Professional Documents
Culture Documents
Uhmm - Post - bipoleIII - Concepts - Review - COMPARATIVO DE COSTES
Uhmm - Post - bipoleIII - Concepts - Review - COMPARATIVO DE COSTES
Uhmm - Post - bipoleIII - Concepts - Review - COMPARATIVO DE COSTES
Report of the
Concepts Review Panel
March 17, 2011
Report of the
Concepts Review Panel
David Farlinger, P.Eng., F.E.I.C.
(Principal, CMC Consultants Inc.) – Panel Chair
Ed Tymofichuk, P. Eng.
(Vice President Transmission, Manitoba Hydro)
2 - Manitoba Hydro
Third Party Disclaimer
The content of this document is not intended for the use of, nor is it
intended to be relied upon by any person, firm or corporation, other
than Manitoba Hydro.
I would also like to thank Shane Dew P. Eng. of Manitoba Hydro for his
administrative support and untiring efforts in his role as Administrative
Assistant to the Panel. As well, I wish to extend my thanks to technical staff
of Manitoba Hydro and Manitoba Hydro International for their support
throughout this review, specifically to Jason West for his skillful portrayal
of models illustrating the train transport of submarine cable in long
lengths, to Sarah Wach for drafting the AC and DC route maps for the
report and to Dean Reske for compiling estimates of the cost of various
electrical installations.
5 Cable Installation. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 73
5.1 Submarine Cable Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 73
6 - Manitoba Hydro
5.1.1 Cable Laying Barge . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 73
5.1.2 Submarine Cable Trenching . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 74
5.1.3 Cable Jointing Operation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 77
5.1.4 Cable Laying Procedure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 79
5.1.5 Cable Laying Schedule . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 80
5.2 Underground Cable System Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 81
5.2.1 Civil Work. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 81
5.2.2 Cable Transportation. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 82
5.2.3 Cable Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 83
5.2.4 Cable Jointing and Terminating . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 84
7 Cost Comparisons . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 91
7.1 Interpretation of Estimate Results . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 94
8 Regulatory Issues. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 95
8.1 Licencing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 95
8.2 Regulatory Issues with Lake Winnipeg Routing. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 95
9 Project Risks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 97
9.1 Design Risks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 97
9.2 System Operation Risks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 99
10 Benefits and advantages of underground and submarine cable installations. 101
11 Findings and Conclusions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 103
12 References. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 105
Proposal 4 Transporting DC cable with extruded insulation on widened flatcars in a figure 8 pattern. . . . . 139
Appendix 5: 500 kV Global Cable System Applications. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 143
Appendix 6: Differences Between AC and DC Cable Technologies . . . . . . . . . . . . . . . . . . . . 151
Appendix 7: Grand Rapids Bottleneck . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .155
Appendix 8: Cable Laying Schedule . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 161
Appendix 9: Bipole I and Bipole II Reliability, 1993 - 2008. . . . . . . . . . . . . . . . . . . . . . . . . . . . . .163
For purposes of this Panel’s review, and for completeness, it was assumed that
this fourth major transmission line from northern generation to southern load
centres could be either DC or AC.
1 AC OH 1273 0 0
1 DC OH 1273 0 0
OH-UG
2 AC 1025 175 4 700
Hybrid
OH-UG
2 DC 1025 175 3 525
Hybrid
OH-UG
3 AC 830 263 4 1052
Hybrid
OH-UG
3 DC 830 263 3 789
Hybrid
OH-Sub
4 DC 812 178 3 534
Hybrid
OH-Sub
5 DC 704 287 3 861
Hybrid
OH-Sub
6 AC 703 240 4 960
Hybrid
10 - Manitoba Hydro
Table 2: Transmission Line Route Details
1 This would be an AC or DC overhead line with no Requires two long overhead spans between islands and mainland
underground or submarine cable and no cable- of about one km in Cedar Lake.
AC or DC related reactive compensation equipment and
thus inherently more reliable. Location of “island hops” less than 20 km from Bipole I-II at Grand
Rapids.
A 500 kV AC transmission interconnection
between northern generation and the southern Permission is required for overhead line to cross about 20 km of
system would strengthen the AC system in the “protected area” park along the east shore of Lake Winnipegosis.
south.
2 After connecting to the Grand Rapids Permission is required for overhead line to cross about 20 km of
underground cable, the overhead line would be at “protected area” park along the east shore of Lake Winnipegosis.
AC or DC least 50 km away from Bipole I-II all the way to the
Winnipeg area. 500 kV AC cable systems of this length have never been installed
anywhere in the world. The impacts on the transmission system
No novel transport methods required. are not known and need more study.
3 No novel transport methods required. The overhead line would be less than 30 km from Bipole I-II as it
goes around the Peguis Reserve.
AC or DC
500 kV AC cable systems of this length have never been installed
anywhere in the world. The impacts on the transmission system
are not known and need more study.
4 There would be adequate lake sediment for the To get to the Warren Landing site, the OH line from the Nelson
entire length of the submarine cable, thus no River Generating Area would have to cross the Nelson River with
DC mechanical barrier protection required for the a long span of about 1 km.
submarine cable (no rock cutting, rock dumping,
or protective mattresses). The OH line would be less than 30 km from Bipole I-II as it goes
around the Peguis Reserve east of Lake St. Martin.
5 There would be adequate lake sediment for the To get to the Warren Landing site, the OH line from Nelson River
entire length of the submarine cable thus no Generating Area would have to cross the Nelson River with a long
DC mechanical barrier protection required for the span of about 1 km.
submarine cable (no rock cutting, rock dumping,
or protective mattresses.) Dredging of the lake bottom and river at Powerview/Pine Falls
may be required for barge access to rail siding.
6 A 500 kV AC transmission interconnection There is little sediment along the entire east shore of Lake
between northern generation and the southern Winnipeg, extending in places for about 30 km off shore.
AC system would strengthen the AC system in the Throughout this area the lake bottom has rough rocky terrain.
south. Because of the required short lengths of AC cable, about 200
km of AC cable would have to be laid near the shore on this
unfavourable terrain. Because of the lack of sediment, the
cable would have to be covered by rock dumping or protective
mattresses. Only the 50 km line from Riverton to Traverse Bay
would be covered by sediment.
Performance of AC and DC cables operating at Table 3 illustrates the worst case and best case
500kV in other commercial projects is examined cable service reliability based on known CIGRE
along with cable system reliability and life survey data for all cables except AC and DC
expectancy. With respect to AC or DC submarine submarine cables. The best case uses only
cables, because of lack of data, it is not possible internal failures while the worst case takes into
to accurately determine failure rates. Despite this, account external failure statistics. The Panel
in the case of DC MI cables, it should be expected acknowledges that these worst case failure rates
that they would experience some faults during may be overly pessimistic.
their lifetime. With regard to DC XLPE cables,
there is still no 500 kV cable system in service Table 3: Estimated Cable System Failure Frequency Ranges
(Worst case – Best case)
and the expected date of maturity for
this cable is at least 15 years away, hence at
Failure Frequency Failure Frequency
this stage it has no failure rate. As for AC Route Option
Installation
Range (No Long Trains) Range (Long Trains)
XLPE underground cable, a cable failure may Mode
(years) (years)
be expected approximately every 3 to 11 years
Line 2 AC Land 4.2 – 10.8
depending on route length. For DC XLPE
Line 2 DC Land 6.1 – 16.6
underground cable, a cable failure may be
Line 3 AC Land 2.8 – 7.1
expected approximately every 4 to 17 years
Line 3 DC Land 4.1 – 11.1
depending on route length. However, the
Line 4 DC1 Water ? ?
Panel recognizes that there is a great deal of
Line 5 DC 1
Water ? ?
variability in these results due to the lack of
Line 6 AC1 Water ? ?
quality data. The prime reason for this is
that the electrical power industry has limited
Note 1: A Failure Frequency Range for routes 4, 5 and 6 cannot be
service experience on 500 kV underground or
determined because of lack of data.
submarine cables.
12 - Manitoba Hydro
Maturity of cable types and systems for AC and long lengths of up to 100 km by train (in two
DC submarine and underground transmission approximately 50 km lengths), and off-loaded
were reviewed. ‘Maturity’ of cable systems in 2010 to a barge on Lake Winnipeg or nearby storage
and as forecast for 2025, are summarized in turntables. Four rail transportation concepts
Table 4. were developed. The concept considered by
the Panel to have the best potential for future
Table 4: Cable options and upper voltage limits for ‘mature’ success is described further in this report. The
AC and DC underground or submarine applications in 2010 panel concludes that transportation of long
and 2025 continuous lengths of cable using multiple rail flat
cars would need
Unpressurized Unpressurized Unpressurized
to be carefully
Unpressurized researched
Mass Impregnated Cross-Linked Cross-Linked
Mass Impregnated
Cable Application
MI Polyethylene Polyethylene and studied by
MI
XLPE XLPE railway engineers
and cable
2010 2010 2025 2025 manufacturing
experts. Feasibility
AC Underground Not Applicable 500 kV Not Applicable 600 kV
is not yet proven.
AC Submarine Not Applicable 420 kV Not Applicable 500 kV
Installation of
DC Underground 450 kV 150 kV 600 kV 500 kV
both submarine
DC Submarine 450 kV 150 kV 600 kV 500 kV and underground
cables is discussed
in the report. A comparison of using continuous
It can be assumed that XLPE insulation cables long lengths of cable versus shorter lengths of
will be available for AC and DC underground and cable on reels for submarine applications is also
submarine applications in 2025. MI insulation discussed, in the event that train transportation of
cables will also continue to be available for long cables is shown to be unrealistic.
submarine cable applications in 2025 for
DC. Costs and reliability data in 2025 would Risks and regulatory issues associated with
ultimately determine final submarine cable type use of submarine cables in Lake Winnipeg
selection. are numerous and extensive as they relate to
initial installations, operation, maintenance,
System design impacts resulting from the use transmission line reliability, system reliability and
of long cables are discussed. High voltage reactive to the environment. These include:
compensation devices are necessary to enable • Complex licensing and regulatory issues
maximum transmission of power through long • Loss in system reliability due to a failed
AC cables and to control voltage, which could cable (mitigatable using spare cables and
otherwise exceed equipment and cable ratings special mechanical protection).
under some operating conditions. For DC cable • Costly manufacturer warranties due
systems compensation devices are not necessary. to remote locations and unproven rail
transportation
Transportation concepts were developed, • Lengthy route siting process
whereby cables would be transported by ship • Complex system operations for hybrid
from an overseas manufacturing facility to a overhead-submarine or overhead-
port in Canada, transferred and transported in underground systems
1 DC All overhead via Cedar Lake 1,273 0 1,273 635 (DC Base)
1 AC All overhead via Cedar Lake 1,273 0 1,273 809 (AC Base)
14 - Manitoba Hydro
Assumptions and notes:
1. Costs are expressed in 2010 CAD dollars.
2. 500 kV AC overhead line is single circuit capable of
1000 MW.
3. 500 kV DC overhead line is similar to Bipole I-II
construction.
4. DC underground cables are XLPE.
5. DC submarine cables are MI due to maturity
6. AC underground cables are XLPE.
7. AC submarine cables are XLPE.
8. For underground options, cables would be shipped
from Thunder Bay to site by truck (4.0km cable/truck
for DC; 1.8 km cable/truck for AC).
9. For submarine options with no long train shipping,
cables would be shipped from Thunder Bay to
Powerview/Pine Falls by rail (1.8 km cable/car for DC;
1.2 km cable/car for AC).
10. For submarine options with long train shipping,
cables would be shipped from Montreal, Prince
Rupert or Vancouver, a maximum distance of about
2500 km.
11. MH Project Management and Engineering costs not
included.
12. Contingencies not included.
13. Interest during construction not included.
14. Insurance for cable transportation not included.
15. Converter costs for DC alternatives not included.
16. Static VAR compensator for AC alternatives not
included.
17. Cable manufacturing capacity is assumed available.
18. Taxes and import duties not included.
19. Estimates are Class 5, as defined by AACE
International, to be used only for concept screening
purposes with low project definition. Class 5
estimates typically have accuracies in the following
range:
Low: -20% to -50%
High: -30% to +100 %”
20. All estimates contain only labour and material.
1. System studies indicate that with Bipole III 9. A hybrid 500 kV AC line may degrade system
(LCC) in service, the Manitoba Hydro power reliability, as compared to an overhead line.
system would experience network frequency This potential degraded level of reliability
stability problems with an additional LCC may impact the reputation and value of
HVDC transmission link. Therefore it is very Manitoba Hydro’s product.
unlikely that a fourth HVDC (LCC) bipole
10. An underground AC or DC cable system
would be implemented in Manitoba [19].
failure can be expected approximately once
2. The same studies have concluded that every 3 to 17 years. A lack of meaningful
additional north-south 500 kV AC industry data for AC and DC submarine
transmission would be recommended to cables prevents determination of statistical
integrate the next major northern generation failure rates.
plant [19].
11. The repair time for underground cables
3. With current cable technology and unproven is considerably less than for submarine
cable transportation methods, an AC cables. A spare cable for submarine and
submarine cable under Lake Winnipeg is not underground options would minimize forced
a viable option at this time. outage times.
4. Assuming in the foreseeable future that 12. All hybrid options have cost premiums
the Manitoba Hydro system develops to compared to overhead lines. Any of the
accommodate a fourth Bipole of any mode solutions using cables result in incremental
(overhead or hybrid), and together with cost increases of about $0.36B and could be as
further research and technological advances, a high as $1.58B, assuming that long submarine
DC submarine or underground cable may be cables could be successfully transported by
a viable option. train.
16 - Manitoba Hydro
13. Routing through Grand Rapids would require 21. The life expectancy of an overhead line is
detailed engineering studies. Underground approximately 100 years. Life expectancy
segments, including a tunnel, are required for an underground or submarine cable is
to alleviate issues with congestion and approximately 40 to 50 years. Therefore a
proximity to existing Bipole lines. complete cable system replacement could be
anticipated about half way through the life of
14. With present technology, estimates indicate
overhead line sections.
that short length submarine cables shipped
on reels would take twice as long to splice
22. VSC HVDC technology, if only implemented
and lay compared to long train shipping
as a future fourth HVDC Bipole transmission
methods. Using reels for shipping submarine
line, would not improve the vulnerability to
cable would be more expensive, impractical
common mode faults. Assuming that there
and is not recommended.
are no technological developments or system
15. The least costly hybrid DC or AC route would developments that would remove system
be approximately 1.5 and 2.8 times more constraints to allow a fourth Bipole and given
expensive respectively, than the base case the operating complexities and reliability
overhead route, assuming long train shipping risks of a hybrid AC transmission line, an
is feasible. overhead AC line should be considered first.
22 - Manitoba Hydro
1 Introduction
The subject of this report is the use of submarine of the lake. In 2008 Manitoba Hydro began a
or underground power cables as part of a fourth lengthy process of environmental assessments to
major north – south 500 kV transmission line locate a route generally west of Lake Manitoba
in Manitoba. Bipoles I, II, and the planned and Lake Winnipegosis. An ‘Interlake Route’
Bipole III comprise the first three major north- between Lake Winnipegosis and Lake Winnipeg
south transmission links. The fourth, post-Bipole was considered, but weather risk assessment
III line is not expected to be required before studies showed that: “…locating the Bipole III
approximately 2025, based on domestic load transmission line on the East Route or West Route
growth forecasts and system reliability needs. would significantly reduce the likelihood that all
three lines would be exposed to the same extreme
All activities related to the generation, weather conditions, compared to locating Bipole
transmission and distribution of electricity in III on the Interlake Route.” “In summary, the
Manitoba are governed by the Manitoba Hydro Act larger the separation distance between the lines,
and the Manitoba Hydro Electric Board, which the greater the reduction of common event risk.”
oversees the operations of the Manitoba Hydro [2].
Corporation. The Board is appointed by the
Provincial Government. The receipt of a licence for Bipole III is scheduled
and expected in the fall of 2012. Bipole III is
Manitoba Hydro’s mission is “to provide for the scheduled to be in service five years later.
continuance of a supply of energy to meet the
needs of the province and to promote economy Concepts for possibly implementing the post-
and efficiency in the development, generation, Bipole III link using submarine or underground
transmission, distribution, supply and end-use of cable segments are discussed in this report.
energy.” The fourth major transmission link will be to
accommodate the Gillam Island generating
In Manitoba approximately 70% of all power station, a 900 MW development.
generated in the province is transmitted from
the north via two high voltage 500 kV direct In early 2008, retired University of Winnipeg
current (DC) lines. They share a common right- geography professor Dr. John Ryan wrote several
of-way, which is a reliability concern. Each line articles promoting the idea of installing a portion
is approximately 900 km long, from two sites on of the Bipole III line under Lake Winnipeg. He
the Nelson River to the Dorsey converter station generally explored the feasibility of transporting
just northwest of Winnipeg. and installing long sections of submarine cables
in a land-locked lake, inaccessible by specialized
Manitoba Hydro is presently designing a third ocean-going cable laying vessels [12]. Dr. Ryan
DC line (Bipole III) and activities have been proposed a concept of using long trains with
well documented over the past several years specially modified flat cars linked to hold long
[18]. Routing of this transmission line, critical to cable lengths in a continuous looping method.
Manitoba’s electricity reliability and security, has The cable would arrive by ship from a factory at
been controversial. Although initially there was a port such as Thunder Bay, Montreal, Vancouver
preference to route the line east of Lake Winnipeg or Prince Rupert and be transferred to a special
for economical, technical, and reliability reasons, unit train, transported to the Lake Winnipeg
the Provincial Government’s decision to protect area, off-loaded onto a specially built barge
this boreal forest region, precluded a route east equipped for cable laying, and subsequently
24 - Manitoba Hydro
With these technical, political and economic • Identify the concept with the highest
issues in focus, Manitoba Hydro appointed a feasibility for long-length transportation
Concepts Review Panel, to examine the potential and installation that may need to be
use of 500 kV submarine and underground cables advanced for further research and
for long distances in Manitoba. The detailed investigation by world experts.
Terms of Reference of the Panel (i.e. Purpose of
the Panel and Items of Concern) are contained in • Address cost implications of any concepts
Appendix 1 and summarized below. that may have merit.
Thompson
Detailed maps of both the AC and DC route
options are provided at the end of this report
(Map 1: DC concept routes and Map 2: Flin Flon
AC concept routes).
The Pas
Grand Rapids
Selkirk
Winnipeg Figure 1:
Route 1 AC or DC
Brandon
Overhead across
Cedar Lake
28 - Manitoba Hydro
2.3 Route 3 AC or DC Underground East
Selkirk
Winnipeg
Figure 3:
Brandon Route 3 AC or DC
Underground East
Flin Flon
Selkirk
Winnipeg
Figure 4: Route 4 DC
Brandon Submarine and through
Eastern Interlake
30 - Manitoba Hydro
2.5 Route 5 DC Two Segments of
Submarine exiting at Traverse Bay
Grand
Rapids
Figure 5:
Selkirk
Winnipeg Route 5 DC Two
Segments of
Brandon Submarine exiting at
Traverse Bay
Selkirk Figure 6:
Winnipeg Route 6 AC with
Two Segments of
Brandon Submarine exiting at
Traverse Bay
32 - Manitoba Hydro
Table 6: Cable Route Option Length and Number
OH Submarine
Total UG Submarine Total Submarine
Route Route UG Route UG Cable Route
Mode Cable Cable Cable Length
Option Length Length (km) Numbers Length
Length (km) Numbers (km)
(km) (km)
1 AC OH 1273 0 0
1 DC OH 1273 0 0
Cable
Cable Field
AC Transition AC Transition Shipping Field
DC Shipping Joints
Route Comp. Comp. Length Joints
Mode Transition Length(km) (No Terminations
Option Stations – Stations – (km) (No (Long
Stations (Long Long
Line Ends Intermediate Long Trains)
Trains) Trains)
Trains)
1 AC OH
1 DC OH
OH-UG
2 AC 2 2 1.8 1.8 389 389 24
Hybrid
OH-UG
2 DC 2 4.0 4 175 175 6
Hybrid
OH-UG
3 AC 2 3 1.8 1.8 877 877 40
Hybrid
OH-UG
3 DC 2 4.0 4 263 263 6
Hybrid
OH-Sub
4 DC 2 1.8 12 x 45 495 9 6
Hybrid
OH-Sub 15 x 47,
5 DC 4 1.8 797 12 12
Hybrid 3 x 52
8 x 33,
OH-Sub 8 x 36,
6 AC 4 2 1.2 1400 8 32
Hybrid 4 x 50,
4 x 52
34 - Manitoba Hydro
Table 8: Transmission Line Route Details
1 This would be an AC or DC overhead line with no Requires two long overhead spans between islands and
underground or submarine cable and no cable- mainland of about one km in Cedar Lake.
AC or DC related reactive compensation equipment and thus
inherently more reliable. Location of “island hops” less than 20 km from Bipole I-II
at Grand Rapids.
A 500 kV AC transmission interconnection between
northern generation and the southern system Permission is required for overhead line to cross about 20
would strengthen the AC system in the south. km of “protected area” park along the east shore of Lake
Winnipegosis.
2 After connecting to the Grand Rapids underground Permission is required for overhead line to cross about 20
cable, the overhead line would be at least 50 km km of “protected area” park along the east shore of Lake
AC or DC away from Bipole I-II all the way to the Winnipeg Winnipegosis.
area.
500 kV AC cable systems of this length have never been
No novel transport methods required. installed anywhere in the world. The impacts on the
transmission system are not known and need more study.
A 500 kV AC transmission interconnection between
northern generation and the southern system Cable-related reactive compensation equipment needed
would strengthen the AC system in the south. for AC alternative.
3 No novel transport methods required. The overhead line would be less than 30 km from Bipole
I-II as it goes around the Peguis Reserve.
AC or DC
500 kV AC cable systems of this length have never been
installed anywhere in the world. The impacts on the
transmission system are not known and need more study.
4 There would be adequate lake sediment for the To get to the Warren Landing site, the OH line from the
entire length of the submarine cable, thus no Nelson River Generating Area would have to cross the
DC mechanical barrier protection required for the Nelson River with a long span of about 1 km.
submarine cable (no rock cutting, rock dumping, or
protective mattresses). The OH line would be less than 30 km from Bipole I-II as it
goes around the Peguis Reserve east of Lake St. Martin.
5 There would be adequate lake sediment for the To get to the Warren Landing site, the OH line from
entire length of the submarine cable thus no Nelson River Generating Area would have to cross the
DC mechanical barrier protection required for the Nelson River with a long span of about 1 km.
submarine cable (no rock cutting, rock dumping, or
protective mattresses.) Dredging of the lake bottom and river at Powerview/Pine
Falls may be required for barge access to rail siding.
Options for installing an HVAC or DC link Figure 7: Grand Rapids Transmission Corridors
through the Grand Rapids area are limited
due to the bottleneck effect from the
congestion of existing transmission lines,
generating station, and ancillary facilities.
Routes 2 and 3 include installation of
underground cables through the area.
Work would entail construction of a
single trench for an AC or DC system and
a tunnel under the spillway and tailrace
approximately 600 m long. Horizontal
Directional Drilling was considered
instead of a tunnel, but there was concern
that there could be high potential to
disturb the environment (possibility of
drilling mud frac-outs, water turbidity
and harm to fish habitat). Further issues
may exist due to proximity of overhead
lines, etc., however, for this report these have
been limited to environmental and physical
examinations. For details see Appendix 7.
36 - Manitoba Hydro
3 Cable System Performance
This section describes performance of mature Self contained fluid-filled cables
cable systems for underground and submarine
applications. Later sections will describe how the Self contained fluid-filled (SCFF) cables are
cable systems can be used to implement several comprised of a hollow central conductor,
concepts for post-Bipole III transmission, and will surrounded by laminar insulating tapes and
provide reliability approximations. pressurized with insulating fluid. The cable core
is encapsulated in a hermetic seal, typically a
continuous lead or aluminum ‘sheath’, at the
factory. The cables are shipped to the site on
3.1 Description of Cable Types for
reels, ready for installation. They are connected
Underground Transmission
to adjacent sections using joints, terminated at
Before explaining cable performance, descriptions cable ends and permanently pressurized via the
are provided for the various underground cable hollow conductor. Three such cables are required
types and a basis for optimal type selection. to provide a 3-phase AC circuit. SCFF cables with
Following are basic descriptions of those types conventional kraft paper tape insulation have
that could be considered generally available relatively high energy losses, lower transmission
for AC and DC underground transmission. capacity and thicker insulation compared
Only some are feasible for the 500 kV level, for to SCFF cables using PPL tapes (SCFF-PPL).
the reasons explained below. More detailed Pressurization of the insulating fluid is usually
descriptions of cable types can be found in done with passive pressure tanks located at
textbooks [1,14,15]. underground cable ends, and for longer lines,
at some intermediate joints. SCFF cable systems
First cables with laminar or lapped dielectrics are have been commercialized for 500 kV AC and
discussed, followed by a discussion of cables with DC and have been in service for several decades.
extruded dielectrics.
38 - Manitoba Hydro
result in damage. Implications are that HV DC Ethylene Propylene Rubber cables
MI submarine cables cannot be coiled into the
hold of a freighter for ocean transportation, but EPR cables use insulation made of extruded
instead must be transported on special ships electrical grade ethylene propylene rubber. The
with carousels or turntables, as shown in Figures upper voltage limit for EPR cables is about 150
21 and 24. This must also be taken into account kV AC due to high insulation losses and they are
when developing methods to transport long not commercially available for DC, so no further
continuous lengths by train, as described in consideration is given for this application.
Appendix 4 (with Method 1 being preferred for
this reason).
Polyethylene cables
Figure 10: Mass Impregnated EHV Submarine Cable (Source: PE cables use insulation made of extruded
www.prysmian.com)
electrical grade low density polyethylene (LDPE),
a thermoplastic polymer. The insulation softens
significantly at conductor temperatures above
about 70 °C, which limits thermal-mechanical
performance and therefore transmission capacity.
Although many circuits continue to operate at the
400 kV AC level, manufacturing has been mostly
discontinued for transmission applications. Also,
they have not been proven for DC use. Therefore
PE insulation cables are not given further
consideration for this application.
40 - Manitoba Hydro
3.2 Description of Cable Types for Cross-linked polyethylene cables
Submarine Transmission
Only relatively short XLPE submarine cables have
been installed at the 420 kV AC level [8]. However
The same basic cable types for underground
an order has recently been placed for a 13 km 420
transmission generally apply for submarine
kV AC circuit across the Oslofjord between Norway
transmission. However, there are some
and Sweden. Therefore 500 kV AC XLPE cables
exceptions, which are presented in the following
are not presently available for this application.
discussion. It’s noteworthy that, excluding HPFF
However, the upper limit is expected to increase to
and HPGF pipe-type cables from discussion,
500 kV AC within the next decade, also with longer
submarine cables are generally similar to
installation distances. Presently, the upper limit for
underground cables, except they have external
planned DC XLPE submarine applications is about
armour to provide additional mechanical
the same as for underground, i.e. 320 kV, with
protection and manage high tensions during
two suppliers claiming they have done sufficient
laying. However, there are important differences
development and prototype tests to demonstrate
for deep water applications, where special
commercial availability for 500 kV DC [7].
constructions are needed to handle high internal
tension, torsion and shear forces applied to the
various layers during laying. Special measures 3.2.1 Maturity of State-of-Engineering of
are also taken to inhibit water ingress in the 500 kV Cable Technologies in Use
event of damage. But for the relatively shallow World-wide Today
Lake Winnipeg application, in general cable
constructions would be similar for underground Discussions of the relative state of maturity of
and submarine cables, except for the presence various cable systems are described below in the
of armour wires for the latter. This of course same order in which they are summarized in
increases the outer diameter and weight, so that Tables 4 and 5.
less submarine cable can be accommodated on The Panel’s definition of ‘maturity’ is:
the same reels used for underground cables.
Since a cable’s minimum bending radius is • Industry standards and recommendations
proportional to its outside diameter, submarine describe tests for manufacturing such
cables cannot be bent to as small a diameter as systems.
an equivalent underground cable. The net result
• Existing applications are ‘long distance’,
is that submarine cables are generally more
meaning at least five km for underground
expensive to manufacture and transport.
cables and 20 km for submarine cables.
Following is a description of cable types generally
• Applications have been in service for at
available for submarine transmission.
least five years.
HPFF and HPGF cable systems are limited in • A complete cable system, including
length to the distances that cables can be pulled all accessories such as joints and
into steel pipes, which usually restricts them terminations, is commercially available
to a length of one to two kilometres for water from at least one supplier.
crossings. Therefore, they are not considered to
be suitable for this application, where crossing Table 9 describes ‘mature’ cable types and their
lengths could be up to 70 km for 500 kV AC and upper voltage limits for AC and DC underground
287 km for 500 kV DC. and submarine applications, as commercially
available in 2010.
AC Underground
500 kV AC 500 kV AC 150 kV AC NA 500 kV AC 150 kV AC
(3.2.2)
AC Submarine
500 kV AC NA NA NA 420 kV AC 150 kV AC
(3.2.3)
DC Underground
500 kV DC NA NA 450 kV DC 200 kV DC* NA
(3.2.4)
DC Submarine
500 kV DC NA NA 450 kV DC 200 kV DC* NA
(3.2.5)
*Cross-sound 150 kV cables commissioned in 2003; 200 kV TransBay cables installed in 2010; 250 kV Honshu-Hokkaido cables to be installed in 2012,
200 kV East-West interconnector to be installed in 2012, 320 kV DolWin1 cables to be installed in 2013 (2 x 75 km sea cable; 2 x 90 km land cable).
Table 10 describes cable types for AC and DC underground and submarine applications and their upper
limits on voltage level, as anticipated to be ‘mature’ in 2025.
Table 10: Anticipated Cable options and upper voltage limits for ‘mature’ AC and DC underground or submarine
applications in 2025
AC Underground
500 kV AC 500 kV AC 150 kV AC NA 600 kV AC 150 kV AC
(3.2.2)
AC Submarine
500 kV AC NA NA NA 500 kV AC 150 kV AC
(3.2.3)
DC Underground
600 kV DC NA NA 600 kV DC 500 kV DC NA
(3.2.4)
42 - Manitoba Hydro
For references regarding maturity, Appendix 3.2.3 Maturity of 500 kV AC Submarine
5 lists the existing 500 kV AC and 500 kV DC Cable Systems
cable systems in service in the world today
for underground and submarine applications Self Contained Fluid-Filled (SCFF) AC
(believed to be complete, but there could be Submarine Cables
several omissions for shorter applications).
There are industry standards for testing these
cables to the 500 kV AC level. On the basis of
this and performance of the 26 year old, double
3.2.2 Maturity of 500 kV AC Underground circuit 500 kV AC 1200 MW submarine cable
Cable Systems system from the British Columbia mainland to
Vancouver Island, 500 kV AC SCFF submarine
SCFF AC Underground Cables cable systems are judged to be ‘mature’. The
Hainan Island 500 kV AC SCFF submarine cable
There are industry standards for testing these system has been in service since early 2009. There
cables to the 500 kV AC level (IEC 141-1). There are no other 500 kV AC SCFF submarine cables
are many long and short distance applications in service. Therefore, SCFF AC submarine cable
described in Appendix 5, dating back to 1973 systems are considered to be mature at the 500 kV
(Grand Coulee). Therefore, SCFF AC underground AC level.
cable systems are considered to be mature at the
500 kV AC level.
Cross-Linked Polyethylene (XLPE) AC
Submarine Cables
XLPE AC Underground Cables
There are industry standards for testing these
There are industry standards for testing these cables, but only up to the 150 kV AC level
cables up to 500 kV AC (IEC 62067; Japanese (Electra No. 189-1 and IEC 60840). However, an
Standard; French Standard). There are two long International Council on Large Electrical Systems
distance lines in Japan and two more have been (CIGRE) Working Group (B1.27) is revising the
commissioned in China in 2009 and 2010. applicable document up to the 500 kV AC level,
Both systems are in tunnels. The technology is with completion planned in 2012.
considered to be mature at the 500 kV AC level for
installations in tunnels using similar methods and There are no 500 kV AC XLPE submarine cable
accessories as for the Japanese applications. There systems in service in the world. However,
is no evidence that tests have been conducted there is one short distance (2.5 km) 420 kV AC
to prove adequate performance of joints and application in service in Norway since 2006 [8]
terminations in very cold weather conditions, as and an 11 km 345 kV AC application is planned
prevail in winter at the study site. for New Jersey - Brooklyn in 2011. A 13 km
420 kV circuit is planned across the OsloFjord
Therefore, XLPE AC underground cable systems between Sweden and Norway, which will be
are generally considered to be mature at the commissioned in 2011-12.
500 kV AC level for tunnel installations, but the
accessories (joints and terminations) do not
appear to be proven for very cold climates. These
cables are mature at the 500 kV AC level for
typical applications.
44 - Manitoba Hydro
XLPE DC Underground Cables 3.2.6 Conclusions about Maturity of 500 kV
Underground and Submarine Cable
There are industry recommendations for testing
Systems
these cables, but only up to 250 kV DC (CIGRE
Technical Brochure 219). However, CIGRE
For 2025 AC applications, XLPE cable systems
Working Group B1.32 is revising the applicable
will likely have reached sufficient maturity and
document up to the 500 kV AC level, with
reliability for both underground and submarine
completion planned in 2011. There are no 500 kV
applications. They are recommended for the
DC XLPE underground cable systems in service
500 kV AC ‘concepts’. However, it is not certain
and the present upper voltage limit for five year
that sufficient reliability will be proven for such
in-service cables is the 170 km long 150 kV DC
long applications described for post-Bipole III
MurrayLink project in Australia.
in this report. Cable system reliability is directly
proportional to length, so field-proven reliability
Therefore, XLPE DC underground cables are not
of, for example, a 50 km long circuit for 50
considered to be mature at the 500 kV DC level,
years, does not equate to similar reliability for
however they are expected to be mature at the 500
a 150 km circuit. This may not be as important
kV DC level by 2025.
for underground applications where repairs can
be made more quickly and at less cost, but for
submarine applications reliability is more critical.
Mass Impregnated (MI) DC Underground
Cables
For DC submarine cable applications in
There are industry recommendations for testing 2025, mass impregnated (MI) and XLPE cable
these cables up to 800 kV DC (Electra 189-2). systems will also have likely achieved sufficient
There are two installations in the world at the 500 maturity and reliability. However, MI cables
kV DC level, both with joints in the underground were selected as the basis for estimating costs of
sections. One is a Neptune monopolar link from submarine DC cable ‘concepts’ because they can
New Jersey to Long Island, New York, comprised be manufactured in longer lengths with fewer
of 23 km on land and commissioned in 2007. factory joints. They also have a proven 40-year
The other is the first phase of a double monopolar positive reliability history at 250 kV DC to 300 kV
link from Italy to Sardinia, which entered service DC and over 20 years at 400 kV DC. Reliability
in mid 2009 with 14 km on land. is especially important for submarine cables
in Lake Winnipeg because of long repair times
Therefore, MI DC underground cables are during winter (October 31 – May 1). Cable system
considered to be mature at the 450 kV DC level reliability will be discussed more in later sections.
but not quite at the 500 kV level because they do
not yet meet the five year criteria. For DC underground applications in 2025, XLPE
cable systems will have achieved acceptable
However, MI DC underground cable systems are maturity and reliability, and are recommended
considered to be mature at the 500 kV DC level for underground DC cable ‘concepts’. They
for underground cable applications beyond 2012, are favoured on land over MI cables because
when they will have met the five year experience of light weight, ease of field jointing, longer
criteria. shipping lengths and relatively fast repairs.
Outage durations would be months shorter for
underground cables than for submarine cables.
There are similar concerns about reliability of
long distance 500 kV DC XLPE underground
Table 11: Recommended Cable Types for 2005 (assuming Minimum soil temperature,
adequate proven reliability for long distances 0.5m deep: -0.8 °C*
46 - Manitoba Hydro
3.3.2 AC Transmission Capacity Figure 14: 500kV AC cable switching arrangement for
spare cable
It is assumed that the required transmission
capacity would be 1000 MW. This could be 500 kV AC cables with spare cable – 1000 MW
Right-of-Way
Select backfill
This is a simplified diagram that omits auxiliary AC underground cables are assumed to be
cables, such as ground continuity conductors approximately as follows. Conductor size is
and fibre-optic cables for monitoring, preliminary and subject to change depending
telecommunication, telecontrol and system on the results of detailed reactive compensation
protection. Each cable configuration would be studies, to optimize reactor size versus cable
enclosed in a minimum 75 mm thick concrete ampacity.
envelope, to provide protection from third
party damage, tree root damage and other Conductor: 1400 mm2 copper milliken type
natural hazards. In the event of a cable failure, Maximum conductor
transmission capacity of the link would initially temperature: 90°C
be reduced to zero until the failed cable could Insulation: Cross-linked polyethylene (XLPE)
be isolated at transition stations using remotely Sheath: Continuous extruded or
operated disconnects and the spare cable inserted longitudinally seam-welded
to take its place while repairs were made. This smooth aluminum
would substantially reduce the time for lost Jacket: High density polyethylene (HDPE)
transmission capacity. One solution using External diameter: Approximately 130 mm
disconnects is shown in Figure 14. Weight: Approximately 25 kg/m
Lake Surface
Water depth D
Lake Bottom
1.00 to 2.00 m approx.
48 - Manitoba Hydro
Industry practice for AC submarine cables is • During an outage of one pole, the other
that they typically do not use special sheath could be operated continuously with
bonding systems. Instead sheaths and armour ground return.
circuits are solidly connected to ground at
• For a pole outage, in case long-term
both ends, making integration of a spare cable
ground current flow is undesirable, the
easier than for underground systems. As for the
bipolar system could be operated in
underground option, in the event of a cable
monopolar metallic return mode. Transfer
failure, transmission capacity of the link would
of the current to metallic path and back
initially be reduced to zero until the failed cable
without interruption requires a Metallic
could be isolated at transition stations using
Return Transfer Breaker and other special-
remotely operated disconnects and the spare
purpose switchgear in the ground path of
cable inserted to take its place while repairs were
one terminal.
made. This would substantially reduce the time
for lost transmission capacity. • During maintenance of ground electrodes
or electrode lines, operation is possible
Some of the route options require AC cable with connection of neutrals to the
lengths to be 50 to 70 km long. Capacitive grounding grid of the terminals, but only
charging current for typical 500 kV AC XLPE if the imbalance current between the two
cables is about 23 A/km, half of which flows poles is held to a very low value.
into each cable terminal. Shunt reactors are
required near the ends of these cable segments to • When one pole cannot be operated with
compensate for the charging current, otherwise full load current, the two poles of the
transmission of useable real power would be bipolar scheme could be operated with
limited, voltage regulation would be poor and different currents, assuming that both
serious system over-voltages could result. This is ground electrodes are connected.
described in greater detail in later sections.
• In case of partial damage to DC line
insulation, one or both poles could be
3.3.3 DC Transmission Capacity continuously operated at reduced voltage.
1.50 approx.
50 - Manitoba Hydro
Figure 19: Assumed DC Submarine Cable Configuration (dimensions in metres)
Lake Bottom
1.00 to 2.00 m approx.
Cables would be buried one to two metres below Figure 20: DC Underground and Submarine Cable Spare
the lake bed, depending on bottom hardness, water Cable Transfer Bus Arrangement
depth and susceptibility to bottom scouring by
wind-blown ice islands in winter and other natural 500 kV DC cables with spare cable
hazards.
Maximum conductor
temperature: 55°C
Insulation: Mass impregnated kraft paper (MI)
Sheath: Continuous extruded lead alloy NO NO
Predicting reliability of long 500 kV cable systems Underground cable system failures could be
for post-Bipole III applications is challenging, caused by man-made (anthropogenic) or natural
because little is known about probability of hazards. For this application, the main man-made
future cable failures due to internal spontaneous hazards would be dig-ins by third party excavators
electrical breakdowns or due to probability of and vandalism, especially at terminal stations. The
failures from external natural and man-made main natural hazards are tree roots growing into
hazards. It was not within the Panel’s Terms the cables and soil instability due to surface water
of Reference to conduct new investigations on erosion, landslides, etc. In addition extremely cold
historical cable system reliability, so the Panel winter air temperatures could affect performance
instead relied on published information by of outdoor cable terminations.
others.
Appendix 5 lists global applications of 500 kV External Cable System Failures – Submarine
AC and DC cable systems. Panel members are Surface vessel traffic is light on Lake Winnipeg
not aware of any failures of 500 kV AC XLPE compared to ocean sites and cables are assumed
cables resulting in forced outages reported in to be initially buried or otherwise protected from
the technical literature. Both cable suppliers and both man-made and natural hazards. Because of
utilities are reluctant to discuss failures. However, possible hazards and dangers to submarine cables,
it is understood from private communications listed below, it is recommended that they be
that there has been one in-service 500 kV XLPE buried in the lake sediment to at least one metre
termination failure, attributed to an auxiliary in depth. Where burial is not possible, perhaps
problem, and one in-service cable failure. There due to very hard exposed bedrock, cables would
have also been failures during commissioning be protected with rock dumping or protective
tests. mattresses. Such burial and supplemental
protection has been proven in most instances to
Before beginning to quantify reliability for the be effective in protecting submarine cables from
various underground and submarine cable external damage.
systems, it is valuable to reflect on the possible
threats and hazards for cable systems. They can Submarine cable system failures could be caused
be classified as hazards internal and external to by man-made or natural hazards. For this
the cable system. application, the following is a list of the main
man-made hazards to submarine cables.
• Boat anchors and keels impacting cables
Internal Cable System Failures • Boats and barges running aground onto
These are due to faulty manufacturing and cables
installation of cables, joints and terminations. • Boat propellers striking cables
Failure usually results in spontaneous electrical • Fishing gear impacting cables
breakdown and a forced outage. • Uncontrolled dredging and dumping by
others
• Vandalism, especially at cable terminals
52 - Manitoba Hydro
Following is a list of the main natural hazards to The matter of ice scour should be a major concern
submarine cables. in selecting the location of the cable coming
• Scouring of lake bottom and at shores by ashore, and, if at all possible, efforts should be
ice islands in winter made to avoid places where there is evidence of
• Littoral drift migration of bottom this occurring. Also the depth of ice scour has to
sediments and shore erosion be carefully determined so that the cable could
• Abrasion on exposed bedrock and in areas be buried at an appropriate depth. However,
of fast water currents excessively deep burial should be avoided, if
• High wave energy changing beach possible, because this would significantly add
morphology, possibly exposing cables to costs and could result in cable over-heating,
over time necessitating larger conductors, increasing costs
• Wind-induced disturbance of the water further.
column and lake bed dynamics causing
bottom sediment migration over time Ice ridges or pressure ridges on lake ice are
• Pounding of driftwood logs along formations that may extend parallel and generally
shorelines causing cable damage fairly close to shore for many kilometres. In
• Sand waves and mega-ripples exposing extremely cold weather, especially if there is a
buried cables over time in some areas lack of insulating snow cover, ice will shrink
• Extremely cold winter air temperatures in volume, opening up long cracks which
affecting performance of outdoor cable immediately fill with water and freeze again. Later
terminations when the temperature rises, the ice expands and
forces itself upward along the lines of the crack.
It is recommended that none of the above hazards At times a submerged volume of broken ice under
be dismissed until thoroughly investigated, since a ridge is forced downwards by pressure; this is
all example cable routes are subject to change. A termed an ice keel. In the spring, as the ice breaks
discussion of the specifics of each risk factor that up, wind-driven pressure ridge keels may drag on
may affect submarine cables follows. the lakebed and form furrows. On Lake Winnipeg
these furrows may be found close to shore in the
Ice scour is a geological term for a narrow shallow sections of the northwestern North Basin
ditch or furrow in a seabed or lakebed caused by and in the southern part of the South Basin. In
moving ice. Synonyms include ice gouging, ice general, ice ridges form in a north-south direction
ploughing, ice scour and keel scour. Geologically, approximately one kilometre or less from shore
ice scour is normally associated with glacial running from one mainland point to another or
ice in the form of icebergs. In the case of Lake from island to island. In the South Basin there
Winnipeg, ice scour occurs in the spring when in is normally one major north-south ridge that
some places, as the lake ice breaks up, the wind develops down the centre of the lake.
blows sheets or chunks of ice toward the shore. As
this occurs, occasionally these masses of ice may The problems created by ice ridges are comparable
pile up into layers, with some tilting sidewise and to those of ice scour, so care has to be taken
extending below the surface, and then drag along regarding the cable route, especially where the
the lakebed as they are pushed ashore. Some of cable comes ashore. Fortunately, it appears that
these ice scours or furrows have been reported ice ridge keel furrows occur mostly in areas fairly
anecdotally to be a metre or more in depth, but close to shore or in parts of the lake where no
there are no data on exact depths, location of cable routes have been proposed. Hence the
occurrences, or the regularity of occurrences at hazard of ice ridges may not pose a threat to the
specific locations. Ice scour may also occur as a two proposed DC routes since they would extend
result of ice pressure ridges, as discussed below.
54 - Manitoba Hydro
• Cable system failure rates are based on on the subject. The purpose was to collect and
lower voltage applications, thus reliability analyze data relating to installed quantities of
predictions may not be applicable at underground and submarine cable systems rated
500 kV. at 60 kV and above, together with their service
experience and performance. Results showed a
• Assuming cable system failure rates based continuing trend toward application of XLPE AC
on experience elsewhere may not be cables to replace SCFF AC cables, spreading to
valid because winter ambient air and soil the highest voltages, i.e. 500 kV. Unfortunately
temperatures at the sites are lower than there was very little data on performance of 500
most other applications, and most cable kV cables. For DC applications, the survey showed
systems have not been laboratory tested MI cables continuing to dominate, but with XLPE
for such low temperatures. cables used more frequently up to 150 kV.
• Cable system failure rates vary
Unfortunately the TB 379 survey data reported
with manufacturer and their long
that internal failure rates are zero for AC XLPE,
term experience with cable system
DC XLPE or DC MI submarine cables, based
development. It is unknown which
on the survey data (see TB 379 Table 29 for DC
manufacturer will ultimately supply the
XLPE and Table 30 for the others). There is an
systems and their future capabilities or
acknowledgement, however, that some of the
factory quality assurance programs.
failures reported as “other”, could have been
• Cable system failure rates depend on internal. Of course a zero failure rate is unrealistic
installation quality assurance when because it would infer infinite cable life, whereas
making cable joints and terminations. it is commonly accepted that cable systems have
Poor workmanship (or poor instructions a design life of 40 to 50 years under normal
to installation technicians) is a major loading and maintenance conditions. It is also
cause of AC XLPE cable system failures. unfortunate that there was insufficient survey
At this stage there is no way to be sure data to quantify a failure rate for submarine
that good workmanship practices will be cable accessories (joints and terminations). In
followed. addition, some of the external failure rates due to
external factors in TB 379 Table 30 for submarine
It can be concluded that there is no accurate way cables do not reflect the satisfactory performance
to predict internal failure rates for cables and their of many long lines and could provide too
accessories (joints and terminations) in 2025. pessimistic an approach to applications in
However, some semi-quantitative and somewhat 2025, which would incorporate technological
subjective approximations can be made for both improvements in manufacturing and installation.
internal and external failure hazards, as described
below. To overcome these challenges and uncertainties
about applicability of the TB 379 Table 30 data to
In April 2009, CIGRE Working Group B1.10 the Lake Winnipeg site, it was decided not to use
completed Technical Brochure 379 “Update it for Lake Winnipeg submarine cable failure rate
of Service Experience of HV Underground and forecasts. Since there was no known alternative
Submarine Cable Systems” [16]. It compiled dependable failure rate information available, it
the results of a power utility survey completed was decided to simply record cable failure rates
in December 2005, so the results are now about as unknown. However, it was agreed to use the
five years out-of-date. However, it remains the TB 379 Table 11 failure data for underground
most comprehensive industry survey ever done AC XLPE cables (all voltages) for both AC and
The final assumed cable failure rates for internal and external causes are summarized in Table 12.
Table 12 Assumed Internal and External Origin Cable and Accessory Failure Rates (Worst Case/Best Case)
AC XLPE DC XLPE
AC XLPE Submarine DC MI Submarine
Underground Underground
Cables
(per 100 cct-km/year 0.030 0.058 0.010 0.019
for AC and per cable- / / / /
km for DC) 0.030 0.000 0.010 0.000
Joints
0.005 0.003 0.005 0.003
(failures/year/100
/ / / /
joints)
0.005 0.000 0.005 0.000
Terminations
0.007 0.006 0.007 0.006
(failures/year/100
/ / / /
terminations)
0.007 0.006 0.007 0.006
56 - Manitoba Hydro
The following sections apply the preceding The methodology was to first determine the
assumed failure rates for the various AC and maximum lengths of AC or DC cable that could
DC, underground and submarine cable systems, be shipped on reels by truck for the underground
and route alternatives described in Section 3. options, where there is no rail access. Then
Options for shipping cables on reels versus long similar methods were used to determine
continuous lengths on rail cars were initially maximum AC or DC cable lengths shipped on
taken into account in developing the tables. reels by rail on flat cars to Lake Winnipeg for the
However, because no reasonably accurate failure submarine options, as compared to shipping
rates were available for submarine cable joints, cables in long continuous lengths on rail cars.
it was not possible to quantify any reliability Once reel lengths were determined, and route
improvements due to shipping long submarine segment lengths known, it was possible to
cables in continuous lengths with trains. determine the number of joints and terminations,
and finally apply the assumed failure statistics
(see Table 12, Table 13, and Table 14)
Table 13: Estimated Total Cable System Failure Rates and Frequencies – Worst Case
Failure Failure
Cable Internal & Termination
Joint Internal Frequency Frequency
External Failure Internal &
Instal- & External Total Failure Rate (Long Total Failure Rate (Long
Route Rate (per 100 External Failure
lation Failure Rate (No Long Trains) Trains) (Long Trains) Trains)
Option cct-km/year for AC Rate (per 100
Mode (per 100 (per year) (years (per year (years
and per cable-km terminations/
joints/year) between between
for DC) year)
failures) failures)
(534/(1 x 100)) x ? +
Line 4 (534/(1 x 100)) x ? + (297/100) x ?+
Water ? ? ? ? (15/100) x ? + (10/100) ?
DC (6/100) x ? = ?
x?=?
(861/(1 x 100)) x ? +
Line 5 (861/(1 x 100)) x ? + (478/100) x ? +
Water ? ? ? ? (20/100) x ? + (20/100) ?
DC (12/100) x ? = ?
x?=?
(960/(3 x 100)) x ? +
Line 6 (960/(3 x 100)) x ? + (800/100) x ? +
Water ? ? ? ? (14/100) x ? + (56/100) ?
AC (32/100) x ? = ?
x?=?
Failure Failure
Cable Internal & Termination
Joint Internal Frequency Frequency
External Failure Internal &
Instal- & External Total Failure Rate (No Long Total Failure Rate (Long
Route Rate (per 100 cct- External Failure
lation Failure Rate (No Long Trains) Trains) (Long Trains) Trains)
Option km/year for AC Rate (per 100
Mode (per 100 (per year) (years (per year (years
and per cable-km terminations/
joints/year) between between
for DC) year)
failures) failures)
(890/(1 x 100)) x ? +
Line 4 (534/(1 x 100)) x ? + (297/100) x ?+
Water ? ? ? ? (15/100) x ? + (10/100) ?
DC (6/100) x ? = ?
x?=?
(1428/(1 x 100)) x ? +
Line 5 (8615/(1 x 100)) x ? + (478/100) x ?
Water ? ? ? ? (20/100) x ? + (20/100) ?
DC +(12/100) x ? = ?
x?=?
(1682/(3 x 100)) x 0.030
Line 6 (960/(3 x 100)) x ? + (800/100) x ? +
Water ? ? ? ? + (14/100) x ? + (56/100) ?
AC (32/100) x ? = ?
x?=?
Results show that an underground cable system For underground options, repair times could be
failure can be expected about once every 3 to two to three months, depending on location and
17 years, depending on route length and cable time of year. But with the spare underground
type. Even if it’s argued that the most optimistic cable available and switching arrangements
TB 379 underground cable failure data is similar to the submarine cable terminal stations,
overly pessimistic, Manitoba Hydro could still outage durations could also be limited to several
experience many underground cable repairs over hours or days.
the operating life of a long underground cable
system. Comparisons with overhead transmission
line reliability shows that overhead lines are
Wait and repair times could be up to eight considerably more reliable. For example, a
months if a cable fault occurred in Lake Winnipeg compilation of CIGRE survey statistics collected
at the end of the fall season. However, by between 1993 and 2008 shows that the Bipole
switching in the spare cable, the outage duration I and II overhead lines had an average of 0.057
could be reduced to several hours or days, forced outages per 100 km/year (see Appendix 9),
depending on the type of switching implemented at least three times better than the worst-
at the terminal stations. performing underground segment. Most overhead
line repairs could be done in less than a week;
much faster than for cable systems.
58 - Manitoba Hydro
3.3.5 Life Expectancy of Cable Systems 3.4 Literature Review of Current Research
Cable systems are typically designed and tested for Further Technological Development
on the basis of a 40 year life. Actual longevity of 500 kV Cables
can exceed this time if loading is not excessive
and regular maintenance programs are followed. A review was completed of recent technical
There is a growing trend to acknowledge that a 50 publications at CIGRE, IEEE and Jicable
year actual life may be more realistic, based on conferences.
service experience with cables less than 500 kV.
Comparing with an approximate 100 year life for The results show that little development work
overhead line alternatives leads to the conclusion is being done for SCFF cables and production
that an underground or submarine cable system capacity is declining as a shift continues toward
would need to be replaced about once during the use of XLPE insulations for AC applications.
life of the equivalent overhead line.
Production of mass impregnated cables, only
used for DC applications, has been retained
3.3.6 Operation and Maintenance by established cable suppliers, while other
Requirements for Cable Systems suppliers without MI cable manufacturing
capabilities concentrate on XLPE insulations for
Modern cable systems are often installed with DC. Established suppliers of MI cables can also
real-time monitoring systems, which help to provide XLPE DC cables. A Korean cable supplier
ensure that they are operated within their thermal completed a new submarine cable factory in
and electrical limits. For underground cables, 2009, capable of manufacturing both MI for DC
DC jacket tests are required between three and submarine cables, and XLPE for both AC and DC
five years, to ensure that metal sheaths do not submarine cables.
corrode, which could allow water ingress and
premature insulation failure. Otherwise, only Some established suppliers are considering
annual inspections of cable transition stations expanding MI cable capacity and developing
and sheath bonding connection points are paper-polypropylene laminate insulations for DC
required, except for regular patrols for possible applications up to 600 kV. It is claimed that such
external aggression by third parties. For insulations allow 80 °C operating temperatures
submarine cables, DC jacket tests are usually compared to 55 °C for conventional kraft paper
impractical. Underwater inspections should be insulations. This allows a substantial increase in
carried out where depth of cable burial could transmission capacity for the same conductor, or
change. Annual inspections of transition stations alternatively a smaller conductor and cable for the
are required. More extensive maintenance same transmission capacity.
requirements are needed for the reactive
compensation stations, which are mandatory for Production of XLPE cables for AC and DC
the long AC cable systems for this application. applications is increasing, with over 40 companies
It is important that emergency response plans capable of supplying AC XLPE cables up to the
be developed and spare cable materials are well 220 kV level. New joint ventures are being formed
maintained, so that submarine cable repairs can between the established cable manufacturers and
be carried out quickly. those in some fast-growing developing countries,
which are now capable of manufacturing 500
kV AC XLPE cables. There are at least eight cable
suppliers claiming they have the capability to
manufacture 500 kV AC XLPE cables. There are now
at least three suppliers of 500 kV DC MI cable.
60 - Manitoba Hydro
requirements. With a DC transmission option, • A long cable connected to a generating
the compensation requirements needed to station can also be an application for
transmit AC power can be eliminated, reducing compensation. The generator capability
the costs of the transmission line. In addition, curve has limitations for excessive
fewer cables are needed since DC requires only absorption of reactive power due to either
two paths, where an AC option requires three. generator load angle stability or end
winding heating in the generator stator.
For the purposes of illustrative analysis, the AC
option is explored since operational issues on As the timing for a future north-south line
the Manitoba Hydro grid dictate that a stronger dictates, preliminary planning studies for options
southern AC network will be required in the future using AC cables would examine the following:
[19]. AC cables have similarities with capacitors in
• The types of cable to use
the sense that there are two metallic surfaces with
a dielectric material in between, which is the cable • Effects of parallel transmission paths
insulation. This means that the cable will produce • Shunt compensation schemes
reactive power in the same way as a capacitor. The
capacitive (or charging) current will increase with • Phase transposition and cross-bonding
cable length and voltage. The following reasons • Voltage stability and transient stability
exist for compensating this capacitance produced limits
by the cable:
• Effects of harmonic frequencies on the
• The critical cable length is reached where cable connected system
the cable’s full ampacity in the sending
end is taken up by the capacitive current A power system with long cables will have
and hence no active or real (watts) power characteristics that differ from a system
transport is possible. One way to reduce of overhead lines along the same route.
this problem is to compensate along the Conceptually, the purpose of an overhead
cable route. The Ferranti effect, which is transmission line is the same as an underground
the well-known phenomena associated or submarine cable – transport energy in the form
with transmission lines where open end of electricity from one end to the other. However,
voltage can rise above safe limits, also the physics of moving electricity with cables
dictates the need for compensation. has some distinct differences from overhead
transmission lines. Specifically:
• With high capacitance there can be too
large a voltage step change when the cable • AC cables are not just simple three wire
is connected or disconnected. Typically systems. They form a complex system
a ±3% voltage change is acceptable but of six or more conductors, thus adding
this is dependent on the grid code for complexities to the mathematical
the specific grid. The size of the change modelling.
is dependent on the reactive power • Level of shunt compensation required is
produced and the strength of the grid much greater than overhead lines.
point, which is usually called the Short
Circuit Capacity. • Lower system resonance frequency can
lead to risk of poor voltage quality or mis-
• The grid code may impose requirements operation due to harmonic injection.
on the range of power factor for delivery
to a certain grid point.
• Single pole re-closing and blocked re- Long AC cables require compensation in the
closing for cable faults form of shunt reactors to eliminate or reduce the
capacitive effect of the cable, which is produced
due to the time-varying nature of alternating
3.6 Thermal Properties and Ampacity of current (AC) or voltage. Cable compensation is
Cables necessary to minimize cable losses in transmitting
power through a long cable, and to control the
Thermal limit (ampacity) is a very important voltage which could otherwise exceed equipment
cable parameter for grid operations. With ratings.
overhead lines, the thermal limit is mainly
dependent on ambient air temperatures and
wind speed.
62 - Manitoba Hydro
There is a critical cable length that when reached,
the cable’s full ampacity at the sending end is
consumed by the capacitive current; thus no
active real power transport is possible. Either
a larger cable with higher ampacity must be
installed, or the capacitive current must be
reduced by installing reactive compensation
devices at the ends of the cables, and if required,
along the cable route.
This section deals with the transportation of Figure 21: C/S Guilio Verne (source: Cabletricity)
submarine cables from the manufacturing facility
by ship to a port in Canada where they would be
transferred to a rail transportation system. At the
destination the cables would subsequently be off-
loaded at Lake Winnipeg to a specially built barge
complete with a cable laying system.
66 - Manitoba Hydro
Figure 25: Looped cables on train (Proposal 1), four cars are shown for simplicity
Proposal 1 presents a concept on how long this case. Both the Montreal and Powerview-Pine
sections of 500 MW 500 kV DC submarine Falls locations meet this requirement.
cable with either MI or XLPE insulation might
be transported by train. MI cable would be When the ship with cable arrives in Montreal,
approximately 130 mm (five inches) in diameter the cable would be immediately transferred
with single-wire armour, have a supported onto a turntable positioned on or near the dock
bending diameter of approximately three metres and adjacent to a railway track. It is necessary
(nine feet, 10 inches) and weigh about 45 kg/m. to quickly unload the ship to avoid expensive
500 kV AC XLPE cable would be about 150 mm port costs estimated at about $200,000 per day
in diameter and weigh approximately 65 kg/m. for a cable ship. The turntable would be at the
This procedure could be used for both AC and midpoint of the required 1.2 km of track. From
DC cables, but this example continues with MI the turntable, the end of the cable would be
cable to illustrate the concept. lifted to the top of a 10-metre gantry, propelled
by a “caterpillar” (a special traction machine for
Cable could be loaded on the unit train at the this purpose). The gantry would overhang the
port of Montreal, for example, and unloaded at railway track and from there the cable would be
Powerview-Pine Falls, where the track is 300 m lowered onto the floor of the first flatcar. The
from a bay on the Winnipeg River that flows into train would then advance along the track and
Lake Winnipeg. The total distance between these the cable would continue to be released and laid
two locations is about 2500 km. on all following cars until the end of the train.
In this proposal it would take 29 flatcars to When the cable reaches the end of the last car,
transport 50 km of cable. A 29 flatcar train is a steel rim, three metres in diameter would be
almost 600 m in length. The procedure to load or fitted on the cable and pressed up to the vertical
unload the cable requires a track at the dockside length of cable extending from the top of the
to be twice the length of the train, or 1.2 km in gantry. At this point the train would back up,
68 - Manitoba Hydro
4.3 Transportation of short lengths of Figure 26: Equipment to move 500kV AC cable reels in the
submarine or underground cable factory (Photo from IEEE ICC 2007, Nexans France)
Table 15: Reel dimensions for maximum submarine cable length for rail transport (approximate)
500 kV DC MI 1000
44 0.120 2.8 1800 2.8 x 4.2 x 3.5
mm2
70 - Manitoba Hydro
Once the cable reels are transported to With this procedure the number of joints in
Powerview-Pine Falls near the dock where the Routes 4, 5 and 6 would be as follows:
barge would be moored, the jointing of these
short lengths of cable could proceed – AC lengths • Route 4 – 534 km/1.8 km = 297 joints
being 1.2 km and DC 1.8 km. A large jointing • Route 5 – 861 km/1.8 km = 478 joints
house would be constructed at this location,
• Route 6 – 960 km/ 1.2 km = 800 joints
large enough to contain three jointing assembly
lines. Outside this structure there would be
The time that it would take to install the cable in
three approximately 20 km capacity turntables
Routes 4, 5 and 6 would be as follows (see Table
dedicated to each of the assembly lines. Nearby,
17):
there would also be a large 50 km storage
turntable. • Route 4 – 3 summers
Tokyo ‘Shin-Toyosu’ (2
2000 500 AC XLPE N/A 1800 40 2 x 3 x 40 N/A
circuits)
DolWin1 2012-
320 DC XLPE N/A N/A 90 2 x 90 N/A
(land segment) 13
Skagerrak IV (land
2014 500 DC MI N/A N/A 90 90 N/A
segment)
Maximum underground cable lengths can also be calculated using the same methods as used for
submarine cables, but with a net 65 tonne limit due to road weight restrictions, not considering
special conditions along final right-of-way.
Reel dimensions can be determined using the same methods as for submarine cables.
Table 17: Reel dimensions for maximum underground cable length for truck transport
Cable Description Cable Cable External Minimum Bending Maximum Cable Reel Dimensions
weight Diameter Diameter (24 x cable Length per Reel Barrel x Flange x
(kg/m) (m) diameter) (m) Axial Length
(m) (m)
500 kV AC XLPE 1400 mm2 25 0.131 3.1 1800 3.1 x 4.2 x 5.5
copper
500 kV DC XLPE 1000 mm2 11 0.105 2.5 4000 2.5 x 4.2 x 6.0
aluminum
Compared to the submarine cable alternatives, into prepared trenches or use of many serial
the above four kilometre lengths for DC cables powered rollers and cable pushers to assist
would require substantially fewer joints and they end pulling machines. Results of cable system
could be of the pre-molded type, leading to faster reliability calculations summarized in Table
installation times for underground applications. 13 indicate that the extra effort to ship four
For Routes 2 and 3 approximately 131 and 197 kilometre lengths of underground DC XLPE
joints would be required respectively. Installing cables may not provide a significant increase in
four kilometre lengths of underground cables reliability, although there could be savings in
would require novel methods, including use of jointing costs.
travelling reel carriers to side-load cables directly
72 - Manitoba Hydro
5 Cable Installation When fully loaded, such a barge would have a
draft of about 2.5 m. The boat builder could
This section describes both submarine and land build such a barge as a modular structure, with
cable installations, the equipment required, several possibilities, e.g., a 25 x 25 m section in
schedule and processes. the middle, flanked by 20 x 25 m sections at each
end, or three 15 x 25 m sections flanked by 10 x
25 m sections. These sections would be bolted
5.1 Submarine Cable Installation and welded together to compose a single rigid
The laying of submarine cable in Lake Winnipeg unit, with a solid deck on the top. The sections
would be conducted from a barge, with its base would also be suitably reinforced to carry the
at a dock in a bay of the Winnipeg River at weight of the turntable and cable. The exact
Powerview-Pine Falls – only a few kilometres dimensions and structure of the barge would
from the lake. Three potential submarine cable have to be determined and designed by a naval
routes have been identified for illustrative architect.
purposes.
To tow a large barge of this size as well as the
The procedure for laying cable underwater is necessity to keep the barge stationary in rough
complex. A cable laying vessel, a barge in this weather during the jointing operation may
instance, is the heart of a cable laying operation. require both a dynamic positioning (DP) system
Hence it is useful to provide a description of the and one or more tugboats. A DP system by itself
barge and its wide variety of equipment. The might be sufficient to propel the barge and keep it
procedure for jointing and burying the cable stable, together with anchors, during the jointing
in a trench on the lake floor is described to aid operation, but the cable installation contractor
understanding. may decide to use tugboats as well. This may be
for purposes of safety and the necessity to move
the barge as quickly as possible from the loading
5.1.1 Cable Laying Barge dock to the cable laying area, with the final and
furthest destination being about 370 km.
The cable barge is a specially equipped marine
vessel for the express purpose of delivery Central to what would be required on the barge
and installing submarine cable on site. The is a motorized 20 m diameter steel turntable,
cable turntable, jointing equipment, gantries, weighing about 200 tonnes, which would be
navigation systems, power plant and thrusters, located at the midpoint of the barge. It must be
wheel house, living quarters and cranes, are all capable of transporting 50 km of cable, where the
contained on the barge. DC cable would weigh approximately 2,250 tonnes
and an AC cable approximately 2,500 tonnes.
A local boat building company at Lake Winnipeg
could be capable of building such a barge suitable A specially designed “jointing house,” measuring
for laying cable, with expert advice from a cable about 4 x 17 m [1], would need to be constructed
laying company.4 The parameters of the barge are along one side of the barge at the stern end.
calculated below as part of this discussion.
The total weight to be transported, including the 4 A naval architect has provided an estimate of $10 million for
the barge, including some of its basic equipment, but
weight of the cable, the barge, the turntable, and
excluding a dynamic positioning system and thrusters.
all the associated equipment, would be about
4,000 tonnes. The estimated dimensions for a 5 A naval architect at Transport Canada considered this to be
barge to carry this weight are 65 x 25 x 4 metres.5 reasonable, but a full study by a naval architect would be
required for any official approval.
As on a dedicated cable laying vessel, the barge 5.1.2 Submarine Cable Trenching
must be equipped with a variety of equipment,
Sometimes the laying of the cable and its
some of it quite bulky. A large wheel or chute is
subsequent burial in a trench are conducted
required at the stern of the barge for deploying
simultaneously from the cable laying vessel. An
cable into the lake. Cable tensioners or linear
alternative would be to bury cables as separate
cable engines (caterpillars) are necessary for the
operations utilizing different vessels, as described
movement of cable on board and for applying
below. In this case, especially because the cable
tension during laying or temporary recovery.
is being laid from a barge with limited space, it
appears advisable to conduct these as separate
Each cable laying operation is different so the
operations.
cable manufacturer and installation contractor
would have to determine the required support
A small barge or other support vessel is therefore
equipment for cable laying.
assumed to be used to operate a cable trenching
machine. For a Lake Winnipeg application in
Of critical importance is a dynamic positioning
bottom sediments, trenching machines would
(DP) system to enable the barge to move along
be relatively small, both in size and weight, e.g.,
a pre-determined course or to remain in a
Nexans Capjet 50 measures 8 x 4 x 2.5 m and
stationary position. This would utilize a GPS-
weighs 12.5 tonnes. The exact size and nature of
supported navigation system. The system would
the support vessel would have to be determined
involve the installation of azimuth thrusters at
by the cable laying contractor. As an alternative, it
each corner of the barge. Four self-contained
may be possible to use a cable trenching machine
diesel-hydraulic power units would be positioned
in conjunction with a new vessel, such as the
on deck at each corner, and a DP navigation
Pumpemaron, specially designed to operate the
control room would be installed at the top of
Nexan’s Capjet. This vessel has a power unit
the barge’s bridge. A video of the assembly of
which operates an engine for its own propulsion,
such a system can be viewed at reference [10].
and for the water pumps to the Capjet. From this
Within certain limits, a DP system should be able
vessel the Capjet is operated by remote control
to maintain a barge’s position even when wind,
and would not need any diver-based operation.
waves or currents threaten to move it off course.
74 - Manitoba Hydro
Figure 30: Nexans Capjet (source: Nexans Norway, Marine Installation Department)
Its first successful operation took place in the When lowered into the water, the Capjet machine
spring of 2010 with the burial of the Valhall cable is connected by an umbilical cable to the surface
(292 km) in the North Sea. vessel in order to provide power and data
communication. It carries high-pressure water
Nexans Capjet is one example of an advanced pumps to create large water flows at high pressure,
form of cable burial equipment that uses the jetting swords, cable tracking equipment, process
water-jetting principle for both trenching and monitoring sensors, positioning systems and
propulsion. Unlike other systems that employ powerful lights and cameras. The machine is
heavy equipment which could damage the cable, neutrally buoyant in water but can be ballasted
no force is applied to the cable minimizing the during the trenching operation. It can create a
likelihood of damage. Also, the machine can start narrow trench to a depth of one to three metres,
and stop at any point along the route. depending on the need and the type of sediment.
Figure 31: Light duty sled type cable burial system (source: Figure 33: HydroJet Machine (source: Sumitomo Electric USA)
Cabletricity)
76 - Manitoba Hydro
5.1.3 Cable Jointing Operation 7 specialized equipment would include welding
materials and apparatus for MI cables, a semi-
In only one part of the lake is it possible to lay a automatic lapping machine for the application
length of cable without joints – the 50 km section of insulation tapes, equipment to have the joints
between Traverse Bay and Riverton. Elsewhere, the vacuum-dried and a semi-automatic armouring
routes are too long for the length of cable that can machine.
be transported, and therefore these shorter pieces
must be jointed or connected together. Rigid joints cannot be used for MI DC cable,
but for Lake Winnipeg they could be used for
In these areas, after the first section of cable is cable with extruded insulation and for AC
laid, the end of the cable would be carefully cables. Hence, if XLPE AC cables were to be
capped with a cable seal equipped with a pulling installed, steel casing tubes would be required.
eye and hooking arrangement to which a strong The following descriptions are for flexible joints
wire would be attached. The cable would then applied to MI DC cables.
be lowered to the lake bottom with a marking
buoy attached. Later, when the barge arrives with Jointing is a highly specialized procedure that
another section of cable, the cable in the water requires a team of highly skilled technicians. It
would be pulled onboard over the laying wheel would take approximately five days to make each
and into the jointing house. The end of the cable joint on the cable laying vessel. Certified jointers
on the turntable would be pulled into the jointing for 500 kV cables are scarce and it may not be
house from the opposite entrance where the two possible to find any in North America. Therefore
cables would then be joined. it may be necessary to bring skilled workers from
Europe or Asia.
The newly-joined cable would be removed from
the jointing house either through the opening of Before the onset of a jointing operation, there
a slot along the side of the house or by raising the must be some assurance of reasonable weather
upper part of the house to allow the cable to be conditions for several days. However, Lake
removed. If the joint is a flexible joint, the cable Winnipeg is notorious for sudden storms,
could be transferred through the ordinary laying 8
despite good weather forecasts. Hence, weather
equipment of the barge and passed over the stern may prove to be a hazard, especially during
wheel into the water. The cable would need to be the jointing sessions. Heavy weather imposes
kept under suitable tension in order to preserve a risk for the jointing crew and the cable. The
the joint from undue bending at the touchdown greatest danger would occur if a severe storm
point on the lake bottom. should cause the cable tensioners to slip or
the securing devices to break and the cable
If the joint design is rigid, it could not be pulled becomes unfastened in the jointing room.
through the ordinary on-barge cable route and Once the jointing process is started it cannot be
over the stern wheel. With a rigid joint, the cable interrupted, so the cable would have to be cut
would have to be carefully lifted with cranes and and the process restarted, resulting in lost time
winches to deploy it into cable laying machinery. and money.
This would be a complicated procedure since
great care must be taken to avoid sharp bends of 7 In this section, reference has been made to sections of
the cable near the rigid joint area, and equal care Thomas Worzyk, Submarine Power Cables, Berlin: Springer,
must be exercised in laying it on the lake bottom. 2009 [1]
In addition to what has already been mentioned 8 Information provided by Captain Curtis Grimolfson, an
to be provided in the jointing house, other experienced fisherman, operator of tugboats, and captain
on cruise ships on Lake Winnipeg and the Red River.
78 - Manitoba Hydro
The completed flexible joint can be transferred The winch would haul in the pull wire and the
through the ordinary laying equipment and cable to its destination at the terminal. During the
passed over the stern laying wheel into the water. pull-in, the cable would be guided on a system of
rollers, either within the trench or alongside it. In
the case of the latter, the cable would be pushed
5.1.4 Cable Laying Procedure into the trench afterwards. Once in its proper
position, the cable should be anchored and as the
Long before the cable is laid, the cable routes
floatation devices are removed, it would settle on
must be precisely determined and carefully
the lake bottom. The barge could then proceed
surveyed to avoid crossing underwater
with the regular cable laying operation.
obstructions, if possible, and to ensure that
there would be no obstacles in the sediment. For At the end transition station, a somewhat different
example, over the years there have been a number procedure would be followed. The barge would
of shipwrecks on the lake, as well as lost fishing be brought as close as possible to the shore. The
gear and anchors. Given the amount of sediment remaining cable on the barge would then be
in the lake from both glacial Lake Agassiz and equipped with floatation devices. At this point the
Lake Winnipeg itself, it would be unusual to find barge would change direction and proceed a short
rocks in the sediment. distance parallel to the shore while the rest of the
cable is played out. A pull wire would be attached
A careful survey would have to be conducted to to the cable end and the floating cable would be
determine the depth and extent of ice scour and pulled ashore by a winch positioned on shore or
impact of other natural hazards, for the complete near the terminal station (see Figure 52).
cable routes. This would determine the depth
to which the cable would have to be buried in It is necessary to have properly trained personnel
various locations. operating the cable laying equipment. Various
procedures, including the speed of the barge,
It would be prudent to dig or excavate the must be synchronized, otherwise damage could
trenches at the terminal points for the onshore occur to the cable. A series of operations would
three (DC) or four (AC) lines of cable during the be involved. From the motorized turntable, the
fall before the laying operation. The trench profile cable would run over a moveable pickup arm with
must be engineered with respect to thermal cable rollers, through a cable tensioner (or a linear
properties, and the trenches would extend as far cable engine), and then over the laying wheel and
inland as necessary to reach a suitable location for finally into the water. The pickup arm has the
the terminal station. Alternately, conduits could shape of a gooseneck, and in the gap between the
be pre-installed through the littoral zone and turntable and the gooseneck, the cable could hang
cables pulled through them into land trenches loose. The slack is necessary to absorb possible
when the cable laying barge arrives. temporary speed differences between turntable
and tensioner engines. The gooseneck is highly
When all the land preparations are completed,
maneuverable, being pivotal and adjustable in
the barge with a load of cable would be towed as
height.
close as possible to the landing site and remain
anchored or maintained in place by its DP system. The cable could not be let down to the lake
On the shore, a winch would be installed with a bottom vertically because of possible looping
pull wire extending to the barge and connected to and violation of minimum bending radius limits.
the cable end. The cable could then be extended Instead, the cable would have to be positioned
over the laying wheel, and where it would enter in a well-defined catenary line from the laying
the water, floatation devices would be attached wheel to its point of contact on the lake sediment.
so it could be more easily pulled onto the shore.
80 - Manitoba Hydro
Table 18: Cable Installation Durations
Rail cars 2 3 4
Installation Time (summers)
Reels 3 5 6
Rail cars 9 12 8
Number of joints
Reels 297 478 800
Summer is defined as mid May through to the end technicians could be employed, and that they
of October. would be prepared to work for about five months,
with periodic rotations with relief crews. The
There are many uncertainties in preparing cable contractor would provide an experienced captain
installation estimates and weather conditions are and crew for cable laying barge operations.
a major factor. The estimated time for the various
procedures in cable laying has not taken into And finally, it should be noted that this cable
consideration any delays that could be caused by laying operation is in many ways a unique
bad weather. Normally, there are many storms construction project. Never has a major power
during the course of a summer – some which transmission cable system been laid in an inland
might cause serious disruption. lake of this size so there are no precedents for this
type of project.
Along with the uncertainty of weather conditions,
there is the added uncertainty of ice conditions
on Lake Winnipeg in the spring. In recent years
5.2 Underground Cable System Installation
the lake has sometimes been free of ice at the
beginning of May. But, on average, the ice-free 5.2.1 Civil Work
period in the south basin begins about mid-May
and in the north basin the beginning of June.11 The most extensive work for installing
underground cables would be trenching over
Aside from weather and ice conditions, there are long distances, in some cases through areas of
a number of other uncertainties – so over all, it exposed bedrock, if unavoidable. Construction
may take longer to install the cable than indicated equipment and methods would be similar to
in these schedules. It is estimated that 90 to 100 those used throughout North America for oil and
km of cable could be loaded on a turntable in a gas pipelines, mainly using large tracked hydraulic
minimum of five days (seven were allowed in the excavators with rippers and rock hammer
schedule), so to load half this amount on a barge attachments where necessary. In some areas,
turntable may take about a minimum of 3 ½ days. drilling and explosive rock fracturing methods
There is also the assumption that 10 km of cable might be required. Other mechanized equipment
could be laid per day by a barge. It has also been would be used, where practical, for example as
assumed that qualified and experienced jointing shown in Figure 35. Typical trench depth would
be about 1.5 m, as indicated in Figures 13 and 18.
Only one trench is anticipated.
11Information on ice conditions in Lake Winnipeg has been
provided by Robert T. Kristjanson, a commercial fisherman,
with over 50 years of experience on Lake Winnipeg. Captain
Curtis Grimolfson is in agreement with these dates.
82 - Manitoba Hydro
5.2.3 Cable Installation Figure 41: Cable pulling (IEEE ICC Spring 2008)
84 - Manitoba Hydro
6 Transition and Compensation Stations
For both AC and DC systems employing Figure 45: Another example of 500 kV AC Double circuit cable
underground or submarine cables, equipment terminal – Side View
is required to make the transition from
underground/submarine to overhead lines, and to
provide for switching and isolation. For AC cable
and submarine systems, additional equipment in
the form of compensation stations is required,
to provide reactive support to transmit useable
power and control the voltage. This chapter
describes this equipment, and its role in the
context of the routes described in this report.
86 - Manitoba Hydro
DC overhead-underground transition stations would be severely limited for long cable lengths
would be similar to the overhead-submarine and over-voltage conditions could be excessive
transition stations. under some operating conditions.
88 - Manitoba Hydro
Submarine cables would have to be buried to
a sufficient depth to avoid damage from wind-
driven ice, also considering installation cost
constraints. Further detailed study is required to
determine the extent and depth of the ice keels.
Table 19: Cost estimate summary for route concepts (direct costs only; long length submarine cable shipping by rail
assumed feasible for this table)
Route Lengths
(km) Cost Premium
Cost Estimate
Route Type Description above Base
(M$)
Over- Cable (M$)
Total
head System
1 DC All overhead via Cedar Lake 1,273 0 1,273 635 (DC Base)
1 AC All overhead via Cedar Lake 1,273 0 1,273 809 (AC Base)
1. Costs are expressed in 2010 CAD dollars. • Cable supply costs were based on budgetary quotes
2. 500 kV AC overhead line is single circuit capable of from suppliers.
1000 MW. • Overhead line costs were based on Manitoba Hydro
3. 500 kV DC overhead line is similar to Bipole I-II 500 kV AC and DC line cost estimates
construction. • Overhead line costs were based on Manitoba Hydro
4. DC underground cables are XLPE. 500 kV AC line costs.
5. DC submarine cables are MI due to maturity • Stations and local service were based on Manitoba
6. AC underground cables are XLPE. Hydro cost estimates.
7. AC submarine cables are XLPE. • Transportation costs by rail were estimates from CN
8. For underground options, cables would be shipped logistics.
from Thunder Bay to site by truck (4.0km cable/truck • Trucking costs were supplied by a Manitoba trucking
for DC; 1.8 km cable/truck for AC). firm.
9. For submarine options with no long train shipping, • Transportation of underground cables by sea were
cables would be shipped from Thunder Bay to based on a per diem cost of $250k per day. Submarine
Powerview/Pine Falls by rail (1.8 km cable/car for DC; cable transportation by sea was based on $5M per 100
1.2 km cable/car for AC). km (or one ship load).
10. For submarine options with long train shipping, cables • Tunnel cost estimates were derived from a similar
would be shipped from Montreal, Prince Rupert or project in Vancouver.
Vancouver, a maximum distance of about 2500 km.
11. MH Project Management and Engineering costs not
included.
12. Contingencies not included.
13. Interest during construction not included.
14. Insurance for cable transportation not included.
15. Converter costs for DC alternatives not included.
16. Static VAR compensator for AC alternatives not
included.
17. Cable manufacturing capacity is assumed available.
18. Taxes and import duties not included.
19. Estimates are Class 5, as defined by AACE
International, to be used only for concept screening
purposes with low project definition. Class 5 estimates
typically have accuracies in the following range:
Low: -20% to -50%
High: -30% to +100 %”
20. All estimates contain only labour and material.
92 - Manitoba Hydro
A table of cost premiums for submarine cabling
over an equivalent length of overhead line for
1000 MW is presented below in the Table 20: Cost
Premiums for Equivalent Line Lengths.
1000 MW Transmission System - Submarine Cable Premium when compared to similar length OH line
94 - Manitoba Hydro
8 Regulatory Issues
8.1 Licencing Other Federal reviews required would include
the Department of Transport under CEAA to deal
The project will require a licence under The with impacts under the Navigable Waters Protection
Environment Act of Manitoba as a Class 3 Act and a Comprehensive Study requirement that
development. Projects of this nature always would involve the Major Projects Management
involve a public review and if there is significant Office. All of this may then require a federal panel
public interest, a project may be referred by the review of the project under CEAA.
Minister of Conservation to the Manitoba Clean
Environment Commission. A major transmission Part of the problem with submarine transmission
project would almost certainly involve a public for regulators in this Province is that it will be
hearing prior to the issuance of a licence by the new technology applied at a fairly large scale. This
Minister to construct. will mean that regulators will need assurance that
the project is feasible, minimizes environmental
effects and has limited risk of failure that could
Aboriginal Interests cause continuing lifetime environmental damage
(e.g. release of contaminants into Lake Winnipeg,
The project will almost certainly involve disturbance of lake bottom and marine habitat).
discussions and negotiations with First Nations This will likely increase the challenge and time
and other Aboriginal peoples in the vicinity of to get environmental approvals as regulators
the transmission route. Supreme Court rulings may impose commitments with respect to future
have clarified that the Crown has a legal duty to submarine cable repairs as part of the initial
consult with Aboriginal people about any action project approval.
that might affect the exercise of an Aboriginal
or Treaty right before taking any action. The There will be other legislation that will need to
Crown must reasonably accommodate concerns be dealt with including Species at Risk Act for
about the effects of a project like the one under threatened and endangered species.
review. Discussions on these matters have
typically involved substantial negotiations about New approvals may be required for each repair
economic opportunities associated with a project. operation and an Environmental Management
Plan may need to be provided with the original
application that describes how submarine cable
8.2 Regulatory Issues with Lake Winnipeg repairs would be carried out.
Routing
98 - Manitoba Hydro
Laying separate complete lines with cable from Jointing workmanship
two different manufacturers should not present a
technical problem, but there could be a liability Each joint must be professionally produced
problem in attempting to joint cable from so that its mechanical strength and electrical
different producers, especially if joint failures properties would be equal to the cable itself,
should occur. Such eventualities must be taken otherwise a line failure could occur.
into consideration. It appears that there are differing views among
the manufacturers on the reliability of cable
Once a routine is established in loading lines with a large number of joints, depending
submarine cable on a train and unloading, it strongly on manufacturer and cable type. For
would be expected that the procedure should be example, there is evidence that DC MI cable joints
flexible in order to meet any expected delivery have performed very well, whereas failures have
schedule. occurred for AC XLPE cable joints.
[9] Brian J. Todd, C.F. Michael Lewis, L Harvey [16] CIGRE Working Group B1.10, Update of
Thorleifson (2006), “Geological Survey of Service Experience of HV Underground
Canada, Open File 3113, Lake Winnipeg and Cable Systems, CIGRE, April 2009.
Project Cruise Report and Scientific
Results”.
Purpose:
The overall purpose of this review panel is to produce a concepts-based report that includes discussion
of the reliability of 500kV high voltages cables and the feasibility of underground and underwater
installation for possible use in a future North-South Transmission line in Manitoba, post-Bipole III.
Items of Concern:
• The Panel shall review the maturity of the state-of-engineering of 500kV cable technologies in
use world-wide today
• The Panel shall research the causes of failure of 500kV cable systems world-wide
• The Panel shall review the literature on current cable research for 500kV and the effects of very
long cable lengths on the power system
• The Panel shall discuss concepts for transporting very long sections of cable on land and over
landlocked inland waterways
• The Panel shall identify the concept with the highest feasibility for transportation and
installation that may need to be advanced for further research and investigation by world
experts
• The Panel shall address cost implications of any concepts that may have merit
David Farlinger is a Civil Engineer and a Principal with CMC Consultants Inc. His interests are
divided into two principal areas, energy and water.
With respect to energy, he was involved for a number of years as a pipeline technical advisor for the
Province of Nova Scotia, in the technical review of proposed natural gas systems for the awarding of
franchises in Mexico as well as two World Bank funded electricity regulatory projects, one in Russia
and the other with the Palestinian Energy Authority.
In 2007 he served as Study Manager for the Manitoba Bipole III Study “Review of Environmental
Considerations” which examined the issues related to alternatives routes.
Previously he served as study manager of a Canadian East-West Electrical Transmission Grid Study
conducted for the fourteen Provincial, Territorial and Federal Energy Ministers and took a leading
role in an External Review of Qulliq Energy Corporation, the electricity provider in Nunavut.
Much of Mr. Farlinger’s water related work involves bringing diverse interest groups to a common
understanding. He served as Chair of the Manitoba Water Commission reviewing the actions
taken during the 1997 Flood of the Century, as Chair of the Lake Winnipeg Shoreline Erosion
Advisory Committee and subsequently as Chair of the Lake Manitoba Regulation Review Advisory
Committee. He also served as Technical Advisor to the Clean Environment Commission with
respect to licencing of the construction of the 200 MW Wuskwatim dam and the expanded
Winnipeg Floodway.
Mr. Farlinger has been active in the Consulting Engineering Industry for many years. He was a
founding Director of CEM, the Consulting Engineers of Manitoba and served as President of the
Association of Consulting Engineers of Canada.
For 28 years Mr. Farlinger was a Director of Teshmont Consultants LP, specialists in High Voltage
Transmission Systems, including a number of years as Chairman. He also served two terms as a
member of the National Research Council representing industry with his expertise in energy.
Most of his career has been in transmission and includes eleven years as Division Manager of
Transmission System Operations which included a time of dynamic industry change involving de-
regulation, market developments, and establishment of enforceable reliability standards.
Mr. Tymofichuk managed and oversaw new interconnection transmission lines to Saskatchewan and
the U.S. including the 500 kV AC line from Winnipeg to Minneapolis (Manitoba portion only), and
many transmission projects in Manitoba.
He has been active in national industry organizations such as Canadian Electricity Association,
Canadian Standards Association, in North American organizations such as the Midwest Reliability
Organization (Chair of Board for 2011), Chair of the North American Electrical Corporation
Members Representatives Committee for 2010, and internationally as past member of the
International Electro-technical Commission (IEC) Standardization Management Committee.
He has consulted on international electricity industry re-structuring in several Balkan countries early
in this decade.
Since March 2009 he has held the position of Vice-President Transmission Business Unit,
comprised of four divisions of approximately 1 400 employees, responsible for the cradle-to-grave
management of transmission assets.
John Ryan, B.A., B.Ed., M.Ed., M.A., Ph.D., is a retired professor of economic geography and
Senior Scholar at the University of Winnipeg where he taught from 1964 to 1996. He specialized
in courses on energy, resources, economic development, and the economic geography of Canada,
the USSR, and Monsoon Asia. His research and travels have taken him to more than 50 countries.
His numerous publications include a pioneer work on the agricultural economy of Manitoba
Hutterite Colonies and a best-selling art and biography book. Since retirement he has continued to
publish in journals and on the Internet on a wide range of subjects, including articles on Canada-
US trade relations, Afghanistan, Iraq, Israel-Palestine, US foreign policy, and Canadian political
affairs. His latest efforts have involved a steep learning curve in engineering and he has acquired
expertise on the nature of HVDC submarine cable, its transport by rail and its possible use in Lake
Winnipeg.
Allen MacPhail has a Bachelor of Applied Science degree (Electrical Engineering) from the
University of British Columbia and is a registered professional engineer in BC and Alberta. He
began his career at British Columbia Hydro as a Distribution Engineer, with an early interest
in underground systems for high load density urban areas. Later he transferred to BC Hydro’s
Transmission Engineering Department, specializing in design, installation and maintenance
of many underground and submarine cable systems, from 69 to 525 kV. He was also an
engineering leader for many external submarine cable projects through BC Hydro’s consulting
subsidiary BC Hydro International, taking him to assignments in Egypt, Jordan, Northern
Ireland, Belize, Alaska and Washington.
In 2006 Allen retired from BC Hydro and began Cabletricity Connections Ltd., to further his
interests in high voltage power cable applications. He is active with a variety of domestic
and international power cable engineering activities and has affiliations with several other
consulting companies specializing in power cables and HVDC systems. Presently he
participates in the IEEE Insulated Conductors Committee as well as CIGRE B1 Working
Groups.
Paul Wilson is currently the Managing Director of Manitoba Hydro Subsidiary Operations,
Manitoba Hydro International Ltd. and the past Managing Director of Manitoba HVDC
Research Centre. The Manitoba HVDC Research Centre is the the engineering arm of MHI
and developer of the advanced Power System Simulator PSCAD®/EMTDC™ used by utilities,
manufacturers, consultants, research centers and universities worldwide to solve technical
problems.
Paul has worked his entire career in the utility industry with Manitoba Hydro and has enjoyed
the challenges associated with Software Development, Distribution Engineering Protection,
System Protection Maintenance and commissioning, and the Y2K project. The Engineering
group of the HVDC Research Centre is very active in power system studies for grid integration
of renewables, HVDC engineering, operational planning studies and electro-magnetics
transient analysis.
Figure A3-2: Arrangement of shunt reactors on a long distance high voltage AC transmission line
Compared with overhead lines, inderground/ Operation of EHV long AC cables requires a
underwater cables are characterized as having high degree of inductive shunt compensation.
low surge impedance (Z0, 40 to 60 Ohms) The sudden voltage change due to routine
and relatively limited implicitly (Iz). The main manoeuvres (e.g. no-load energization or
problem of underground/underwater cables is disconnection for weak system) and rated cable-
that the cable generates far more reactive power charging breaking current of line circuit breakers
than it absorbs. I.e. ampacity of the cable is (for strong systems) dictates a high minimum
lower significantly (several times) than Surge compensation degree (usually over 95%).
Impedance Loading (SIL = V2 /Z0) of the cable.
For a 530 km overhead line section
Under these circumstances, the current
transmitted through the cable is limited to the • 1.3 MVA charging per kilometre, total 728
large charging current (capacitive) of the cable. MVA reactive compensation.
When the cable is fully loaded, the reactive • Surge impedance: 235 ohms
power absorbed by the series reactance is only
about 10% of the reactive power produced by Ferranti effect is a rise of voltage at the open
the cable capacitance. The local shunt reactors receiving end of a transmission line. On a 300 km
(inductances) are installed to compensate for this line the voltage rise is only 8.8% which is not
capacitive charging current.
Figure A3-3: Voltage profile along a transmission line/cable with ends at 1 per unit voltage
1.25
1.2
Voltage [p.u.]
1.15
1.1
1.05
1
0 50 100 150 200 250 300
Length (km)
It is desirable to limit open-circuit voltage rise to connected capacitors are used to maintain the
about 25% at the sending end, and about 40% at voltage levels by compensating the reactive power
the receiving end under worst conditions – that to transmission line.
is with all parallel lines connected, minimum
generators connected, and before the excitation There are many types of shunt compensation
systems on the generators can be reduced to a safe systems which provide varying degrees of control.
level [24].Shunt compensation, especially shunt Fixed and switch compensation shunt reactors
reactive compensation has been widely used offer a coarse level control, where thyristor switch
in transmission system to regulate the voltage reactors/capacitors (TCR/SVC) and STATCOM
magnitude, improve the voltage quality, and devices provide excellent compensation control.
enhance the system stability by employing active TCR/SVC and STATCOM are much more
variable compensation [25]. Shunt-connected expensive and are typically employed to improve
reactors are used to reduce the line over-voltages voltage and transient stability of the power
by consuming the reactive power, while shunt- system.
For the proposed cable route, the above table Using the formulations by T.J.E. Miller [24], it is
indicates that 3351 MVAr of compensation would possible to calculate the required shunt reactor
be required for each circuit in order to transmit sizes along each cable (pages 97-101) to control
1000 MW of power across the cable interface. the open-circuit voltage during energization.
Calculations indicate that the minimum reactor
size is 161.5 MVAr per phase at each terminal
Transmission Line and cable electrical point per cable along the line. Note: when two
analysis cable segments join the reactors are doubled to
2 times 161.5 MVAr. Five line segments were
The Concepts Review Panel studied options of selected (48 km each) for the total 240 km cable
underground cables for the next north-south run. Using PI section models in a simulation
transmission corridor. The corridor will bring with capacitance of 0.22 uF / km, confirms the
1000 MW of power to the Winnipeg area and reactor size is 500 MVAr (3 phase) for each PI
destinations south for export from new generation section end.
built in the north (the amount of this generation
is unspecified at this time). This analysis does not take into account any
parallel path or resonance analysis.
A number of assumptions were made so that
some simple engineering calculations could be
performed to determine typical reactive power
requirements for an AC cable option.
Figure A3-4: Three phase 500kV cable compensation stations per circuit
Source2
V = 500.2 C1 C2 C3 C4 C5 V = 500.2
A PI PI PI PI PI A
V V
Cable Section Cable Section Cable Section Cable Section Cable Section
48 m 48 m 48 m 48 m 48 m
1. The generator terminal voltage increases The energization phenomena includes charging
to the inductive electromotive force. of system elements like transmission lines or
cables, transformers, reactors, capacitor banks, etc.
2. The generator speed increases. with no trapped charge. However, in the case of
re-closure, the transmission line may have been
3. When the transformer inductance and left with a trapped charge after the initial breaker
capacitance of the cable are in a resonant opening and this affect is more pronounced on
condition, a resonant overvoltage will a cable. In such a case the transient overvoltages
appear. can reach very high values up to 4.0 pu [26]. De-
energization includes transient phenomena as a
The temporary overvoltage will sustain longer result of fault clearing and load rejection.
until voltage control equipment reacts
to lower the exciter voltage rectifying
the situation. Transmission line reflections
Vabs Vbcs Vcas
400
300
200
Sending (kV)
100
0
-100
-200
-300
-400
Vabr Vcar Vbcr
600
400
Receiving (kV)
200
0
-200
-400
-600
A52a
A52b
Figure A3-5: Transient Switching A52c
Overvoltages Time 0.7250 0.7300 0.7350 0.7400 0.7450 0.7500 0.7550 ...
...
...
40
emax TRVa TRVb TRVc is similar to series
resonance except that
30
a non-linear inductor,
20
the transformer, can
10
produce a chaotic and
0 unpredictable response.
kV
-10 Ferroresonance is
-20 characterized by large
-30
phase voltages and
currents that may exceed
-40
x 0.2750 0.2760 0.2770 0.2780 0.2790 0.2800 0.2810 0.2820 0.2830 0.2840 ... system ratings damaging
...
... equipment.
[27]
F. Faria da Silva, C. L. Bak, U. S.
Gudmundsdottir, W. Wiechowski and
M. R.Knardrupgård, “Methods to
Minimize Zero-Missing Phenomenon”,
IEEE PES
Transactions on Power Delivery,
TPWRD-00683-2009.
Proposal 1
Transporting long sections of submarine cable by train
by John Ryan, Consultant
Figure A4-1: Four layer vertical loop proposal for cables on flat cars
The purpose of this paper is to present a concept The dimensions of DC cables would be
on how to transport submarine cable from a approximately:
sea port to Lake Winnipeg where it would be • Diameter 130 mm (5 in)
part of a 500 kV transmission line from the • Weight 45 kg/m (30 lb/ft)
power stations in the north of Manitoba to the • Bending diameter 3 m (9 ft 10 in)
Winnipeg area. • A single layer of steel armour wires
It is proposed that long sections of 500 MW 500 The dimensions of AC cables would be
kV DC submarine cable, with mass impregnated approximately:
(MI) insulation, be transported by train. • Diameter 145 mm (5.7 in)
Although not discussed specifically, this concept • Weight 50 kg/m (35 lb/ft)
and the same procedure applies equally well to • Bending diameter 4.4 m (14.3 ft)
cable with greater weight and larger diameters, • One or two layers of copper armour wires
such as 500 kV AC or DC XLPE cable.
The steel rims that support the loops would have Once the first layer of cable is laid, a steel
to be firmly fastened to each other and to the 3-m platform, about a metre wide and positioned
high steel frame surrounding the end and the two about 4.5 m from the first row of rims, must be
sides of the long cars. This could be done by a attached to the sides of the flatcar, high enough
series of narrow metal plates or anchors bolted to to clear the height of the layer of cables (probably
the rims. These would keep the rims at the correct 150 mm or 6 in). The second row of loops
distance apart and firmly in place. To be more (with the rims inside them) would be placed on
specific, at the time the rims are manufactured, this platform, where the rims would be firmly
four strong bolts should be put through the rims attached to each other and to the platform and
and welded in place – equidistant from each the side supports. The same type of platform
other and at the midpoint of the interior concave would have to be installed for the third and
surface. The heads of the bolts should have a fourth rows of loops containing the rims, at
welded steel patch over them to prevent possible heights that would clear the underlying layers of
abrasion to the cable. When the rims are fitted cable.
over the cable they should be so positioned that
two bolts would be vertically aligned – one at It should be pointed out that if the cable is left
the top and one at the bottom – and two would unsupported from the top of the rim to the
be on the sides, opposite each other. Once in floor of the car it would sag in a catenary shape.
position, steel anchors would be fitted over Vibration of the suspended cable could cause
the bolts from the previously installed rim and concentrated sheath fatigue, resulting in loss of
attached to the bolts on the rim being installed – cable life and early failure. To prevent this from
keeping the rims about 130 mm (5 in) apart. In occurring, immediately after the rim is installed
this manner the 11 rims would be firmly fastened and the loop is formed, a specially fashioned
together and they would also be fastened to the support would be inserted in the void between
steel support structure on the sides of the flatcar. the edge of the rim and the curved slope of the
________________________
John Ryan, Ph.D., is Retired Professor of Geography and
Senior Scholar at the University of Winnipeg.
Proposal 2
Transporting Long Lengths of Submarine Cable by Train
by John Ryan, Consultant
This proposal outlines an alternative concept days. A second section of cable could be hauled
on how long lengths of 500 MW 500 kV DC by loading another set of cars with either 46 or
submarine cable can be transported by train. The 50 km cable. Hence the total train would consist
proposal is suitable for cable with either mass of either 54 cars or 58 cars and would transport
impregnated (MI) or extruded insulation (XLPE. either 92 or 100 km of cable, as required.
These cables would be approximately 130 mm
(5 in) in diameter with single-wire armour, have It should be noted that the cable lies in a
a bending diameter of approximately 3 m (9 ft horizontal position on the ship’s turntable and
10 in), and weigh about 45 kg per metre. This that it would be lifted and conveyed to form a
proposal is unsuitable for AC cable because of its horizontal loop on the flatcar. Because the cable
larger bending diameter. would be transferred from a horizontal position
on the ship to a horizontal position on the train
As presented in Proposal 1, the cable would be there should be no torsional twist exerted on
designated for Lake Winnipeg, and the same the cable. That is the main advantage of this
amounts of cable would need to be transported. alternative proposal.
Also, by way of example, Montreal would be the
arrival port for the cable, and the procedure at the As in Proposal 1, the same number and type
dock for loading the cable on the train would be of flatcars would be required. However, in this
identical to that presented in Proposal 1. However, proposal the flatcars would require 0.6 m (2 ft)
in this alternative concept, the procedure for high steel supports along the sides, but the first
loading the cable on the long cars at each end of and last cars would require 1.8 m (6 ft) high
the train would differ. steel supports. At the ends of the first and last
cars, there would be, bolted to the floor, specially
In this alternative proposal, when the cable designed 1.5 m (5 ft) high aluminum drums,
reaches the end of the last car it would be carefully measuring 3 m in diameter. It is around these
looped horizontally around a vertically positioned drums that the cable would be looped, allowing
3-m diameter aluminum drum (bolted to the it to double back. For each 22-row layer there
car floor), enabling the cable to double back and would be 11 loops around the drum, which
form the second row. At this point the train would would measure about 1.4 m (4 ½ ft) high. The
go in reverse and back up while the cable would drum for the second layer should be positioned
continue to be laid on the cars as they pass by. On about 4.5 m from the first drum, and it would
reaching the end car the cable would once again be bolted on supports above the first layer (so as
be looped around a 3-m drum and thereby double not to exert any weight on the cables in the first
back to form the third row. In this manner, with layer). The drum for the third layer should be
the train going back and forth, the entire 46 or 50 positioned about 4.5 m from the second drum,
km of cable could be loaded in a matter of several and again it would be bolted on supports above
Proposal 3
Transporting long sections of DC submarine cable
with extruded insulation by train, coiled on widened flatcars
by John Ryan, Consultant
In this proposal an additional concept is these would not involve sharp bends this may
presented on how long sections of 500 MW 500 not be detrimental to the cable. Nevertheless,
kV DC submarine cable with extruded insulation this procedure should be tested to ensure that
(XLPE) can be transported by train. The no damage could occur to these short sections
procedure involves coiling the cable on a series between the cars.
of specially widened flatcars. Cable with extruded
insulation may tolerate a certain degree of coiling Since the bending diameter of the cable is 3 m (9
and twisting so this procedure may be feasible. ft 10 in) and the standard flatcar is 3.05 metres
However, because of the coiling and torsional (10 ft) wide, to accommodate four rows of 130
twist involved in this concept, this process would mm (5 in) diameter cable, both ends of the car
not be suitable for cable with mass impregnated would have to be widened to 4.3 m (14 ft) by the
(MI) insulation since this cable cannot be coiled addition of 0.6 m (2 ft) extensions on each side of
or twisted. the car. This additional width at each end of the
car should extend along the length of the car for
As presented in Proposal 1, the cable would be 4.3 m (14 ft). Hence the car would have a type of
designated for Lake Winnipeg, and the same hour-glass configuration, as shown in the attached
amounts of cable would need to be transported. diagram.
Also, by way of example, Montreal would be the
arrival port for the cable. A support structure, measuring 1.2 m (4 ft) in
height, would have to be built on all four sides
In this proposal, a 46 or 50 km length of cable of the car. These supports could be made of steel
would be loaded on a series of flatcars, with bars at intervals of about 0.6 m (2 ft), and sheets
supports for sides, by means of coiling the cable of plywood or some other material would be
in several rows along the outer edges of each installed to prevent the bars from damaging the
car. Once the first car is loaded, the cable would cable. The extensions to the floor on each side of
be extended to the adjoining car – a distance of the car at both ends could also be made of steel
almost a metre (3 ft 2 ½ in) – and then with the bars and covered with plywood or some other
same procedure the second car would be loaded material. Steel bars would be far less expensive
and all other succeeding cars. The connecting than the use of solid steel plates.
cable between the cars should be enclosed in
a specially designed and correctly curved rigid The adaptation would have to be made to 30 cars
protective case. This would protect the cable for a 50 km length of cable. It should be possible
from vibration and possible damage. This to haul two lengths of cable per trip so the
section of cable would still be subjected to slight adaptation would have to be made to 60 cars.
bends as the train navigates curves, but because
Proposal 4
Transporting DC cable with extruded insulation
on widened flatcars in a figure 8 pattern
by John Ryan, Consultant
This is a further concept on how long sections cross over diagonally to the other end where it
of 500 MW 500 kV DC submarine cable with would form another 180 degree curve but in
extruded insulation (XLPE) may be transported by the opposite direction, thereby eliminating any
train. overall twist to the cable. As such, this would
eliminate the cumulative torsional stress that
As presented in Proposal 1, the cable would be would occur if the cable were coiled on the car.
designated for Lake Winnipeg, and the same
amounts of cable would need to be transported. Since the bending diameter of the cable is 3 m
Also, by way of example, Montreal would be the (9 ft 10 in) and the standard flatcar is 3.05 m (10
arrival port for the cable. ft), to accommodate four rows of 130 mm (5 in)
diameter cable, both ends of the car would have
In this proposal, it should be possible to load a 46 to be extended to a width of 14 feet (4.3 m) by
or 50 km length of cable on a series of flatcars by the addition of 2-foot (0.6 m) extensions on each
loading it in a prescribed manner on individual side of the car. This additional width at each end
cars. Once the first car is loaded, the cable would of the car should extend along the length of the
be extended to the adjoining car – a distance of car for 14 feet (4.3 m). Hence the car would have
almost a metre (3 ft 2 ½ in) – and then with the a type of hour-glass configuration, as shown in
same procedure the second car would be loaded the diagram.
and all other succeeding cars. The connecting cable
between the cars should be enclosed in a specially The main restricting feature and drawback of this
designed and correctly curved rigid protective case. proposal is the limitation on the height of cable
This would protect the cable from vibration and where it criss-crosses at the midpoint of the car.
possible damage. This section of cable would still In crossing diagonally from one corner of the
be subjected to slight bends as the train navigates car to the other the cables cross each other at
curves, but because these would not involve sharp the midpoint section. The height restriction on
bends this may not be detrimental to the cable. trains from Montreal to Winnipeg is 6.1 m (20 ft).
Nevertheless, this procedure should be tested to Since the flatcar has a height of 1.2 m (4 ft), this
ensure that no damage could occur to these short leaves 4.9 m (16 ft) for the cable. With the cable
sections between the cars. being 130 mm (5 in) in diameter, this would
theoretically allow for 38 layers of cable. However
The cable would not be coiled within the some type of material, perhaps about a ¼ of an
individual cars – instead it would be laid in a inch thick would have to be inserted between
type of figure eight configuration, as shown in the cables to prevent rubbing damage and to
the accompanying diagram. After forming a 180 alleviate the weight from the upper layers on the
degree curve at one end of the car the cable would lower layers of cable. Considering this, plus a
Grand Coulee
J-Power Systems 1977 20.0/3 Tunnel SCFF
Dam; USA
Tsuruga P/S;
J-Power Systems 1985 0.7/3 SCFF-PPL 2500
Japan
Imaichi P/S;
J-Power Systems 1987 0.615 XLPE 1400
Japan
Shimogo P/S;
J-Power Systems 1988 0.19 XLPE 800
Japan
Shimogo P/S;
J-Power Systems 1990 0.381 XLPE 800
Japan
Shiobara P/S;
Viscas 1992 0.46 XLPE 1400
Japan
Okukiyotsu 2nd
J-Power Systems 1995 2 x 0.280 XLPE 800
P/S; Japan
Okumino P/S;
J-Power Systems 1996 1.4 XLPE 800
Japan
Okumino P/S;
J-Power Systems 1996 2.4 XLPE 800
Japan
Matsuura P/S;
J-Power Systems 1996 1.246 XLPE 1200
Japan
1996,
Viscas; J-Power Shinkeiyo- XLPE 27
1997, 2 x 40.0 69 Tunnel 1200 2500
Systems Toyuso; Japan km
2000
1996,
Viscas; J-Power Shinkeiyo- XLPE 27
1997, 2 x 40.0 69 Tunnel 1200 2500
Systems Toyuso; Japan km
2000
Okutataragi P/S;
J-Power Systems 1997 1.459 Tunnel XLPE 800
Japan
Kashiwazaki P/S;
J-Power Systems 1997 4.6/3 SCFF-PPL 2500
Japan
Okutataragi P/S;
J-Power Systems 1997 4.4/3 XLPE 800
Japan
Kazunogawa P/S;
Viscas 1997 2.2 XLPE 1000
Japan
Tianhuangping
J-Power Systems 1997 3 x 0.697 XLPE 800
P/S; China
Tachibanawan
J-Power Systems 1998 2 x 1.614 XLPE 1000
P/S; Japan
Tachibanawan
J-Power Systems 1998 4.8/3 XLPE 1000
P/S; Japan
Anan Converter
J-Power Systems 1998 0.219 XLPE 1200
Station; Japan
Anan Converter
J-Power Systems 1998 0.272 XLPE 800
Station; Japan
Anan Converter
J-Power Systems 1998 0.289 XLPE 800
Station; Japan
Anan Converter
J-Power Systems 1998 0.202 XLPE 1200
Station; Japan
Kihioku S/S;
Viscas 1998 6 x 0.600 XLPE 800
Japan
Tachibanawan
J-Power Systems 1999 1.015 XLPE 800
P/S; Japan
Tachibanawan
J-Power Systems 1999 1.023 XLPE 1000
P/S; Japan
Echizen P/S;
Viscas 1999 1.2 XLPE 1400
Japan
Kihioku S/S;
Viscas 1999 2 x 0.360 XLPE 1500/800
Japan
Hitachi-Naka P/S;
J-Power Systems 2001 0.547 XLPE 2500
Japan
Dachaoshan HPP;
Suedkabel/ABB 2002 0.77 No XLPE 800
Yunnan, China
Kannagawa S/S;
Viscas 2003 1 x 1.750 XLPE 1000
Japan
Zheijang P/S;
Viscas 2003 1 x 0.814 XLPE 800
China
Bureskaya HPP:
Suedkabel 2005 0.8 No Tunnel ? XLPE 800
Russia
Omarugawa P/S;
Viscas 2005 1 x 1.480 XLPE 800
Japan
Sanbanxi P/S;
J-Power Systems 2005 0.477 XLPE 1200
China
Yunan Huaneng
Viscas Xiaowan P/S; 2007 1 x 2.050 XLPE 1000
China
Henan
Viscas 2007 1 x 1.050 XLPE 800
Heimifeng; China
Boaquan P/S;
J-Power Systems 2007 2 x 0.734 XLPE 800
China
Huizhou P/S;
J-Power Systems 2007 2 x 0.500 XLPE 800
China
Bailianhe P/S;
J-Power Systems 2007 2 x 0.372 XLPE 800
China
Omarugawa P/S;
J-Power Systems 2007 1.328 XLPE 800
Japan
Xilongchi P/S;
Viscas 2008 0.850/3 Tunnel XLPE 800
China
Kashiwazaky
Viscas 2008 1 x 0.550 XLPE 2500
Kariwa; Japan
Yunan Huaneng
Viscas Xiaowan P/S; 2008 1 x 2.478 XLPE 1000
China
Huizhou P/S;
J-Power Systems 2008 4 x 0.627 XLPE 800
China
0.810 +
Nexans France Ochakova; Russia 2009 0.720; 1.820 DB 660 XLPE 2500; 800
800 sq mm
Kashiwazaky
Viscas 2009 1 x 0.640 XLPE 2500
Kariwa; Japan
Shimane P/S;
Viscas 2009 1 x 1.504 XLPE 2000
Japan
Luoyang P/S;
Viscas 2009 1 x 0.493 XLPE 800
China
Kashiwazaky 1 x 1.720 + 1
Viscas 2009 XLPE 800
Kariwa; Japan x 1.577
Liaoning Pushihe;
Viscas 2009 1 x 1.066 XLPE 2500
China
Kashiwazaki P/S;
J-Power Systems 2009 2 x 0.834 XLPE 2500
Japan
Shibo - Sanlin;
Nexans France 2010 17 Tunnel 1560 XLPE 2500
Shanghai; China
Porce 3 P/S;
Suedkabel 2010 2 x 0.7 No Tunnel 600 XLPE 800
Colombia
Shibo - Sanlin;
Viscas 2010 17 Tunnel 1560 XLPE 2500
Shanghai; China
Kashiwazaki P/S;
J-Power Systems 2010 2 x 0.520 XLPE 2500
Japan
Beskudniko:
Nexans France ? 3 x 0.2 No ? 2000 XLPE 2500
Russia
Cct.
Installation Capacity Insul. Conductor
Supplier Location Year I/S Length Joints
Type (MW) Type (mm2)
(km)
Grand Coulee
BICC 1973 20.0/3 Tunnel SCFF
Dam; USA
1990
Honshu-Shikoku; Bridge and
J-Power Systems and 22.0 SCFF–PPL 2500
Japan DB
1994
Grand Coulee
J-Power Systems 1977 20.0/3 Tunnel SCFF
Dam; USA
The highest voltage XLPE submarine cables are the Gossen Island 420 kV cables installed for the Ormen
Lange offshore gas production project.
The next highest will be a new 345 kV submarine cable crossing between New Jersey and Brooklyn, to be
in-service in 2011.
Cct.
Year Installation Capacity Insul. Conductor
Supplier Location Length Joints
I/S Type (MW) Type (mm2)
(km)
Mainland BC to
2 x (30.0 Submarine; SCFF
Nexans/Prysmian Vancouver Island; 1984 1200/cct 1600
+ 8.0) 400 m deep -kraft
Canada
None exist. The highest voltage system for a completely underground DC application using XLPE cables is
+/- 150 kV (MurrayLink).
St. Lawrence
River crossing, SCFF- Lead
Sumitomo/JPS 1991 5.1 Tunnel
Quebec; kraft alloy
Canada
None exist for a completely underground application, but there are underground sections associated with
the 500 kVdc ‘Neptune’ submarine cable project from New Jersey to Long Island (36 cable reels, weighing
up to 54.4 kg, 4 m diameter). The underground length is 22 km. There are also underground sections
associated with the 500 kV DC Italy-Sardinia project, with 15 km on land.
None exist. The highest voltage system presently in service is 150 kV dc.
In 2010 Prysmian will commission a new 200 kV dc system in the San Francisco Bay area.
In 2010 J-Power systems will commission a new 250 kV dc XLPE cable system between Honshu and
Hokkaido in Japan, which will be designed for LCC converters.
Cct.
Installation Capacity Cable
Supplier Location Year I/S Length Joints Sheath
Type (MW) type
(km)
4 x 50
Honshu- Submarine, 1400 initial SCFF- Lead
Viscas/JPS 2000 km
Shikoku; Japan 75m deep 2800 final PPL alloy
cables
Cct.
Installation Capacity Cable
Supplier Location Year I/S Length Joints Sheath
Type (MW) type
(km)
2 x 390
Italy-Sardinia; 2009, Submarine, Lead
Prysmian km 2 x 500 MI
Italy 2010 1600 m deep alloy
cables
New Jersey – NY
Submarine, 75
Prysmian (Long Island); 2009 82 600 MW MI
m deep
USA
Sweden-Denmark (Konti-
1965 285 300 64 80 MI
Skan 1)
Norway-Denmark
1976 263 250 2 x 125 600 MI
(Skagerrak 1,2)
England-France (Cross-
1986 270 250 8 x 50 55 MI
Channel 2)
Sweden-Denmark (Konti-
1988 285 300 2 x 64 80 MI
Skan 2,3)
Finland-Sweden (Fenno-
1989 400 500 200 117 MI
Skan)
Norway-Denmark
1993 350 500 125 500 MI
(Skagerrak 3)
Sweden-Germany (Baltic
1994 450 600 250 60 MI
Cable)
Norway-Netherlands
2007 450 700 1 x 580 410 MI
(NorNed)
DC Instead of AC Cables
Effect of Capacitance
Cable insulation has a capacitance, C, given by
Calculation of DC insulation stress is far more the following equation:
complex than for AC cables, as reflected in the
following equations.
Where:
C = Insulation capacitance (μFarads/km)
e = Insulation permittivity
Where:
Ic = Insulation charging current (A/km)
Xc = Capacitive reactance (μOhms/km)
f = Frequency (Hz)
AC Cables DC Cables
The proximity of the underground cable or This bottleneck has always caused concern due to
above ground cable to existing transmission the concentration of assets in this location. Some
lines needs to be reviewed. To go overhead, the solutions suggested in the past have included the
potential from a storm knocking out the major creation of islands in Cedar Lake for transmission
transmission of power to the South has to be towers to be placed on.
factored. An option is to bury the cable, leaving
little chance of a storm to damage it; however, While the bottleneck section is quite congested,
terrorism or electrical interference may cause there is opportunity for routing further HVAC or
issues. DC transmission through the area. There is a risk
associated with this due to the concentration of
The use of the Grand Rapids corridor is not transmission in the area and events damaging
free of significant issues as it relates to the numerous lines simultaneously, storm, terrorism,
performance of a transmission link to southern etc. Underground cables may provide a greater
load centers from northern generation. level of protection as the cable is not subjected
to problems associated with transmission towers.
Further studies would be required to determine
Background the effects of locating new HVAC and DC cables
so close.
Grand Rapids is an area approximately 400 km
north of Winnipeg, Manitoba where Cedar Lake
Transmission Lines
Roads
Highway PTH #6
Overview
Grand Rapids lies on the Saskatchewan River, Winnipeg (downstream of Grand Rapids). Two
approximately 400 kilometres north of Winnipeg, communities live in the area immediately below
Manitoba, Canada. The rapids have been the dam site; the community of Grand Rapids on
replaced by an excavated channel and dam for the west side of the river, and the Grand Rapids
the production of electricity. The old riverbed First Nation on the east. The following aerial
contains the spillway structure. The dam is photograph shows the communities along either
located at a narrow strip of land between Cedar side of the river below the dam site.
Lake (upstream of Grand Rapids) and Lake
North
Grand Rapids Topography and Geology Figure A7-5: Trench at Grand Rapids
Conclusion
Explanatory Notes:
Although the cable manufacturer(s) will be This remaining length of cable would be laid at
producing cable continuously during the shipping the beginning of the next summer.
season, this might not be enough to meet the
demands of a regular shipping schedule, so it During the first summer, because of having to
is assumed that an adequate amount of cable wait for the arrival of cable, the train would
would have been produced and stored during the remain idle for 6 weeks and the barge would be
preceding period to provide sufficient cable for idle for 8 weeks.
the entirety of the shipping season, and not cause
any delays due to shortage of cable. According to this schedule, during the first
summer, the first cable line consisting of four
It is assumed that a vessel such as North Ocean 45-km segments would be laid and three
103, fitted with a turntable, would be used to segments of the second line – the remaining
transport the cable. It travels at 16 knot and could fourth segment would be stored on a spare
cover the approximate 6000 km from Europe to turntable and would be laid at the beginning
Montreal in about nine days, which should leave of the second summer.
sufficient time in the two-week slot to transfer the
cable from the ship to a turntable on the dock.
Explanatory Notes:
Combined Bipole I
Bipole I Bipole II
+ Bipole II
Year
No. of Forced Duration of Forced No. of Forced Duration of Forced Average No. of forced
Outages/900km Outages (hrs) Outages/1000km Outages (hrs) outages/100 km/year
Average
1996-2008 0.0909 10.6818 0.9091 16.6091
/900km
Average
1996-2008 0.0101 0.1010
/100km/year
Average
1996-2008
0.0556
/100km year
for both Bipoles
* Based on CIGRE1996-2010 papers on ‘A Survey of the Reliability of HVDC Systems Throughout the World’.
** 19 towers damaged by downburst