Professional Documents
Culture Documents
PS-10 (SA-ABC-JSA-PS10-01) Relocation of Existing Security Facilities
PS-10 (SA-ABC-JSA-PS10-01) Relocation of Existing Security Facilities
Project UPGRADE SECURITY FACILITIES EAST WEST PUMP STATIONS Contractor ABC
Plant Location Saudi Aramco Pump Station 10 (PS-10) Project Number 6601000190
BI Number BI-10-00449
Description of Activity JSA for Relocation of Existing Security Facilities
JSA No. SA-ABC-JSA-PS10-01
Prepared By Reviewed By Reviewed By. Reviewed & Approved By.
ABC HSE Supervisor ABC HSE Manager Project Manager SAPMT SAFETY Advisor/Coordinator
Name Name Name Name
Power Shutdown, Electrical works, Cable Laying and Security devices Relocation Activities: Hand tools, Power Tools ( Grinder, Drill Machine, Heat
Gun), Testing equipment (Multimeter etc.), Power generator and Fusion Splicer
Asphalt Cutting and Manual Excavation Activity: Asphalt cutter, Hand tools ,Power generator Wheel barrow, Hammer Drill
Tools and Equipment used Lifting Activity: Boom Truck, Mobile crane, Flat and Low / trailer and lifting gears
Installation and Dismantling Security fence Activity: Hand tools, Power Tools, Power generator, Hammer Drill, Auger Machine
Backfilling, Spoil Removal and Compaction Activities: Hand tools, Wheel barrow, JCB Backhoe, Wheel Loader, Skid Loader, Dump Truck, Water
Truck, Plate & Roller Compactor
References GI, RIM, PROCEDURE AND CSM :
SMS No. ARAMCO GI SA- CM, GI No. NOTE
SMS 6.01,6.02, 6.03, 6.05 (Hot work G.I. 2.100 Work Permit Procedures CSM, Vol-II, Part-I, Chapter -1 Saudi Aramco Safety All employees involved in the activity shall
permit, Cold work permit, Confined space G.1 6.030 Traffic and Vehicle Safety. Emergency Reporting and Response Hand Book be equiped with all mandatory and hazard
entre permit & Excavation Permit process) Gl.1781.001 Fire Protection and Safety CSM Vol-II, Part-II, Chapter-I specific PPE's like hard hat,safety
Equipment Inspections Excavation and Shoring shoes,safetyglass, gloves,FRC clothing, etc.
GI.6.012 Isolation, Lockout and use of Hold at all times. Other hazard specific PPE's
Tags shall be worn as per applicable.
SMS 6.12 Job Safety Analyses. Gl.1021.000 • Street and Road Closure: CSM, Vol-II, Part· I, Chapter-3
Excavation, Reinstatement and Traffic Personal Protective Equipment
Controls. (PPE)
GI. 1022.000 Road & Paved Surfaces CSM, vol-II, Part Ill -03 Electrical
Maintenance Services Equipment
Page 1 of 25
REQUIRED HAZARDCONTROLS/ SAFE WORK
S.No SEQUENCE OF POTENTIAL PROCEDURES
BASIC JOB STEPS HAZARDS RESPONSIBILITY
1 Authorization and 1 Work delays due to poor Prior to start Electrical and Telecommunication equipment
Permission preparation/failure to relocation activities, obtain all the required permission
secure permission from from the authorities and necessary coordination shall be
concerned authorities and conducted with concern department. ABC Construction
approved documents Ensure approved drawings, JSA and other related Manager
documents are available at site.
Assign a responsible person to double check all the
requirements prior to start the job.
All power tools, hand tools and testing equipment shall be
in good condition, inspected and calibrated.
Assign a responsible person to double check all the
requirements prior to start the job.
2 Commencement of 1 Electrocution. Each person performing electrical work on that equipment ABC SITE
power shut down. must verify the circuit is de-energized. SUPERVISON
GI 6.012, Isolation, Lockout and Use of Hold Tags
System in place.
Use suitable Arc Flash PPE (Arc rated long sleeve shirt
&Pants, Hard hat, safety shoes, electrical gloves, Safety
glass, Arc rated face shield)
Lock off relevant switches/isolators to prevent accidental
energizing.
Turn off main feed from supply source an isolate circuit.
Area Need to barricade &Safety Signage in place.
3 Unclear Communication
with Dispatch & Utility Qualified &Training personnel only allow performing
Operating Personnel. task.
Page 2 of 25
Qualified persons permitted to work within limited
approach boundaries
Keep circuit fully locked off until all contractors have
completed their work around the Circuit
Proper coordination between Utility operation
departments, electrical shutdown task performing
contractor.
The knowledge, skills and techniques to work safely on
energized circuits (i.e., arc flash protection and
boundaries);
4 Using of inadequate PPE The proper use of special precautionary techniques,
& Using of damage tools personal protective equipment (Arc rated FRC, Safety
shoes, safety glass, insulating and shielding materials, and
insulated tools.
3 Relocation of Cables 1 Electrical shock Ensure all the existing connections are Isolated Prior to ABC SITE
for TETRA, NEDAP commence the work. SUPERVISON
ACS Panel and
Readers, Hotline, 2 Entanglement with Provide hazard specific PPE’s
telephone to new rotating parts All portable electrical equipment to be earthed.
Guard House with All rotating parts of machinery/tools to be adequately
using of power tools guarded.
&Hand tools Refrain from wearing loose clothing while operating
(Drill Machine, electrical tools with rotating parts.
Grinder)
PPE (Cover all, Safety Helmet, Safety Shoes, Safety
3 Personal Injury Glass, Hand Gloves & Ear Muff/plug) shall be provide.
All hand tools (pole, metal detector etc.) shall be properly
inspected and it shall be color coded according to Aramco
standards
Appropriate working posture shall be adopted.
Wear appropriate hand gloves.
All power tools proper insulated.
Page 3 of 25
4 Asphalt Cutting 1 Slips, Trips, Falls Clear walkways, work areas of equipment, Tools, carts ABC SITE
and debris. SUPERVISON
Mark, identify, or barricade other obstructions.
Keep cords out of areas where the saw may cut them.
Since water will be used to cool the saw blade, workers
will use caution on wet surfaces.
2 Rotating Parts Keep guards in place during use and do not operate saw if
guards are not placed on rotating parts.
Workers will consult operations manual before
commencement of work.
Ensure the saw is turned off prior to changing blades (if
necessary).
Don't use a dull blade: replace or have sharpened prior to
use.
Be alert for sharp points and edges. Wear cut resistant
work gloves when sharp edges or objects may cause the
possibility of lacerations or other injury.
At no time will any crew member stand in front of the saw
while in operation
3 Struck By / Against heavy Wear reflective warning vests when exposed to vehicular
Equipment traffic.
Make eye contact with operators before approaching
equipment.
Do not attempt verbal communication in high noise
backgrounds.
Work area will be barricaded/demarcated. No traffic will
be allowed to move past the cutting area until crew is
complete with cutting and asphalt patch has been applied.
Barriers shall be used to protect workers from vehicular
traffic.
Page 4 of 25
Isolate/block pinch points to limit motion when inserting
pins, fasteners, closing tackles.
Keep hands, fingers, and feet clear of moving/suspended
materials and equipment
Stay alert at all times.
5 Manual Handling Due to the weight of the walk-behind saw. crew will not
attempt to lift it for any reason.
Physically fit persons to be assigned for any manual work.
Training to be given regarding manual handling.
Where possible, used mechanical means to transfer loads
and reduced distance if possible.
Provision of access shall be installed to areas where access
is unavailable
Proper manual handling method need to be implemented
Provide instruction for manual handling during tool box
meeting.
6 Noise
Use hearing protection when exposed to excessive noise
levels (greater than 85 dBA over an 8-hour work period)
Page 5 of 25
compressor, Hilti drill
machine, shovel, forked 2 Dust Inhalation Water shall be poured adequately to suppress dust.
hoe, pick axe for Dust mask shall be provided to employees
excavation Vehicle/ equipment speed shall be restricted at Work site.
Page 6 of 25
space permit is required.
Gas test shall be conducted prior to entry of personnel.
Continues / frequent gas testing shall be conducted when
there is a potential for hazardous gases in the confined
space.
6 Electric shock & Fire from All electrically operated tools shall be double insulated
Hilti machine. and grounded/ connected with GFCI.
Tools must be inspected and color coded by competent
technician.
Appropriate UL listed fire extinguisher shall be provided
near the work area.
Job rotation shall be implemented; appropriate working
position shall be adopted while handling jack hammer
6 Portable Container, 1 Fall of object from above Rigging equipment should be inspected before use and at ABC SITE
Fence roll, Security due to load failure and regular intervals during extended use, the regular SUPERVISON
gate & Emergency damage or unsuitable use inspection depends on the job.
Generator lifting with of rigging equipment Inspection sheets to be in place for each item.
Crane / Boom Truck Remove slings from service if any of these are present.
Acid or caustic burns
Melting or charring of any part
Snags, punctures, tears or cuts
Broken or worn stitches
Distortion of fittings.
Certificate must be available at site and SWL must be
clearly marked on the lifting tackles.
After inspection, equipment shall be color coded by the
competent person as per Aramco standard.
Page 7 of 25
otherwise specified in the crane manufacturer’s load chart.
5 Unauthorize Two tag lines must be used to tie on the load for a better ABC SITE
person/equipment control during lifting un less their use may cause a greater SUPERVISON
hazard. Tag lines shall not be tied around the hands/wrist.
They shall be fully grip by all fingers.
Only operator and riggers certified by Saudi Aramco are
allowed to conduct the lifting activities.
All lifting gears that are going to be used must be free
from any damage and inspected with color coding of the
month. Inspection must be done by the competent person.
Crane cabs shall provide maximum visibility by removing
or not allowing obstructions such as curtains, cardboard.
Cabs shall be kept clean and clear of items such as rubbish
Page 8 of 25
and loose tools.
The crane operator shall never leave the controls at any
time while a load is attached
Crane operator shall only pick up loads when the boom
head and hook are centered directly over the load. All
crane lifts shall be partially lifted/floated for at least 3
seconds to ensure rigging and lift integrity prior to
proceeding with the actual lift.
Critical lift plan must first be approved by Saudi Aramco
before commencing to work with Critical lift plan shall be
first approved by Saudi Aramco certified Rigger I before
commencing to work.
7 Inadequate inspection and Defective hardware and rigging equipment shall be ABC SITE
maintenance of crane and removed immediately from the SA project site and shall SUPERVISON
rigging equipment be documented.
Slings that will be used for lifting shall be inspected
before using and the slings log shall be available at the site
all the times.
Page 9 of 25
o 4.6meters/15 feet from 50,000 volts to 2000,000
volts
o 6.1meters/20 feet from 200,00 to 350,000 volts
o 7.6meters/25 feet over 350,000 volts
Suspended loads shall not be left unattended.
Workers shall not be under suspended load or rigging
area.
Load lift shall not be performed in wind speeds exceeding
32 km/h, unless otherwise specified by the crane
manufacturer.
Page 10 of 25
2 Personal Injury
Personnel shall wear Personal Protective Equipment such
as Hardhat, Eye Protection, Hand Gloves and Safety
Shoes during CABLE LAYING, PULLING and or
TERMINATION.
Supervisor or Foreman shall give TOOLBOX talk to his
workers prior to start of work.
3 Manual Handling
Workers shall be taught in cable laying and pulling
techniques including the requirement for ensuring good
manual handling techniques.
Workers shall not run when pulling cables.
4 Trapping injuries.
CABLE JACK shall be of sufficient capacity and placed
on an even and hard surface.
WARNING SIGNS shall be positioned adjacent to cable
laying
Area for loading and unloading shall be barricaded
properly.
Damaged Cable Drums shall be repaired before they are
loaded or unloaded for the jobsite.
5 Tripping hazards / damage
to materials Workers shall NOT RUN on installed or laid cables
during cable pulling.
Cables shall be KEPT AWAY from foot and equipment
traffic. Stored materials shall be barricaded and provided
with signs.
Avoid storing materials on walkways or ingress or egress.
8 Backfilling and 1 Personal Injuries Ensure workers are wearing safety gloves. ABC SITE
Compaction Workers to be made aware and kept reminded of the SUPERVISON
(Hand tools, JCB hazards with vehicles.
Backhoe, Wheel
Loader, Bobcat, Dump 2 Struck by/ Against Heavy Ensure operators are Saudi Aramco certified.
Truck, Water Truck Equipment (Man Machine That the equipment before its mobilization possess valid
and Plate & Roller interface)
Page 11 of 25
Compactor) Saudi Aramco or approved third party inspection.
Ensure equipment operators possess valid SAG license
and Saudi Aramco certificates at all times.
Warning signs and barricade shall be installed and posted
to keep unwanted personnel away from the area of
operation.
Flagman shall be provided to guide personnel from
entering the working/affected area.
Provide a pedestrian walkway to prevent personnel from
entering the working areas or roads.
Daily vehicle/equipment pre-use inspections shall be
conducted.
3 Vibration Rotate compaction tasks to minimize worker exposure to
equipment vibration.
Rotate compaction tasks to minimize worker exposure to
equipment vibration
Use compactors with vibration dampening devices
Page 12 of 25
Adequate supervisor at site.
2 Manual Handling Physically fit persons to be assigned for any manual work.
Training to be given regarding manual handling.
Where possible, used mechanical means to transfer loads
and reduced distance if possible.
Provision of access shall be installed to areas where access
is unavailable.
3 Slips, trips and falls Shall remove all obstructions such as wastes, unnecessary
tools and materials that blocked along the door, stairways
and any walkways or access
10 Cable Terminations 1 Personal Injury Trained and competent electricians using suitable tools ABC SITE
shall carry out cable termination. SUPERVISON
Modified Power and Hand tools are not acceptable.
Avoid slashing cables while sliding it on your hand
Use suitable PPE (Safety gloves, safety glass, FRC, safety
boots)
Page 13 of 25
11 Splicing Old URD To 1 Electrocution. Qualified persons permitted to work within limited ABC SITE
New URD. approach boundaries. SUPERVISON
Cable Splicing using Contact Dispatch to De-Energize Wire. Ground At Both
Fusion Splicer Ends.
Use Rubber Gloves to Cut Wire as Added Precaution.
Use suitable Arc Flash PPE (Arc rated long sleeve shirt
&Pants, Hard hat, safety shoes, electrical gloves, Safety
glass, and Arc rated face shield).
Page 14 of 25
DB Use suitable Arc Flash PPE (Arc rated long sleeve shirt
Panel/Breaker/crash &Pants, Hard hat, safety shoes, electrical gloves, Safety
barrier panel. glass, Arc rated face shield)
Are need to barricade &Safe signage’s in place.
Ensure All Those Involved Clearly Understand the Steps
of The Process to Avoid Injury, Property Damage &
Unplanned Outages.
Page 15 of 25
glass) Adequate Supervision.
Ensure Grounds Are All Removed Before Testing.
Double Check to Ensure All Cables Have Been Tested
Before Placing into Service.
Verify Testing Equipment Is in Working Order at Each
Switch Point, Equipment Must Be Clean, Within Test
Dates and Functional.
Check Phasing (Hot Phase/Bottle) Before Energizing.
Be Aware of The Possibility of Such Conditions and Test.
Barricading the testing and commissioning areas/zones.
14 Installation and 1 Personal Injury PPE (Cover all, Safety Helmet, Safety Shoes, Safety ABC SITE
Dismantling Security Glass, Hand Gloves & Ear Muff/plug) shall be provide. SUPERVISON
fence with using of All hand tools shall be properly inspected and it shall be
Hand tools color coded according to Aramco standards
Appropriate working posture shall be adopted.
Wear appropriate hand gloves.
15 Installation and 1 Contact with Equipment All tools and equipment shall be inspected and maintained ABC SITE
Dismantling Security resulting burns or electric properly SUPERVISON
fence with using of shock Generators shall be grounded
Power Tools. All generators are to be enclosed by standard barrier
(Generator, Hammer fencing and kept at a safe distance from unauthorized
Drill, Grinder, Drill person
Machine.) Generator should be without any leakage. Each generator
will have its own fire extinguisher. Provide drip tray.
Containers shall be grounded and bonded during refueling
operation
Page 16 of 25
PPE (Cover all, Safety Helmet, Safety Shoes, Safety
Glass, Hand Gloves & Ear Muff/plug) shall be provided.
All electrically operated tools shall be double insulated
and grounded/ connected with GFCI.
Tools must be inspected and color coded by competent
technician.
Appropriate UL listed fire extinguisher shall be provided
near the work area.
Job rotation shall be implemented; appropriate working
position shall be adopted while handling jack hammer
Hot work permit should be obtained for hot work.
Page 17 of 25
order to complete job task according to predetermined
instructions.
7 Sunburn, Sufficient drinking water must be supplied around the site. ABC SITE
Heatstroke/Stress Drinking water stations must be located near to the SUPERVISON
working areas.
Covered shelters also shall be provided to the workers
could rest at time intervals to minimize the effect of heat.
Tool box talks must be conducted and information shall be
circulated to all workers to aware of heat effects and ways
to improve body resistance against heat.
SA Approved Temperature/Humidity meter should be
available on site.
SA Heat Index chart should be available on work site
Periodically monitor and record Heat index by measuring
air temperature and relative humidity.
Follow the instructions about work/rest periods,
mentioned in SA heat index chart.
If temperature is determined high for workers to resist the
management should consider adjustments on work
timings.
16 Removal / loading and 1 Hand injuries-pain, Ensure workers are wearing safety gloves. ABC SITE
shifting of Spoil, abrasions Workers to be made aware and kept reminded of the SUPERVISON
Material and Debris hazards with vehicles.
from Worksite
2 Struck by/ Against Heavy Keep area barricade/ control unauthorized entry as
Equipment (Man Machine required.
interface) Ensure that equipment warning devices are functional
Page 18 of 25
(horn, back-up alarm).
Flag man shall be assigned to guide the equipment
Page 19 of 25
The power tools must not exceed 120v.
5. Electrical hazards GFCI should be installed.
Dead man switch should be working condition.
The power cables and power tools shall be in good
condition
The electrical power outlets/extension cords should be
UL/ FM listed as described in SA CSM.
Generators supplied for power shall be grounded properly
Compressed gas cylinders
Fire extinguisher should be placed in working area.
(Fire/ Explosion)
Prior to start the task make sure Oxygen and Acetylene
cylinders are well maintained, held tightly on carrying
trolley.
Make sure flash back arrestors are installed.
Use hazards specific PPEs i.e. leather gloves.
Need to deploy fire watcher in place.
Adequate Supervisor on site.
Do soap test on gas equipment before use
Inspect hoses for damage
Close all valves after use
Correct storage procedure
Relocation of Existing 1 Fall of object from above Rigging equipment should be inspected before use and at
Pipe Barriers due to load failure and regular intervals during extended use, the regular
(Concrete foundation damage or unsuitable use inspection depends on the job.
Installation, Pipe of rigging equipment Inspection sheets to be in place for each item.
Lifting and Alignment) Remove slings from service if any of these are present.
Acid or caustic burns
Melting or charring of any part
Snags, punctures, tears or cuts
Broken or worn stitches
Distortion of fittings.
Certificate must be available at site and SWL must be
clearly marked on the lifting tackles.
After inspection, equipment shall be color coded by the
competent person as per Aramco standard.
Page 20 of 25
All cranes shall be levelled in accordance with
2 Contact with unstable manufacturer’s specifications and shall be located on a
ground led to toppling of properly compacted foundation prior to performing any
crane lift.
During a lift, the crane’s outrigger shall be fully extended
and lowered to raise the wheels and level the crane, unless
otherwise specified in the crane manufacturer’s load chart.
Two tag lines must be used to tie on the load for a better
5 Unauthorize control during lifting un less their use may cause a greater
person/equipment hazard. Tag lines shall not be tied around the hands/wrist.
They shall be fully grip by all fingers.
Only operator and riggers certified by Saudi Aramco are
Page 21 of 25
allowed to conduct the lifting activities.
All lifting gears that are going to be used must be free
from any damage and inspected with color coding of the
month. Inspection must be done by the competent person.
Crane cabs shall provide maximum visibility by removing
or not allowing obstructions such as curtains, cardboard.
Cabs shall be kept clean and clear of items such as rubbish
and loose tools.
The crane operator shall never leave the controls at any
time while a load is attached
Crane operator shall only pick up loads when the boom
head and hook are centered directly over the load. All
crane lifts shall be partially lifted/floated for at least 3
seconds to ensure rigging and lift integrity prior to
proceeding with the actual lift.
Critical lift plan must first be approved by Saudi Aramco
before commencing to work with Critical lift plan shall be
first approved by Saudi Aramco certified Rigger I before
commencing to work.
Page 22 of 25
minimum clearance from power lines shall be observed
8 Existing Aramco without exception.
facilities/structures struck o 4.6meters/15 feet up to 50,000 volts
by the load o 4.6meters/15 feet from 50,000 volts to 2000,000
(Overhead Powerlines) volts
o 6.1meters/20 feet from 200,00 to 350,000 volts
o 7.6meters/25 feet over 350,000 volts
Suspended loads shall not be left unattended.
Workers shall not be under suspended load or rigging
area.
Load lift shall not be performed in wind speeds exceeding
32 km/h, unless otherwise specified by the crane
manufacturer.
Page 23 of 25
Fire extinguisher should be present.
4 Fire &burn
All welders must wear proper PPEs (FRC, welding Apron,
welding gloves and welding hood.)
Ensure fire extinguishers are available.
All flammable material shall be removed from the welding
area.
Fire watch shall be available nearby and will remain not
later than 30 minutes after the welding.
NO SMOKING near the vicinity.
5 Smoke
Wear proper respiratory PPEs.
All unauthorized personnel shall be away.
6 Electrocution
Ensure the welding machines are in good condition.
GFCI installed and working condition.
Welding cables will be in good condition.
No joints in the cables are permitted.
All equipment inspected and color coded
Check and ensure the earthling of machines is good.
Damp, humid and wet conditions will be a consideration
for the voltage and type of transformer used.
3-pronged type with ground fault protection
All damaged welding cables shall be removed from
service, temporary repairs and taped joints are prohibited
Page 24 of 25
gloves) shall be provided. SUPERVISON
Ensure that used lumber, planks and plywood have been
de-nailed before storing and stacking.
Properly barricade the working area access route at all
time.
Page 25 of 25