Download as pdf or txt
Download as pdf or txt
You are on page 1of 61

9/08/2022

EXAMPLES

• EXAMPLE 1 (BORED PILES IN CLAY)

1
9/08/2022

• EXAMPLE 1 (BORED PILE in CLAY)

SPT

1.0 m
1.5 m 10
Firm/ stiff clay
SPT = 10 (average)
γ = 16 kN/m3
4.5 m 9 9.0 m

7.5 m 11

9.0 m 31

Very stiff clay


SPT = 30 (average) 1.0 m
γ = 18 kN/m3
10.5 m 30

• EXAMPLE 1 (BORED PILE in CLAY)


• Design assumptions:

• Pile length: 10.00m

• Pile shaft diameter: 0.90m

• Pile base diameter: 0.90m

• Cus (average along pile shaft): ?

• Cub at base: ?

• Phi-g: ?

• Qtotal: ?

• Load-settlement curve (simplified)

2
9/08/2022

• EXAMPLE 1 (BORED PILE in CLAY)


• Design assumptions:

• Pile length: 10.00m

• Pile shaft diameter: 0.90m

• Pile base diameter: 0.90m

• Cus (average along pile shaft): 50kPa

• Cub at base: 150kPa

• Phi-g: 0.5

• EXAMPLE 1 (BORED PILE in CLAY)


• Assessment of undrained shear strength cu from average SPT

• Firm/ stiff clay cu = 50 kPa

• Very stiff clay cu = 150 kPa

3
9/08/2022

• EXAMPLE 1 (BORED PILE in CLAY)


• Simplified way to assess load-settlement curve

• EXAMPLE 1 (BORED PILE in CLAY)


• Simplified way to assess load-settlement curve

• Qs = α * cu * A s

• Qs = 0.35 * 50kPa * 2.83m * 9m = 446 kN

• Qs = 0.45 * 50kPa * 2.83m * 9m = 574 kN

• Qs = 0.70 * 50kPa * 2.83m * 9m = 892 kN

• Qb = Nc * cub * Ab

• Qb = 9 * 150kPa * 0.636m2 = 859 kN

• Qtotal = Qs + Qb

• Qtotal = 1305 kN / 1433 kN / 1751 kN

• Apply phi-g of 0.5 * 1751 kN = 876 kN

4
9/08/2022

load settlement behaviour

The load-settlement behaviour of piles can be approximated based on the


assumption that the ultimate shaft resistance can be fully mobilised at very small
relative displacements of about 1-2% of the pile diameter. The mobilisation of the
ultimate end bearing requires much larger displacements of about 10% of the pile
diameter.

after Raison & Egan, 2016

load settlement behaviour

(876kN)

(446kN)

(430kN)

(9mm) (90mm) after Raison & Egan, 2016

10

5
9/08/2022

• EXAMPLE 2 (BORED PILE IN GRAVEL)

11

• EXAMPLE 2 (BORED PILE in GRAVEL)

SPT 2.0 m
1.5 m 8

Medium Dense sand


4.5 m 19 SPT = 14 (average)
γ = 18 kN/m3 9.0 m
ϕ = 33 deg

7.5 m 15

9.0 m 48

Very dense gravel


SPT > 50 (average) 1.0 m
10.5 m 55 γ = 21 kN/m3
ϕ = 39 deg
12

6
9/08/2022

• EXAMPLE 2 (BORED PILE in GRAVEL)


• Design assumptions:

• Pile length: 10.00m

• Pile shaft diameter: 0.90m

• Pile base diameter: 0.90m

• Phi-g: ?

• Qtotal: ?

• Load-settlement curve (simplified)

13

• EXAMPLE 2 (BORED PILE in GRAVEL)


• Task:

• Calculate the ultimate pile capacity

• Draft a simplified load – settlement curve

• Assess the impact of negative skin friction

• Assess what a potential reduction shaft friction due to the use


of bentonite would have on the pile capacity

• Assess a potential reduction in base capacity

14

7
9/08/2022

• EXAMPLE 2 (BORED PILE in GRAVEL)


• Assessment of pile design parameters from average SPT values

• Loose sand DR > 35%


• γ = 18kN/m3
• φ’ = 33deg
• Very dense gravel DR = 85%
• γ = 21kN/m3
• φ’ = 39deg

15

• EXAMPLE 2 (BORED PILE in GRAVEL)


• Effective stress calculation:

• σ’v01 = (((4.5m * 18kN/m3) – (3.5m * 10kN/m3)

• = 81kPa – 35kPa = 46kPa

• σ’v02 = ((9m * 18kN/m3) + (0.5m * 21kN/m3)) -

• = ((8m * 10kN/m3) + (0.5m * 10kN/m3))

• = (173kPa) – (85kPa)

• = 88kPa

16

8
9/08/2022

• EXAMPLE 2 (BORED PILE in GRAVEL)


• Shaft friction medium dense sand (Meyerhof)

• Qs1 = K * tanδ * σ’v0 * As

• Qs1 = 0.1 * 46kPa * 2.83 m * 9m = 117kN

17

• EXAMPLE 2 (BORED PILE in GRAVEL)


• Shaft friction medium dense sand (B1/VM4 NZ)

• Qs1 = K * tanδ * σ’v0 * As

• Qs1 = 1.0 * 0.46 * 46kPa * 2.83 m * 9m = 539kN

18

9
9/08/2022

• EXAMPLE 2 (BORED PILE in GRAVEL)


• Shaft friction dense gravel (Meyerhof)

• Qs2 = K * tanδ * σ’v0 * As

• Qs2 = 0.35 * 88kPa * 2.83m * 1m = 87kN

19

• EXAMPLE 2 (BORED PILE in GRAVEL)


• Shaft friction dense gravel (B1/VM4)

• Qs2 = K * tanδ * σ’v0 * As

• Qs2 = 2 * 0.56 * 88kPa * 2.83m * 1m = 278kN

20

10
9/08/2022

• EXAMPLE 2 (BORED PILE in GRAVEL)


• Shaft capacity:

• Qs = 117kN + 87kN = 204kN – Meyerhof Method

• Qs = 539kN + 278kN = 817kN – B1/VM4 method

• Base capacity:

• Qb = Nq x σ’v0 x Ab

• σ’v0 = (9m*18kN/m3+21N/m3)–(9m*10kN/m3)=93kPa

• Qb = 170 * 93 kPa * 0.636 m2 = 10,055kN

• Qb = 5,000kPa * 0.636 m2 = 3,180kN

• Qtotal = 817kN + 3,180kN = 3,997kN*0.5 = 1,999kN

21

Pile design - granular soils

End bearing capacity:

Qb = Nq * σ’v0 * Ab + cb’ * Nc ≤ fb

Values of Nq and fb:

22

11
9/08/2022

load settlement (no downdRAG)

(1923kN)

(333kN)
(211KN)

(1590kN)
Considering potential
installation effects and
base resistance
reductions to 4MP
(1272kN)
(9mm) (90mm) after Raison & Egan, 2016

23

• EXAMPLE 2 (BORED PILE in GRAVEL)


• Suggestions to ensure pile performance is met:

• Ensure optimal pile construction

• Cleanliness of pile base and use of sufficient drilling tools

• Use of polymer could reduce base due to sedimentation of


fines (use bentonite)

• Base grouting to ensure design base capacity can be


achieved

• Bitumen coating of the casing to reduce negative skin friction


(also shaft resistance)

24

12
9/08/2022

• EXAMPLE 2 (BORED PILE in GRAVEL)


• CFA piling would be an option but with inconsistent penetration
rates, skin friction should be reduced.

• For pile diameter > 750mm, the base capacity should be carefully
considered as the concrete fills the cavity at a slower rate.

• Belled piles are NOT recommended in granular ground conditions


due to potential instability of the bell under drilling support fluid.

25

• EXAMPLE 3 (BORED PILES IN ROCK)

26

13
9/08/2022

• EXAMPLE 3 (BORED PILE in ROCK)

1.0 m
Firm/ stiff clay
SPT = 10 (average)
γ = 16 kN/m3
9.0 m

Weak SW Sandstone
3.0 m UCS = 2 MN/m2
RQD = 53%

27

• EXAMPLE 3 (BORED PILE in ROCK)


• Design assumptions:

• Pile length 12.00 m

• Rock socket length: 3.00 m

• Pile shaft and base diameter 0.90m

• Shaft friction above rock not considered

• Concrete strength 40 Mpa

• Axial design load (N*) 2,000 kN

28

14
9/08/2022

• EXAMPLE 3 (BORED PILE in ROCK)


• Task

• Calculate the stress on the pile shaft

• Assess the ultimate shaft and base capacity of the bored pile
(rock socket)

• Assess the pile head settlement

• What could be effects of rock socket roughening?

29

• EXAMPLE 3 (BORED PILE in ROCK)


• Stress on the pile shaft:

• σ’ = P / As = 2 MN / 0.63 m2 = 3.2 MPa

• Suitable for 40 MPa concrete

• Rock socket shaft friction:

• fs = a * (qu)b

• fs = 0.3 * (2)0.5 = 424 kPa (Zhang & Einstein)

• Assuming a 3 m long rock socket:

• 424 kPa * 2.83 m * 3 m = 3,600 kN

• Shaft resistance: 3,600 kN * 0.5 = 1,800 kN < 2,000 kN

30

15
9/08/2022

• EXAMPLE 3 (BORED PILE in ROCK)


• Rock socket base resistance:

• fb = a1 * (qu)b1

• fb = 4.8 * (2)0.5 = 6,788 kPa (Zhang/ Einstein)

• Total pile resistance:

• Q = fs + fb = 3,600 kN + (6,788kN * 0.63 m2) = 7,876kN

• Total ULS pile resistance:


7,876 kN * 0.5 = 3,938 kN

• The pile head settlement will be caused through compression of


the rock socket and the base.

31

• EXAMPLE 3 (BORED PILE in ROCK)


• Pile head settlement:

• ρ = (Q * Ip) / (B * Ed) (Pells & Turner, 1978)

• Well-cemented sandstone:

- Modulus ratio of 300 (BS8004) – ratio of


E-modulus of intact rock to its UCS

- Mass factor for RQC up to 50% = 0.2

- Deformation modulus: 0.2*300*2MPa = 120MPa

- Econcrete / Erock: 31,000MPa / 300Mpa = 103

- L / B = 3 m / 0.9 m = 3.33

32

16
9/08/2022

• EXAMPLE 3 (BORED PILE in ROCK)

Ip = 0.3

33

• EXAMPLE 3 (BORED PILE in ROCK)


• Pile head settlement:

• ρ = (Q * Ip) / (B * Ed) (Pells & Turner, 1978)

• Ρ = (2,000 kN * 0.3) / (0.9 m * 120 MPa) = 5.6 mm

• Roughening the rock socket would provide improved shaft


resistance and the entire axial pile load could be transferred by
shaft friction.

• Construction verification for roughening must proof size, pitch


and cleanliness of grooves.

34

17
9/08/2022

• EXAMPLE 3 (BORED PILE in ROCK)

35

• EXAMPLE 4 (HILEY – TIMBER PILES)

36

18
9/08/2022

• EXAMPLE 4 (TIMBER PILE in CLAY)


N* = 100 kN

SPT

10 1.0 m
1.5 m
Firm/ stiff clay
SPT = 10 (average)
γ = 16 kN/m3
4.5 m 9
9.0 m

7.5 m 11

9.0 m 31

Very stiff clay


SPT = 30 (average)
30 γ = 18 kN/m3
10.5 m

37

• EXAMPLE 4 (TIMBER PILE in CLAY)


• Prediction of the resistance of a driven timber pile (circular)
using the ‘Hiley formula’

• Specifications:

• Pile embedment depth: 9.00m

• Pile type: Timber

• Pile diameter: 0.25m

• Cus (average along pile shaft): 50kPa

• Cub at base if pile: 150kPa

• Phi-g: 0.33

• Single acting 3ton hammer with 0.4m drop

38

19
9/08/2022

• EXAMPLE 4 (TIMBER PILE in CLAY)


• Task:

• Assess geotechnical load reduction factor

• Calculate the ultimate pile capacity

• Assess the temporary compression and final set of the pile

• Check driving stresses

• Assess a potential reduction in hammer efficiency with respect


to the pile capacity

39

• DRIVEN PILES (HILEY FORMULA)


• Hiley Formula (1925) – ASG Piling Specification

40

20
9/08/2022

• DRIVEN PILES (HILEY FORMULA)


• Hiley Formula (1925) – ASG Piling Specification

41

• DRIVEN PILES (HILEY FORMULA)


• Civil Engineering Code of Practice No. 4 (1954) U.D.C. 624.15

42

21
9/08/2022

• DRIVEN PILES (HILEY FORMULA)


• If W > Pe and the pile has not reached refusal

• n = (W + Pe2) / (W + P)

• If W < Pe and the pile has not reached refusal

• n = ((W + Pe2) / (W + P)) – ((W - Pe2) / (W + P))

• Where

• n = efficiency of the blow [dimensionless]

• W = weight of the hammer [kN]

• P = weight of the pile, anvil, helmet, follower [kN]

• e = coefficient of restitution of materials subject to impact [dimensionless].

43

• DRIVEN PILES (HILEY FORMULA)


• Single (left) versus double (right) acting hammers

• Single acting hammers:

- In single acting pile driving hammers, the ram is moved by


compressed air or steam up to the specified drop height before
the pressure is released and the ram falls under gravity.

• Double acting hammers:

- They are similar to single acting hammers but air or steam


pressure is applied to the ram during its decent to make the
hammer faster.

44

22
9/08/2022

• DRIVEN PILES (HILEY FORMULA)


• Single (left) versus double (right) acting hammers
(Examples)

45

• DRIVEN PILES (HILEY FORMULA)


• For piles driven with a double-acting hammer
the following blow efficiencies can be assumed:

• Steel piles without driving cap: 0.5

• RC piles without helmet but with packing on top of piles: 0.5

• RC piles with short dolly, helmet, packing: 0.4

• Timber piles: 0.4

46

23
9/08/2022

• DRIVEN PILES (HILEY FORMULA)


• Piles driven with single-acting or drop hammer show the
following blow efficiencies:

• RC piles without helmet but with packing


on top of piles: 0.4

• Steel or steel tube piles with driving cap


and short dolly covered with steel plate: 0.32

• RC piles with helmet, packing and dolly in


good condition: 0.25

• timber piles in good condition: 0.25

• timber piles in poor condition: 0.0

47

• DRIVEN PILES (HILEY FORMULA)


• PILE STRESSES AND HARDNESS OF DRIVING

• The comparative hardness of driving is expressed in terms of the


compressive stress in the pile or shoe. Indicative values are shown
below:

48

24
9/08/2022

• DRIVEN PILES (HILEY FORMULA)


• FACTORS OF SAFETY

• The ultimate axial compressive pile capacity, determined either


by test loadings or as the ultimate driving resistance derived from
the
Hiley formula, shall be divided by a factor of safety appropriate to
the circumstances prevailing, particularly the reliability of the
available data and the consequences of failure
of the structure being considered.

49

• DRIVEN PILES (HILEY FORMULA)


• FACTORS OF SAFETY

• ASG recommendations

50

25
9/08/2022

• DRIVEN PILES (HILEY FORMULA)


• FACTORS OF SAFETY

• Civil Engineering Code of Practice No. 4 (1954) U.D.C. 624.15

In this
example,
select FOS = 3

51

• EXAMPLE 4 (TIMBER PILE in CLAY)


• Assessment of undrained shear strength cu from average SPT

• Firm/ stiff clay cu = 50kPa

• Very stiff clay cu = 150kPa

52

26
9/08/2022

• EXAMPLE 4 (TIMBER PILE in CLAY)


• For preliminary design calculations, it is necessary to estimate the
value of R as followed:

• Assuming a compressive stress in the pile,

• Obtaining a hardness of driving,

• Obtaining the corresponding value of C

• Calculating R from the Hiley formula,

• Calculating the compressive stress in the pile

• Comparing that stress with the assumed value,

• If necessary, repeating the calculation, and until agreement is


reached.

53

• EXAMPLE 4 (TIMBER PILE in CLAY)


• Prediction of the resistance of a driven timber pile (circular)
using Hiley formula:

• Allowable stress in pile (medium driving) 7.0MPa

54

27
9/08/2022

• EXAMPLE 4 (TIMBER PILE in CLAY)


• Simplified way to assess load-settlement curve

55

• EXAMPLE 4 (TIMBER PILE in CLAY)


• Prediction of the resistance of a driven timber pile (circular)
using Hiley formula:

• Qs = α * cu * A s

• Qs = 0.8 * 50kPa * 0.79m * 9 m = 284 kN

• Qb = Nc * cub * Ab

• Qb = 9 * 150kPa * 0.049m2 = 66 kN

• Qtotal = Qs + Qb

• Qtotal = 284kN + 66kN = 350 kN * 0.33 = 116 kN

• Stress in the pile: 350 kN / 0.049m2 = 7.14 MPa

56

28
9/08/2022

• EXAMPLE 4 (TIMBER PILE in CLAY)


• Hiley formula and ASG specifications:

57

• EXAMPLE 4 (TIMBER PILE in CLAY)


• Hiley formula and Civil Engineering Code of Practice No. 4 (1954)
U.D.C. 624.15

• :

58

29
9/08/2022

• EXAMPLE 4 (TIMBER PILE in CLAY)


• Prediction of the resistance of a driven timber pile (circular)
using Hiley formula and ASG specifications:

• Total temporary compression C is derived from:

• C = Cc + Cp + Cq

• C = 2.0 mm + 7.0 mm + 3.0 mm = 12.0 mm (ASG)

• C = 2.5 mm + 6.7 mm + 2.5 mm = 11.7 mm (CEC)

• (Pile shaft is 10m long with 9m pile embedment)

59

• EXAMPLE 4 (TIMBER PILE in CLAY)


• If W > Pe, and the pile has not reached refusal

• W = 30kN > (8.4 * 0.25 * 0.25 = 0.525 kN)

• n = (W + Pe2) / (W + P)

• n = (30 + 0.525) / (30 + 8.4) = 0.79

• where:
• n = efficiency of the blow

• W = 30 kN

• P = 7kN/m3 *10m* 0.049m2 = 3.4kN + 5kN = 8.4kN

• e = 0.25 (single acting hammers for good timber)

60

30
9/08/2022

• EXAMPLE 4 (TIMBER PILE in CLAY)


• R = (W * h * n) / (s + c/2)
• R = (30kN * 400mm* 0.79) / (21 + 12/2 mm)
• R = 9480 kNmm / 27mm = 351kN * 0.33 = 117 kN

• where:

• R = ultimate driving resistance [kN]

• W = 30 kN

• s = 21.0 mm (specify 200-250mm per 10 blows)

• c = 12.0 mm

• n = efficiency of blow [/]

• h = 400 mm

61

• EXAMPLE 4 (TIMBER PILE in CLAY)


• Prediction of the resistance of a driven timber pile (circular)
using Hiley formula:

• Stress in the pile: 351kN / 0.049m2 = 7.1MPa

• Allowable stress in pile (medium driving) 7.0MPa

62

31
9/08/2022

• EXAMPLE 4 (TIMBER PILE in CLAY)


• If W > Pe, and the pile has not reached refusal

• W = 25kN > (8.4 * 0.25 * 0.25 = 0.525kN)

• n = (W + Pe2) / (W + P)

• n = (25 + 0.525) / (25 + 8.4) = 0.76

• where:
• n = efficiency of the blow

• W = 25kN (REDUCED DUE TO DEFECT)

• P = 7kN/m3 *10m* 0.049m2 = 3.4kN + 5kN = 8.4kN

• e = 0.25 (single acting hammers for good timber)

63

• EXAMPLE 4 (TIMBER PILE in CLAY)


• R = (W * h * n) / (s + c/2)
• R = (25kN * 400 mm* 0.76) / (21 + 12/2 mm)
• R = 7600 kNmm / 27 mm = 281kN * 0.33 = 94 kN

• where:
Instead of 117 kN
• R = ultimate driving resistance [kN]

• W = 25 kN (REDUCED DUE TO DEFECT)

• s = 21.0 mm (specify 200-250mm per 10 blows)

• c = 12.0 mm

• n = efficiency of blow [/]

• h = 400 mm

64

32
9/08/2022

• EXAMPLE 5 (SCREW PILE IN CLAY)

65

• EXAMPLE 5

P
Ignore top 0.5 m

2 MPa / 17 = 118 kPa


1.0 m
1 MPa / 17 = 58 kPa
Firm/ stiff clay
SPT = 10 (average)
γ = 16 kN/m3 0.8 MPa / 17 = 47 kPa
9.0 m

1 MPa / 17 = 58 kPa

6 MPa = 1,100 kPa EB

Weak 16
SWMpa
Sandstone
= 5,000 kPa
End bearing
3.0 m UCS = 2 MN/m2
RQD = 53%

66

33
9/08/2022

• EXAMPLE 5

P
Ignore top 0.5 m

2 MPa / 17 = 118 kPa


1.0 m
1 MPa / 17 = 58 kPa
Firm/ stiff clay
SPT = 10 (average)
γ = 16 kN/m3 0.8 MPa / 17 = 47 kPa
9.0 m

1 MPa / 17 = 58 kPa

6 MPa = 1,000 kPa EB

Weak 16
SWMpa
Sandstone
= 5,000 kPa
End bearing
3.0 m UCS = 2 MN/m2
RQD = 53%

67

• EXAMPLE 5 (SCREW PILE IN CLAY)


• Design assumptions:

• Pile length 5.00 m

• Screw pile shaft 114 x 6.75 mm

• Screw pile helix 400 x 12 mm

• Number of helices 1

• Spacing between helices N/A

• Average shaft friction 56 kPa

68

34
9/08/2022

Pile design - correlations

Generic correlations for granular soils

Relative density Dr (%) Cone resistance qc Typical φ


[Mpa]
Very loose Dr < 15 < 2.5 < 30°

Loose Dr = 15 – 35 2.5 – 5.0 30°- 35°

Medium dense Dr = 35 – 65 5.0 – 10.0 35° - 40°

Dense Dr = 65 – 85 10.0 – 20.0 40° - 45°

Very dense Dr > 85 > 20.0 > 45°

69

Pile design - granular soils

End bearing capacity:

Qb = Nq * σ’v0 * Ab + cb’ * Nc ≤ fb

Values of Nq and fb:

70

35
9/08/2022

Pile design - Screw piles

The bearing capacity of screw piles based on individual


bearing failure is given by the following equation:
Rd, ug = Σ Ah * fb + fm,x * H’πd
n

- Rd, ug = design ultimate helix strength


- Ah = area of the helix
- fb = ultimate soil bearing pressure at deeper helix level
- N = number of helical bearing plates
- fm,x = ultimate shaft friction
- d = diameter of screw pile shaft
- H’ = effective shaft length
Individual failure typically occurs for helix spacings in
excess of 3 times the helix diameter.
71

• EXAMPLE 5 (SCREW PILE IN CLAY)


• Individual bearing mechanism:

• Rd, ug = Σ Ah * fb + fm,x * H’πd

• Ah = area of the helix

• fb = ultimate soil bearing pressure below helix

• N = number of helical bearing plates

• fm,x = ultimate shaft friction

• d = diameter of screw pile shaft

• H’ = effective shaft length

72

36
9/08/2022

• EXAMPLE 5 (SCREW PILE IN CLAY)


• Assess pile resistance:

• Rd, ug = Σ Ah * fb + fm,x * H’πd

• Rd, ug = ((0.126 m2 * 1,000 kPa)) +


(0.114 m * πd * 4.5 m * 56 kPa)

• (126 kN) + (90 kN) = 216 kN

• Rg* ≥ ø * Rd (Geotechnical design strength)

• No load testing: Rg* = 216 kN * 0.5 = 108 kN

• Static load testing: Rg* = 216 kN * 0.8 = 173 kN

73

• EXAMPLE 5

P
Ignore top 0.5 m

2 MPa / 17 = 118 kPa


1.0 m
1 MPa / 17 = 58 kPa
Firm/ stiff clay
SPT = 10 (average)
γ = 16 kN/m3 0.8 MPa / 17 = 47 kPa
9.0 m

1 MPa / 17 = 58 kPa

6 MPa = 1,000 kPa EB

Weak 16
SWMpa
Sandstone
= 5,000 kPa
End bearing
3.0 m UCS = 2 MN/m2
RQD = 53%

74

37
9/08/2022

• EXAMPLE 5 (SCREW PILE IN CLAY)


• Design assumptions:

• Pile length 3.00 m

• Screw pile shaft 114 x 6.75 mm

• Screw pile helix 400 x 12 mm

• Number of helices 2

• Spacing between helices 1.2 m

75

• EXAMPLE 5 (SCREW PILE IN CLAY)


• Task

• Calculate the ultimate pile resistance

• Cylindrical failure mode

• Individual bearing failure

• What difference would make a static load test in estimating the


geotechnical pile resistance

• Ignore structural design in this example (e.g. welding


connections, structural capacity of shaft and helices, pile head
connection)

76

38
9/08/2022

Pile design - Screw piles

The bearing capacity of screw piles based on individual


bearing failure is given by the following equation:
Rd, ug = Σ Ah * fb + fm,x * H’πd
n

- Rd, ug = design ultimate helix strength


- Ah = area of the helix
- fb = ultimate soil bearing pressure at deeper helix level
- N = number of helical bearing plates
- fm,x = ultimate shaft friction
- d = diameter of screw pile shaft
- H’ = effective shaft length
Individual failure typically occurs for helix spacings in
excess of 3 times the helix diameter.
77

• EXAMPLE 5 (SCREW PILE IN CLAY)


• Individual bearing mechanism:

• Rd, ug = Σ Ah * fb + fm,x * H’πd

• Ah = area of the helix

• fb = ultimate soil bearing pressure below helix

• N = number of helical bearing plates

• fm,x = ultimate shaft friction

• d = diameter of screw pile shaft

• H’ = effective shaft length

78

39
9/08/2022

• EXAMPLE 5 (SCREW PILE IN CLAY)


How much load will be
• Assess pile resistance: transferred by the upper
helix? In this example, the
• Rd, ug = Σ Ah * fb + fm,x * H’πd upper helix is ignored.

• Rd, ug = ((0.126 m2 * 58 kPa * 9) * 1) +


(0.114 m * πd * 2.5 m * 56 kPa)

• (66 kN) + (50 kN) = 116 kN

• Rg* ≥ ø * Rd (Geotechnical design strength)

• No load testing: Rg* = 116 kN * 0.5 = 58 kN

• Static load testing: Rg* = 116 kN * 0.8 = 93 kN


• Please be very careful about founding end bearing piles in firm/
soft clay without reliable settlement assessments!

79

Pile design - Screw piles

The bearing capacity of multiple helix screw piles based on


cylindrical shear failure is given by the following equation:
Rd, ug = Ah * fb + fm,x * H’πd + Σ(π * Dh * S * τ)

- Rd, ug = design ultimate helix strength


- Ah = area of the helix
- fb = ultimate soil bearing pressure at deeper helix level
- fm,x = ultimate shaft friction
- d = diameter of screw pile shaft
- H’ = effective shaft length
- Dh = diameter of the cylindrical shaft
- τ = shear strength of the soil between helical plates
- S = spacing of helical plates (typically ≤ 3Dh)

80

40
9/08/2022

• EXAMPLE 5 (SCREW PILE IN CLAY)


• Cylindrical shearing mechanism:

• Rd, ug = Ah * fb + fm,x * H’πd + Σ(π * Dh * S * τ)

• Ah = area of the helix

• fb = ultimate soil bearing pressure below helix

• fm,x = ultimate shaft friction

• d = diameter of screw pile shaft

• H’ = effective shaft length

• Dh = diameter of the cylindrical shaft

• τ = soil shear strength between helical plates

• S = spacing of helical plates (typically ≤ 3Dh)

81

This approach heavily relies


• EXAMPLE 5 on soil plugging between the
helices, ensure adequate soil
• Assess pile resistance: shear strength for plugging

• Rd, ug = Ah * fb + fm,x * H’πd + Σ(π * Dh * S * τ)

• Rd, ug = (0.126 m2 * 58 kPa * 9) +


(0.114 m * πd * 1.3 m * 55 kPa) +

• (π * 0.4 m * 1.2 m * 49 kPa)

• (66 kN) + (26 kN) + (74 kN) = 166 kN

• Rg* ≥ ø * Rd (Geotechnical design strength)

• No load testing: Rg* = 166 kN * 0.5 = 83 kN

• Static load testing: Rg* = 166 kN * 0.8 = 133 kN

• Use lowest value unless verified by load testing.

82

41
9/08/2022

• EXAMPLE 5 (SCREW PILE IN CLAY)


• Discussion (use lower value for initial design)

• Cylindrical failure mode

• 83 kN (no testing) or 133 kN (static load test)

• Individual bearing failure

• 58 kN (no testing) or 92 kN (static load test)

• Static load testing will provide verification and real test data
about the pile performance. Founding in the sandy bearing layer
almost doubles the geotechnical pile resistance.

83

• EXAMPLE 5

P
Ignore top 0.5 m

2 MPa / 17 = 118 kPa


1.0 m
1 MPa / 17 = 58 kPa
Firm/ stiff clay
SPT = 10 (average)
γ = 16 kN/m3 0.8 MPa / 17 = 47 kPa
9.0 m

1 MPa / 17 = 58 kPa

6 MPa = 1,000 kPa EB

Weak 16
SWMpa
Sandstone
= 5,000 kPa
End bearing
3.0 m UCS = 2 MN/m2
RQD = 53%

84

42
9/08/2022

• EXAMPLE 5 (SCREW PILE IN CLAY)


• Assess pile resistance:

• Rd, ug = Σ Ah * fb + fm,x * H’πd

• Rd, ug = ((0.126 m2 * 1,000 kPa)) +


(0.114 m * πd * 4.5 m * 56 kPa)

• (126 kN) + (90 kN) = 216 kN

• Rg* ≥ ø * Rd (Geotechnical design strength)

• No load testing: Rg* = 216 kN * 0.5 = 108 kN

• Static load testing: Rg* = 216 kN * 0.8 = 173 kN

• USE LONGER PILES EMBEDDED IN BEARING LAYER

85

• EXAMPLE 6 (LATERAL PILE RESISTANCE - TIMBER PILES)

86

43
9/08/2022

• EXAMPLE 6 (TIMBER PILE in CLAY) – Lateral pile


resistance
? kN 100kN
0.1 m

SPT
10 1.0 m
1.5 m

4.5 m 9 9.0 m
Firm/ stiff clay
SPT = 10 (average)
γ = 16 kN/m3
7.5 m 11

9.0 m 31
Very stiff clay
SPT = 30 (average)
30 γ = 18 kN/m3
10.5 m

87

• EXAMPLE 6 (TIMBER PILE in CLAY)


• Assessment of undrained shear strength cu from average SPT

• Firm/ stiff clay cu = 50kPa

• Very stiff clay cu = 150kPa

88

44
9/08/2022

• EXAMPLE 6 (TIMBER PILE in CLAY)


• Prediction of the lateral resistance of a timber pile (circular)
using Broms method:

• Pile embedment: 9.00m

• Pile type: timber

• Pile diameter: 0.25m

• Cus (average along pile shaft): 50kPa

• Cub at base if pile: 150kPa

• Stiffness of pile (EI) 13MPa

• with E = 10,000MPa

• I = 0.0013m4

89

• EXAMPLE 6 (TIMBER PILE in CLAY)


• Prediction of the lateral resistance of a driven timber pile
(circular) using Broms’ method.

Chart
Chart for for
short piles long
piles

90

45
9/08/2022

• EXAMPLE 6 (TIMBER PILE in CLAY)

βh = (Khb/EI)1/4

kh = 0.4 (k/b)

kh = 0.4 (8/0.25)=6.3

Outside of chart
USE LARGER PILE

6.3

91

• EXAMPLE 6 (TIMBER PILE in CLAY)


• Prediction of the lateral resistance of a driven timber pile
(circular) using Broms’ method.

• The assessment of the lateral displacements is not possible as


the displacement might be too large for the long pile or the
method is unsuitable to assess the displacement. The input value
was outside the
design chart.

• Use a larger pile diameter


or ‘over-boring’.

92

46
9/08/2022

• EXAMPLE 6A (CONCRETE PILE in CLAY) – Lateral


pile resistance
? kN 100kN
0.1 m

SPT 600mm steel sleeve filled


10 1.0 m
1.5 m with 40MPa concrete and
3m depth

4.5 m 9 9.0 m
Firm/ stiff clay
SPT = 10 (average)
γ = 16 kN/m3
7.5 m 11

9.0 m 31

Very stiff clay


SPT = 30 (average)
30 γ = 18 kN/m3
10.5 m

93

• EXAMPLE 6A (CONCRETE PILE in CLAY)


• Prediction of the lateral resistance of a concrete pile (circular)
using Broms method:

• Pile length: 3.00m

• Pile type: Concrete

• Pile diameter: 0.60m

• Cus (average along pile shaft): 50kPa

• Cub at base if pile: 150kPa

• Stiffness of pile (EI) 205MPa

• with E = 32,000MPa

• I = 0.0064m4

94

47
9/08/2022

• EXAMPLE 6A (CONCRETE PILE in CLAY)


• Prediction of the lateral resistance of a concrete pile (circular)
using Broms method:

Chart
Chart for for
short piles long
(free head) piles

95

• EXAMPLE 6A (CONCRETE PILE in CLAY)


• Prediction of the lateral resistance of a concrete pile (circular)
using Broms method:

Chart
Chart for for
short piles long
(fixed head) piles

96

48
9/08/2022

• EXAMPLE 6A (CONCRETE PILE in CLAY)


• Prediction of lateral movement of a concrete pile

• Estimation of lateral pile deflections

97

• EXAMPLE 6A (CONCRETE PILE in CLAY)


• Prediction of lateral movement of a concrete pile
Estimation of lateral pile deflections free head:

y0 * kh * D * L / Qa = 5.1

y0 * 5.3 * 0.6 m * 3 m / 63 kN = 5.1

0.15 y0 = 5.1

y0 ≈ 34 mm

Estimation of lateral pile deflections fixed head: (be clear


about the applied load)

y0 * 5.3 * 0.6 m * 3 m / 270 kN = 1.5

0.04 y0 = 1.5

y0 ≈ 37 mm (about 10 mm for 63 kN lateral loading)


We should compare deflections under similar loads
98

49
9/08/2022

• EXAMPLE 6A (CONCRETE PILE in CLAY)


• Prediction of the lateral resistance of a concrete pile (circular)
using Broms’ method:

• The lateral resistance after Broms method provided about 63 kN


lateral resistance (free head), with a geotechnical reduction factor
= 0.5.

• The assessment of the lateral displacements for the 600 mm


diameter concrete section provided estimates of 34 mm (free
head) and 10 mm (fixed head) with 63 kN lateral loading at the pile
head.

• Considering the depth of the maximum moment, the 3 m depth


seems to be appropriate.

99

• EXAMPLE 7 (LATERAL PILE RESISTANCE - BORED PILES)

100

50
9/08/2022

• EXAMPLE 7 (BORED PILE in SAND) Lateral pile


resistance
? kN 100kN
0.1 m

SPT 600mm steel sleeve 2.0 m


1.5 m 4
filled with 40MPa
concrete and 3m depth

4.5 m 4 Loose sand 9.0 m


SPT = 4 (average)
γ = 17 kN/m3
7.5 m 5 ϕ = 27 deg

9.0 m 48

Very dense gravel


SPT > 50 (average)
55 γ = 21 kN/m3
10.5 m
ϕ = 39 deg

101

• EXAMPLE 7 (BORED PILE in SAND)


• Assessment of undrained shear strength cu from average SPT

• Loose sand DR = 15%


• γ = 17kN/m3
• φ’ = 27deg

102

51
9/08/2022

• EXAMPLE 7 (BORED PILE in SAND)


• Prediction of the lateral resistance of a bored pile (circular) using
B1/VM4 method:

• Pile length: 3.00m

• Pile type: concrete

• Pile diameter: 0.60m

• (Stiffness of pile (EI) 205MPa

• with E = 32,000MPa

• I = 0.0064m4

Consider temporary support of the 3m deep


hole up to 1m below ground water level in
loose sands!

103

• EXAMPLE 7 (BORED PILE in SAND)


• Prediction of the lateral resistance of a bored pile (circular) using
Broms method.

Chart Chart
for for
short long
piles piles
(free
head)

104

52
9/08/2022

• EXAMPLE 7 (BORED PILE in SAND)


• Prediction of lateral movement of a concrete pile

• Estimation of lateral pile deflections

105

• EXAMPLE 7 (BORED PILE in SAND)


• Prediction of lateral movement of a concrete pile

• Estimation of lateral pile deflections free head:


Lateral
• (y0 * (EI)0.6 * nh0.4))/ QaD = 20
movements
are usually
• (y0 * (205)0.6 * 0.40.4)) / (68 * 3) = 20
limited to
50mm (TBC)
• y0 ≈ 240 mm (values at the boundary of chart)

• Estimation of lateral pile deflections fixed head:

• (y0 * (EI)0.6 * nh0.4))/ QaD = 1.3

• (y0 * (205)0.6 * 0.40.4)) / (68 * 3) = 1.3

• y0 ≈ 16 mm Similar load applied as for free head

106

53
9/08/2022

• EXAMPLE 7 (BORED PILE in SAND)


• Prediction of the lateral resistance of a concrete pile (circular)
using Broms’ method:

• The lateral resistance after Broms method provided about 68 kN


lateral resistance (free head), with a geotechnical reduction factor
= 0.5.

• The assessment of the lateral displacements for the 600mm


diameter concrete section provided estimates of 240mm (free
head) and 16mm (fixed head) with 68 kN lateral loading at the pile
head.

• Considering the depth of the maximum moment, the 3m depth


seems to be appropriate.

107

• EXAMPLE 7A (BORED PILE in SAND) Lateral pile


resistance
? kN 100kN
0.1 m

SPT 600mm steel sleeve 1.0 m


1.5 m 10
filled with 40MPa
concrete and 3m depth

4.5 m 9 Medium Dense sand 9.0 m


SPT = 10 (average)
γ = 18 kN/m3
7.5 m 11 ϕ = 32 deg

9.0 m 48

Very dense gravel


SPT > 50 (average)
55 γ = 21 kN/m3
10.5 m
ϕ = 39 deg

108

54
9/08/2022

• EXAMPLE 7A (BORED PILE in SAND)


• Assessment of undrained shear strength cu from average SPT

• Medium Dense sand DR = 35%


• γ = 18kN/m3
• φ’ = 32deg

109

• EXAMPLE 7A (BORED PILE in SAND)


• Prediction of the lateral resistance of a bored pile (circular) using
B1/VM4 method:

• Pile length: 3.00m

• Pile type: concrete

• Pile diameter: 0.60m

• (Stiffness of pile (EI) 205MPa

• with E = 32,000MPa

• I = 0.0064m4

Consider temporary support of the 3m deep


hole up to 2m below ground water level in
loose sands!

110

55
9/08/2022

• EXAMPLE 7A (BORED PILE in SAND)


• Prediction of the lateral resistance of a bored pile (circular) using
Broms method.

Chart Chart
for for
short long
piles piles
(free
head)

111

• EXAMPLE 7A (BORED PILE in SAND)


• Prediction of lateral movement of a concrete pile

• Estimation of lateral pile deflections

112

56
9/08/2022

• EXAMPLE 7A (BORED PILE in SAND)


• Prediction of lateral movement of a concrete pile

• Estimation of lateral pile deflections free head:


Lateral
• (y0 * (EI)0.6 * nh0.4))/ QaD = 10
movements
are usually
• (y0 * (205)0.6 * 1.50.4)) / (89 * 3) = 10
limited to
50mm (TBC)
• y0 ≈ 70 mm (y0 ≈ 240 mm in loose sand)

• Estimation of lateral pile deflections fixed head:

• (y0 * (EI)0.6 * nh0.4))/ QaD = 1.0 Similar load applied as


for free headed case
• (y0 * (205)0.6 * 1.50.4)) / (89 * 3) = 1.0

• y0 ≈ 7 mm (y0 ≈ 16 mm in loose sand)

113

• EXAMPLE 7A (BORED PILE in SAND)


• Prediction of the lateral resistance of a concrete pile (circular)
using Broms’ method (MD sand):

• The lateral resistance after Broms method provided about 89 kN


lateral resistance (free head), with a geotechnical reduction factor
= 0.5.

• The assessment of the lateral displacements for the 600 mm


diameter concrete section provided estimates of 70mm (free head)
and 7mm (fixed head) with 89 kN lateral loading at the pile head.

• Considering the depth of the maximum moment, the 3m depth


seems to be appropriate.

114

57
9/08/2022

• SUMMARY (BORED PILE in SAND)


• Consider methodology related limitations of some ground
investigation methods, e.g. DCP testing. Such test is commonly
used up to 3 m depth but due to increased soil resistance along the
DCP rods, the blow count could be higher as it reflects both, cone
resistance and friction along the shaft.

• Such practice could lead to the over-estimation of soil layers,


which can have significant impacts on the design and the actual
performance of the pile (e.g. 240 mm versus 70+ mm lateral
deflections for free headed piles in this example)

115

DISCLAIMER
Engineering New Zealand and/or the author do not guarantee or warrant the accuracy,
reliability, completeness or currency of the information in this presentation nor its
usefulness in achieving any purpose.
The recipients of this presentation are responsible for assessing the relevance and
accuracy of the content of this presentation.
This presentation should not be substituted for your own engineering judgement.
Engineering New Zealand and/or the author will not be liable for any loss, damage,
cost or expense incurred or arising out of or in connection with any unauthorised use
of this presentation.
The work and opinions expressed in this presentation are those of the author.

116

58
9/08/2022

THANKS. • Dr Martin Larisch


• Jacobs New Zealand Ltd

• Martin.Larisch@jacobs.com

117

59

You might also like