How do you suppose this played out? What do you suppose this
incident did to the relationship between the mechanical sub and the owner’s
rep? They had worked on 15 projects together successfully up to this point.
_____________________________________________________________
_____________________________________________________________
_____________________________________________________________
_________________________________
Should I go on? How does the $1,400 look now? How about $30,000? Do
you suppose the owner’s rep taught the PE a lesson? But the casino
received two wonderful nearly new restrooms. Did the maintenance
manager get what he wanted? Be careful working with representatives of
the project owner on your jobs who are not necessarily empowered to
authorize, or pay for, extra work.
Post script: This PE eventually went back to school and became a
construction attorney. I wonder if she ever sets up a construction
professional in her law practice. Do attorneys do that?
_____________________________________________________________
_____________________________________________________________
_____________________________________________________________
_________________________________
Case study #14.14: Zero change orders?
Many in the built environment will say change orders are inevitable, and
that is likely true to some extent. All parties should plan for an efficient
change order process. But do they occur on all projects? And a project
which touts they did not have any changes, was something else at play?
Projects with overly inflated contract values, or those performed on a time
and material basis, may not see their overall budgets increased. But did
changes occur that cost the project money? Were these changes absorbed
within savings pockets such that other potential cost under-runs did not
materialize?
The internal owner’s representative for a pharmaceutical company was
required to bid a complicated project by his board of directors. He had bad
experiences with changes on bid work with a previous employer. He
attempted to convince his board to negotiate this clean room project but did
not prevail. The successful general contractor (GC) was not a typical lump
sum (LS) bidder but saw this project as a potential opportunity to enter a
new market and gain a new client. Is diving on a bid for this cause risky?
The GC estimator was made aware by his friend the architect that the owner
had set their budget expectations too low. The project would likely be
exposed to a lengthy value engineering (VE) process post bid with the low-
bidding GC. Is this insider knowledge unethical? It all played out as the
estimator had anticipated. The owner’s representative notified him he had
the successful bid but they (client and GC) needed to partner with the
architect and VE the project so it met budget. The two-month VE process
was successful and the parties entered into a LS contract. Was this prudent
of the owner? Should they have chosen another contract format? Should
they have re-bid the project after VE? This sometimes happens. Would that
be fair to the original low-bidder?
The owner was still concerned about change orders and allowed the GC a
1% increase in its fee if they would not process small discrepancy changes.
This was also in appreciation for the GC’s effort with VE. The GC agreed
as through the VE process they had plugged most of the estimate holes,
bought out all of the subcontractor scopes, and now had earned an
additional 1% in fee. Was this unethical? What the owner was unaware of
was the GC estimator (and subcontractors) had not been returning 100% for
VE credits. Is this a common practice? How can owners and architects
protect against contractors skimming off of VE preconstruction or credit
change orders during construction? This project actually finished at exactly
the same contract value as was agreed. There were zero change orders!
How was this possible? All parties, owner/architect/GC, saw this as a
successful project. Both the owner and architect suggested this GC to other
pharmaceutical companies. The estimator had accomplished his initial goal.
Did everybody win?
_____________________________________________________________
_____________________________________________________________
_____________________________________________________________
_________________________________
The sub which reportedly caused the fire declared bankruptcy and forfeited
their $25,000 insurance deductible. The GC also filed for bankruptcy and
forfeited their $50,000 deductible. Is bankruptcy a ‘get out of jail (almost)
free card’? So now you can see how clear cut this case is. You are on the
jury. Fill in whatever missing information you feel is relevant to your case –
it seems the parties did that. Who pays who?
_____________________________________________________________
_____________________________________________________________
_____________________________________________________________
_________________________________
Notes
15
Construction completion
Including punch list, close-out, testing, and
inspections
Introduction
An expeditious construction completion and project close-out are in
everyone’s best interest. There is much more to completion than just
cleaning up of the punch list – although that is critical and a few examples
in this chapter discuss that. But close-out has both a physical (construction
work) and paper component. The general contractor’s (GC’s) project
superintendent is typically in charge of the physical completion of the
project. This includes attending to the punch list and obtaining all necessary
inspections and approvals. The GC’s project manager and his or her project
engineer, handle the bulk of the financial and managerial close-out
responsibilities. This includes final change orders, final pay requests, lien
releases, as-built drawings, operation and maintenance manuals, startup,
and a host of others. Quality control (Chapter 12), or lack of, throughout the
course of construction shows up at project completion. Many good and bad
case study examples are discussed in this chapter highlighting these
processes.
The project close-out requirements should be established in the special
conditions of the specifications as well as the contract. Close-out should
start at the inception of the project, including defining close-out in
subcontract agreements. The project owner has been holding 5% to 10% of
the construction team’s money throughout the course of construction. This
is known as retention. The amount of retention held approximately equals a
contractor’s fee. Receipt of the retention is therefore ultimately receipt of
fee, which is a very important milestone for construction companies. This
chapter includes the following case studies related to construction
completion, punch list, close-out, testing, and inspections:
15.1: Paint shop
15.2: Double-door elevator
15.3: Framing liability
15.4: Stop light penalty
15.5: Pressurization test
15.6: As-built estimate
15.7: Punch list and a rolling table
15.8: Punch list and a shopping cart
15.9: Storm before the calm
15.10: Punch list: Love it or hate it
15.11: Drywall close-out
15.12: Inspectors
15.13: Stepped retention
15.14: Slow close
15.15: Ideal close
Case studies throughout this book connect with multiple chapters. Case
studies in this Chapter #15 also connect with other chapters including:
Case studies #15.2, 15.3, and 15.9 – Chapter 1, project owners and
owner representatives
Case study #15.4 – Chapter 7, scheduling
Case study #15.6 – Chapter 6, estimating
Case study #15.11 – Chapter 10, subcontractors
Many case studies in this chapter also connect with Chapter 12 on
construction controls, particularly quality control
The airplane manufacturer had orders to fill for commercial airlines and
associated stiff penalties if the planes were late. A photograph of the
building’s interior is included as Figure 15A. This project was on schedule,
but just barely. One week before the scheduled turnover during mechanical
start-up and testing, all heck broke loose. The exhaust opened up but the
intake did not correspond and the result was the fresh air louver was sucked
into the supply fan. Meetings were held. Inspections were conducted.
Letters and emails and phone calls were all over the air waves. The project
owner blamed the GC. The mechanical sub blamed the louvers (purchased
by the GC) and the owner’s control system. The louver supplier blamed the
mechanical sub. No one wanted to budge on a fix and assume responsibility
for the damage. Voices were raised and the owner directed the GC to “Just
fix it!” Do we resolve the ‘why’ before we repair? Will this be a change
order to the owner? Put your louver supplier hat on: Will you provide a new
louver without guarantee of payment? Put your mechanical subcontractor
hat on: Will you fix the fan without guarantee of payment? Do you know
what consequential damages are? This is why contractors (attempt to)
eliminate that clause from their contract. How much is a commercial
airplane worth?
_____________________________________________________________
_____________________________________________________________
_____________________________________________________________
_________________________________
Figure 15A
Figure 15B
The client received the owner’s rep report and saw a photograph of this
exact hip. Evidently the owner’s rep took the photograph but did not realize
the field error at that time. She typically took 20 random photographs per
visit. Should she have noticed? If she had, should she have shut the project
down at that time? Is that within the realm of responsibility of an owner’s
rep? The client asked her to cover the cost of repairs. Is she liable? This is
the same GC that struggled with the guaranteed maximum price contract
discussed in case #5.4. They also used this framing error, and cost to repair,
as a basis for their end-of-project cost over-runs. Should the owner pay
them for these repairs? Can you see the error in the photograph?
_____________________________________________________________
_____________________________________________________________
_____________________________________________________________
_________________________________
Case study #15.4: Stop light penalty
Should contractors be penalized for trying to do a good job but falling
slightly short, possibly at no fault of their own? Project owners – both
public and private – use liquidated damages (LDs) as a method to force
timely completion. Contractual language indicates LDs are not meant to
penalize, but charging daily or hourly fees for a late completion feels like a
penalty (opinion). Some owners will say: “We just wanted to get your
attention with the LDs”. Do owners believe contractors would like to finish
a project late? Aren’t they aware that the costs of jobsite general conditions
are largely time-dependent and the longer a project lasts the more it costs
the contractor? Isn’t that enough of a penalty?
A contactor had negotiated a five-story partially underground parking
garage with a general contractor (GC). This was a difficult project. See also
case study #2.3. The city required the addition of a traffic signal to be paid
for by the project developer. Requirements such as this are known to
developers as mitigation or extraction fees. The developer asked the GC to
add this $500,000 traffic light scope to the garage contract. The GC’s
project manager (PM) was polite and indicated this work was not their
specialty and provided the developer with a list of three other contractors
who could help. The owner did not want to engage another GC and insisted
the PM accept the work. Can the GC be forced contractually to do extra
work? Why would an owner prefer to stay with one contractor? The change
order came with strings attached in the form of $5,000 per day LDs. The
developer indicated the city required this, but that was never substantiated.
The contractor hired one of the specialists as a subcontractor and they did
their best, but the work was finished five days late. The developer withheld
$25,000 from the GC’s final retention check. Can he do this? When and
how are LDs (or bonus if applicable) settled up? Was it ethical? Was it fair
to the GC?
_____________________________________________________________
_____________________________________________________________
_____________________________________________________________
_________________________________
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
B. An old-school GC superintendent did not like inspectors rejecting
work, but he was just fine with acceptances and approvals. The
medical office building example for this case study was built of
structural steel and had a metal deck roof structure. The rigid
insulation and rubber roof product were to remain dry during
installation. Unfortunately it rained and saturated the insulation.
The roofer dried it out the best they could and proceeded to finish
the rubber membrane. After a few days of heat, the membrane and
insulation separated from each other. Large pockets of air formed
between the two. The young roofing inspector rejected the roof. The
superintendent and inspector and GC project manager (PM) met on
the roof to discuss the problem. The PM was 10 minutes late and
found the superintendent and inspector toe to toe against the
parapet. But this parapet was not three feet high, but rather was
comprised simply of two 2x6s laid flat so it was only three inches
high. The inspector’s heals were against this very short curb two
stories in the air with the superintendent pounding on his chest with
his finger and cussing and spitting all over the place. If you
intimidate an inspector enough, will he or she change their report?
The PM pulled the two apart and sent the inspector home. This was
obviously not a good example of leadership or communication or
collaboration or a whole lot of construction management concepts
discussed in this book. What should have happened? What would
you recommend happen now? No, firing the superintendent is likely
not one of your options.
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
C. A small residential builder was not accustomed to others telling him
what to do. He knew most of the local building inspectors. They
would typically give him a wave from their car window as they
passed by his projects, passing his inspection slips out the window
as they drove away. The builder was a carpenter by trade and did
most of the work by himself with his two sons and a nephew or
two. What background do you suppose building inspectors have?
One day a new inspector showed up at the site. He got out of his
car, was formal with his introductions, and asked to borrow the
contractor’s ladder. The inspector climbed up and took note of the
quantity of 16d galvanized nails securing the top plate of the
framing wall to the window header. How many nails are required?
In commercial construction there are likely some ‘rules’ but for this
builder, the amount needed was the amount he always put in; his
houses didn’t fall down, he never counted the nails. The inspector
told him he was short a few nails. The builder was not short with
his response. There was a lot of loud hollering and the expletives
were flying faster than nails out of a nail gun (exaggeration). The
inspector couldn’t get a word in edge-wise. He started sweating and
huffing and puffing and collapsed – he had a heart attack right then
and there. Well the ambulance got their quickly and the inspector
lived to inspect another day, but he wouldn’t return to this builder’s
projects. Would you? Obviously this is not the way to do business.
What should have happened? You cannot change the attitudes of
older builders (or designers or owners or inspectors) but how can
we manage the team without causing each other to be ill?
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
What other recommendations do you have for a timely and ideal close-out?
We can learn from both good and bad experiences.
_____________________________________________________________
_____________________________________________________________
_____________________________________________________________
_________________________________
16
Leadership
Including ethics and careers
Introduction
Construction leadership is definitely an advanced topic, but most leadership
books and seminars focus on business, religious, military, and/or sports
leadership examples. The project management and superintendent books
referenced in the appendix each have a chapter which is specific to
construction leadership. This chapter includes examples of both good and
bad leadership within construction organizations. Many case studies
throughout this book also connect with leadership. Our examples include
corporate executives but also explore leadership, ethics, and career growth
examples of superintendents, project managers, and project engineers. All
of these people are leaders in some regards and many can become better
leaders if they improve their communication skills (Chapter 11).
Construction personnel need to pay their dues and put in their time to learn
the technical aspect of the industry. Many superintendents start their careers
as carpenter apprentices and move through the ranks as journeymen and
foremen. Most college graduates will start their careers as project engineers
in hopes of becoming a project manager, senior project manager, and
eventually company executive. These growth paths are included in several
examples in this chapter as well. This chapter includes the following case
studies related to leadership, ethics, and construction careers:
16.1: My way or the highway
16.2: Unethical PM
16.3: The law of the lid
16.4: Schedule errors
16.5: Are you a PE?
16.6: In the right place at the right time
16.7: Job walk
16.8: Am I still relevant?
16.9: Second shift PE
16.10: QC foreman
16.11: Rising through the ranks
16.12: I was set up
16.13: Fore
16.14: Never quit learning
16.15: Draw the line
16.16: Donut hoarder
16.17: The squeaky wheel gets __
16.18: Don’t cry PE
Case studies throughout this book connect with multiple chapters. Case
studies in this Chapter #16 also overlap with other chapters including:
Case study #16.2 – Chapter 13, cost control
Case study #16.4 – Chapter 7, scheduling
Case studies #16.12 and 16.13 – Chapter 3, construction
organizations
Case study #16.15.A – Chapter 10, subcontractors
Many case studies and chapters cross-connect and references are included
in the example narratives in this chapter. In addition, multiple case
examples included with other chapters also connect with this chapter on
leadership including cases #1.4.B, 2.10, 3.5, 3.13, 3.15, 6.3, 6.7, 6.9, 8.10,
several from Chapters 7, 11, and 14, and others.
When this author was a GC PM and had PEs working for him, a few of
them also had civil engineering degrees and professional engineering
licenses. I would not allow them to put “PE” on their business cards and
told them to keep their PE stamp at home. Why was that? Was I short-
sighted? Was that unfair? What is your experience with GC PEs who have a
professional stamp?
_____________________________________________________________
_____________________________________________________________
_____________________________________________________________
_________________________________
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
B. A senior project manager (SPM) had assisted this younger female
PM with entering the biotechnology construction sector by securing
a competitively bid project for her to manage. These projects are
complicated and the drawings were not perfect so there was upside
fee potential. How might that be? The project owner and architect
knew of the SPM and his experience in this field. Rather than
welcoming him to the team, they asked his office for his
involvement to be limited. What were they afraid of? The two
middle-aged married men were very taken with the young female
PM. Now what do you think is going on? They even invited her to
attend an out of town industry conference with them. If you were
her, would you go? Should her employer let her go? Might the
employer encourage her? When do you draw the line? The PM was
learning as she went along with this first project in this field and her
first as a PM. She did an adequate job and there are always learning
pains. She was very nice to the owner and architect and caved on
nearly every change order opportunity. Now what do you think is
going on? The PM’s office had to step in to strong-arm the project
owner on final change orders to keep the project from being
recorded as a total loser.
Post script: When the project finished and the contractor reported a loss the
SPM was blamed for a bad estimate. Was that fair to him? Unrelated but
neither the owner nor architect invited the young PM to work on any of
their future projects. Was that fair to her?
_____________________________________________________________
_____________________________________________________________
_____________________________________________________________
_________________________________
Notes
17
Advanced case studies
Introduction
We learn lessons from our successes, but more so from our failures. There
are also valuable life lessons to learn from the actions of others, both good
and bad. The advanced case studies presented in this chapter provide
valuable lessons we should all add to our respective toolboxes. These
examples are based on actual experiences and observations of the author,
but names of the real parties are not included and any resemblances of
actual projects are coincidental. Some of the narratives have also been
elaborated on a bit for the reader’s enjoyment. Most of the case studies in
this chapter are quite complex and their topics could be spread across
several chapters. And many of the cases in the previous 16 chapters are also
connected to this chapter and the next on applied projects. A fun way to
present or resolve these issues is to have different individuals or teams take
opposing positions and the balance of the class or group judge which is
most convincing. Although some answers are likely more correct than
others, in many circumstances it ‘depends’ on the reader’s background and
personal bias. This chapter includes the following advanced case studies:
17.1: CM/GC double-dip
17.2: Misrepresentation
17.3: To the victor go the spoils
17.4: Architectural preferences
17.5: Oh rats!
17.6: LD favors
17.7: Design-build accountability
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
B. This large medical facility example project was setup exactly as
described above. None of the usual concrete subs wanted to bid to
the CM as the CM was also bidding concrete to itself. They were
successful and received a $15 mil LS subcontract agreement. This
situation is reflected in Figure 17A. The concrete project manager
(PM) was new to the company and had a LS attitude. It was his goal
to make as much money as possible on this one project. Whereas
the CM’s PM had a fixed fee and her goal was to treat the owner
fairly in hopes of repeat work in the future. She was bombarded
daily with change orders from the in-house concrete sub, many of
them unsubstantiated and others significantly over-priced. When
she complained to the corporate executives they told her to look the
other way and approve the changes. Her concern was if the project
owner later discovered this flagrant behavior in an audit scenario,
the contractor would not be invited back for future work. What
should she do? How should she, or should she, document her
office’s direction?
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
C. On another CM/GC example project the contractor was allowed to
negotiate the concrete into its scope. The project owner employed
an estimating consultant who ratified the estimate and kept an
oversight on change orders and audited actual expenditures. Why
would an owner allow the addition of the concrete scope? Why
would an owner have this system of oversight in place? But the CM
had to competitively bid the structural steel erection. They turned
out to be low-bidder on this scope and awarded their own company
a lump sum contract. When the owner and their concrete estimator
offered similar oversight for the structural steel package, the CM
declined. They had to bid against subcontractors and if the
subcontractors had been successful their books would have been
‘closed’. Why did the owner not allow the steel to be negotiated?
Do they have the same open-book audit rights? Why would the CM
not open its steel accounting books?
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
D. During the course of construction on this same CM/GC project the
superintendent did everything he could to help the steel
subcontractor superintendent – which was actually his co-employee.
He covered hoisting, forklift use, safety rails, survey alignment, and
cleanup. He provided the subcontractor with a jobsite office trailer
at no cost. After the structural steel was erected and the
subcontractor demobilized, the CM superintendent installed the
bulk of the miscellaneous steel (hand rails, stairs, corner guards,
etc.) with his own carpenters and ironworkers. This work was
contractually included in the steel subcontractor’s scope. Needless
to say the subcontractor made a substantial fee – almost 50% of its
bid. This obviously was not ethical. The superintendent argued it
was the most ‘efficient’ approach. Was he correct? Should the CM’s
PM have stepped in or gone over the superintendent’s head? These
examples are not what the CM/GC delivery method was to
accomplish. How can these abuses be prevented? Should the
CM/GC delivery method be abolished?
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
Figure 17A
Case study #17.2: Misrepresentation
A business owner with very little real estate experience needed additional
office space. A local developer had arranged several parcels of land and
was proposing a major waterfront mixed-use business park. Eventually the
project would include a dozen mid-rise buildings, all with views of the lake.
The uses included a hotel, offices, wineries, restaurants, retail,
condominiums, apartments, parking garages, a park, and more. Essentially
this was to be a live-work-play destination. No buildings had yet been built
but the developer had a fairly good set of civil drawings and had the two
six-story signature office buildings at the project’s entrance through the
schematic design (SD) phase. The developer had a complete
preconstruction (precon) team including a geotechnical engineer, surveyor,
architect, structural engineer, and general contractor (GC). Who is missing
from this list?
The GC had prepared a $15 mil budget for one of the two towers – the one
our example business owner was interested in (Tower ‘A’). The two parties
executed an option to purchase this one tower. The purchase and sale (P/S)
agreement included the current set of design documents. All the precon
team then transitioned to the buyer’s team. The developer had prepared a
stand-alone pro forma for tower A and shared this with the buyer.
According to the pro forma, this project ‘penciled’. What is a pro forma?
What does ‘penciled’ mean with respect to real estate development? It
seemed like a perfect fit, but was it?
The business owner was not comfortable with closing quite yet. He didn’t
really understand how to read drawings and although the budget was 12
pages long, he couldn’t make heads or tails from it. If a contractor’s
estimate is lengthy, it must be complete, isn’t it? By the way the GC’s
estimate was labeled as a ‘budget’ but the developer/seller referred to it as a
‘bid’ in all his discussions with the buyer. What are the differences between
the three terms ‘estimate’, ‘budget’, and ‘bid’ as they relate to construction?
The architect recommended the buyer hire an agency construction manager
(CM) who could advise him on the feasibility of the project. Now is when
the tables turn! The CM was well respected and had worked with all the
precon team members before, except he had not worked with the business
park developer. Here are some issues he found within two weeks of diving
into the documents, including the purchase and sale agreement.
Although the P/S agreement indicated tower A included an
underground garage, only 20 stalls were actually under building A.
200 stalls were to be located under future building B and were to be
shared with all the business park tenants and owners. Building A’s
garage space would not be secured from the balance of the garage.
There was an underground tunnel that connected the two garages
and ran under the main park entrance road. You might want to
sketch this as the SD documents did not have it very clear. The
tunnel and main road would not be within tower A’s lot line, but the
work to build these was on its drawings, along with the park’s
primary utility connections (water, sewer, gas, power, phone). The
buyer of tower A would need to pay for these scopes, although
these line items did not show up in the GC’s budget or the
developer’s pro forma. The new building would not be usable until
the road, utilities, tunnel, and complete garage were installed.
The GC’s budget was of course not a bid. The SD documents did
not have enough detail to obtain competitive subcontractor quotes.
The estimator had received a few $/SF plugs from subcontractors
(subs), but very few of them had looked at any drawings and there
were not specifications to accompany an SD set. When is the design
complete enough to solicit competitive sub bids? The estimate was
full of ‘allowances’, ‘plugs’, and ‘contingencies’. Many
construction elements were not included at all in the budget as the
design had not progressed that far. These budget gaps included
shoring at the tunnel and main road. Evidently shoring was to be
performed by a design-build (DB) subcontractor. Other necessary
elements were also missing as the GC had not been provided with
the P/S agreement and was not aware of business park scopes
which were the responsibility of tower A as discussed above. Is the
GC’s estimator at fault here? It would be easy to blame them, but
what would you have done?
The GC’s budget recommended the owner carry a 15%
contingency. Is this a fair amount to accompany SD documents?
The pro forma did not include this line item.
The building design and estimate lacked any finishes. The
developer had contracted with the design team for a ‘cold’ shell.
What is a ‘cold’ shell and how does that compare to a ‘warm’ shell?
The tenant improvement (TI) design work would have fallen under
the responsibility of a tenant if the developer had retained control of
the building. The design fee for the finishes and the cost of the TI
construction was not included in any of the estimates.
Mechanical, electrical, plumbing, and fire protection scopes were
all to be DB and would have also been the tenant’s responsibility.
Only very rough service connections were shown in the documents
and allowed for in the GC’s budget.
Our business owner buyer was also planning on occupying Tower
A, therefore there was not a separate tenant. Where is the estimate
for the TI costs, or finishes, for the buyer covered?
The geotechnical report indicated the water table was only five feet
deep, yet the garage required a 15-foot excavation. The GC had
excluded dewatering.
The GC’s estimator also excluded taxes and many soft costs such as
permits and inspections, but these would eventually need to be paid
for by the property owner. They were not on the pro forma.
We could go on and on but you see where this is going. The CM provided
narratives, evidence, and potential costs for all the above and more to the
potential buyer. Guess what happened to the pro forma when these costs
were plugged in? Did it still pencil? Should the buyer walk away at this
point? He had spent several months performing his due diligence study and
$50,000 of unrecoverable soft costs. Should the two parties renegotiate?
Postscript: The buyer walked away from this deal. The seller was very upset
as the property had been tied up and no other buyers had come forward. All
the design team lost a project. The GC lost a job too. Yes, their budget was
full of holes, but was that their fault? Should they have practiced precon
due diligence and either plugged these holes or flagged them as exclusions?
Were they laying in the weeds and planning on change ordering the new
buyer? Could any of the precon parties be liable from either the buyer or
seller? Because of the CM’s investigation he also lost a potential
construction project. Why do you suppose he did not just look the other
way? What would have happened if he had done just that, the deal went
forward, and the buyer was surprised with all these costs later on? Did he
ruin this deal for everyone? Do you suppose the CM and the
developer/seller are now buddies?
_____________________________________________________________
_____________________________________________________________
_____________________________________________________________
_________________________________
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
B. After removing topsoil for a new parking lot this GC discovered a
literal gold mine of clean gravel. They consulted with the
geotechnical (geo) engineer and since a building was not planned
for the site, both parties agreed the gravel could be excavated and
exported and replaced with less-expensive imported select backfill.
They were not substituting bad dirt for good dirt, but rather great
gavel with good dirt. Should the owner have been consulted at this
time? Doesn’t the geo typically work for the owner? The contractor
dug a hole 20’ deep and 200’ in diameter. It seemed there was no
end to the good gravel. The excavation stopped the day the agency
owner’s representative (rep) made his weekly jobsite visit. What do
you suppose the owner’s rep said to the GC’s superintendent? The
contractor of course sold the gravel at three times the value of the
import, including covering for equipment and trucking costs. Can
you figure out how many cubic yards were involved here and at
reasonable material prices, what their profit was? Was this legal?
Was it ethical? Should the owner’s rep look the other way? Should
the GC pay the owner? Would it matter if this were a lump sum or
GMP project? If it were a GMP project, might the over-excavation
equipment cost also have been rolled into the cost of the new
parking lot, essentially part of the cost of the work? Do you know
what a ‘borrow pit’ is?
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
Case study #17.4: Architectural preferences
This author once heard a prestigious architect at a college commencement
tell the new graduates: “You must stick to your ideals and be willing to
walk away from a project if your client does not accept your design
proposal.” Do you believe that it is ‘my way or the highway’ when it comes
to design work in the built environment? Sure, designers should recommend
what they feel is best and potentially influence or politely insist. But aren’t
we all, as builders and designers, here to satisfy our clients? The next four
examples represent extreme approaches to architectural influence.
A. An award-winning architect who was designing a boutique
restaurant knew her clients. She knew that the owners and operators
were 90% female and small in stature. Unbeknownst to the owner
or the preconstruction contractor, she chose a custom kitchen
cabinet and shelving system design that was two inches lower than
standard. Her interior design color boards had two totally
unacceptable groupings of materials and colors and one which was
her favorite. Guess which one the client approved? Was this ethical?
She also specified custom appliances which cost twice that of
conventional appliances and were also shorter. The owner pushed
back and demanded commercial size and grade restaurant
appliances. When all the materials were delivered, the appliance
and cabinet heights did not match. The architect’s position: “I
thought this would be better for you.” The client had to pay their
contractors to build custom bases for all the cabinets and lift them
two inches. Case study #4.4 is another example of when the
architect felt he knew better than the client – and in that case he did.
Are there subtle differences between: Present, recommend,
influence, push, insist, and/or demand?
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
B. Another smaller architecture firm in town had a very successful
business. Grandfather, father, and now daughter proprietors worked
with many repeat speculative developers. Their clients knew the
real estate development business and the architect drew what the
clients wanted. The architect knew what was a) necessary to gain
city approval, b) sufficient for a guaranteed maximum price
estimates and contracts, but not lump sum, and c) detailed enough
to get competitive subcontractor and supplier pricing. Is this
company selling itself short? Are they violating the design
fraternity creed (likely no such thing – I hope I didn’t offend
anyone)? The GCs enjoyed working with the architect as well
because many details and material selections were left to the
contractor’s means and methods choices. This architectural firm
didn’t receive many awards, but they enjoyed their success with the
built environment community they worked with. Were they wrong?
Were they not as good or as strong as architect A above? Should
they have imposed their design creativity even if it caused prices to
increase or impact the developers’ ability to lease or sell?
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
C. Another sole proprietor architect did not personally interface with
his clients or contractors much. He seldom attended coordination
meetings or visited the jobsites. Should this be a requirement? He
communicated mostly through email and occasionally via the
telephone. A lot of his design creativity came from searching the
internet. He even applied for building permits online. On a
downtown tenant improvement project he specified several custom
high-end materials. He found light fixtures and motorized window
blackout shades that were not carried by any local supplier. What
can be the advantages to ‘buy local’? The products were from an
overseas vendor. The contractor complained and attempted to value
engineer these specialties, but the architect did not approve. The
material arrived three weeks late to the site and upon inspection by
the electrical subcontractor, did not have an Underwriters’
Laboratory (UL) sticker. What is a UL sticker and why is that
important? Will the city or Labor and Industries approve materials
or equipment without a UL sticker? When the GC notified the
architect, he said that it was up to them to get stickers added in the
field. Is this possible? What is the process? What will it cost and
who will pay?
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
D. This is a similar situation to architect B, but to a different degree.
This one developer knows exactly what he wants to build. He
directs his architect what to draw and how and quantity of sheets
and level of detail of specifications etc. On one project he actually
obtained a rendering form another (former) architect and gave it to
his new architect and told him to replicate it. Is that legal? Is it
ethical? This developer would go so far as to tell his design team,
including engineers: “Draw what I tell you”. This is obviously the
exact opposite of the commencement speech discussed earlier. I
doubt many architects would say this is why they went to college
and this is how they want their careers to be remembered – drawing
what others told them to. How would you react? Would you work
for this developer? What if he paid well?
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
Is there a fair balance that can be reached here? Can a designer be creative
but still appease the project owners and contractor’s interests? Propose a
compromise approach. Prepare a scenario where architect A is right for a
particular project and another for B, C, and D. If you could recommend one
change in approach for each architect, what would it be?
_____________________________________________________________
_____________________________________________________________
_____________________________________________________________
_________________________________
Case study #17.5: Oh rats!
Maybe it is a secret, maybe not, but some biotechnology (biotech)
companies use live animals in their experiments. A general contractor (GC)
had been the successful low bidder on a biotechnology remodel project. The
two-story annex building, apparently utilized for storage, was to undergo a
major renovation. Both floors were to be built-out as state-of-the-art
laboratories (labs). The existing flat tar roof was to be removed and an
additional third floor would be added. This third floor would house all the
mechanical and electrical equipment including boilers, chillers, fans,
pumps, switchgear, and emergency generator. Some of the owner’s process
equipment would end up on this new utility floor as well.
The roof removal, new structural steel frame, metal siding, and new built-
up roof were all scheduled for August to minimize potential weather
damage to the new lab finishes work occurring in parallel on the two floors
below. All was proceeding according to plan until an unexpected
thunderstorm hit the city over a weekend. Although much of the new roof
and siding was in place, the roof drains and flashing had not yet been
completed. Water entered the new space and caused damage to the finishes,
especially the drywall. Should the GC have staffed the project 24-7 just in
case a disaster happens?
The GC’s project superintendent and project manager (PM) were assessing
the damage first thing Monday morning and developing a plan for repairs –
this was all manageable. The owner’s representative appeared from the
building next door and he was very upset about the water damage. He
informed the team that they had killed six valuable laboratory rats in the
basement below. The GC’s team didn’t even know the building had a
basement, let alone it was occupied, apparently including rats. He said the
lab rats were worth $10,000 each and the GC would have to pay this as a
consequential damage and he wanted a separate check for it by the end of
the week. Why did he want a check? If the contract did not specifically
address consequential damages (or loss of business damages) is it assumed
to be included or excluded? Needless to say the parties disagreed. Some of
their points, in relative order included the following:
From the GC:
The unexpected rain storm was an act of god and therefore not
the GC’s responsibility. Is this true?
The owner was to carry property insurance (AKA builder’s risk
insurance) for cases such as this, and the GC’s interest, as well as
that of the rats, should be covered under that policy. Have you
ever seen a copy of the property insurance policy on your
project? When should the contractor have asked to review that
and who should have reviewed it on their behalf?
The PM asked the owner’s representative for a copy of that
policy that morning, but the owner refused to comply. Does the
PM have a right to see it? Why did the owner refuse? Can he
refuse?
From the PM: “$10,000 is a ridiculous price for rats. You can
buy them at the pet store for $5 per each.”
The GC was not planning on making a claim against the owner’s
insurance policy and would pay for the lab floor cosmetic repairs
out of savings generated from their structural work. They felt
this was a fair compromise. Should you ever compromise when
you are confident you are correct?
B. OR asked his old friend Martin, the GC’s PM, whom he had known
since high school, under who’s authority or approval did he have to
change the design. Martin responded that this was a performance-
based design-build contract, and the city was getting exactly what
they had requested. OR requested actual cost backup to see if WYT
was under-running their estimate or how the contingency funds
were being allocated but Martin told him his office would not allow
any open-book review on a closed-book job. Is he correct? OR
confided in him that he was worried about his own personal
responsibility with these goings-on and that Martin needed to cover
him with some paperwork. Martin then sent through several RFIs
and submittals to the design team that worked for, or joint-ventured
with, WYT who rubber-stamped them all approved. Is this
acceptable? Where are the checks and balances with a design-build
project? Eventually the project finishes one month ahead of
schedule utilizing the same 20 man crew throughout as estimated.
WYT requests a bonus for finishing early but the city has indicated
that they did not really intend on charging LDs if WYT finished
late, and the two-month extension they received was not justified,
so the bonus clause in change order number one is invalid. If both
parties sign a contract change order, can one party later withdraw
their approval or can they enter into a renegotiation? Do contractors
actually write a check for LDs if the project finishes late? Do
owners actually pay a bonus if the contractor finishes early?
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
C. It turns out that there may be some minor punch list issues to
address, but WYT has demobilized and is forwarding all of their
calls to their attorney. The diving board broke and the swimming
fund-raiser isn’t working out for Betty. The tank has cracked and is
leaking and causing erosion to work its way down the field and
covering the councilman’s dairy ranch. The cause of the crack is
unclear. There was not a retention clause in the contract, so none
was withheld. There are not any close-out requirements stipulated
so the city does not have as-built drawings or O&M manuals to
compare anything against. The rancher sues the city for $1 mil. Isn’t
he suing himself? The liner subcontractor was short-paid by $1 mil
and liens the city and is threatening to foreclose. Can they do that?
Drygulch did not receive any interim or unconditional lien releases
from any of the parties and did not request performance and
payment bonds. The city files a claim against WYT for $5 mil to
cover claims against them and the estimated costs of repairs.
Drygulch hired an estimating consultant to provide backup for their
request. The city also files a claim against OR for $500,000, for
missing these obvious design and construction errors, which was
twice his fee. Is that reasonable?
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
D. Drygulch separately sues AIL for $2 mil on the basis that their
documents were not stamped, they did not perform field
inspections, and they did not run submittal approvals past the DRB.
Drygulch also claims it is illegal in this state to call yourself an
architect if you haven’t passed the state exam. Is this true? WYT is
happy to step back and allow this direct lawsuit. Can they do that?
WYT reports to AIL that they have spent their entire budget and
there is not any savings. AIL hires a professor from the local
community college to come up with a guestimate of actual costs.
How should actual expenditures be validated? What are typically
consultants’ limits of liability? Can WYT pass their claim on to
anybody? Will Drygulch be able to call any family members to the
stand to testify against each other? Is DB the solution for all
projects? How can DB be more ‘water-tight’?
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
C. During the design phase, Capital and CM and Arch are all working
together as expected. The owner remains a very active participant,
despite hiring a CM, and continues so throughout construction. CM
prepares very formal design reviews, noting recommendations to
save cost and improve constructability. Many design errors are
discovered and resolved, which should help minimize future change
orders. CM develops three different such documents, with a total of
1,000 entries. The owner does not provide any written reviews.
During the design process, Arch and their second-tier sub
consultants are not playing very well. The electrical engineer is
eventually dismissed. Many of CM’s review comments do not get
incorporated in subsequent design issues. The owner and CM did
not play a role in sub consultant short-listing or selection. Should
they have? Could they have required this? Do architects have
favorites? Do general contractors (GCs) have favorite
subcontractors?
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
D. All school projects have to be complete by September 1 in this
state. These six projects are estimated to take a year of construction
time, plus one month of bid cycle, so the CM schedules letting the
RFQ in July the year prior. The design team is not quite there with
their documents but the RFQ is sent to the seven GCs requesting
bids. During the two-week bid cycle the design team produces a
300-page revision. Is that a reasonable size of addendum? This
architect prefers to put very little on the drawings, but rather uses 8
½ x 11 pages of detailed sketches. Many of the same generic
drawings are used on all six projects; in fact many have been used
on other schools. The drawings then refer to a 5.5 inch thick sketch
book. Many of the sketches do not apply to this project; they are
just a conglomerate of the old ‘sticky-backs’. The addendum also
includes several sections of specifications not included with the
original RFQ, and three sets of specifications and cut sheets for
equipment the owner is going to purchase and the contractor has to
coordinate. What does a typical set of for-bid documents look like
on a public works project? How does that differ from a private
negotiated project and why the differences?
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
E. One of the seven bidders is a small-time local contractor. Their
largest projects thus far have been a series of You-wash car cleaning
facilities and custom homes, with a total annual volume of $5 mil.
The small GC’s chief executive officer (CEO) is well-known and a
well-liked member in the local community, with connections on the
school board. He has never worked with CM or Arch prior. The
GC’s catchy name is Small-Time Projects, or simply STP. Public
work rules allow anyone who can pay for the drawing set to bid on
the job. They did not ask any questions at the pre-bid meeting or
during the bid cycle. As happens often with public projects, an
unqualified contractor ends up as low-bidder and this was also the
case with STP; in fact they were at $9.5 mil, just under the budget.
The next firm was at $11 mil, with the 3rd and 4th bidders both at
about $11.1 mil. What do you think the right number was? How
low should low be? Most owners feel that within 10% is
competitive. Is that true? CM met with STP and tried to get them to
pull their bid. Can the owner’s agent do this legally? CM reportedly
wrote a letter to Capital, and recommended that STP be
disqualified, but during ‘discovery’ no one seems to have kept a
copy of that letter. STP gets the job. The one-page bid form filled
out and signed by STP on bid day is the official construction
contract. It refers to the ‘contract documents’ and the general
conditions in divisions 00 and 01 of the architect’s specification
book. There is no mention of CM’s role in any of these documents
either. The contract stipulates $1,000 per day liquidated damages,
with no bonus for early completion. How do bid bonds come into
play? Can a low-biding contractor be technically and legally
disqualified (DQ’d)? If they are DQ’d, will STP then have grounds
for a lawsuit? If they are awarded the project, will the second bidder
have grounds for a lawsuit?
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
F. The first sign CM had that STP was going to have difficulty was
their inability to provide a construction schedule. CM actually had
to provide the GC with scheduling software. The detailed critical
path schedule required in the contract from the contractor ends up
as a very summary level one-page 8 ½ x 11 bar chart with all six
projects included and no indication of any critical path. The GC’s
project manager (PM) had never worked on a commercial
construction project prior. Can the owner reject the contractor’s
personnel on a lump sum bid job? Construction proceeds fine for
about the first three months, and then the change orders begin to
roll in. With every change order, STP requests additional contract
time and extended general conditions. For example the cost to move
a door due to a design conflict is $200 in material and $200 in labor,
plus three-weeks in schedule extension and $5,000 in jobsite
general conditions. The bid form filled in by the GC indicates 10%
total overhead and fee on changes, but they request 20% (10% +
10%) on top of the above for each submission. The GC also filled in
a figure of $100/day general conditions costs for proven schedule
impacts on the bid form. The CM routinely marks up the changes,
approving all the direct and subcontractor costs requested with the
contracted bid markups, and rejecting the schedule and extension
costs. There will eventually be 750 change requests processed, 250
of which are rejected outright under advice from Arch that the work
is adequately referenced “in the documents”. What is a fair change
order process? How can a project owner ‘control’ the amount of
markups GCs and subcontractors include on change orders? How
can reasonable or ‘actual’ labor and material and subcontractor
pricing be verified? Can anyone (architect, owner, owner’s rep)
physically modify a GC’s change order? Can a GC do this to a
subcontractor?
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
G. Complicating this mess are the three specialty vendors selected
solely by the owner: Fried Kitchen Equipment, Sonics Sports
Courts, and Homeland Security Alarms. None of this work is
designed, delivered, installed, or coordinated very well. Who should
take the lead on this? During construction, there is not one
workshop or special meeting to address any of these coordination
problems. Purchase orders (POs) are drafted by CM for Capital to
sign. Should specialty vendors enter into contracts direct with the
project owner or should their costs be run through the GC’s books?
Who is responsible for performance? Should POs be the vehicle to
contract with specialty vendors who also provide field labor or
should they use subcontract agreements? How are issues such as
insurance, safety, labor unions, and security addressed?
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
H. Here are some additional facts in this case that are important in
resolving what is likely going to end up in a dispute:
_______________________________________________________
_______________________________________________________
_______________________________________________________
_________________________________
I. Prepare a spreadsheet showing original contract values for all of the
parties. Prepare another which indicates who is claiming who and
for how much. If all of these claims are filed simultaneously, with
the same court, what would be the judge’s first action? Are claim
resolution processes prescribed in the contract the parties should
follow? Place yourself in the position of an expert witness under the
employment of the owner, architect, CM, or GC. Pick one. Prepare
a three-point argument why you are correct. Anticipate the position
of the other side when you do this. Take the position of a mediator –
how might you get all four parties to reconcile? Take the position of
an arbitrator and make a firm irreversible decision in each of the
claims.
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
B. The successful bidding GC was a company which specialized in bid
work more so than negotiated work. They expected the documents
to tell the whole story, and if they didn’t they would be paid for
changes. They were not concerned with long-term relations as there
was always plenty of bid work available that welcomed low bids.
The GC had bought out all of their subcontractors (subs) and
suppliers (who also were contracted via bid pricing) and had
processed most of the submittals. The project had been proceeding
as-planned and the five story underground concrete garage was
complete and wood framing was ready to start. The framing
subcontractor (Framers) noted the wood i-joist did not have a
manufacturer listed in the technical specification book (specs) nor
did they see a call-out on the drawings. They had received two
prices for this material on bid day and chose the lowest supplier,
Brand X (BX) and forwarded their submittal to the GC for that
product. Upon review of the submittal, the GC’s project engineer
(PE) discovered a note on the concrete foundation bid drawings
which called for Brand Y (BY) i-joist or approved equal. Upon
notifying their subcontractor, Framers responded to the PE that this
was a better product and provided additional supporting
calculations. It was better than ‘equal’ in their opinion and therefore
is ‘approved’. The GC forwarded the submittal for BX as an
alternate with the engineering to show they are within 5% tolerance.
Can suppliers take exceptions to the bid documents? Why do they
do that? Isn’t the purpose of the specifications to call out required
manufacturers? What is the process to get an alternate product
approved and when is that supposed to happen? Should the GC or
the subcontractor provide a substitution request form?
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
C. The submittal was forwarded by the architect to the structural
engineer (SE) without comment (or review) and the SE quickly
rejected it noting BX was ‘potentially’ an acceptable manufacturer
but the specific joist flanges submitted did not meet spec. The
framing sub submitted additional information reflecting BX with
saw-cut flanges did meet the specified structural requirements. The
PE held an on-site meeting with all the parties, including Framers,
GC, and the architect. The architect did not ask SE to attend as that
would have been an extra service. The architect said they felt the
BX brand joist would be acceptable (they have used them on other
projects) pending confirmation they meet the city’s requirements for
the fire-rated assembly. The city also was not at this meeting.
Framers promptly ordered i-joist as bid. It was clear to them BX
was approved at this site meeting. Do verbal approvals count? The
GC later submitted additional information reflecting fire-rated
assembly requirements would be met, but the city returned this
submittal stating they would not review until the SE of record had
approved the product. The subcontractor soon begins installation of
joist. They are being pressured by the GC’s superintendent to keep
the job moving. The architect and engineer get together and later
reject the entire submittal and revert to their previous stance that the
joist do not meet spec and are not approved. The project owner is
notified by the architect that there ‘may’ be a problem. By this time
the first floor of joist are installed and the sheeting has been laid
and wall layout for floor two is underway. Why do parties posture
like this? Do superintendents push to get a project moving,
regardless of process or contract? Do you believe in the phrase: “It
is easier to ask for forgiveness than to ask for permission”? Why
did the city not take a stand? Since the owner has contracted with
the GC and the GC with the sub, shouldn’t the GC just resolve this
in favor of the owner?
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
D. Many letters and emails begin to flow from all parties. The owner
pressures the architect to approve the first floor as-is. The apartment
rental market has gotten even hotter and pre-leasing has been very
successful. The architect and structural engineer relent on floor one
but are requiring the GC and its sub to meet the requirements of the
contract documents on all upper floors and install Brand Y joist.
Here are some of their positions:
The project owner wants a credit for the BX alternate used in the
amount of $100,000. There is not backup to this amount, they
just feel the builders should be penalized. If they don’t provide
this credit, the first floor will require removal (even though the
architect has now finally approved in writing and the city has
accepted). How could this value have been substantiated?
The owner also threatens the GC with consequential damages if
the project finishes late. Can you have both LDs and
consequential damages in the same contract? Can they
unilaterally sue for consequential damages?
The GC claims the project was bought out based upon the bid
specs, and these did not list a particular manufacturer or flange
type.
Many material alternates were approved both prior to this
occurrence and throughout construction. The owner was always
looking to save money. The design team was not necessarily on
board with many of these substitutions. Did they set a precedent?
The framer is refusing to provide a credit to the GC and the GC
is refusing a credit to the project owner as they had chosen the
bid procurement method and the construction team is contracted
to the bid documents provided by the owner.
The framer claims BX met the structural requirements and since
that was what was included in their bid, the owner had already
benefited from a lower price. How might this have been
substantiated?
The project proceeds but updated drawings will not be
forthcoming with BX listed as an approved alternate.
The framer submits a change order request for $135,000 for the
change from BX to BY for the upper floors due to ‘restocking’
charges. They actually use both products on many of their
projects, but these joist had been fabricated to specific lengths
and will require modification to be acceptable for another
project. Does the project owner or architect approve this change
order?
_______________________________________________________
_______________________________________________________
_______________________________________________________
_________________________________
E. So, ‘who done it’? Who is responsible? The project owner? The
architect? The structural engineer? The general contractor? The
framing subcontractor? The subcontractor’s suppliers? The city?
Pick one and make a three-point argument why that party is at fault.
Place yourself in the position of another party. Make a three-point
argument why you are not at fault? Hint: There are many fingers in
this pie, as is often the case. Have you been on a project where
alternate materials were either (a) submitted, or (b) delivered and
installed without receiving approval for a substitution request? How
was that resolved?
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
J. Do subs bid the same price to all of the GCs? Do they give some
preferential bids? Why would they do this? What risks are the subs
taking? How does the GC respond if they discover they did not
receive the same bid from a sub as did their competitor GCs?
K. Is it ethical to use late sub bids (a) on a public project, (b) on a
private project, and/or (c) if the GC did not receive a valid bid in
that category and used its own plug number?
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
B. There are also some potentially unethical cash improvement
methods. If a contractor is discovered utilizing any of these, their
credibility with the project owner, and their subcontractors, will be
damaged. Hopefully you have not experienced any of these
examples. Do you know of other unethical methods?
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
When confronted, and audited (can the owner do that with an A102
contract?), the GC indicated they were holding 10% on their subcontractors
for the owner’s best interest. What are they talking about? What interests?
Do you agree this is a good practice? Yes it is done. Is it legal? Is it ethical?
Post script: The over-held retention was released two weeks after the audit,
but the mechanical sub still suffered on this project.
_____________________________________________________________
_____________________________________________________________
_____________________________________________________________
_________________________________
Figure 17B
Sometimes juries take a quick vote just to see where everyone is. That was
the case with this trial and the first vote was 9-3 in the city’s favor. Are you
surprised? Why do you feel it went that way? The judge in this case said the
jury did not need to come to a unanimous decision (12-0) but rather a super
majority of at least 10-2 would be required. At this time each of the jurors
was allowed to introduce themselves a bit more and explain their beliefs in
the case. One of the three holdouts was a bus driver who was being paid a
full wage to be on jury duty and didn’t want to go back to work. Do all
employers pay their people while on jury duty? Should they? Another
holdout wanted to hear more. This is a productive position. The third was a
former city employee who thought the city owed everybody, including him.
Was he being open-minded?
As each of the jurors explained their views it became quickly apparent that
the built environment community was well represented. One juror was a
real estate developer. One was an architect and the third was a general
contractor. Should they have been allowed on the jury? Juries are allowed to
ask to see physical evidence and one of these three asked the bailiff for a
copy of the contract between the city and the contractor. Later it was
reported that the attorneys were surprised of this request. They thought the
jury would want to see medical records. The developer opened the contract
and read the following clause to her colleagues: “The city is not responsible
for safety. The contractor is completely responsible for safety. The
contractor’s superintendent, or representative, is the individual responsible
for safety.” These three jurors felt the contract would state such, as most do,
and that is why they voted in favor of the city. The final vote was 11-1. Can
you guess who the holdout was? The jury was not allowed to know before
deliberation, but the former flagger had previously settled claims and was in
the process of filing other claims. Who might those claims be filed against?
Have you ever been on a jury? When you get a chance, do so, it is an
educational experience.
_____________________________________________________________
_____________________________________________________________
_____________________________________________________________
_________________________________
Notes
18
Applied construction projects
Introduction
Many of the previous examples highlight what happened during a
construction project or towards project completion. The cases here set the
projects up and discuss procurement, delivery, pricing, contracts, and
construction organizations. All the cases in this chapter connect with the
most important document on any construction project, the contract (Chapter
5). Each of these cases could be added to an example or two from the
previous 17 chapters to create a more involved and longer discussion. Most
of the applied project examples also reference other specific case studies
within their respective narratives. This chapter includes the following case
studies which introduce a variety of unique construction projects:
18.1: Speculative developer
18.2: Executive townhomes
18.3: Unit price bids
18.4: Bohemian mixed-use development
18.5: Infrastructure financing
18.6: Build-to-suit projects
18.7: Owner contracts with specialists
18.8: CMAR hotel
18.9: Multiple-prime school delivery
18.10: Mixed-use development
18.11: Heavy civil roundabout
18.12: Commercial-industrial hybrid
Case studies throughout this book connect with multiple chapters. Case
studies in this Chapter #18 also connect with other examples threaded in the
book. The project descriptions included here could be combined or cross-
referenced with numerous other cases. For example, this chapter has
overlaps with:
Project developers and owners in Chapter 1
The design team in Chapter 2
Contracts from Chapter 5
Estimates in Chapter 6
Scheduling from Chapter 7, and others.
This example project owner chose to utilize a lump sum (LS) bid
procurement process and a traditional general contractor (GC) delivery
method where the owner has two separate contracts, one with the GC and
one with the architect. Why would a private owner choose LS? What role
does an owner’s architect take in advising an owner of procurement,
contracting, and pricing methods for a contractor? All of the parties entered
into standard American Institute of Architects (AIA) contract agreements.
Why do architects prefer AIA contracts?
This is a large mixed use development (MXD) project which includes,
offices, a small restaurant, delicatessen and small grocery store, two floors
of underground parking, and utilizes many sustainable enhancements. The
project is being built by the developer on speculation of attracting tenants.
Should a developer start construction before signing up a tenant? It is
considered a shell and core construction style with minimal tenant
improvements (TI) planned at the outset. The interiors will be built out as
TI once the tenants are identified. Make a spreadsheet and list what is
included with shell versus TI. For example, foundations are part of shell
and carpet is part of TI. Now it is your turn.
The building structure includes a variety of cast-in-place concrete systems
including elevated slabs and slabs on metal deck. The structural engineer
transitioned from all concrete to all steel as the building rose out of the
ground. It has extensive excavation and shoring elements, complicated
siding system, green roofs and terraces, and several elevators. Why would a
speculative developer include sustainable elements? Aren’t they expensive?
The mechanical and electrical (M&E) design is minimal in a shell and core
project. Design-build (DB) subcontractors will bid to the established criteria
and the M&E designers will continue throughout construction on a design-
assist basis. This may also be referred to as a bridging delivery method.
Make an argument why M&E engineers might prefer a design-bid-build
delivery method with 100% drawings and specifications and another in
favor of pure DB. Is bridging a good compromise?
The total estimate at schematic design was approximately $50 million and
the construction duration was planned for 20 months. What happens at
project completion if the developer has not yet secured a tenant? Do the
designers and builders get paid? When does the owner transfer from a
construction loan to a permanent loan?
_____________________________________________________________
_____________________________________________________________
_____________________________________________________________
_________________________________
As the end users of facilities, project owners should be able to identify the
needs that the project must fulfill and set the project objectives accordingly.
They often are motivated to build something that would reduce costs during
the operations of the built facility. Therefore, the homeowner would
probably attempt to obtain an attractive and comfortable home; the
university would seek a library building that is both durable and
inexpensive to operate and maintain; and the oil company would seek a
facility that is easy and safe to operate while limiting the need for
extraordinary maintenance. This all factors into a study of life-cycle
costing. Who prepares estimates on behalf of project owners? Address this
with our three examples listed above. How might a project owner address
design and construction standards differently if they plan to occupy the
project for 20 years versus selling it within a year of completion?
_____________________________________________________________
_____________________________________________________________
_____________________________________________________________
_________________________________
During the design phase, the owner, who also does not have in-
house construction expertise, selects and hires an agency
construction management (CM) firm. The CM can help select a GC
once the design is completed and supervise the execution of the
project. Also, the agency CM will review the design to identify
potential issues with constructability and provide suggestions
before the design is submitted to competitive pricing. Why doesn’t
the architect also provide these services? How do you suggest the
owner contracts with the CM?
Once the design is completed, the owner, architect, and the agency
CM work to identify a GC which will price the project. Since the
team has chosen the bid procurement method, how would you
recommend they choose contractors to request bids from? How
many GCs should bid the project? 1, 3, 5, 10? Does the length and
makeup of the bid list vary on a project pending its size and
complexity? If you were a bidding GC, how long of bid list would
you prefer? How would your answers differ if a negotiated
procurement option would be utilized?
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
__________________________________________________________
__________________________________________________________
__________________________________________________________
_________________________________
Figure 18
List of abbreviations
We use many abbreviations and acronyms in construction, it is almost like
another language. All of those utilized in this book have been included in
this appendix, along with many other standard construction management
abbreviations.
2D, 3D, 4D, 5D two-dimensional (length and width), three-
dimensional (depth), four-dimensional (time) and five-
dimensional (cost)
A4S all four sides
AB anchor bolt
ABC activity-based costing
ACE assumptions, clarifications, and exclusions (bid and/or
contract document)
ACP asphalt
ACT acoustical ceiling tile, formerly asbestos ceiling tile
ADA Americans with Disabilities Act (law or building codes)
ADR alternative dispute resolution
AEC architecture, engineering and construction (design-build
company type)
AGC Associated General Contractors of America
AHJ authority having jurisdiction, often city building
department
AHU air handling unit (mechanical equipment)
AIA American Institute of Architects
AIL Architects in Landcaster, fictitious case study firm
AKA also known as
Allow allowance
Alt alternate or alternative
Arch architect or architectural
ASI architect’s supplemental instruction, AIA form G710
Asst assistant or assist
BC back charge
BCF bank cubic feet
BCY bank cubic yard
BE built environment
BF board foot (lumber); also backfill
BIM building information models or modeling
Board board of directors (BOD) or Dispute Resolution Board
(DRB)
BOT build – operate – transfer (delivery method), or bottom (also
BTM) or bottom of truss
BTR better (lumber grading, for example DF#2 and BTR)
BTU British thermal units (heat)
BY bank yard (cubic yard of dirt before excavation)
CA construction administration (architect’s role during
construction), also carpenter
CAD computer-aided design
CD(s) construction document(s) (design phase or drawings)
CE civil engineer or engineering, also construction engineering
or chief estimator
CEO chief executive officer
Cert certificate or certified
CF cubic foot or cubic feet
CFO chief financial officer
CIP cast-in-place (concrete)
CM construction manager or management
CM cement mason, concrete finishing craftsman
CM/GC construction manager/general contractor (also known as
GC/CM or CMAR)
CMA construction manager agency (delivery method)
CMAR construction manager at-risk (delivery method); also
CM/GC
CO change order, county, or cased opening
C-O close-out
C of O certificate of occupancy
Contractor general contractor or subcontractor
COO chief operating officer, also construction operations officer
Coor(n) coordination (process or drawings)
COP change order proposal
CP cost proposal, cost plus, carpet (also CPT), or critical path
CPFF cost-plus fixed fee
CPM critical path method, also critical path network (CPN)
CPPF cost-plus percentage fee (similar to T&M)
CPT complete or carpet (also CP)
Craft craftsman (construction field worker)
CSI Construction Specifications Institute
CVG clear vertical grain (Douglass fir trim)
CY cubic yard
D dimension, diameter (also dia), dryer, or depth
d penny (nail gauge such as 8d or 16d)
DA development agent (similar to owner’s representative), also
district attorney
DB or D-B or D/B design-build (delivery method)
DBB design-bid-build (delivery method)
DBO design build operate
DBOM design build operate maintain
DD design development (documents or phase)
Demo demolition
Demob demobilization
DF Douglass fir (tree species and lumber grade)
DFH(W) doors, frames, and hardware
Dia diameter
DL direct labor (estimate or cost area)
DM direct material (estimate or cost area)
Doc(s) document(s)
DQ or DQ’ddisqualify, or disqualified
DRB Dispute Resolution Board, or design review board, also
board
E engineer, east, exit, existing, or electrical
EA each
ECD estimated completion date (schedule)
EE electrical engineer
Elect electrical (subcontractor or systems)
EMR experience modification rating (safety)
EPC engineering, procurement and construction (design build
delivery)
Est estimate
ETA estimated time of arrival
EV earned value
EVM earned value method
EW each way or East-West
F furniture, Fahrenheit, or fire protection
FE field engineer or fire extinguisher
FF finished floor (elevation); also finish to finish
(schedule); also free float (schedule)
FF&E fixtures, furniture and equipment (often owner
supplied)
FIC furnished and installed by contractor
FIO furnished and installed by owner
FOB freight on board or free on board (material delivery
location)
FOIC furnished by owner and installed by contractor, also OFCI
FP food processing (equipment or industry sector), also fire
protection
FT foot or feet
F10.5 spot footing size, 10’-6” x 10’-6”
GC general conditions, also general contractor
GC/CM general contractor/construction manager delivery method,
see also CM/GC and CMAR
Gen or general general contractor
Geo or geotech geotechnical (report or engineer); also known as
soils engineer or report
GF general foreman (similar to an assistant superintendent)
GMP guaranteed maximum price (estimate or contract)
GWB gypsum wall board (also sheetrock or wall board or
drywall)
H height (also HT) or horizontal
HM hollow metal (door or frame)
HO home office
HOOH home office overhead
HR human resources, also hour
HT height (also H)
HVAC heating, ventilating, and air conditioning (mechanical
system or contractor)
IPD integrated project delivery
ITB instructions to bidders, also invitation to bid
IW ironworker (craftsman)
JIT just-in-time (material deliveries)
JV joint venture
Lab laboratory
LDs liquidated damages
LEED Leadership in Energy and Environmental Design
(sustainability)
LLC limited liability company or corporation
LLP limited liability partnership
LOI letter of intent
LR lien release
LS lump sum (cost estimate, bid, contract, agreement, or
process); also life safety (drawing); also late start (schedule)
M&E mechanical and electrical (contractors or designers)
M&M means and methods
MACC maximum allowable construction cost (similar to
GMP)
MBA master in business administration (college degree)
MBE minority owned business enterprise
MBF thousand board feet (dimensional lumber measure)
ME mechanical engineer
Mech mechanical (subcontractor or systems)
MEP mechanical, electrical, and plumbing (systems or
contractors)
MH(s) man-hour(s) or man hole (sanitary sewer)
Mil million
Mo(s) month(s)
Mob mobilization or medical office building (MOB)
MS Microsoft
MUP master use permit (entitlement permit)
NA or N/A not applicable or not available
NCR non-conformance report
NIC not-in-contract, also not included
No number (also #), or north
NTP notice to proceed
O&M(s) operation and maintenance manual(s)
OAC owner-architect-contractor (commercial construction
project meeting)
OC on center (dimension)
OE operating engineer, also owner’s equity
OFCI owner furnished contractor installed, also FOIC
OH overhead
OH&P overhead and profit (also known as fee)
OIC officer-in-charge
OM order-of-magnitude (cost estimate)
OR owner’s representative
OSHA Occupational Safety and Health Administration
OT overtime
PE project engineer, pay estimate, professional engineer, or
project executive
PEx project executive, also PE or PX
PL punch list (also punch), plate, plastic laminate (also plam)
PM project manager or management
PNW Pacific Northwest
PO purchase order or project owner
PPE personal protective equipment (safety)
PPP or P3 public-private partnership (delivery method) or Primavera
Project Planner
PR payment request, pair (doors); or public relations
Precon preconstruction (services or contract or fee)
Prefab prefabricated
P/S purchase and sale agreement
PT post tension (concrete cables), pressure treated (lumber), also
physical therapy
Punch punch list, also PL
PX project executive, also PE or PEx
QC quality control
QTO quantity take-off
QTY quantity, also Q
Rebar concrete reinforcement steel
Recap cost recapitulation sheet (estimating)
Rep representative (owner’s representative)
RFI request for information, or request for interpretation
RFP request for proposal
RFQ request for qualifications, also request for quotation
R/I rough-in
ROI return on investment
ROM rough-order-of-magnitude (cost estimate)
ROT rule of thumb
S structural, south, supply, or survey (drawing)
Schd schedule
SD(s) schematic design (documents or phase); also smoke detector,
soap dispenser, or storm drain
SE structural engineer, or south east
SF square foot or square feet, also start to finish (schedule
relationship)
SFCA square foot of contact area
SFF square foot of floor
SFW square foot of wall
SGF super general foreman
SHT(s) sheet(s) (plywood)
Sim similar
SOG slab-on-grade (concrete)
SOMD slab on metal deck (concrete composite slab)
SOV schedule of values (estimate or pay request)
Spec or specs specifications, also speculation
SPM senior project manager
Sprinks fire sprinklers, also nickname for fire protection sprinkler fitters
SQ square (one hundred square feet, roofing measure)
STP Small Time Projects (fictitious case study GC), also the
AGC’s Superintendent Training Program,
S/U start-up
Sub(s) subcontractor(s)
Subm submittal
Super or Supt superintendent
SVP senior vice president
SWPPP storm water pollution protection plan
SY square yard
T thermostat, time, thickness, title sheet (drawing), topography
(drawing), or ton
T&B top and bottom
T&M time and materials (contract or billing); similar to CPPF
TBD to be determined
TC tower crane
TCO temporary certificate of occupancy
TESC temporary erosion and storm water control
TI tenant improvement
TJI Truss Joist International (engineered lumber/’I’ beam)
TN or Ton tonnage (2,000 pounds)
TNG tongue and groove (also T&G)
Trade tradesman (construction field worker)
TVD target value design
Typ typical
U.L. Underwriter’s Laboratory
UMH unit man-hours
UNO unless noted otherwise, also unless otherwise noted (UON)
UP unit price
U.S. or USA United States of America
USGBC United States Green Building Council (sustainability)
UW University of Washington
V volume, vacuum, volt (electrical), vent, valve, or vertical
VCT vinyl composition tile
VE value engineering
Vol volume or volt
VP vice president
W west, width, wide flange (steel beam), waste, water, watt
(electrical), or washer (clothes)
W or w/ with
WA Washington State
WBS work breakdown structure
WBE women-owned business enterprise
WK or wks weeks
w/o without
WRT with respect to
WT weight
WWF welded wire fabric, also known as wire mesh (concrete
reinforcement)
WYT Wet Your Whistle (fictitious case study GC)
X times (multiplication), cross bracing, or ‘by’ as in
dimensional lumber (for example: 2x4)
YD yard
YR year
References
AIA Document A102 – 2017 Standard Form of Agreement
between Owner and Contractor where the basis of payment is Cost
of the work Plus a Fee with a Guaranteed Maximum Price.
Retrieved 2019 from American Institute of Architects [AIA].
http://aiad8.prod.acquia-sites.com/sites/default/files/2017-
07/A102_2017.sample2.pdf.
AIA Document A201 – 2017 General Conditions of the Contract
for Construction. Retrieved 2019 from American Institute of
Architects [AIA]. https://www.aiacontracts.org/contract-
documents/25131-general-conditions-of-the-contract-for-
construction.
American Institute of Architects. Contract documents produced
by the AIA. aiacontracts.org.
ConsensusDocs. Contract association which replaced the AGC
contracts. https://www.consensusdocs.org.
Construction Specification Institute: National association of
builders and material suppliers, source of the Master Format CSI
divisions and specification sections. csiresources.org.
Holm, L. (2019). 101 Case Studies in Construction
Management. New York, NY: Routledge.
Holm, L. (2022). A Contractor’s Guide to Planning, Scheduling,
and Control. Hoboken, NJ: John Wiley and Sons, Inc.
Holm, L. (2020). Construction Contract Documents, Amazon.
Holm, L., Schaufelberger, J. (2021). Construction Cost
Estimating. New York, NY: Routledge, previous editions published
by Prentice Hall and LAD.
Holm, L., and Schaufelberger, J. (2020). Construction
Superintendents, Essential Skills for the Next Generation, New
York, NY: Routledge.
Holm, L. (2019). Cost Accounting and Financial Management
for Construction Project Managers. New York, NY: Routledge.
Migliaccio, G., and Holm, L. (2018). Introduction to
Construction Project Engineering. New York, NY: Routledge.
Schaufelberger, J., and Migliaccio, G. (2019). Construction
Equipment Management (2nd ed.). New York, NY: Routledge.
Schaufelberger, J., and Lin, K. (2014). Construction Project
Safety. Hoboken, NJ. John Wiley and Sons, Inc.
Schaufelberger, J., and Holm, L. (2017). Management of
Construction Projects, A Constructor’s Perspective (2nd ed.). New
York, NY: Routledge.
Author background
Len Holm grew up in a construction family. His father Arne Holm was a
high-end residential and light commercial general contractor in Grays
Harbor County, Washington. Len was shoveling concrete and driving nails
from the age of 10. He eventually became a journeyman carpenter and
foreman. Len was the only member of his family to go to college and
earned bachelor degrees in Building Construction and Economics and a
master’s degree in Construction Management all from the University of
Washington. Len’s first job out of college in the early 1980s was as an
estimator and a scheduler traveling around the country building power
plants for Bechtel, one of the largest engineering and construction firms in
the world. He later found his way back to Seattle and worked on numerous
high-technology, medical, and industrial projects with a large local general
contractor as a project manager, senior project manager, and company
stockholder. Len founded his own company, Holm Construction Services,
in 1994 which has provided a variety of construction consulting services on
hundreds of residential and commercial projects including owner’s
representation, expert witness, and contractor training. He has been an
associate teaching professor at the University of Washington since 1993 and
has taught over 140 quarter-long courses on 13 different topics to
approximately 4,000 students. Len has authored and co-authored a dozen
books and several articles on a variety of construction issues including
project management, estimating, and dispute resolution. These books are
standard textbooks for many construction management programs
throughout the United States and in other countries: Management of
Construction Projects, A Constructor’s Perspective; Construction Cost
Estimating; and Construction Superintendents, Essential Skills for the Next
Generation co-authored with John Schaufelberger. Several others have been
written solo including Cost Accounting and Financial Management for
Construction Project Managers; 101 Case Studies in Construction
Management; Construction Contract Documents, and most recently,
Planning, Scheduling and Control. Questions or comments regarding this
book may be sent to holmcon@aol.com. I hope you enjoyed this new
endeavor.
Notes
Notes