Pneumatic Hammer Excavation Productive Rate

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

23/03/2023, 07:56 Pneumatic Hammer Excavation

Pneumatic Hammer Excavation


Print

Category: Excavation Hits: 13043

 Pneumatic Hammer Bulk Excavation

* Production rates listed are based on 8-hr shift. The above figures are for general estimation
purpose only and must not be used to guarantee any production figure to the customer. The actual
working results may vary according to the quality and structure of the material to be broken, required
degree of material size reduction, installation, condition of the carrier, conditions at the worksite,
haulage of the broken material, skills of the operator etc.
Task / Description Slow   Ave   Fast    Units
Hammer (2,200lb - 1,000kg) - 315C        

Excavator

   Non-Reinforced Concrete 150cu.yd - 200cu.yd - 375cu.yd - cu.yd &

115m3 153m3 287m3 m3/8hr

   Reinforced Concrete 140cu.yd - 160cu.yd - 240cu.yd - cu.yd &

107m3 122m3 184m3 m3/8hr

   Sedimentary Rock 165cu.yd - 200cu.yd - 300cu.yd - cu.yd &

126m3 153m3 229m3 m3/8hr

   Volcanic Rock 75cu.yd  -   110cu.yd -   150cu.yd - cu.yd &

57m3 84m3 115m3  m3/8hr

 Hammer (3,740lb - 1,700kg) - 330C        

Excavator

   Non-Reinforced Concrete 275cu.yd - 375cu.yd - 490cu.yd - cu.yd &

210m3 287m3  375m3 m3/8hr

   Reinforced Concrete 200cu.yd - 150cu.yd - 350cu.yd - cu.yd &

153m3 115m3 268m3 m3/8hr

   Sedimentary Rock 250cu.yd - 150cu.yd - 400cu.yd - cu.yd &

191m3 115m3 306m3 m3/8hr

https://methvin.org/estimating-production-rates/excavation/pneumatic-excavation?tmpl=component&print=1 1/2
23/03/2023, 07:56 Pneumatic Hammer Excavation

   Volcanic Rock 135cu.yd - 150cu.yd - 275cu.yd - cu.yd &

103m3 115M3 210m3 m3/8hr

 Hammer (6,946lb - 3,150kg) - 345C        

Excavator

   Reinforced Concrete 300cu.yd - 385cu.yd - 850cu.yd - cu.yd &

229m3 295m3 650m3  m3/8hr

   Sedimentary Rock 350cu.yd - 440cu.yd - 900cu.yd - cu.yd &

268m3 337m3 688m3  m3/8hr

   Volcanic Rock 200cu.yd - 275cu.yd - 600cu.yd - cu.yd &

153m3 210m3 459m3  m3/8hr

 
 
 

https://methvin.org/estimating-production-rates/excavation/pneumatic-excavation?tmpl=component&print=1 2/2