Task / Description Slow   Ave   Fast    Units


 Dozer, 0.8m3 bucket, Sand/Soil, pushed 5-50m to stockpile 13.9  20.4  25.0   m3/hr

 Dozer, 0.8m3 bucket, Sand/Soil, pushed 50-120m to stockpile 7.6  9.5  12.6   m3/hr

 Dozer, 0.8m3 bucket, Gravel, pushed 5-50m to stockpile 14.2  20.4  25.6   m3/hr

 Dozer, 0.8m3 bucket, Gravel, pushed 50-120m to stockpile 7.6  10.2  12.8   m3/hr

 Dozer, 0.8m3 bucket, Clay/Chalk, pushed 5-50m to stockpile 12.7  18.4  23.2   m3/hr

 Dozer, 0.8m3 bucket, Clay/Chalk, pushed 50-120m to stockpile 6.9  8.9  11.6   m3/hr

 Dozer, 0.8m3 bucket, Boulder Clay, pushed 5-50m to stockpile 11.6  16.9  21.3   m3/hr

 Dozer, 0.8m3 bucket, Boulder Clay, pushed 50-120m to stockpile 6.3  8.2  10.4   m3/hr

 Dozer, 1.2m3 bucket, Sand/Soil, pushed 5-50m to stockpile 23.8  28.5  35.7   m3/hr

 Dozer, 1.2m3 bucket, Sand/Soil, pushed 50-120m to stockpile 16.7  18.5  20.4   m3/hr

 Dozer, 1.2m3 bucket, Gravel, pushed 5-50m to stockpile 25.0  32.0  37.0   m3/hr

 Dozer, 1.2m3 bucket, Gravel, pushed 50-120m to stockpile 17.2  19.3  21.2   m3/hr

 Dozer, 1.2m3 bucket, Clay/Chalk, pushed 5-50m to stockpile 21.7  27.5  33.3   m3/hr

 Dozer, 1.2m3 bucket, Clay/Chalk, pushed 50-120m to stockpile 15.1  16.9  18.8   m3/hr

 Dozer, 1.2m3 bucket, Boulder Clay, pushed 5-50m to stockpile 19.6  24.5  30.3   m3/hr

 Dozer, 1.2m3 bucket, Boulder Clay, pushed 50-120m to stockpile 13.7  15.9  17.5   m3/hr

 Dozer, 0.6m3 bucket, 50-200m2, Sand/Soil 18.6  28.5  38.5   m3/hr

 Dozer, 0.6m3 bucket, over 200m2, Sand/Soil 24.4  37.2  50.0   m3/hr

 Dozer, 0.6m3 bucket, 50-200m2, Gravel 18.9  28.6  38.4   m3/hr

 Dozer, 0.6m3 bucket, over 200m2, Gravel 24.2  37.2  50.0   m3/hr

 Dozer, 0.6m3 bucket, 50-200m2, Hardcore 15.8  23.5  31.2   m3/hr

 Dozer, 0.6m3 bucket, over 200m2, Hardcore 19.2  29.6  40.0   m3/hr

 Dozer, 0.6m3 bucket, 50-200m2, Boulder Clay 17.2  26.4  35.7   m3/hr

 Dozer, 0.6m3 bucket, over 200m2, Boulder Clay 22.2  33.8  45.4   m3/hr

https://methvin.org/estimating-production-rates/excavation/spread-and-level?tmpl=component&print=1 1/2
23/03/2023, 07:57 Spread and Level

 Dozer, 1.2m3 bucket, 50-200m2, Sand/Soil 43.5  48.0  52.6   m3/hr

 Dozer, 1.2m3 bucket, over 200m2, Sand/Soil 55.5  61.1  66.7   m3/hr

 Dozer, 1.2m3 bucket, 50-200m2, Gravel 43.8  48.3  52.9   m3/hr

 Dozer, 1.2m3 bucket, over 200m2, Gravel 55.5  61.1  66.7   m3/hr

 Dozer, 1.2m3 bucket, 50-200m2, Hardcore 37.1  40.3  43.5   m3/hr

 Dozer, 1.2m3 bucket, over 200m2, Hardcore 47.6  51.6  55.6   m3/hr

 Dozer, 1.2m3 bucket, 50-200m2, Boulder Clay 43.8  45.7  47.6   m3/hr

 Dozer, 1.2m3 bucket, over 200m2, Boulder Clay 55.6  59.1  62.5   m3/hr