Uhmm - Post - bipoleIII - Concepts - Review - COMPARATIVO DE COSTES

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 168

Potential Use of Submarine or

Underground Cables for


Long Distance Electricity
Transmission in Manitoba

A Post Bipole III


Concepts Review

Report of the
Concepts Review Panel
March 17, 2011

(Revised April 4th, 2011)


Potential Use of Submarine or
Underground Cables for
Long Distance Electricity
Transmission in Manitoba

A Post Bipole III


Concepts Review

Report of the
Concepts Review Panel
David Farlinger, P.Eng., F.E.I.C.
(Principal, CMC Consultants Inc.) – Panel Chair

Allen MacPhail, P. Eng.


(Principal Engineer, Cabletricity Connections Ltd.)

John Ryan, Ph.D.


(Retired Professor of Geography and Senior Scholar
at the University of Winnipeg)

Ed Tymofichuk, P. Eng.
(Vice President Transmission, Manitoba Hydro)

Paul Wilson, P. Eng.


(Managing Director, Subsidiary Operations,
Manitoba Hydro International Ltd.)

Report of the Concepts Review Panel - 1


Revisions
Rev Description Date

1 Finding 12 amended, pages 16 and 103 April 4, 2011


Finding 15 amended, pages 17 and 104

2 - Manitoba Hydro
Third Party Disclaimer

The content of this document is not intended for the use of, nor is it
intended to be relied upon by any person, firm or corporation, other
than Manitoba Hydro.

This document is restricted to the use of Manitoba Hydro. The written


authorization of Manitoba Hydro must be sought regarding any use
of this document.

Manitoba Hydro denies any liability whatsoever to any parties for


damages or injury suffered by such third party arising from the use
of this document by the third party, without the express prior written
authority of Manitoba Hydro.

Copyright © 2011, Manitoba Hydro

Report of the Concepts Review Panel - 3


4 - Manitoba Hydro
Acknowledgements
As Chair of the Concepts Review Panel I want to thank and acknowledge the
Panel members’ professionalism, expertise, and diligence in the challenging
work that culminated in this report. Specifically, I would like to thank John
Ryan Ph.D., who through his research and publications put the idea of an
underwater cable on the public agenda and who developed several concepts
for transporting long lengths of cable by train, Allen MacPhail P. Eng., an
internationally recognized expert in high voltage power cable applications,
for his contribution to many areas of the report, as well as Paul Wilson
P. Eng., Managing Director of Manitoba Hydro International Ltd. and Ed
Tymofichuk P. Eng.,Vice President Transmission of Manitoba Hydro who
both brought their extensive experience and expertise in High Voltage Power
Transmission to the Panel and the writing of the report.

I would also like to thank Shane Dew P. Eng. of Manitoba Hydro for his
administrative support and untiring efforts in his role as Administrative
Assistant to the Panel. As well, I wish to extend my thanks to technical staff
of Manitoba Hydro and Manitoba Hydro International for their support
throughout this review, specifically to Jason West for his skillful portrayal
of models illustrating the train transport of submarine cable in long
lengths, to Sarah Wach for drafting the AC and DC route maps for the
report and to Dean Reske for compiling estimates of the cost of various
electrical installations.

David Farlinger P.Eng., F.E.I.C.


Panel Chair

Report of the Concepts Review Panel - 5


Table of Contents
Third Party Disclaimer . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .3
Acknowledgements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
Executive Summary. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .9
Findings and Conclusions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
Foreword . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19
Glossary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21
1 Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23
2 Transmission Line and Cable Routes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27
2.1 Route 1 AC or DC – Overhead across Cedar Lake . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27
2.2 Route 2 AC or DC Underground through Grand Rapids West . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 28
2.3 Route 3 AC or DC Underground East . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29
2.4 Route 4 DC – Submarine and through Eastern Interlake. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30
2.5 Route 5 DC – Two Segments of Submarine Exiting at Traverse Bay . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31
2.6 Route 6 AC – Two Segments of Submarine Exiting at Traverse Bay . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 32
2.7 Grand Rapids Congestion Issues . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 36

3 Cable System Performance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 37


3.1 Description of Cable Types for Underground Transmission . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 37
3.1.1 Laminar, or Lapped Dielectric . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 37
3.1.2 Extruded Dielectric. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 39
3.2 Description of Cable Types for Submarine Transmission. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 41
3.2.1 Maturity of State-of-Engineering of 500 kV Cable Technologies in Use World-wide Today. . 41
3.2.2 Maturity of 500 kV AC Underground Cable Systems. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 43
3.2.3 Maturity of 500 kV AC Submarine Cable Systems . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 43
3.2.4 Maturity of 500 kV DC Submarine Cable Systems. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 44
3.2.5 Maturity of 500 kV DC Underground Cables. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 44
3.2.6 Conclusions about Maturity of 500 kV Underground and Submarine Cable Systems. . . . . . 45
3.3 Performance of AC and DC Cables Operating at 500 kV. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 46
3.3.1 Conditions Imposed by the Natural Environment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 46
3.3.2 AC Transmission Capacity. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 47
3.3.3 DC Transmission Capacity . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 49
3.3.4 Cable System Reliability. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 52
3.3.5 Life Expectancy of Cable Systems. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 59
3.3.6 Operation and Maintenance Requirements for Cable Systems . . . . . . . . . . . . . . . . . . . . . . . . 59
3.4 Literature Review of Current Research for Further Technological Development of 500 kV Cables . . . . . 59
3.5 System Impacts Considering Long Cables . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 60
3.6 Thermal Properties and Ampacity of Cables . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 62
3.7 Compensation of Long AC Cables. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 62

4 Submarine Cable Transportation by Water and Land . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 65


4.1 Transporting long lengths of 500 kV AC or DC submarine cable by ship. . . . . . . . . . . . . . . . . . . . . . . . . . 65
4.2 Transporting long lengths of submarine cable via rail . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 66
4.3 Transportation of short lengths of submarine or underground cable . . . . . . . . . . . . . . . . . . . . . . . . . . . . 69

5 Cable Installation. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 73
5.1 Submarine Cable Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 73

6 - Manitoba Hydro
5.1.1 Cable Laying Barge . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 73
5.1.2 Submarine Cable Trenching . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 74
5.1.3 Cable Jointing Operation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 77
5.1.4 Cable Laying Procedure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 79
5.1.5 Cable Laying Schedule . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 80
5.2 Underground Cable System Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 81
5.2.1 Civil Work. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 81
5.2.2 Cable Transportation. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 82
5.2.3 Cable Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 83
5.2.4 Cable Jointing and Terminating . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 84

6 Transition and Compensation Stations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 85


6.1 Transition Stations – 500 kV AC. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 85
6.2 Transition Stations – 500 kV DC . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 86
6.3 Compensation Stations – 500 kV AC. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 87
6.4 Shore Landing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 88
6.5 Ice Scouring . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 88

7 Cost Comparisons . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 91
7.1 Interpretation of Estimate Results . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 94

8 Regulatory Issues. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 95
8.1 Licencing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 95
8.2 Regulatory Issues with Lake Winnipeg Routing. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 95

9 Project Risks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 97
9.1 Design Risks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 97
9.2 System Operation Risks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 99
10 Benefits and advantages of underground and submarine cable installations. 101
11 Findings and Conclusions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 103
12 References. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 105

Appendix 1: Terms of Reference. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 109


Appendix 2: Panel Members . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 111
Appendix 3: Long AC Cable Compensation. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 117
Appendix 4: Cable Transportation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 127
Proposal 1 Transporting long sections of submarine cable by train. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 127
Proposal 2 Transporting Long Lengths of Submarine Cable by Train . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 134
Proposal 3 Transporting long sections of DC submarine cable with extruded insulation by train,
coiled on widened flatcars . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 136

Proposal 4 Transporting DC cable with extruded insulation on widened flatcars in a figure 8 pattern. . . . . 139
Appendix 5: 500 kV Global Cable System Applications. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 143
Appendix 6: Differences Between AC and DC Cable Technologies . . . . . . . . . . . . . . . . . . . . 151
Appendix 7: Grand Rapids Bottleneck . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .155
Appendix 8: Cable Laying Schedule . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 161
Appendix 9: Bipole I and Bipole II Reliability, 1993 - 2008. . . . . . . . . . . . . . . . . . . . . . . . . . . . . .163

Report of the Concepts Review Panel - 7


8 - Manitoba Hydro
Executive Summary
In September 2009, Manitoba Hydro appointed a Concepts Review Panel
to investigate the potential future use of submarine or underground cables
for long distance hydro-electric transmission. This report reviews 500kV AC
and DC submarine and underground concepts for a potential transmission
line extending from the lower Nelson River to the Winnipeg vicinity with no
certainty regarding timing, except it could be a number of years beyond BPIII.

For purposes of this Panel’s review, and for completeness, it was assumed that
this fourth major transmission line from northern generation to southern load
centres could be either DC or AC.

To conceptually examine the use of cables in a post-Bipole III link, six


illustrative routes were developed. One route is an all overhead line and
serves as the base reference case while the five others each employ a segment
or segments of submarine or underground cable along with overhead lines,
and are referred to as hybrid lines. Significant additional engineering research
and study would be required to confirm the merits and validity of one or
more of the conceptual routes employing cables, or to determine possibly
superior routes. Details of the routes studied in this report are described in
the following Tables 1 and 2, and are shown on Maps 1 and 2 accompanying
the report, as well as Figures 1 through 6.

Report of the Concepts Review Panel - 9


Table 1: Cable Route Option Length and Number

OH Route Total UG Submarine Submarine Total Submarine


Route UG Route UG Cable
Mode Length Cable Route Cable Cable Length
Option Length (km) Numbers
(km) Length (km) Length (km) Numbers (km)

1 AC OH 1273 0 0

1 DC OH 1273 0 0

OH-UG
2 AC 1025 175 4 700
Hybrid
OH-UG
2 DC 1025 175 3 525
Hybrid
OH-UG
3 AC 830 263 4 1052
Hybrid
OH-UG
3 DC 830 263 3 789
Hybrid
OH-Sub
4 DC 812 178 3 534
Hybrid
OH-Sub
5 DC 704 287 3 861
Hybrid
OH-Sub
6 AC 703 240 4 960
Hybrid

10 - Manitoba Hydro
Table 2: Transmission Line Route Details

Route Advantages Disadvantages

1 This would be an AC or DC overhead line with no Requires two long overhead spans between islands and mainland
underground or submarine cable and no cable- of about one km in Cedar Lake.
AC or DC related reactive compensation equipment and
thus inherently more reliable. Location of “island hops” less than 20 km from Bipole I-II at Grand
Rapids.
A 500 kV AC transmission interconnection
between northern generation and the southern Permission is required for overhead line to cross about 20 km of
system would strengthen the AC system in the “protected area” park along the east shore of Lake Winnipegosis.
south.

2 After connecting to the Grand Rapids Permission is required for overhead line to cross about 20 km of
underground cable, the overhead line would be at “protected area” park along the east shore of Lake Winnipegosis.
AC or DC least 50 km away from Bipole I-II all the way to the
Winnipeg area. 500 kV AC cable systems of this length have never been installed
anywhere in the world. The impacts on the transmission system
No novel transport methods required. are not known and need more study.

A 500 kV AC transmission interconnection Cable-related reactive compensation equipment needed for AC


between northern generation and the southern alternative.
system would strengthen the AC system in the
south. A tunnel would be required at Grand Rapids.

3 No novel transport methods required. The overhead line would be less than 30 km from Bipole I-II as it
goes around the Peguis Reserve.
AC or DC
500 kV AC cable systems of this length have never been installed
anywhere in the world. The impacts on the transmission system
are not known and need more study.

Cable-related reactive compensation equipment needed for AC


alternative.

4 There would be adequate lake sediment for the To get to the Warren Landing site, the OH line from the Nelson
entire length of the submarine cable, thus no River Generating Area would have to cross the Nelson River with
DC mechanical barrier protection required for the a long span of about 1 km.
submarine cable (no rock cutting, rock dumping,
or protective mattresses). The OH line would be less than 30 km from Bipole I-II as it goes
around the Peguis Reserve east of Lake St. Martin.

Dredging of the lake bottom and river at Powerview/Pine Falls


may be required for barge access to rail siding.

Disturbance of lake bottom sediment.

5 There would be adequate lake sediment for the To get to the Warren Landing site, the OH line from Nelson River
entire length of the submarine cable thus no Generating Area would have to cross the Nelson River with a long
DC mechanical barrier protection required for the span of about 1 km.
submarine cable (no rock cutting, rock dumping,
or protective mattresses.) Dredging of the lake bottom and river at Powerview/Pine Falls
may be required for barge access to rail siding.

Disturbance of lake bottom sediment.

Report of the Concepts Review Panel - 11


Table 2 (continued)

Route Advantages Disadvantages

6 A 500 kV AC transmission interconnection There is little sediment along the entire east shore of Lake
between northern generation and the southern Winnipeg, extending in places for about 30 km off shore.
AC system would strengthen the AC system in the Throughout this area the lake bottom has rough rocky terrain.
south. Because of the required short lengths of AC cable, about 200
km of AC cable would have to be laid near the shore on this
unfavourable terrain. Because of the lack of sediment, the
cable would have to be covered by rock dumping or protective
mattresses. Only the 50 km line from Riverton to Traverse Bay
would be covered by sediment.

500 kV AC cables of this length have never been installed


anywhere in the world. The impacts on the transmission system
are not known and require further study.

Cable-related reactive compensation equipment needed.

Disturbance of lake bottom sediment.

Very complex operating a hybrid link with these components.

Performance of AC and DC cables operating at Table 3 illustrates the worst case and best case
500kV in other commercial projects is examined cable service reliability based on known CIGRE
along with cable system reliability and life survey data for all cables except AC and DC
expectancy. With respect to AC or DC submarine submarine cables. The best case uses only
cables, because of lack of data, it is not possible internal failures while the worst case takes into
to accurately determine failure rates. Despite this, account external failure statistics. The Panel
in the case of DC MI cables, it should be expected acknowledges that these worst case failure rates
that they would experience some faults during may be overly pessimistic.
their lifetime. With regard to DC XLPE cables,
there is still no 500 kV cable system in service Table 3: Estimated Cable System Failure Frequency Ranges
(Worst case – Best case)
and the expected date of maturity for
this cable is at least 15 years away, hence at
Failure Frequency Failure Frequency
this stage it has no failure rate. As for AC Route Option
Installation
Range (No Long Trains) Range (Long Trains)
XLPE underground cable, a cable failure may Mode
(years) (years)
be expected approximately every 3 to 11 years
Line 2 AC Land 4.2 – 10.8
depending on route length. For DC XLPE
Line 2 DC Land 6.1 – 16.6
underground cable, a cable failure may be
Line 3 AC Land 2.8 – 7.1
expected approximately every 4 to 17 years
Line 3 DC Land 4.1 – 11.1
depending on route length. However, the
Line 4 DC1 Water ? ?
Panel recognizes that there is a great deal of
Line 5 DC 1
Water ? ?
variability in these results due to the lack of
Line 6 AC1 Water ? ?
quality data. The prime reason for this is
that the electrical power industry has limited
Note 1: A Failure Frequency Range for routes 4, 5 and 6 cannot be
service experience on 500 kV underground or
determined because of lack of data.
submarine cables.

12 - Manitoba Hydro
Maturity of cable types and systems for AC and long lengths of up to 100 km by train (in two
DC submarine and underground transmission approximately 50 km lengths), and off-loaded
were reviewed. ‘Maturity’ of cable systems in 2010 to a barge on Lake Winnipeg or nearby storage
and as forecast for 2025, are summarized in turntables. Four rail transportation concepts
Table 4. were developed. The concept considered by
the Panel to have the best potential for future
Table 4: Cable options and upper voltage limits for ‘mature’ success is described further in this report. The
AC and DC underground or submarine applications in 2010 panel concludes that transportation of long
and 2025 continuous lengths of cable using multiple rail flat
cars would need
Unpressurized Unpressurized Unpressurized
to be carefully
Unpressurized researched
Mass Impregnated Cross-Linked Cross-Linked
Mass Impregnated
Cable Application
MI Polyethylene Polyethylene and studied by
MI
XLPE XLPE railway engineers
and cable
2010 2010 2025 2025 manufacturing
experts. Feasibility
AC Underground Not Applicable 500 kV Not Applicable 600 kV
is not yet proven.
AC Submarine Not Applicable 420 kV Not Applicable 500 kV
Installation of
DC Underground 450 kV 150 kV 600 kV 500 kV
both submarine
DC Submarine 450 kV 150 kV 600 kV 500 kV and underground
cables is discussed
in the report. A comparison of using continuous
It can be assumed that XLPE insulation cables long lengths of cable versus shorter lengths of
will be available for AC and DC underground and cable on reels for submarine applications is also
submarine applications in 2025. MI insulation discussed, in the event that train transportation of
cables will also continue to be available for long cables is shown to be unrealistic.
submarine cable applications in 2025 for
DC. Costs and reliability data in 2025 would Risks and regulatory issues associated with
ultimately determine final submarine cable type use of submarine cables in Lake Winnipeg
selection. are numerous and extensive as they relate to
initial installations, operation, maintenance,
System design impacts resulting from the use transmission line reliability, system reliability and
of long cables are discussed. High voltage reactive to the environment. These include:
compensation devices are necessary to enable • Complex licensing and regulatory issues
maximum transmission of power through long • Loss in system reliability due to a failed
AC cables and to control voltage, which could cable (mitigatable using spare cables and
otherwise exceed equipment and cable ratings special mechanical protection).
under some operating conditions. For DC cable • Costly manufacturer warranties due
systems compensation devices are not necessary. to remote locations and unproven rail
transportation
Transportation concepts were developed, • Lengthy route siting process
whereby cables would be transported by ship • Complex system operations for hybrid
from an overseas manufacturing facility to a overhead-submarine or overhead-
port in Canada, transferred and transported in underground systems

Report of the Concepts Review Panel - 13


• Possible failure of joints and terminations Cable laying seasons for AC submarine cables
when exposed to extremely low ambient could be as long as three summers. For DC
temperatures (-40°C and below) submarine cables, installation may take 1.5 to 2.5
• Cable quality at point of manufacture and summers depending on route. Using cable on
at point of delivery reels instead of long train transportation could
• Possible cable damage due to abnormal double this installation time.
number of multiple transfers and
handling of cables between factory and Manufacturing capacity of two submarine or
installation underground cable suppliers may be required to
• Cable integrity after laying in water in un- meet this schedule.
energized state for several years prior to
commercial use Concept costs are estimated and summarized in
• Possible in-service damage due to lake the following Table 5 extracted from the report.
bottom ice scouring, shoreline erosion Important assumptions are listed beneath the
and other natural hazards table.
• Environmental impacts due to trenching
hundreds of kilometres of lake bottom
• Installation delays due to adverse weather
conditions on Lake Winnipeg
Table 5: Cost Comparisons (labour and material only)

Route Lengths Cost


(km) Cost
Premium
Route Type Description Estimate
Over- Cable above Base
Total (M$)
head System (M$)

1 DC All overhead via Cedar Lake 1,273 0 1,273 635 (DC Base)

O/H with U/G along east side of Lake


2 DC 1,025 175 1,200 1,076 444
Winnipegosis

O/H with U/G along west side of Lake


3 DC 830 263 1,092 1,236 601
Winnipeg

O/H along west side of Lake Winnipeg


4 DC with submarine section (long length 812 178 990 995 360
shipping)

O/H with two submarine sections


5 DC exiting at Traverse Bay (long length 704 287 991 1,319 684
shipping)

1 AC All overhead via Cedar Lake 1,273 0 1,273 809 (AC Base)

O/H with U/G along east side of Lake


2 AC 1,025 175 1,200 1,942 1,133
Winnipegosis

O/H with U/G along west side of Lake


3 AC 830 263 1,092 2,387 1,579
Winnipeg

O/H with two submarine sections


6 AC exiting at Traverse Bay (long length 703 240 993 2,268 1,459
shipping)

14 - Manitoba Hydro
Assumptions and notes:
1. Costs are expressed in 2010 CAD dollars.
2. 500 kV AC overhead line is single circuit capable of
1000 MW.
3. 500 kV DC overhead line is similar to Bipole I-II
construction.
4. DC underground cables are XLPE.
5. DC submarine cables are MI due to maturity
6. AC underground cables are XLPE.
7. AC submarine cables are XLPE.
8. For underground options, cables would be shipped
from Thunder Bay to site by truck (4.0km cable/truck
for DC; 1.8 km cable/truck for AC).
9. For submarine options with no long train shipping,
cables would be shipped from Thunder Bay to
Powerview/Pine Falls by rail (1.8 km cable/car for DC;
1.2 km cable/car for AC).
10. For submarine options with long train shipping,
cables would be shipped from Montreal, Prince
Rupert or Vancouver, a maximum distance of about
2500 km.
11. MH Project Management and Engineering costs not
included.
12. Contingencies not included.
13. Interest during construction not included.
14. Insurance for cable transportation not included.
15. Converter costs for DC alternatives not included.
16. Static VAR compensator for AC alternatives not
included.
17. Cable manufacturing capacity is assumed available.
18. Taxes and import duties not included.
19. Estimates are Class 5, as defined by AACE
International, to be used only for concept screening
purposes with low project definition. Class 5
estimates typically have accuracies in the following
range:
Low: -20% to -50%
High: -30% to +100 %”
20. All estimates contain only labour and material.

Report of the Concepts Review Panel - 15


Findings and Conclusions

1. System studies indicate that with Bipole III 9. A hybrid 500 kV AC line may degrade system
(LCC) in service, the Manitoba Hydro power reliability, as compared to an overhead line.
system would experience network frequency This potential degraded level of reliability
stability problems with an additional LCC may impact the reputation and value of
HVDC transmission link. Therefore it is very Manitoba Hydro’s product.
unlikely that a fourth HVDC (LCC) bipole
10. An underground AC or DC cable system
would be implemented in Manitoba [19].
failure can be expected approximately once
2. The same studies have concluded that every 3 to 17 years. A lack of meaningful
additional north-south 500 kV AC industry data for AC and DC submarine
transmission would be recommended to cables prevents determination of statistical
integrate the next major northern generation failure rates.
plant [19].
11. The repair time for underground cables
3. With current cable technology and unproven is considerably less than for submarine
cable transportation methods, an AC cables. A spare cable for submarine and
submarine cable under Lake Winnipeg is not underground options would minimize forced
a viable option at this time. outage times.

4. Assuming in the foreseeable future that 12. All hybrid options have cost premiums
the Manitoba Hydro system develops to compared to overhead lines. Any of the
accommodate a fourth Bipole of any mode solutions using cables result in incremental
(overhead or hybrid), and together with cost increases of about $0.36B and could be as
further research and technological advances, a high as $1.58B, assuming that long submarine
DC submarine or underground cable may be cables could be successfully transported by
a viable option. train.

5. Future transmission development A reference of cost premiums for submarine


should proceed on the basis of overhead, cabling over an equivalent length of overhead
underground and submarine in that order of line is presented in Section 7, Table 20: Cost
preference. Studies and circumstances at the Premiums for Equivalent Line Lengths.
time would determine the actual choice.
These are represented as ratios:
6. Once all overhead and underground options submarine segment (cost per route km)
have been exhausted, further research on long overhead segment (cost per route km)
length cable transportation by train, related
transportation handling and installation may For Route 4 DC the ratio is 6.6, for 5 DC
be initiated. it is 6.8 and for Route 6 AC it is 11.9. This
means that on an equivalent length basis
7. Based on years of operating experience with the submarine options are 6.6 to 11.9 times
long transmission lines in Manitoba, an costlier than an overhead line.
overhead transmission line should have a
higher reliability than a hybrid line. These estimates and ratios that express the
premiums include labour and material only.
8. A hybrid 500 kV AC line with several cable
sections and associated multiple transition
and compensation stations would be difficult
to operate.

16 - Manitoba Hydro
13. Routing through Grand Rapids would require 21. The life expectancy of an overhead line is
detailed engineering studies. Underground approximately 100 years. Life expectancy
segments, including a tunnel, are required for an underground or submarine cable is
to alleviate issues with congestion and approximately 40 to 50 years. Therefore a
proximity to existing Bipole lines. complete cable system replacement could be
anticipated about half way through the life of
14. With present technology, estimates indicate
overhead line sections.
that short length submarine cables shipped
on reels would take twice as long to splice
22. VSC HVDC technology, if only implemented
and lay compared to long train shipping
as a future fourth HVDC Bipole transmission
methods. Using reels for shipping submarine
line, would not improve the vulnerability to
cable would be more expensive, impractical
common mode faults. Assuming that there
and is not recommended.
are no technological developments or system
15. The least costly hybrid DC or AC route would developments that would remove system
be approximately 1.5 and 2.8 times more constraints to allow a fourth Bipole and given
expensive respectively, than the base case the operating complexities and reliability
overhead route, assuming long train shipping risks of a hybrid AC transmission line, an
is feasible. overhead AC line should be considered first.

16. The base case DC overhead line is the most


23. With a low probability of HVDC being
economic option, despite being longer than
implemented, and the costs, reliability,
other DC conceptual routes. A base case AC
complexity and operating difficulties
overhead line would cost approximately 27%
associated with hybrid AC lines, the preferred
more than the base case DC overhead line.
post-Bipole III option is therefore overhead
17. Installation time of DC submarine cable 500 kV AC.
would range between 2 to 3 years, depending
on route alternative and assuming long train
transportation. For AC submarine cable it
would be about 4 years.

18. The complete manufacturing capacity of two


cable suppliers may be required to meet this
schedule for submarine cables.

19. The world’s ocean going cable laying fleet


does not have access to Lake Winnipeg. A
suitably equipped cable laying barge would
need to be constructed locally and launched.

20. A dock and cable handling facilities would


need to be constructed on a Lake Winnipeg
harbour.

Report of the Concepts Review Panel - 17


18 - Manitoba Hydro
Foreword
This report explores and reviews 500 kV AC In order to better develop, explain and evaluate
and DC submarine and underground cable the various concepts, transmission line routes
application concepts for a possible post-Bipole were defined for comparison purposes. These
III 1000 MW transmission line from the lower routes are by no means final and should be
Nelson River to southern Manitoba. The new link considered as illustrative only. No field work
is not expected to be required before 2025, based was conducted for any of the example routes.
on domestic load growth forecasts. Furthermore, the Panel did not concern itself
with the preliminary preferred routing of
Some of the concepts include application of Bipole III.1
cable technologies at voltage levels higher
than presently commercially available. They The report contents reflect the consensus of
also include untested and unproven methods the panel members. Because of the speculative
of transporting long continuous lengths of nature of future cable technology development,
submarine cables on trains to Lake Winnipeg. uncertainty about future routes and limited
Although some concepts could be considered Terms of Reference to provide engineering detail,
unproven and risky today, there are reasonable the report must be considered as conceptual in
probabilities of development prior to 2025. The nature.
Concept Review Panel’s Terms of Reference did
not include investigating and describing how a
hybrid AC or DC transmission line with overhead
and cable segments would be reliably integrated
into the existing power grid.

Many long submarine cable links in other parts


of the world are primarily for opportunity sales
of electricity (merchant trade) between countries.
But the main purpose of an additional north-
south link in Manitoba would be to serve the
domestic load in a reliable and economical
manner. In addition, most, if not all other long
submarine cable links are in salt water bodies not
subject to freezing. However, Lake Winnipeg’s
surface is frozen during winter, making repairs
impractical for approximately six months of the
year. Therefore, consequences of a submarine
cable failure may not be as critical elsewhere
in the world as in Lake Winnipeg. It is also
significant that there have been no significant
Extra High Voltage submarine cable applications
anywhere in the world, where ocean-going
freighters or cable laying vessels did not have ease
of access.
1
The preliminary preferred routing for Bipole III was
announced on July 29, 2010.

Report of the Concepts Review Panel - 19


20 - Manitoba Hydro
Glossary
AC Alternating electric current that Fault The state of an item
is a periodic function of time. characterized by inability to
perform a required function
Ampacity The maximum value of electric
current which can be carried Fault Level The amount of fault current
continuously by a conductor, a available at a particular location
device or an apparatus, under on an electrical network,
specified conditions without measured in MVA or kA.
its steady-state temperature
exceeding a specified value. Fetch The distance a wind blows
unobstructed over water,
Bipole A common HVDC transmission especially as a factor affecting
configuration where a pair of the build-up of waves.
conductors is used, each at a
high potential with respect to Hybrid line A transmission line that is a
ground, in opposite polarity. combination of overhead and
underground or submarine
Capacitive The coupling between electric sections.
Effect or circuit elements, by which a
Coupling voltage between the terminals Joint A splice or joining of two
of one of them gives rise to underground or submarine
an electric charge in another cables forming a continuous
element current carrying path that
maintains the electrical and
Coil To wind into continuous insulation integrity.
regularly spaced series of rings,
one adjacent to the other where LCC HVDC transmission using
allowed. A coil produces a twist Line Commutated Converters.
in the cable. Changing power flow direction
requires polaritry reversal.
Compensation A special purpose substation
Station to provide reactive power Monopole Is a common HVDC
compensation to high voltage transmission configuration.
underground, submarine, or One of the terminals of the
overhead AC transmission lines. rectifier is connected to earth
ground and the other terminal,
DC A continuous flow of current at a potential high above or
that is not periodic as a function below ground, is connected to
of time. a transmission line. The earthed
terminal may be connected to
EHV Extra High Voltage - the voltage the corresponding connection at
range between 220 kV and 500 the inverting station by means of
kV a second conductor.

Report of the Concepts Review Panel - 21


Reactor Two-terminal device VSC HVDC transmission using
characterized essentially by its Voltage Sourced Converters
inductance. where AC is converted to a
DC voltage, or DC voltage is
Reactive Devices or systems that provide converted to AC. Unlike LCC
Power reactive power in high voltage converters, VSC converters can
Compensation AC networks to control voltage change power flow direction
and optimize the transmission without polarity reversal.
of power.

Reeling To wind cable on to adjacent


spools directly from one
to another. A reel does not
produce any twists in the cable.

Short Circuit The highest electric current


Capacity which can exist in a particular
electrical system under
short circuit conditions. It is
determined by the voltage
and impedance of the supply
system, affected by switching
configurations.

Termination Specially prepared cable end


providing a seal to the external
environment, maintaining
internal cable pressure, if any,
and controlling electrical stress
for the transition between
cable and external insulations
(usually to air in the case of
outdoor terminations).

Transition A substation dedicated to


Station management of the transition
from overhead to underground
or submarine cables.

22 - Manitoba Hydro
1 Introduction
The subject of this report is the use of submarine of the lake. In 2008 Manitoba Hydro began a
or underground power cables as part of a fourth lengthy process of environmental assessments to
major north – south 500 kV transmission line locate a route generally west of Lake Manitoba
in Manitoba. Bipoles I, II, and the planned and Lake Winnipegosis. An ‘Interlake Route’
Bipole III comprise the first three major north- between Lake Winnipegosis and Lake Winnipeg
south transmission links. The fourth, post-Bipole was considered, but weather risk assessment
III line is not expected to be required before studies showed that: “…locating the Bipole III
approximately 2025, based on domestic load transmission line on the East Route or West Route
growth forecasts and system reliability needs. would significantly reduce the likelihood that all
three lines would be exposed to the same extreme
All activities related to the generation, weather conditions, compared to locating Bipole
transmission and distribution of electricity in III on the Interlake Route.” “In summary, the
Manitoba are governed by the Manitoba Hydro Act larger the separation distance between the lines,
and the Manitoba Hydro Electric Board, which the greater the reduction of common event risk.”
oversees the operations of the Manitoba Hydro [2].
Corporation. The Board is appointed by the
Provincial Government. The receipt of a licence for Bipole III is scheduled
and expected in the fall of 2012. Bipole III is
Manitoba Hydro’s mission is “to provide for the scheduled to be in service five years later.
continuance of a supply of energy to meet the
needs of the province and to promote economy Concepts for possibly implementing the post-
and efficiency in the development, generation, Bipole III link using submarine or underground
transmission, distribution, supply and end-use of cable segments are discussed in this report.
energy.” The fourth major transmission link will be to
accommodate the Gillam Island generating
In Manitoba approximately 70% of all power station, a 900 MW development.
generated in the province is transmitted from
the north via two high voltage 500 kV direct In early 2008, retired University of Winnipeg
current (DC) lines. They share a common right- geography professor Dr. John Ryan wrote several
of-way, which is a reliability concern. Each line articles promoting the idea of installing a portion
is approximately 900 km long, from two sites on of the Bipole III line under Lake Winnipeg. He
the Nelson River to the Dorsey converter station generally explored the feasibility of transporting
just northwest of Winnipeg. and installing long sections of submarine cables
in a land-locked lake, inaccessible by specialized
Manitoba Hydro is presently designing a third ocean-going cable laying vessels [12]. Dr. Ryan
DC line (Bipole III) and activities have been proposed a concept of using long trains with
well documented over the past several years specially modified flat cars linked to hold long
[18]. Routing of this transmission line, critical to cable lengths in a continuous looping method.
Manitoba’s electricity reliability and security, has The cable would arrive by ship from a factory at
been controversial. Although initially there was a port such as Thunder Bay, Montreal, Vancouver
preference to route the line east of Lake Winnipeg or Prince Rupert and be transferred to a special
for economical, technical, and reliability reasons, unit train, transported to the Lake Winnipeg
the Provincial Government’s decision to protect area, off-loaded onto a specially built barge
this boreal forest region, precluded a route east equipped for cable laying, and subsequently

Report of the Concepts Review Panel - 23


installed on the lake bottom. The complete Where wide water bodies separate regions by more
process would need to be validated by submarine than 50 to 75 km, AC transmission at the 400
cable manufacturing and installation experts, as to 500 kV level is usually not feasible. However,
well as professional railway engineers. The risks DC submarine cable systems provide practical
associated with transportation, multiple handling alternatives. The highest operating voltage
and laying of cables, as well as future reliability, submarine DC cables in Canada are the +/-300
maintenance and repairing of the cables in the kV Vancouver Island cables, commissioned in
middle of Lake Winnipeg are identified in this 1969 and 1975 (total cable length = 5 x 32 km).
report. The highest operating voltage DC underground
cables in Canada are the +/- 450 kV cables in
Besides technical problems, risks and costs the Radisson-Nicollet tunnel link under the St.
associated with unproven submarine cable Lawrence River in Quebec, commissioned in 1992
transportation systems, there are additional (total cable length = 6 x 5.1 km). The highest
complexities because some possible route voltage DC submarine cable in North America is
alternatives could make partial use of the 500 kV Neptune link between New Jersey and
underground cables instead of submarine cables. Long Island, New York, commissioned in 2007
They would avoid difficulties associated with (total cable length = 1 x 105  km).
overhead lines and geographical restrictions, for
example through the congested Grand Rapids The Manitoba Hydro system presently has one of
area. the highest penetrations of high voltage DC into
a local AC network in the world. With the future
Historically, Manitoba Hydro and other utilities development of Keeyask and Conawapa, the three
around the world have built high voltage bipole system could be loaded up to 5500 MW.
transmission lines overhead, provided land for Because of the tight electrical coupling between
rights-of-way was available. Such designs, using the HVdc converters, a fault in the northern AC
AC or DC transmission, are the most economical collection system, or in the southern Manitoba
method of transporting bulk electric power AC network, can cause the temporary loss of all
over long distances and have a proven record of the DC power for the duration of the fault. This
acceptable reliability at minimum cost. Today temporary loss of power causes the frequency
the highest voltage overhead line in the world is of the southern system to decay rapidly during
in China. It operates at +/-800 kV DC and was the fault due to the low inertia in the southern
commissioned in June 2010. There are many Manitoba network. Inertia is normally provided
765 kV AC overhead lines operating in the world by nearby synchronous generators but in the
including in Quebec and the United States. case of Manitoba it is also provided by local
synchronous condensers. The susceptibility of the
In congested urban areas where AC systems HVdc bipoles to interruption in power delivery
dominate and overhead systems are impractical, due to an AC fault places a limit on the HVdc
transmission lines have been placed penetration level in southern Mantioba. Studies
underground. For water crossings beyond the have demonstrated that the addition of Bipole III,
reach of overhead lines, AC submarine cables loaded with Keeyask and Conawapa generation,
are used. 500 kV AC submarine cable systems increases the DC to that penetration limit. As
spanning distances of approximately 30 km a result, there appears to be many reliability
and using pressurized insulations, have been in advantages if a post Bipole III north-south link
service for over 25 years. was developed at 500 kV AC, rather than DC [19].

24 - Manitoba Hydro
With these technical, political and economic • Identify the concept with the highest
issues in focus, Manitoba Hydro appointed a feasibility for long-length transportation
Concepts Review Panel, to examine the potential and installation that may need to be
use of 500 kV submarine and underground cables advanced for further research and
for long distances in Manitoba. The detailed investigation by world experts.
Terms of Reference of the Panel (i.e. Purpose of
the Panel and Items of Concern) are contained in • Address cost implications of any concepts
Appendix 1 and summarized below. that may have merit.

• Discuss feasibility of underground and Membership of the Panel is described in


underwater 500 kV cables for possible use Appendix 2.
in a future North-South Transmission line
in Manitoba, post Bipole III. In order to achieve the Panel’s mandate, members
collectively and conceptually investigated cable
• Review maturity of the state-of-engineering transportation methods by rail and road, possible
of 500 kV cable technologies in use world- cable system types and implications of applying
wide today. them to illustrative transmission routes for
comparison purposes. The concepts review and
• Research performance of cables operating report is not about routing or route selection
at 500 kV. as the routes depicted in this report are for
illustrative purposes only. Example routes were
• Research the causes of failure of 500kV comprised of an overhead line, and several hybrid
cable systems world-wide. lines with segments of overhead and submarine
or underground cables.
• Review the literature on current cable
research for 500 kV cables and the effects With these example routes established, scenarios
of very long cable lengths on the power could be conceptually engineered, characterized
system. and ranked in terms of cost and performance.
Cable system performance issues were explored to
• Discuss concepts for transporting very determine their present maturity and anticipated
long sections of cable on land and over failure rates when applied to the example route
landlocked inland waterways. scenarios in 2025.

A detailed discussion of example transmission


routes is provided in Section 2.

Report of the Concepts Review Panel - 25


26 - Manitoba Hydro
2 Transmission Line and Cable Routes
The Panel examined a number of example route 2.1 Route 1 AC or DC – Overhead across
options for the next transmission line from the Cedar Lake
Nelson River generating station area to southern
Manitoba, following commissioning of Bipole This route, which begins at Gillam Island on the
III. The northern terminus was assumed to Nelson River, passes through several Provincial
be Gillam Island and the southern terminus and Aboriginal Resource Management areas, and
assumed to be Riel Substation, for illustrative along the western edge of the Grand Rapids area.
purposes only, to provide a basis for line length The route would then extend along the eastern
calculations. It was assumed that the fourth side of Lake Winnipegosis and then on to the
Nelson River line would have a capacity of 1000 Winnipeg area. The total length of the route
MW and for completeness, options were studied would be 1273 km. The closest distance between
for AC and DC, notwithstanding that a stronger it and the Bipole I-II corridor is about 17 to 25
AC network is desirable at the receiving end to km but the total extent of this section is only
improve system stability. about 100 km or 10% of the line length.

In addition to an entirely overhead route option


for either AC or DC, two of the conceptual
routes contain underground cable segments for
AC or DC and three routes contain submarine Churchill Hudson
cable segments (two for DC and one for AC). Bay
Extensive engineering studies will be required to MANITOBA
confirm the ultimate merits and validity of any Gillam
Island
route and concept, with the distinct possibility
that variations may ultimately be shown to be
superior. Gillam

Thompson
Detailed maps of both the AC and DC route
options are provided at the end of this report
(Map 1: DC concept routes and Map 2: Flin Flon
AC concept routes).

The Pas
Grand Rapids

Selkirk
Winnipeg Figure 1:
Route 1 AC or DC
Brandon
Overhead across
Cedar Lake

Report of the Concepts Review Panel - 27


2.2 Route 2 AC or DC Underground
through Grand Rapids West

This route is a hybrid overhead–underground


cable–overhead line. It begins generally at Gillam
Island and extends overhead to the north of Lake
Winnipeg, where it transitions to an underground
cable that would follow the Bipole I-II corridor
Churchill Hudson
Bay
through the Grand Rapids area, then veers to the MANITOBA
eastern edge of Lake Winnipegosis. From there Gillam
it would transition back to an overhead line and Island

proceed to the Winnipeg area. The main purpose


for using cables for this route is to avoid common
Gillam
mode failure of the new line and existing Bipole
I-II lines due to extreme weather events. The Thompson
closest distance between the new and existing
overhead lines is about 50 km. It is assumed
that a tunnel would be used to carry cables Flin Flon

under the Saskatchewan River at Grand Rapids


tailrace and spillway. The total length of the The Pas
route would be 1200 km with one underground Grand Rapids
segment of 175 km. Tunnel length is assumed
to be about 0.6 km. The AC solution would
have reactive compensation equipment at each
overhead/underground transition station and at
two intermediate stations in the underground
segment. A spare cable would be provided to
improve reliability in case of a cable failure.
Selkirk
Winnipeg Figure 2:
Route 2 AC or DC
Brandon Underground through
Grand Rapids West

28 - Manitoba Hydro
2.3 Route 3 AC or DC Underground East

This route is a hybrid overhead–underground


cable–overhead line, beginning at Gillam Island
and then proceeding overhead to the north of
Lake Winnipeg where it would connect to an Churchill Hudson
underground cable. The cable would follow Bay
along the Bipole I-II corridor through the MANITOBA
Grand Rapids area then veer to the western Gillam
Island
edge of Lake Winnipeg. From there it would
transition back to an overhead line and extend
to the Winnipeg area. The total length of the
Gillam
line would be 1093 km with one underground
segment of 263 km. The AC solution would Thompson
have reactive compensation equipment at each
overhead/underground transition station and at
Flin Flon
three intermediate stations in the underground
segment. A spare cable would be provided to
improve reliability in case of a cable failure. The Pas
Grand Rapids

Selkirk
Winnipeg
Figure 3:
Brandon Route 3 AC or DC
Underground East

Report of the Concepts Review Panel - 29


2.4 Route 4 DC Submarine and through
Eastern Interlake

This route is a hybrid overhead–submarine


cable–overhead line. It would begin at Gillam
Island extending overhead to Warren Landing.
There it would transition to a submarine cable Churchill Hudson
that would extend to McBeth Point on the Bay
western shore of Lake Winnipeg, where it would MANITOBA
transition back to an overhead line extending Gillam
Island
along the eastern side of the Interlake to the
Winnipeg area. The total route length would
be 990 km including one submarine segment Gillam
of 176 km. A spare submarine cable would be
included. Thompson

Flin Flon

The Pas Grand


Rapids

Selkirk
Winnipeg
Figure 4: Route 4 DC
Brandon Submarine and through
Eastern Interlake

30 - Manitoba Hydro
2.5 Route 5 DC Two Segments of
Submarine exiting at Traverse Bay

This route is comprised of an overhead line with


two segments of submarine cable. The route
would extend from Gillam Island overhead to
Warren Landing. There it would transition to Churchill Hudson
a submarine cable that would extend to Island Bay
View on the west shore of the lake near the MANITOBA
Narrows, then transition back to an overhead Gillam
Island
line to Riverton. From there it would transition
to a submarine cable across the lake to Traverse
Bay. Finally, it would transition back to the last Gillam
overhead line segment which would continue
Thompson
on to the Winnipeg area. The total route length
would be 991 km including two submarine
segments of 235 and 52 km. A spare submarine Flin Flon
cable would be included for each segment to
improve reliability.
The Pas

Grand
Rapids

Figure 5:
Selkirk
Winnipeg Route 5 DC Two
Segments of
Brandon Submarine exiting at
Traverse Bay

Report of the Concepts Review Panel - 31


2.6 Route 6 AC with Two Segments of
Submarine exiting at Traverse Bay

This route, similar to Route 5, is comprised of an


overhead line with two segments of submarine
cable. The route would begin at Gillam Island
and extend overhead to the northern edge of the Churchill Hudson
Poplar River Protected Area on the northeastern Bay
shore of Lake Winnipeg. There it would transition
MANITOBA
Gillam
to a submarine cable which would extend Island
(with two additional land stops for reactive
compensation stations) to Island View. From
there it would transition to an overhead line to Gillam
Riverton, then to another submarine cable to
Thompson
Traverse Bay, and finally back to an overhead
line which would continue on to the Winnipeg
area. The total route length would be 943 km Flin Flon
including submarine segments of 188 and 52 km.
A spare submarine cable would be included for
each segment to improve reliability. There would The Pas
Grand Rapids
be reactive compensation equipment at each
overhead/underground transition station and at
two intermediate compensation stations in the
northern submarine cable segment.

Selkirk Figure 6:
Winnipeg Route 6 AC with
Two Segments of
Brandon Submarine exiting at
Traverse Bay

32 - Manitoba Hydro
Table 6: Cable Route Option Length and Number

OH Submarine
Total UG Submarine Total Submarine
Route Route UG Route UG Cable Route
Mode Cable Cable Cable Length
Option Length Length (km) Numbers Length
Length (km) Numbers (km)
(km) (km)

1 AC OH 1273 0 0

1 DC OH 1273 0 0

2 AC OH-UG 1025 175 4 700


Hybrid
2 DC OH-UG 1025 175 3 525
Hybrid
3 AC OH-UG 830 263 4 1052
Hybrid
3 DC OH-UG 830 263 3 789
Hybrid
4 DC OH-Sub 812 178 3 534
Hybrid
5 DC OH-Sub 704 287 3 861
Hybrid
6 AC OH-Sub 703 240 4 960
Hybrid

Report of the Concepts Review Panel - 33


Table 7: Cable Route Options Transitions, Joints, and Terminations

Cable
Cable Field
AC Transition AC Transition Shipping Field
DC Shipping Joints
Route Comp. Comp. Length Joints
Mode Transition Length(km) (No Terminations
Option Stations – Stations – (km) (No (Long
Stations (Long Long
Line Ends Intermediate Long Trains)
Trains) Trains)
Trains)

1 AC OH

1 DC OH

OH-UG
2 AC 2 2 1.8 1.8 389 389 24
Hybrid
OH-UG
2 DC 2 4.0 4 175 175 6
Hybrid
OH-UG
3 AC 2 3 1.8 1.8 877 877 40
Hybrid
OH-UG
3 DC 2 4.0 4 263 263 6
Hybrid
OH-Sub
4 DC 2 1.8 12 x 45 495 9 6
Hybrid
OH-Sub 15 x 47,
5 DC 4 1.8 797 12 12
Hybrid 3 x 52
8 x 33,
OH-Sub 8 x 36,
6 AC 4 2 1.2 1400 8 32
Hybrid 4 x 50,
4 x 52

34 - Manitoba Hydro
Table 8: Transmission Line Route Details

Route Advantages Disadvantages

1 This would be an AC or DC overhead line with no Requires two long overhead spans between islands and
underground or submarine cable and no cable- mainland of about one km in Cedar Lake.
AC or DC related reactive compensation equipment and thus
inherently more reliable. Location of “island hops” less than 20 km from Bipole I-II
at Grand Rapids.
A 500 kV AC transmission interconnection between
northern generation and the southern system Permission is required for overhead line to cross about 20
would strengthen the AC system in the south. km of “protected area” park along the east shore of Lake
Winnipegosis.

2 After connecting to the Grand Rapids underground Permission is required for overhead line to cross about 20
cable, the overhead line would be at least 50 km km of “protected area” park along the east shore of Lake
AC or DC away from Bipole I-II all the way to the Winnipeg Winnipegosis.
area.
500 kV AC cable systems of this length have never been
No novel transport methods required. installed anywhere in the world. The impacts on the
transmission system are not known and need more study.
A 500 kV AC transmission interconnection between
northern generation and the southern system Cable-related reactive compensation equipment needed
would strengthen the AC system in the south. for AC alternative.

A tunnel would be required at Grand Rapids.

3 No novel transport methods required. The overhead line would be less than 30 km from Bipole
I-II as it goes around the Peguis Reserve.
AC or DC
500 kV AC cable systems of this length have never been
installed anywhere in the world. The impacts on the
transmission system are not known and need more study.

Cable-related reactive compensation equipment needed


for AC alternative.

4 There would be adequate lake sediment for the To get to the Warren Landing site, the OH line from the
entire length of the submarine cable, thus no Nelson River Generating Area would have to cross the
DC mechanical barrier protection required for the Nelson River with a long span of about 1 km.
submarine cable (no rock cutting, rock dumping, or
protective mattresses). The OH line would be less than 30 km from Bipole I-II as it
goes around the Peguis Reserve east of Lake St. Martin.

Dredging of the lake bottom and river at Powerview/Pine


Falls may be required for barge access to rail siding.

Disturbance of lake bottom sediment.

5 There would be adequate lake sediment for the To get to the Warren Landing site, the OH line from
entire length of the submarine cable thus no Nelson River Generating Area would have to cross the
DC mechanical barrier protection required for the Nelson River with a long span of about 1 km.
submarine cable (no rock cutting, rock dumping, or
protective mattresses.) Dredging of the lake bottom and river at Powerview/Pine
Falls may be required for barge access to rail siding.

Disturbance of lake bottom sediment.

Report of the Concepts Review Panel - 35


6 A 500 kV AC transmission interconnection between There is little sediment along the entire east shore of
northern generation and the southern system Lake Winnipeg, extending in places for about 30 km off
AC would strengthen the AC system in the south. shore. Throughout this area the lake bottom has rough
rocky terrain. Because of the required short lengths of AC
cable, about 200 km of AC cable would have to be laid
near the shore on this unfavourable terrain. Because of
the lack of sediment, the cable would have to be covered
by rock dumping or protective mattresses. Only the 50
km line from Riverton to Traverse Bay would be covered
by sediment.

500 kV AC cables of this length have never been installed


anywhere in the world. The impacts on the transmission
system are not known and require further study.

Cable-related reactive compensation equipment needed.

Disturbance of lake bottom sediment.

Very complex operating a hybrid link with these


components.

2.7 Grand Rapids Congestion Issues

Options for installing an HVAC or DC link Figure 7: Grand Rapids Transmission Corridors
through the Grand Rapids area are limited
due to the bottleneck effect from the
congestion of existing transmission lines,
generating station, and ancillary facilities.
Routes 2 and 3 include installation of
underground cables through the area.
Work would entail construction of a
single trench for an AC or DC system and
a tunnel under the spillway and tailrace
approximately 600 m long. Horizontal
Directional Drilling was considered
instead of a tunnel, but there was concern
that there could be high potential to
disturb the environment (possibility of
drilling mud frac-outs, water turbidity
and harm to fish habitat). Further issues
may exist due to proximity of overhead
lines, etc., however, for this report these have
been limited to environmental and physical
examinations. For details see Appendix 7.

36 - Manitoba Hydro
3 Cable System Performance
This section describes performance of mature Self contained fluid-filled cables
cable systems for underground and submarine
applications. Later sections will describe how the Self contained fluid-filled (SCFF) cables are
cable systems can be used to implement several comprised of a hollow central conductor,
concepts for post-Bipole III transmission, and will surrounded by laminar insulating tapes and
provide reliability approximations. pressurized with insulating fluid. The cable core
is encapsulated in a hermetic seal, typically a
continuous lead or aluminum ‘sheath’, at the
factory. The cables are shipped to the site on
3.1 Description of Cable Types for
reels, ready for installation. They are connected
Underground Transmission
to adjacent sections using joints, terminated at
Before explaining cable performance, descriptions cable ends and permanently pressurized via the
are provided for the various underground cable hollow conductor. Three such cables are required
types and a basis for optimal type selection. to provide a 3-phase AC circuit. SCFF cables with
Following are basic descriptions of those types conventional kraft paper tape insulation have
that could be considered generally available relatively high energy losses, lower transmission
for AC and DC underground transmission. capacity and thicker insulation compared
Only some are feasible for the 500 kV level, for to SCFF cables using PPL tapes (SCFF-PPL).
the reasons explained below. More detailed Pressurization of the insulating fluid is usually
descriptions of cable types can be found in done with passive pressure tanks located at
textbooks [1,14,15]. underground cable ends, and for longer lines,
at some intermediate joints. SCFF cable systems
First cables with laminar or lapped dielectrics are have been commercialized for 500 kV AC and
discussed, followed by a discussion of cables with DC and have been in service for several decades.
extruded dielectrics.

3.1.1 Laminar, or Lapped Dielectric Figure 8: SCFF AC Underground Cable


Source: http://www.nexans.no/Norway/2007
For this type of underground cable the electrical HighVoltageCable_2.pdf
insulation is typically comprised of high purity
paper tapes made using the ‘kraft’ sulphate
process. Tapes are wound around a central
conductor, vacuum dried, saturated with
insulating fluid and pressurized. Several suppliers
provide laminated kraft paper-polypropylene-
paper (PPL) tapes. These tapes provide lower AC
energy losses and higher allowable voltage stresses
than typical kraft paper insulation. Higher stress
limits result in thinner insulation than any other
commercial cable type, which makes the insulated
cable ‘cores’ smallest in overall diameter.

Report of the Concepts Review Panel - 37


High pressure fluid-filled cables High pressure Gas-filled cables
High pressure fluid-filled (HPFF) ‘pipe-type’ High pressure gas-filled (HPGF) ‘pipe-type’
cables do not contain a saturated, lapped paper- cables are similar to HPFF cables except the
insulated cable core within a metal sheath. wound paper insulation core is saturated with
Instead, the cores are shipped to the site on higher viscosity insulating fluid. Cables are also
individually sealed reels. Three such cores are shipped to the site in individually sealed reels.
simultaneously pulled into a pre-installed steel Three cores are simultaneously pulled into a pre-
pipe, joined to adjacent sections, terminated and installed steel pipe, joined to adjacent sections,
subsequently pressurized from outside the cores terminated and subsequently pressurized with dry
with insulating fluid, to provide a 3-phase AC nitrogen gas instead of insulating fluid, to provide
circuit. Due to the heat generated in their carbon a 3-phase AC circuit. The absence of liquid
steel pipes, HPFF cable systems have higher energy insulating fluids and related complex pressurizing
losses and lower transmission capacity than the systems makes HPGF cables inherently simpler
other feasible types. The pipes and pressurizing than HPFF systems and avoids all risks due to
systems also contain much more insulating fluid liquid insulation fluid leaks compared to the
than SCFF cable systems (approximately 18,000 other laminar insulation systems described above.
l/km compared to 250 l/km for typical 230 kV However, the present upper AC voltage limit for
installations), which increases the potential leak HPGF cables is only about 150 kV. They are not
volumes and possible environmental impacts. commercially available for DC and therefore they
They operate at higher pressures than most SCFF will not be given further consideration for this
cable systems, so their pressurizing systems are application.
more complex, requiring large fluid storage tanks,
pumps, valves and automatic controls. Although Mass impregnated cables
HPFF cable systems have been tested for 500 kV
Mass Impregnated (MI) cables are similar to SCFF
AC, they are not commercially available for
cables except that they are not pressurized and
500 kV AC or DC, and therefore will not be
therefore do not have a hollow conductor core.
further considered for this application.
The absence of pressurization results in very poor
performance for AC applications, with an upper
Figure 9: High Pressure Fluid-Filled ‘Pipe-type’ practical limit of about 69 kV [3]. However, they
underground cable - Source: www.okonite.com have been tested to the 600 kV DC level by several
suppliers and are commercially available at 500
kV DC. Long distance 500 kV DC MI cables have
been in service for approximately three years [4]
and 450 kV DC MI cables for about 16 years [5].
They have proven to be very reliable.

A characteristic of DC MI cables for applications


above about 300 kV is that they cannot be
coiled. This is because in order to accommodate
the high electric stresses, the insulating tapes
must be wrapped around the conductor core at
relatively high tensions. When cables are coiled,
as opposed to being wound on a reel, carousel
or turntable, torsional forces are exerted on
the highly tensioned insulating tapes that can

38 - Manitoba Hydro
result in damage. Implications are that HV DC Ethylene Propylene Rubber cables
MI submarine cables cannot be coiled into the
hold of a freighter for ocean transportation, but EPR cables use insulation made of extruded
instead must be transported on special ships electrical grade ethylene propylene rubber. The
with carousels or turntables, as shown in Figures upper voltage limit for EPR cables is about 150
21 and 24. This must also be taken into account kV AC due to high insulation losses and they are
when developing methods to transport long not commercially available for DC, so no further
continuous lengths by train, as described in consideration is given for this application.
Appendix 4 (with Method 1 being preferred for
this reason).
Polyethylene cables
Figure 10: Mass Impregnated EHV Submarine Cable (Source: PE cables use insulation made of extruded
www.prysmian.com)
electrical grade low density polyethylene (LDPE),
a thermoplastic polymer. The insulation softens
significantly at conductor temperatures above
about 70 °C, which limits thermal-mechanical
performance and therefore transmission capacity.
Although many circuits continue to operate at the
400 kV AC level, manufacturing has been mostly
discontinued for transmission applications. Also,
they have not been proven for DC use. Therefore
PE insulation cables are not given further
consideration for this application.

Cross-linked polyethylene cables


3.1.2 Extruded Dielectric XLPE cables use insulation made of extruded
electrical grade cross-linked polyethylene, which
The electrical insulation on extruded dielectric is a thermoset polymer. An organic peroxide is
cables is comprised of highly refined elastomers added to the LDPE to form cross-links between
or polymers extruded around the central the long hydro-carbon chains in the PE matrix
conductor and vulcanized (cross-linked) at high during vulcanization. This significantly improves
temperature and pressure. There is no free fluid important thermal and mechanical properties,
or pressurization system, so a continuous metal such as maximum operating temperature
sheath or pipe is not required for containment, (typically 90 °C) before insulation softening
and there is no possibility of leaks into the occurs. Thermal-mechanical performance and
environment. However, most extruded dielectric transmission capacity is therefore better than
cable types for higher stressed transmission PE cables. XLPE underground cables have been
applications require a continuous metal moisture commercialized to 500 kV AC and long distance
barrier to prevent water penetration into the lines have been in service for about ten years
insulation, which can have a long term degrading [6]. By modifying the insulating compound
effect. and refining semi-conducting conductor and
insulation shields, cable systems have been
manufactured to the 250 kV DC level (Honshu-
Hokkaido). Several suppliers have completed

Report of the Concepts Review Panel - 39


development tests as well as industry standard approximately eight known cable manufacturers
pre-qualification and type tests for the 320 to who have passed industry standard tests to prove
400 kV DC level. Two claim that they have done their 500 kV AC XLPE underground cable systems.
sufficient development and prototype tests to At least one manufacturer has developed an 800
demonstrate commercial availability for 500 kV AC XLPE underground cable system.2� For the
kV DC. [7]. At the time of writing, orders have reasons described above regarding pressurization
been placed for XLPE DC cables at the 320 kV difficulties for long distances, AC SCFF cables
level (e.g. DolWin1 and BorWin2 wind farms), are not given further consideration for this
but none have yet been installed above 200 kV application.
(TransBay).
At present, the three possible cable types for post-
Figure 11: XLPE AC Underground Cable Bipole III 500 kV DC underground applications
Source: http://www.nexans.no/Norway/2007/HighVoltage are SCFF, MI and XLPE. MI and XLPE cables are
Cable_2.pdf usually favoured over SCFF cables because they do
not have pressurized insulating fluid, which poses
higher environmental impacts and limits cable
lengths to about 50 km due to difficulties with
maintaining pressures during transient loading.
For these reasons DC SCFF cables are not given
further consideration for this application.

Figure 12: DC underground cable with XLPE insulation (source:


www.abb.com; “It’s time to connect”)

Feasible cable types


At present, the two possible cable types for post-
Bipole III 500 kV AC underground applications
are SCFF (with PPL insulation) and XLPE. XLPE
cables are usually favoured over SCFF cables
because of the absence of pressurized insulating
fluid and lower maintenance. XLPE cables
also have a lower insulation permittivity and
capacitance, which reduces charging current and
therefore allows longer transmission distances
(further discussion on this issue is presented
later in this report). However, few long distance
500 kV AC XLPE circuits have been installed, so
reliability is relatively unproven. This is expected
to change as more long distance installations
are planned and more manufacturers develop
500 kV cable systems before post-Bipole III 2 Private communications between A. MacPhail and
applications are needed. At present there are P. Argaut, Silec Cables; Display at CIGRE 2010 Technical
Exhibiton, August 2010.

40 - Manitoba Hydro
3.2 Description of Cable Types for Cross-linked polyethylene cables
Submarine Transmission
Only relatively short XLPE submarine cables have
been installed at the 420 kV AC level [8]. However
The same basic cable types for underground
an order has recently been placed for a 13 km 420
transmission generally apply for submarine
kV AC circuit across the Oslofjord between Norway
transmission. However, there are some
and Sweden. Therefore 500 kV AC XLPE cables
exceptions, which are presented in the following
are not presently available for this application.
discussion. It’s noteworthy that, excluding HPFF
However, the upper limit is expected to increase to
and HPGF pipe-type cables from discussion,
500 kV AC within the next decade, also with longer
submarine cables are generally similar to
installation distances. Presently, the upper limit for
underground cables, except they have external
planned DC XLPE submarine applications is about
armour to provide additional mechanical
the same as for underground, i.e. 320 kV, with
protection and manage high tensions during
two suppliers claiming they have done sufficient
laying. However, there are important differences
development and prototype tests to demonstrate
for deep water applications, where special
commercial availability for 500 kV DC [7].
constructions are needed to handle high internal
tension, torsion and shear forces applied to the
various layers during laying. Special measures 3.2.1 Maturity of State-of-Engineering of
are also taken to inhibit water ingress in the 500 kV Cable Technologies in Use
event of damage. But for the relatively shallow World-wide Today
Lake Winnipeg application, in general cable
constructions would be similar for underground Discussions of the relative state of maturity of
and submarine cables, except for the presence various cable systems are described below in the
of armour wires for the latter. This of course same order in which they are summarized in
increases the outer diameter and weight, so that Tables 4 and 5.
less submarine cable can be accommodated on The Panel’s definition of ‘maturity’ is:
the same reels used for underground cables.
Since a cable’s minimum bending radius is • Industry standards and recommendations
proportional to its outside diameter, submarine describe tests for manufacturing such
cables cannot be bent to as small a diameter as systems.
an equivalent underground cable. The net result
• Existing applications are ‘long distance’,
is that submarine cables are generally more
meaning at least five km for underground
expensive to manufacture and transport.
cables and 20 km for submarine cables.
Following is a description of cable types generally
• Applications have been in service for at
available for submarine transmission.
least five years.

HPFF and HPGF cables • Reliability has been ‘acceptable’.

HPFF and HPGF cable systems are limited in • A complete cable system, including
length to the distances that cables can be pulled all accessories such as joints and
into steel pipes, which usually restricts them terminations, is commercially available
to a length of one to two kilometres for water from at least one supplier.
crossings. Therefore, they are not considered to
be suitable for this application, where crossing Table 9 describes ‘mature’ cable types and their
lengths could be up to 70 km for 500 kV AC and upper voltage limits for AC and DC underground
287 km for 500 kV DC. and submarine applications, as commercially
available in 2010.

Report of the Concepts Review Panel - 41


Table 9: Cable options and upper voltage limits for ‘mature’ AC and DC underground or submarine applications in 2010

Laminar or Lapped Dielectric Extruded Dielectric

Application Pressurized Pressurized Pressurized Unpressurized Unpressurized Unpressurized


Self Contained High Pressure High Pressure Mass Cross-Linked Ethylene Propylene
(report section
Fluid-Filled Fluid-Filled Gas-Filled Impregnated Polyethylene Rubber
number)
SCFF HPFF HPGF MI XLPE EPR

AC Underground
500 kV AC 500 kV AC 150 kV AC NA 500 kV AC 150 kV AC
(3.2.2)

AC Submarine
500 kV AC NA NA NA 420 kV AC 150 kV AC
(3.2.3)

DC Underground
500 kV DC NA NA 450 kV DC 200 kV DC* NA
(3.2.4)

DC Submarine
500 kV DC NA NA 450 kV DC 200 kV DC* NA
(3.2.5)

*Cross-sound 150 kV cables commissioned in 2003; 200 kV TransBay cables installed in 2010; 250 kV Honshu-Hokkaido cables to be installed in 2012,
200 kV East-West interconnector to be installed in 2012, 320 kV DolWin1 cables to be installed in 2013 (2 x 75 km sea cable; 2 x 90 km land cable).

Table 10 describes cable types for AC and DC underground and submarine applications and their upper
limits on voltage level, as anticipated to be ‘mature’ in 2025.

Table 10: Anticipated Cable options and upper voltage limits for ‘mature’ AC and DC underground or submarine
applications in 2025

Laminar or Lapped Dielectric Extruded Dielectric


Application Pressurized Pressurized Pressurized Unpressurized Unpressurized Unpressurized
Self Contained High Pressure High Pressure Mass Cross-Linked Ethylene
(report section
Fluid-Filled Fluid-Filled Gas-Filled Impregnated Polyethylene Propylene Rubber
number)
SCFF HPFF HPGF MI XLPE EPR

AC Underground
500 kV AC 500 kV AC 150 kV AC NA 600 kV AC 150 kV AC
(3.2.2)

AC Submarine
500 kV AC NA NA NA 500 kV AC 150 kV AC
(3.2.3)

DC Underground
600 kV DC NA NA 600 kV DC 500 kV DC NA
(3.2.4)

DC Submarine 600 kV DC NA NA 600 kV DC 500 kV DC NA


(3.2.5)

42 - Manitoba Hydro
For references regarding maturity, Appendix 3.2.3 Maturity of 500 kV AC Submarine
5 lists the existing 500 kV AC and 500 kV DC Cable Systems
cable systems in service in the world today
for underground and submarine applications Self Contained Fluid-Filled (SCFF) AC
(believed to be complete, but there could be Submarine Cables
several omissions for shorter applications).
There are industry standards for testing these
cables to the 500 kV AC level. On the basis of
this and performance of the 26 year old, double
3.2.2 Maturity of 500 kV AC Underground circuit 500 kV AC 1200 MW submarine cable
Cable Systems system from the British Columbia mainland to
Vancouver Island, 500 kV AC SCFF submarine
SCFF AC Underground Cables cable systems are judged to be ‘mature’. The
Hainan Island 500 kV AC SCFF submarine cable
There are industry standards for testing these system has been in service since early 2009. There
cables to the 500 kV AC level (IEC 141-1). There are no other 500 kV AC SCFF submarine cables
are many long and short distance applications in service. Therefore, SCFF AC submarine cable
described in Appendix 5, dating back to 1973 systems are considered to be mature at the 500 kV
(Grand Coulee). Therefore, SCFF AC underground AC level.
cable systems are considered to be mature at the
500 kV AC level.
Cross-Linked Polyethylene (XLPE) AC
Submarine Cables
XLPE AC Underground Cables
There are industry standards for testing these
There are industry standards for testing these cables, but only up to the 150 kV AC level
cables up to 500 kV AC (IEC 62067; Japanese (Electra No. 189-1 and IEC 60840). However, an
Standard; French Standard). There are two long International Council on Large Electrical Systems
distance lines in Japan and two more have been (CIGRE) Working Group (B1.27) is revising the
commissioned in China in 2009 and 2010. applicable document up to the 500 kV AC level,
Both systems are in tunnels. The technology is with completion planned in 2012.
considered to be mature at the 500 kV AC level for
installations in tunnels using similar methods and There are no 500 kV AC XLPE submarine cable
accessories as for the Japanese applications. There systems in service in the world. However,
is no evidence that tests have been conducted there is one short distance (2.5 km) 420 kV AC
to prove adequate performance of joints and application in service in Norway since 2006 [8]
terminations in very cold weather conditions, as and an 11 km 345 kV AC application is planned
prevail in winter at the study site. for New Jersey - Brooklyn in 2011. A 13 km
420 kV circuit is planned across the OsloFjord
Therefore, XLPE AC underground cable systems between Sweden and Norway, which will be
are generally considered to be mature at the commissioned in 2011-12.
500 kV AC level for tunnel installations, but the
accessories (joints and terminations) do not
appear to be proven for very cold climates. These
cables are mature at the 500 kV AC level for
typical applications.

Report of the Concepts Review Panel - 43


Therefore, XLPE AC submarine cable systems are Mass Impregnated (MI) Submarine Cables
considered to be mature at the 420 kV AC level
within one year, but not for 500 kV AC. By 2025 There are industry recommendations for testing
they are expected to be mature at 500 kV AC. these cables up to 800 kV DC (Electra No. 189-
However it is not certain that they will be proven 2). There are two installations in the world at the
reliable for such long installations as envisioned 500 kV DC level. One is a Neptune monopolar
for the post-Bipole III options described in this link from New Jersey to Long Island, New
report. York, comprised of 23 km on land and 82 km
underwater. This project went into service in June
2007.
3.2.4 Maturity of 500 kV DC Submarine
Cable Systems The other is a double monopolar link from Italy
to Sardinia, with the first phase entering service in
Self Contained Fluid-Filled (SCFF) DC mid 2009. It is comprised of 14 km on land and
Submarine Cables 390 km underwater. There are similar or longer
applications operating at the +/-450 kV DC level
There are industry standards for testing these (NorNed) placed into service in 2008 comprised
cables up to 800 kV DC (Electra No. 189-2; IEC of 580 km submarine cables.
141-1). The 50 km, 500 kV DC SCFF submarine
cable system from Honshu to Shikoku has Therefore, MI DC submarine cable systems are
now been in service for nine years, although considered to be mature at the 500 kV DC level
only at the 250 kV level. However, an extensive for submarine cable applications beyond 2012.
development test and type test program was
followed to qualify for the 500 kV DC level.
Therefore, SCFF DC submarine cable systems are 3.2.5 Maturity of 500 kV DC Underground
considered to be mature at the 500 kV DC level. Cables

SCFF DC Underground Cables


XLPE DC Submarine Cables
There are industry recommendations for testing
There are industry recommendations for testing these cables up to 800 kV DC (Electra No. 189-2).
these cables, but only up to 250 kV DC (CIGRE The only dedicated underground application of
Technical Brochure 219; IEC 62067). However, 500 kV DC SCFF cables is the St. Lawrence tunnel
a CIGRE Working Group (B1.32) is revising crossing for Hydro Quebec as part of the Radisson
the applicable document up to the 500 kV DC Nicollet link, commissioned in 1992 (operating
level, with completion planned for 2011. There at +/- 450 kV DC). However, there is also a 43 km
are no 500 kV DC XLPE cable systems in service long 400 kV underground installation for part
anywhere in the world. The highest voltage in of the Greece-Italy link, commissioned in 2002.
service is the 200 kV Transbay VSC HVDC system, Notwithstanding the solitary 500 kV application
commissioned in late 2010. Honshu-Hokkaido for the St. Lawrence crossing, SCFF underground
250 kV DC is planned for 2012. The DolWin1 cables are considered to be mature at the 500 kV
and BorWin2 320 kV DC projects located in DC level, since they have been proven for long
Germany for an offshore wind farm cluster are 500 kV DC submarine cable applications, such as
planned for 2013. 50 km 500 kV DC Honshu-Shikoku link.
Submarine applications are generally more
Therefore, XLPE DC submarine cable systems are demanding than underground applications, so
not considered to be mature at the 500 kV DC 500 kV SCFF cables can be considered mature for
level. By 2025 they are expected to be mature. underground applications.

44 - Manitoba Hydro
XLPE DC Underground Cables 3.2.6 Conclusions about Maturity of 500 kV
Underground and Submarine Cable
There are industry recommendations for testing
Systems
these cables, but only up to 250 kV DC (CIGRE
Technical Brochure 219). However, CIGRE
For 2025 AC applications, XLPE cable systems
Working Group B1.32 is revising the applicable
will likely have reached sufficient maturity and
document up to the 500 kV AC level, with
reliability for both underground and submarine
completion planned in 2011. There are no 500 kV
applications. They are recommended for the
DC XLPE underground cable systems in service
500 kV AC ‘concepts’. However, it is not certain
and the present upper voltage limit for five year
that sufficient reliability will be proven for such
in-service cables is the 170 km long 150 kV DC
long applications described for post-Bipole III
MurrayLink project in Australia.
in this report. Cable system reliability is directly
proportional to length, so field-proven reliability
Therefore, XLPE DC underground cables are not
of, for example, a 50 km long circuit for 50
considered to be mature at the 500 kV DC level,
years, does not equate to similar reliability for
however they are expected to be mature at the 500
a 150 km circuit. This may not be as important
kV DC level by 2025.
for underground applications where repairs can
be made more quickly and at less cost, but for
submarine applications reliability is more critical.
Mass Impregnated (MI) DC Underground
Cables
For DC submarine cable applications in
There are industry recommendations for testing 2025, mass impregnated (MI) and XLPE cable
these cables up to 800 kV DC (Electra 189-2). systems will also have likely achieved sufficient
There are two installations in the world at the 500 maturity and reliability. However, MI cables
kV DC level, both with joints in the underground were selected as the basis for estimating costs of
sections. One is a Neptune monopolar link from submarine DC cable ‘concepts’ because they can
New Jersey to Long Island, New York, comprised be manufactured in longer lengths with fewer
of 23 km on land and commissioned in 2007. factory joints. They also have a proven 40-year
The other is the first phase of a double monopolar positive reliability history at 250 kV DC to 300 kV
link from Italy to Sardinia, which entered service DC and over 20 years at 400 kV DC. Reliability
in mid 2009 with 14 km on land. is especially important for submarine cables
in Lake Winnipeg because of long repair times
Therefore, MI DC underground cables are during winter (October 31 – May 1). Cable system
considered to be mature at the 450 kV DC level reliability will be discussed more in later sections.
but not quite at the 500 kV level because they do
not yet meet the five year criteria. For DC underground applications in 2025, XLPE
cable systems will have achieved acceptable
However, MI DC underground cable systems are maturity and reliability, and are recommended
considered to be mature at the 500 kV DC level for underground DC cable ‘concepts’. They
for underground cable applications beyond 2012, are favoured on land over MI cables because
when they will have met the five year experience of light weight, ease of field jointing, longer
criteria. shipping lengths and relatively fast repairs.
Outage durations would be months shorter for
underground cables than for submarine cables.
There are similar concerns about reliability of
long distance 500 kV DC XLPE underground

Report of the Concepts Review Panel - 45


cable applications, as for long distance 500 kV AC 3.3.1 Conditions Imposed by the Natural
XLPE submarine cables. However, because repairs Environment
to underground cables can be made more quickly
and at less cost, reliability may not be as critical. The cable system, including transition stations
must be designed to withstand the following
Cables with pressurized fluids are not proposed conditions:
for any route option studied due to the high
cost of operations, and potential environmental Maximum air temperature: 40 °C
objections to their use. Many manufacturers and
customers have indicated a preference to move Minimum air temperature: -50 °C2

away from this technology and this trend is


Maximum soil temperature
expected to continue to 2025. at 1.0 m deep: 14 °C*

Table 11: Recommended Cable Types for 2005 (assuming Minimum soil temperature,
adequate proven reliability for long distances 0.5m deep: -0.8 °C*

Cable Route Type Cable Technology Minimum soil temperature


1.0 m deep: 0.3 °C*
AC Underground XLPE
Minimum soil temperature
AC Submarine XLPE 1.5 m deep: 1.4 °C*

Minimum soil temperature


DC Underground XLPE 3.0 m deep: 3.8 °C*

DC Submarine MI or XLPE Maximum lake bottom


temperature: 15 °C

Maximum wind speed where OH lines > 100 km from Bipole


I-II: 161 km/hour
3.3 Performance of AC and DC Cables
Operating at 500 kV Maximum wind speed where OH lines are less than 100 km
but greater than 50 km from Bipole I-II: 220 km/hour
A technical comparison of AC and DC cable
systems is provided in Appendix 6. *Reference: http://climate.weatheroffice.gc.ca/climate_normals/
Temperatures stated for Gimli, Manitoba

In general, performance is expressed in terms of


how measurable goals and objectives are met. For In addition, submarine cable systems must be
purposes of this report, performance was defined capable of withstanding other natural hazards,
by the following, each to be described in greater such as scouring by ice accumulation in the
detail in following sections. littoral zone, by drifting ice islands and shore
erosion. There is some evidence that scouring
• Conditions imposed by the natural can penetrate the lake bottom to depths of
environment approximately one metre. Further explanations
are provided in section 4.3.4.
• Transmission capacity
• Reliability
• Life expectancy 3 Parts of cable system exposed to this temperature require
• Operation and maintenance requirements. special engineering and design; lower range matches other
equipment specifications at Manitoba Hydro.

46 - Manitoba Hydro
3.3.2 AC Transmission Capacity Figure 14: 500kV AC cable switching arrangement for
spare cable
It is assumed that the required transmission
capacity would be 1000 MW. This could be 500 kV AC cables with spare cable – 1000 MW

transmitted with AC using a single circuit C B A

overhead transmission line. However, actual


power transfer would depend on the generation
connected at the transmitting end,
and system stability constraints.
NC NC NC

For AC underground sections, one cable circuit


with a spare cable would be required for 1000
MW capacity, approximately as shown in the
NO NO NO
Figure 13 configuration.

Figure 13: Cable circuit with spare cable 1000 MW 500kV AC

Right-of-Way

Cable circuit with spare cable


1000 MW C B A

500 kV AC Overhead Line – 1000 MW


1.50 approx.

Select backfill

Single-point sheath bonding would be used, in


order to enable spare cable switching, which
would be impractical with conventional cross-
0.60

bonded sheath systems. At least one parallel


ground continuity conductor would be installed
0.50 approx. Typ Thermal backfill in the same trench as the cables.

This is a simplified diagram that omits auxiliary AC underground cables are assumed to be
cables, such as ground continuity conductors approximately as follows. Conductor size is
and fibre-optic cables for monitoring, preliminary and subject to change depending
telecommunication, telecontrol and system on the results of detailed reactive compensation
protection. Each cable configuration would be studies, to optimize reactor size versus cable
enclosed in a minimum 75 mm thick concrete ampacity.
envelope, to provide protection from third
party damage, tree root damage and other Conductor: 1400 mm2 copper milliken type
natural hazards. In the event of a cable failure, Maximum conductor
transmission capacity of the link would initially temperature: 90°C
be reduced to zero until the failed cable could Insulation: Cross-linked polyethylene (XLPE)
be isolated at transition stations using remotely Sheath: Continuous extruded or
operated disconnects and the spare cable inserted longitudinally seam-welded
to take its place while repairs were made. This smooth aluminum
would substantially reduce the time for lost Jacket: High density polyethylene (HDPE)
transmission capacity. One solution using External diameter: Approximately 130 mm
disconnects is shown in Figure 14. Weight: Approximately 25 kg/m

Report of the Concepts Review Panel - 47


For AC submarine sections, one circuit with a spare cable
would also be provided. Cables would be separated by
approximately twice the water depth, but no less than 10 m,
as shown in Figure 16. Cables would be buried one to two
metres below the lake bed, depending on bottom hardness,
water depth and susceptibility to bottom scouring by wind-
blown ice islands and other natural hazards.

AC Submarine cables are assumed to be approximately as


follows:

Conductor: 1600 mm2 copper milliken type


Maximum conductor
temperature: 90°C
Insulation: Cross-linked polyethylene (XLPE)
Sheath: Continuously extruded, high
fatigue resistance lead alloy
Jacket: Polyethylene
Armour: Copper wires or straps
External diameter: Approximately 150 mm
Weight in air: Approximately 65 kg/m

Figure 16: Assumed AC Submarine Cable Configuration (dimensions in metres)

Cable circuit with spare cable


1000 MW

Lake Surface
Water depth D

Lake Bottom
1.00 to 2.00 m approx.

2 x Water Depth min, but no less than 10.00 m Typ.

48 - Manitoba Hydro
Industry practice for AC submarine cables is • During an outage of one pole, the other
that they typically do not use special sheath could be operated continuously with
bonding systems. Instead sheaths and armour ground return.
circuits are solidly connected to ground at
• For a pole outage, in case long-term
both ends, making integration of a spare cable
ground current flow is undesirable, the
easier than for underground systems. As for the
bipolar system could be operated in
underground option, in the event of a cable
monopolar metallic return mode. Transfer
failure, transmission capacity of the link would
of the current to metallic path and back
initially be reduced to zero until the failed cable
without interruption requires a Metallic
could be isolated at transition stations using
Return Transfer Breaker and other special-
remotely operated disconnects and the spare
purpose switchgear in the ground path of
cable inserted to take its place while repairs were
one terminal.
made. This would substantially reduce the time
for lost transmission capacity. • During maintenance of ground electrodes
or electrode lines, operation is possible
Some of the route options require AC cable with connection of neutrals to the
lengths to be 50 to 70 km long. Capacitive grounding grid of the terminals, but only
charging current for typical 500 kV AC XLPE if the imbalance current between the two
cables is about 23 A/km, half of which flows poles is held to a very low value.
into each cable terminal. Shunt reactors are
required near the ends of these cable segments to • When one pole cannot be operated with
compensate for the charging current, otherwise full load current, the two poles of the
transmission of useable real power would be bipolar scheme could be operated with
limited, voltage regulation would be poor and different currents, assuming that both
serious system over-voltages could result. This is ground electrodes are connected.
described in greater detail in later sections.
• In case of partial damage to DC line
insulation, one or both poles could be
3.3.3 DC Transmission Capacity continuously operated at reduced voltage.

• Failure of an underground or submarine


It is assumed that the required DC transmission cable would result in monopolar
capacity would also be 1000 MW. For purposes operation with 500 MW capacity until
of this report a conventional Line Commutated the spare cable could be switched into
Converter (LCC) Bipole system is assumed, position.
using earth return, as shown in Figure 17. Several
suppliers have passed tests for 300 kV XLPE DC Figure 17: Bipolar Conventional DC System, One Valve Group
cables for use with LCC converters as well as VSC. per Pole
Operational capabilities for the assumed LCC
converter/cable arrangement would be as follows:

Report of the Concepts Review Panel - 49


For DC underground sections, three parallel cables DC Underground cables are assumed to be
(two for normal operation plus a spare) would be approximately as follows
required in one trench, approximately as shown in
the Figure 18 configuration Conductor: 1000 mm2 aluminum
Maximum conductor
temperature: 70°C
Figure 18: Typical DC underground right-of-way
(dimensions in metres) Insulation: Cross-linked polyethylene
(XLPE)
Right-of-Way Sheath: Continuous extruded or
longitudinally seam-welded
Cable circuit with spare cable smooth aluminum
1000 MW Jacket: High density polyethylene
(HDPE)
External diameter: Approximately 105 mm
0.60 approx.

1.50 approx.

Select backfill Weight: Approximately 11 kg/m

For DC submarine sections, a spare cable would


be provided to compensate for long cable repair
times in winter. Cables would be separated by
approximately twice the water depth, but no less
Thermal backfill 0.50 approx. Typ.
than 10 m, as shown in Figure 19.

This is a simplified diagram that omits auxiliary


cables, such as fibre-optic cables for monitoring,
telecommunication, telecontrol and system
protection. The cable formation would be
enclosed in a minimum 75 mm thick concrete
envelope, to provide protection from third
party damage. In the event of a cable failure,
transmission capacity of the link would be
reduced to 500 MW until repairs could be made.
A spare cable would be provided. In the event of
a cable failure, transmission capacity of the link
would initially be reduced to 500 MW until the
failed cable could be isolated at transition stations
using remotely operated disconnects and the spare
cable inserted to take its place while repairs were
made. This would substantially reduce the time
for lost transmission capacity. One solution using
disconnects is shown in Figure 19.

50 - Manitoba Hydro
Figure 19: Assumed DC Submarine Cable Configuration (dimensions in metres)

Cable circuit with spare cable


1000 MW
Lake Surface
Water depth D

Lake Bottom
1.00 to 2.00 m approx.

2 x Water Depth min, but no less than 10.00 m Typ.

Cables would be buried one to two metres below Figure 20: DC Underground and Submarine Cable Spare
the lake bed, depending on bottom hardness, water Cable Transfer Bus Arrangement
depth and susceptibility to bottom scouring by
wind-blown ice islands in winter and other natural 500 kV DC cables with spare cable

hazards.

For this study, DC submarine cables are assumed to


be approximately as follows.

Conductor: 1000 mm2 copper NC NC

Maximum conductor
temperature: 55°C
Insulation: Mass impregnated kraft paper (MI)
Sheath: Continuous extruded lead alloy NO NO

Jacket: High density polyethylene (HDPE)


External diameter: Approximately 118 mm
Weight: Approximately 44 kg/m

The DC submarine cable transition stations and


spare cable switching arrangements would be
similar to DC underground transition stations, to
reduce the time when only 500 MW transmission
capacity was available, as shown in Figure 20.
500 kV DC Overhead Line

Report of the Concepts Review Panel - 51


3.3.4 Cable System Reliability External Cable System Failures – Underground

Predicting reliability of long 500 kV cable systems Underground cable system failures could be
for post-Bipole III applications is challenging, caused by man-made (anthropogenic) or natural
because little is known about probability of hazards. For this application, the main man-made
future cable failures due to internal spontaneous hazards would be dig-ins by third party excavators
electrical breakdowns or due to probability of and vandalism, especially at terminal stations. The
failures from external natural and man-made main natural hazards are tree roots growing into
hazards. It was not within the Panel’s Terms the cables and soil instability due to surface water
of Reference to conduct new investigations on erosion, landslides, etc. In addition extremely cold
historical cable system reliability, so the Panel winter air temperatures could affect performance
instead relied on published information by of outdoor cable terminations.
others.

Appendix 5 lists global applications of 500 kV External Cable System Failures – Submarine
AC and DC cable systems. Panel members are Surface vessel traffic is light on Lake Winnipeg
not aware of any failures of 500 kV AC XLPE compared to ocean sites and cables are assumed
cables resulting in forced outages reported in to be initially buried or otherwise protected from
the technical literature. Both cable suppliers and both man-made and natural hazards. Because of
utilities are reluctant to discuss failures. However, possible hazards and dangers to submarine cables,
it is understood from private communications listed below, it is recommended that they be
that there has been one in-service 500 kV XLPE buried in the lake sediment to at least one metre
termination failure, attributed to an auxiliary in depth. Where burial is not possible, perhaps
problem, and one in-service cable failure. There due to very hard exposed bedrock, cables would
have also been failures during commissioning be protected with rock dumping or protective
tests. mattresses. Such burial and supplemental
protection has been proven in most instances to
Before beginning to quantify reliability for the be effective in protecting submarine cables from
various underground and submarine cable external damage.
systems, it is valuable to reflect on the possible
threats and hazards for cable systems. They can Submarine cable system failures could be caused
be classified as hazards internal and external to by man-made or natural hazards. For this
the cable system. application, the following is a list of the main
man-made hazards to submarine cables.
• Boat anchors and keels impacting cables
Internal Cable System Failures • Boats and barges running aground onto
These are due to faulty manufacturing and cables
installation of cables, joints and terminations. • Boat propellers striking cables
Failure usually results in spontaneous electrical • Fishing gear impacting cables
breakdown and a forced outage. • Uncontrolled dredging and dumping by
others
• Vandalism, especially at cable terminals

52 - Manitoba Hydro
Following is a list of the main natural hazards to The matter of ice scour should be a major concern
submarine cables. in selecting the location of the cable coming
• Scouring of lake bottom and at shores by ashore, and, if at all possible, efforts should be
ice islands in winter made to avoid places where there is evidence of
• Littoral drift migration of bottom this occurring. Also the depth of ice scour has to
sediments and shore erosion be carefully determined so that the cable could
• Abrasion on exposed bedrock and in areas be buried at an appropriate depth. However,
of fast water currents excessively deep burial should be avoided, if
• High wave energy changing beach possible, because this would significantly add
morphology, possibly exposing cables to costs and could result in cable over-heating,
over time necessitating larger conductors, increasing costs
• Wind-induced disturbance of the water further.
column and lake bed dynamics causing
bottom sediment migration over time Ice ridges or pressure ridges on lake ice are
• Pounding of driftwood logs along formations that may extend parallel and generally
shorelines causing cable damage fairly close to shore for many kilometres. In
• Sand waves and mega-ripples exposing extremely cold weather, especially if there is a
buried cables over time in some areas lack of insulating snow cover, ice will shrink
• Extremely cold winter air temperatures in volume, opening up long cracks which
affecting performance of outdoor cable immediately fill with water and freeze again. Later
terminations when the temperature rises, the ice expands and
forces itself upward along the lines of the crack.
It is recommended that none of the above hazards At times a submerged volume of broken ice under
be dismissed until thoroughly investigated, since a ridge is forced downwards by pressure; this is
all example cable routes are subject to change. A termed an ice keel. In the spring, as the ice breaks
discussion of the specifics of each risk factor that up, wind-driven pressure ridge keels may drag on
may affect submarine cables follows. the lakebed and form furrows. On Lake Winnipeg
these furrows may be found close to shore in the
Ice scour is a geological term for a narrow shallow sections of the northwestern North Basin
ditch or furrow in a seabed or lakebed caused by and in the southern part of the South Basin. In
moving ice. Synonyms include ice gouging, ice general, ice ridges form in a north-south direction
ploughing, ice scour and keel scour. Geologically, approximately one kilometre or less from shore
ice scour is normally associated with glacial running from one mainland point to another or
ice in the form of icebergs. In the case of Lake from island to island. In the South Basin there
Winnipeg, ice scour occurs in the spring when in is normally one major north-south ridge that
some places, as the lake ice breaks up, the wind develops down the centre of the lake.
blows sheets or chunks of ice toward the shore. As
this occurs, occasionally these masses of ice may The problems created by ice ridges are comparable
pile up into layers, with some tilting sidewise and to those of ice scour, so care has to be taken
extending below the surface, and then drag along regarding the cable route, especially where the
the lakebed as they are pushed ashore. Some of cable comes ashore. Fortunately, it appears that
these ice scours or furrows have been reported ice ridge keel furrows occur mostly in areas fairly
anecdotally to be a metre or more in depth, but close to shore or in parts of the lake where no
there are no data on exact depths, location of cable routes have been proposed. Hence the
occurrences, or the regularity of occurrences at hazard of ice ridges may not pose a threat to the
specific locations. Ice scour may also occur as a two proposed DC routes since they would extend
result of ice pressure ridges, as discussed below.

Report of the Concepts Review Panel - 53


along the middle of the lake, and there is no In these locations, after a severe storm, the
evidence of furrows along the east shore where depth of sediment may vary by several metres –
the AC route would be located. leaving some areas with exposed bedrock while
other areas would be heaped up in mounds.
Shoreline erosion Fortunately, this occurrence is largely restricted
During the glacial Lake Agassiz phase of present to the section of the lake known as The Narrows.
day Lake Winnipeg, varying depths of clays and This is the funnel-like narrow section that
silts were deposited over the tills left by the separates the North Basin from the South Basin.
glacial ice advance. These lacustrine clays and In addition to storms, long periods of strong
silts are generally free of stones and relatively winds from either the north or the south can also
unconsolidated. Compared to cobble/boulder cause sediment mobility.
tills, the silts and clays are highly erodible and are
present along the west shore of Lake Winnipeg as Because of this phenomenon, it would be
well as the eastern shore south of Manigotogan inadvisable to try to install submarine cable
[20] [21]. through The Narrows. Other parts of the lake may
experience minor degrees of sediment mobility,
Comparison of shoreline positions over time so careful note must be made of such locations in
indicates typical shoreline recession rates of 0.3 selecting a cable route.
m to 0.6 m per year with extremes of two metres
per year. Sandwaves and mega-ripples (dunes) have
been reported in some areas but because a thorough
Care should be taken in selecting sites for high resolution lakebed survey has not been done,
submarine cables where they enter or exit the the extent of their existence is not known.
lake, and in the design and installation of
shoreline protection.
Reliability Predictions
Lack of sufficient sediment poses problems
Lack of information on the external hazards
for cable burial and may require rock dumping
described above explains why it is difficult at this
or protective mattresses to adequately bury
time to determine their ultimate influence on
the cable. Along the entire east shore of Lake
total cable system reliability. Following are some
Winnipeg there is little sediment, extending in
reasons why predicting cable system internal
places for about 30 km off shore. Throughout this
failure rates for 2025 post-Bipole III applications
area, the lake bottom has rough rocky terrain.
is also difficult.
If AC cables were to be installed in this region,
they would be laid relatively near the shore • There are three different cable types to be
between the transition/compensation stations, considered (AC XLPE, DC XLPE, DC MI).
on unfavourable terrain, and would have to be
covered by rock dumping or protective mattresses. • Some of the proposed cable systems have
no service history for the 500 kV level (DC
Sediment mobility occurs in areas of the XLPE underground and submarine; AC
lake where swift currents, exacerbated by XLPE submarine).
strong winds, are capable of moving sand, silt,
clay and other sediments from one location • Those that have been developed for
to another, sometimes in a dramatic manner. the 500 kV level either have too short
service experience (DC MI) or a shortage
of service reliability data (AC XLPE
underground).

54 - Manitoba Hydro
• Cable system failure rates are based on on the subject. The purpose was to collect and
lower voltage applications, thus reliability analyze data relating to installed quantities of
predictions may not be applicable at underground and submarine cable systems rated
500 kV. at 60 kV and above, together with their service
experience and performance. Results showed a
• Assuming cable system failure rates based continuing trend toward application of XLPE AC
on experience elsewhere may not be cables to replace SCFF AC cables, spreading to
valid because winter ambient air and soil the highest voltages, i.e. 500 kV. Unfortunately
temperatures at the sites are lower than there was very little data on performance of 500
most other applications, and most cable kV cables. For DC applications, the survey showed
systems have not been laboratory tested MI cables continuing to dominate, but with XLPE
for such low temperatures. cables used more frequently up to 150 kV.
• Cable system failure rates vary
Unfortunately the TB 379 survey data reported
with manufacturer and their long
that internal failure rates are zero for AC XLPE,
term experience with cable system
DC XLPE or DC MI submarine cables, based
development. It is unknown which
on the survey data (see TB 379 Table 29 for DC
manufacturer will ultimately supply the
XLPE and Table 30 for the others). There is an
systems and their future capabilities or
acknowledgement, however, that some of the
factory quality assurance programs.
failures reported as “other”, could have been
• Cable system failure rates depend on internal. Of course a zero failure rate is unrealistic
installation quality assurance when because it would infer infinite cable life, whereas
making cable joints and terminations. it is commonly accepted that cable systems have
Poor workmanship (or poor instructions a design life of 40 to 50 years under normal
to installation technicians) is a major loading and maintenance conditions. It is also
cause of AC XLPE cable system failures. unfortunate that there was insufficient survey
At this stage there is no way to be sure data to quantify a failure rate for submarine
that good workmanship practices will be cable accessories (joints and terminations). In
followed. addition, some of the external failure rates due to
external factors in TB 379 Table 30 for submarine
It can be concluded that there is no accurate way cables do not reflect the satisfactory performance
to predict internal failure rates for cables and their of many long lines and could provide too
accessories (joints and terminations) in 2025. pessimistic an approach to applications in
However, some semi-quantitative and somewhat 2025, which would incorporate technological
subjective approximations can be made for both improvements in manufacturing and installation.
internal and external failure hazards, as described
below. To overcome these challenges and uncertainties
about applicability of the TB 379 Table 30 data to
In April 2009, CIGRE Working Group B1.10 the Lake Winnipeg site, it was decided not to use
completed Technical Brochure 379 “Update it for Lake Winnipeg submarine cable failure rate
of Service Experience of HV Underground and forecasts. Since there was no known alternative
Submarine Cable Systems” [16]. It compiled dependable failure rate information available, it
the results of a power utility survey completed was decided to simply record cable failure rates
in December 2005, so the results are now about as unknown. However, it was agreed to use the
five years out-of-date. However, it remains the TB 379 Table 11 failure data for underground
most comprehensive industry survey ever done AC XLPE cables (all voltages) for both AC and

Report of the Concepts Review Panel - 55


DC underground options. The rationale for 2003, England – France 270 kV HVDC cable:
doing this was that the Table 11 values for AC Fault at 4 km from UK at 20 m depth.
XLPE underground cable systems are the lowest Buried cable was found twisted and failed
for all cable systems in the survey, providing an after 17 years of service, apparently due to
optimistic approach to this study and thereby initial installation difficulties.
reflecting probable improvements before 2025.
2004, New Zealand 350 kV HVDC cable:
It should be recognized however, that just because One of the three buried cables had a fault at
a dependable data base of submarine cable 150 m away from the North Island landing
failure statistics for internal failures does not point, apparently due to initial installation
exist, and because external failure rate data from difficulties.
other installations may not be applicable to Lake
Winnipeg, doesn’t mean that Manitoba Hydro 2009, Long Island Sound 138 kV AC XLPE cable:
shouldn’t expect submarine cable failures. For One of three buried cables failed within one
example, the authors are aware of the following year of installation, without signs of external
apparently internal submarine cable failures that aggression.
have occurred within the last decade:

The final assumed cable failure rates for internal and external causes are summarized in Table 12.

Table 12 Assumed Internal and External Origin Cable and Accessory Failure Rates (Worst Case/Best Case)

AC XLPE DC XLPE
AC XLPE Submarine DC MI Submarine
Underground Underground

Internal External Internal External Internal External Internal External

Cables
(per 100 cct-km/year 0.030 0.058 0.010 0.019
for AC and per cable- / / / /
km for DC) 0.030 0.000 0.010 0.000

Joints
0.005 0.003 0.005 0.003
(failures/year/100
/ / / /
joints)
0.005 0.000 0.005 0.000

Terminations
0.007 0.006 0.007 0.006
(failures/year/100
/ / / /
terminations)
0.007 0.006 0.007 0.006

Coloured boxes indicate that failures are undefined.

56 - Manitoba Hydro
The following sections apply the preceding The methodology was to first determine the
assumed failure rates for the various AC and maximum lengths of AC or DC cable that could
DC, underground and submarine cable systems, be shipped on reels by truck for the underground
and route alternatives described in Section 3. options, where there is no rail access. Then
Options for shipping cables on reels versus long similar methods were used to determine
continuous lengths on rail cars were initially maximum AC or DC cable lengths shipped on
taken into account in developing the tables. reels by rail on flat cars to Lake Winnipeg for the
However, because no reasonably accurate failure submarine options, as compared to shipping
rates were available for submarine cable joints, cables in long continuous lengths on rail cars.
it was not possible to quantify any reliability Once reel lengths were determined, and route
improvements due to shipping long submarine segment lengths known, it was possible to
cables in continuous lengths with trains. determine the number of joints and terminations,
and finally apply the assumed failure statistics
(see Table 12, Table 13, and Table 14)

Table 13: Estimated Total Cable System Failure Rates and Frequencies – Worst Case

Failure Failure
Cable Internal & Termination
Joint Internal Frequency Frequency
External Failure Internal &
Instal- & External Total Failure Rate (Long Total Failure Rate (Long
Route Rate (per 100 External Failure
lation Failure Rate (No Long Trains) Trains) (Long Trains) Trains)
Option cct-km/year for AC Rate (per 100
Mode (per 100 (per year) (years (per year (years
and per cable-km terminations/
joints/year) between between
for DC) year)
failures) failures)

Line 2 (700/(3 x 100)) x 0.088 + (389/100) Same – no train access


Land 0.088 0.008 0.013 4.2 4.2
AC x 0.008 + (24/100) x 0.013 = 0.240 to land sites

Line 2 (525/(1 x 100)) x 0.029 + (131/100) Same – no train access


Land 0.029 0.008 0.013 6.1 6.1
DC x 0.008 + (6/100) x 0.013 = 0.164 to land sites

Line 3 (1052/(3 x 100)) x 0.088 + (584/100) Same – no train access


Land 0.088 0.008 0.013 2.8 2.8
AC x 0.008 + (24/100) x 0.013 = 0.359 to land sites

Line 3 (789/(1 x 100)) x 0.029 + (197/100) Same – no train access


Land 0.029 0.008 0.013 4.1 4.1
DC x 0.008 + (6/100) x 0.013 = 0.245 to land sites

(534/(1 x 100)) x ? +
Line 4 (534/(1 x 100)) x ? + (297/100) x ?+
Water ? ? ? ? (15/100) x ? + (10/100) ?
DC (6/100) x ? = ?
x?=?
(861/(1 x 100)) x ? +
Line 5 (861/(1 x 100)) x ? + (478/100) x ? +
Water ? ? ? ? (20/100) x ? + (20/100) ?
DC (12/100) x ? = ?
x?=?
(960/(3 x 100)) x ? +
Line 6 (960/(3 x 100)) x ? + (800/100) x ? +
Water ? ? ? ? (14/100) x ? + (56/100) ?
AC (32/100) x ? = ?
x?=?

Report of the Concepts Review Panel - 57


Table 14: Estimated Total Cable System Failure Rates and Frequencies – Best Case

Failure Failure
Cable Internal & Termination
Joint Internal Frequency Frequency
External Failure Internal &
Instal- & External Total Failure Rate (No Long Total Failure Rate (Long
Route Rate (per 100 cct- External Failure
lation Failure Rate (No Long Trains) Trains) (Long Trains) Trains)
Option km/year for AC Rate (per 100
Mode (per 100 (per year) (years (per year (years
and per cable-km terminations/
joints/year) between between
for DC) year)
failures) failures)

Line 2 (700/(3 x 100)) x 0.030 + (389/100) Same – no train access


Land 0.030 0.005 0.013 10.8 10.8
AC x 0.005 + (24/100) x 0.013 = 0.093 to land sites

Line 2 (525/(1 x 100)) x 0.010 + (131/100) Same – no train access


Land 0.010 0.005 0.013 16.6 16.6
DC x 0.005 + (6/100) x 0.013 = 0.060 to land sites

Line 3 (1052/(3 x 100)) x 0.030 + (584/100) Same – no train access


Land 0.030 0.005 0.013 7.1 7.1
AC x 0.005 + (24/100) x 0.013 = 0.141 to land sites

Line 3 (789/(1 x 100)) x 0.010 + (197/100) Same – no train access


Land 0.010 0.005 0.013 11.1 11.1
DC x 0.005 + (6/100)x 0.013 = 0.0907 to land sites

(890/(1 x 100)) x ? +
Line 4 (534/(1 x 100)) x ? + (297/100) x ?+
Water ? ? ? ? (15/100) x ? + (10/100) ?
DC (6/100) x ? = ?
x?=?
(1428/(1 x 100)) x ? +
Line 5 (8615/(1 x 100)) x ? + (478/100) x ?
Water ? ? ? ? (20/100) x ? + (20/100) ?
DC +(12/100) x ? = ?
x?=?
(1682/(3 x 100)) x 0.030
Line 6 (960/(3 x 100)) x ? + (800/100) x ? +
Water ? ? ? ? + (14/100) x ? + (56/100) ?
AC (32/100) x ? = ?
x?=?

Results show that an underground cable system For underground options, repair times could be
failure can be expected about once every 3 to two to three months, depending on location and
17 years, depending on route length and cable time of year. But with the spare underground
type. Even if it’s argued that the most optimistic cable available and switching arrangements
TB 379 underground cable failure data is similar to the submarine cable terminal stations,
overly pessimistic, Manitoba Hydro could still outage durations could also be limited to several
experience many underground cable repairs over hours or days.
the operating life of a long underground cable
system. Comparisons with overhead transmission
line reliability shows that overhead lines are
Wait and repair times could be up to eight considerably more reliable. For example, a
months if a cable fault occurred in Lake Winnipeg compilation of CIGRE survey statistics collected
at the end of the fall season. However, by between 1993 and 2008 shows that the Bipole
switching in the spare cable, the outage duration I and II overhead lines had an average of 0.057
could be reduced to several hours or days, forced outages per 100 km/year (see Appendix 9),
depending on the type of switching implemented at least three times better than the worst-
at the terminal stations. performing underground segment. Most overhead
line repairs could be done in less than a week;
much faster than for cable systems.

58 - Manitoba Hydro
3.3.5 Life Expectancy of Cable Systems 3.4 Literature Review of Current Research
Cable systems are typically designed and tested for Further Technological Development
on the basis of a 40 year life. Actual longevity of 500 kV Cables
can exceed this time if loading is not excessive
and regular maintenance programs are followed. A review was completed of recent technical
There is a growing trend to acknowledge that a 50 publications at CIGRE, IEEE and Jicable
year actual life may be more realistic, based on conferences.
service experience with cables less than 500 kV.
Comparing with an approximate 100 year life for The results show that little development work
overhead line alternatives leads to the conclusion is being done for SCFF cables and production
that an underground or submarine cable system capacity is declining as a shift continues toward
would need to be replaced about once during the use of XLPE insulations for AC applications.
life of the equivalent overhead line.
Production of mass impregnated cables, only
used for DC applications, has been retained
3.3.6 Operation and Maintenance by established cable suppliers, while other
Requirements for Cable Systems suppliers without MI cable manufacturing
capabilities concentrate on XLPE insulations for
Modern cable systems are often installed with DC. Established suppliers of MI cables can also
real-time monitoring systems, which help to provide XLPE DC cables. A Korean cable supplier
ensure that they are operated within their thermal completed a new submarine cable factory in
and electrical limits. For underground cables, 2009, capable of manufacturing both MI for DC
DC jacket tests are required between three and submarine cables, and XLPE for both AC and DC
five years, to ensure that metal sheaths do not submarine cables.
corrode, which could allow water ingress and
premature insulation failure. Otherwise, only Some established suppliers are considering
annual inspections of cable transition stations expanding MI cable capacity and developing
and sheath bonding connection points are paper-polypropylene laminate insulations for DC
required, except for regular patrols for possible applications up to 600 kV. It is claimed that such
external aggression by third parties. For insulations allow 80 °C operating temperatures
submarine cables, DC jacket tests are usually compared to 55 °C for conventional kraft paper
impractical. Underwater inspections should be insulations. This allows a substantial increase in
carried out where depth of cable burial could transmission capacity for the same conductor, or
change. Annual inspections of transition stations alternatively a smaller conductor and cable for the
are required. More extensive maintenance same transmission capacity.
requirements are needed for the reactive
compensation stations, which are mandatory for Production of XLPE cables for AC and DC
the long AC cable systems for this application. applications is increasing, with over 40 companies
It is important that emergency response plans capable of supplying AC XLPE cables up to the
be developed and spare cable materials are well 220 kV level. New joint ventures are being formed
maintained, so that submarine cable repairs can between the established cable manufacturers and
be carried out quickly. those in some fast-growing developing countries,
which are now capable of manufacturing 500
kV AC XLPE cables. There are at least eight cable
suppliers claiming they have the capability to
manufacture 500 kV AC XLPE cables. There are now
at least three suppliers of 500 kV DC MI cable.

Report of the Concepts Review Panel - 59


Development work with extruded insulations is reduce insulation thickness. DC cable systems
focusing on increasing extrusion lengths. Refined have been developed using cross-linked
insulating compounds used for transmission polyethylene insulation with nano-composite
applications, when used with modern extrusion fillers to improve performance during rapid
lines, are capable of extruding about 70 tonnes of polarity reversals, so they can be used with LCC
insulation before dies require cleaning. Extrusion converters.
lengths obviously depend on conductor diameter
and insulation thickness. However at the 230-500 Efforts are ongoing to provide alternate metal
kV level, extrusion lengths in the five to seven sheathing materials, such as copper, to take the
km range are now typical. Maximizing extrusion place of lead alloys for submarine cables. Benefits
lengths creates many manufacturing efficiencies are less weight, higher fatigue resistance, better
and is especially important for long submarine worker safety in factories and perhaps lower
cables, which require extrusion lengths to be environmental impact.
joined in the factory.
Laying depths for 500 kV DC submarine cables
Conventional manufacturing of XLPE cables have now reached 1620 m. Improvements in
causes gaseous byproducts of the cross-linking mechanical designs to accommodate such high
process to remain trapped in the cured insulation. laying tensions lead to design refinements for
This affects performance of insulation and shallower water applications.
accessories, and has worker safety implications,
since some of the gasses such as methane and Real-time monitoring systems are being applied
ethane evolve over time and are flammable. To to address preventive maintenance needs and
overcome the problems, high voltage cables to detect abnormal cable conditions before
need to be placed into large ovens or tanks failures can occur. For example, continuous real-
and heated to approximately 70 °C for several time partial discharge monitoring systems have
weeks to reduce the byproduct concentrations been applied to some strategic cable circuits.
to within safe limits. This has obvious impacts Real-time monitoring of cable sheath currents
on manufacturing efficiency. Efforts are ongoing could reduce the need for performing periodic
to reduce the degassing burden by improving cable jacket tests. Integrated distributed fibre-
traditional compounds or developing new ones. optic temperature sensing and dynamic rating
systems can maximize transmission capacity
Some companies are developing new extruded without risk of irreversible thermal damage, as
insulations that eliminate the need for the well as potentially identify submarine cables with
vulcanizing process altogether. Research is reduced burial depth since initial installation.
being conducted on alternative extruded
insulation systems. For example, polypropylene
insulation has excellent electrical and mechanical
3.5 System Impacts Considering Long
characteristics, but has been difficult to extrude.
Cables
Some manufacturers are overcoming these
problems, with apparent benefits from longer
When considering options for a new north-
extrusion lengths, less energy consumption during
south power corridor to transmit power from
manufacturing, lower equipment complexity,
new generation in the north to markets in
reduced factory footprint, and so on.
the south, both AC and DC options must be
considered. If cables are to be employed for part
Nano-composite extruded insulations are also
of the corridor to meet social and environmental
being developed for AC systems, promising to
restrictions, DC and AC have different electrical

60 - Manitoba Hydro
requirements. With a DC transmission option, • A long cable connected to a generating
the compensation requirements needed to station can also be an application for
transmit AC power can be eliminated, reducing compensation. The generator capability
the costs of the transmission line. In addition, curve has limitations for excessive
fewer cables are needed since DC requires only absorption of reactive power due to either
two paths, where an AC option requires three. generator load angle stability or end
winding heating in the generator stator.
For the purposes of illustrative analysis, the AC
option is explored since operational issues on As the timing for a future north-south line
the Manitoba Hydro grid dictate that a stronger dictates, preliminary planning studies for options
southern AC network will be required in the future using AC cables would examine the following:
[19]. AC cables have similarities with capacitors in
• The types of cable to use
the sense that there are two metallic surfaces with
a dielectric material in between, which is the cable • Effects of parallel transmission paths
insulation. This means that the cable will produce • Shunt compensation schemes
reactive power in the same way as a capacitor. The
capacitive (or charging) current will increase with • Phase transposition and cross-bonding
cable length and voltage. The following reasons • Voltage stability and transient stability
exist for compensating this capacitance produced limits
by the cable:
• Effects of harmonic frequencies on the
• The critical cable length is reached where cable connected system
the cable’s full ampacity in the sending
end is taken up by the capacitive current A power system with long cables will have
and hence no active or real (watts) power characteristics that differ from a system
transport is possible. One way to reduce of overhead lines along the same route.
this problem is to compensate along the Conceptually, the purpose of an overhead
cable route. The Ferranti effect, which is transmission line is the same as an underground
the well-known phenomena associated or submarine cable – transport energy in the form
with transmission lines where open end of electricity from one end to the other. However,
voltage can rise above safe limits, also the physics of moving electricity with cables
dictates the need for compensation. has some distinct differences from overhead
transmission lines. Specifically:
• With high capacitance there can be too
large a voltage step change when the cable • AC cables are not just simple three wire
is connected or disconnected. Typically systems. They form a complex system
a ±3% voltage change is acceptable but of six or more conductors, thus adding
this is dependent on the grid code for complexities to the mathematical
the specific grid. The size of the change modelling.
is dependent on the reactive power • Level of shunt compensation required is
produced and the strength of the grid much greater than overhead lines.
point, which is usually called the Short
Circuit Capacity. • Lower system resonance frequency can
lead to risk of poor voltage quality or mis-
• The grid code may impose requirements operation due to harmonic injection.
on the range of power factor for delivery
to a certain grid point.

Report of the Concepts Review Panel - 61


• Lower series reactance and a higher X/R Cable ampacity or current carrying capacity
ratio can impact protection systems. is the measure of how much current a cable
can carry before the thermal limit is exceeded.
• Cables require special considerations for This measure depends on many factors such
bonding of cable sheaths and armour. as ambient temperature, materials used in the
cable manufacture, installation methods and the
• For transients, the surge impedance
environment in which it is installed (i.e. in water
and traveling wave velocities are both
on the lake bottom, in water buried beneath lake
lower and dependent on the number of
bottom, on land buried with thermal backfills,
layers. This has impact on carrier wave
or air).
communications systems and travelling
wave fault locating technologies.
Cable ampacity must be carefully calculated
considering the location and installation so
Some important issues must be considered and
that conductor temperature does not rise above
studied to successfully operate a long hybrid
a certain limit where cable damage would
transmission line and cable system. The items
occur, reducing the life expectancy of the cable
below are discussed in Appendix 3.
or destroying the insulation integrity. Cables
• No load energization generally have a design limit of 90 °C for AC
XLPE and 70 to 90 °C for DC XLPE; 55 °C for
• Voltage control during load rejection MI cables with kraft paper insulation; and 85 °C
• Switching transients and transient for SCFF AC or DC cables. They are specified to
recovery voltage operate at some accepted level not exceeding these
limits under normal conditions.
• Series resonances and ferro-resonance
analysis Compensation calculations, together with
ampacity calculations based on assumed
• Parallel cable circuit energization
installation conditions, allow the selection of
• Cable impact on system voltage and cable sizes used to determine cable performance.
transient stability See Appendix 3 for a complete discussion.

• Zero miss phenomena


3.7 Compensation of Long AC Cables
• Generator self-excitation

• Single pole re-closing and blocked re- Long AC cables require compensation in the
closing for cable faults form of shunt reactors to eliminate or reduce the
capacitive effect of the cable, which is produced
due to the time-varying nature of alternating
3.6 Thermal Properties and Ampacity of current (AC) or voltage. Cable compensation is
Cables necessary to minimize cable losses in transmitting
power through a long cable, and to control the
Thermal limit (ampacity) is a very important voltage which could otherwise exceed equipment
cable parameter for grid operations. With ratings.
overhead lines, the thermal limit is mainly
dependent on ambient air temperatures and
wind speed.

62 - Manitoba Hydro
There is a critical cable length that when reached,
the cable’s full ampacity at the sending end is
consumed by the capacitive current; thus no
active real power transport is possible. Either
a larger cable with higher ampacity must be
installed, or the capacitive current must be
reduced by installing reactive compensation
devices at the ends of the cables, and if required,
along the cable route.

The calculations to determine the amount of


cable compensation are complex and depend on
many factors. A treatment of this is contained in
Appendix 3 for reference.

Preliminary calculations indicate that reactive


compensation of 500 MVAr 3-phase per circuit
is required at each end of a 50 to 70 km cable
segment, in order to transmit 1000 MW at
500 kV, based on routing concepts depicted in
Section 2 and assumed cable ampacities. For
example, a 100 to 140 km cable length would
need the intermediate point, at approximately
half the total route length, to have both
intermediate cable ends terminated and
connected to 1000 MVArs of compensation, while
each overall end point would be terminated and
connected to 500 MVArs of compensation.

The compensation reactors create heat due to


reactive current flowing through their windings
to ground and due to eddy current and hysteresis
losses in their steel cores. 500 kV reactors would
also be filled with insulating fluid, so would need
to be installed with fluid containment systems
in case of leakage. They can also radiate noise so
sound barriers are often necessary to keep levels
within tolerable limits. Finally, they are very
large and heavy, which presents challenges for
transporting to remote sites, particularly for
Route 6.

For DC cable systems, no compensation devices


are necessary, although the converter systems are
technically complex, expensive and also create
losses.

Report of the Concepts Review Panel - 63


64 - Manitoba Hydro
4 Submarine Cable Transportation by Water and Land

This section deals with the transportation of Figure 21: C/S Guilio Verne (source: Cabletricity)
submarine cables from the manufacturing facility
by ship to a port in Canada where they would be
transferred to a rail transportation system. At the
destination the cables would subsequently be off-
loaded at Lake Winnipeg to a specially built barge
complete with a cable laying system.

4.1 Transporting long lengths of 500 kV AC


or DC submarine cable by ship

All cable suppliers advise that 500 kV DC MI


cables should not be coiled for transportation
and laying. Some also maintain that extruded
insulation cables should not be coiled.
Accordingly, for purposes of this report it is
assumed that no cable coiling is allowed for any
cable types as there is risk of internal insulation
damage due to the high torsional forces that can Figure 22: C/S Skagerrak (source: Cabletricity)
result. That means that all transportation by ship
and barge must use spooling turntable systems to
avoid coiling.

There are many large, modern cable laying vessels


designed for telecom submarine cables. However,
geometries are not suitable for large power cables
and they store cables in internal ‘tanks’ which
would require coiling.

There are presently two large dedicated ocean-


going cable laying ships equipped with turntables,
suitable for laying power submarine cables, as
shown in Figure 21 and Figure 22. Each has a
turntable capacity of about 7,000 tonnes. But both A smaller power cable laying ship, shown in
are too large to pass through the locks leading to Figure 23, with about 4,000 tonne turntable
Lake Superior (Welland Canal maximum vessel capacity has laid 230 kV submarine cables in
dimensions: Length = 222.5 m, Breadth = 23.8 m, Lake Ontario and could pass through the locks to
Draft = 8.0 m, Height above water = 35.5 m). a port at Thunder Bay.

Report of the Concepts Review Panel - 65


Figure 23: C/S Team Oman (source: www. 4.2 Transporting long lengths of
globalmarinesystemsenergy.com submarine cable via rail

Under its Terms of Reference, the Panel was


asked to examine concepts on how long lengths
of submarine cable could be transported by rail
from a Canadian seaport. Specifically, one of the
Panel’s goals was to examine the general concepts
by which submarine cable could be transported
in lengths of up to 50 km from a port location to
its destination at Lake Winnipeg. Since the cable
for proposed submarine routes would be required
to span distances ranging from 52 to 287 km,
transporting long lengths was considered to be
superior to the traditional way of transporting
submarine cable on reels in lengths up to
1800 m.

Long lengths of high voltage submarine power


cables greater than 10 km have never been
transported by train and none of the cable
manufacturers have had any experience with
such transportation methods. To the Panel’s
There is also a growing number of general knowledge, nowhere in the world is there an
purpose construction vessels developed for installation of long lengths (> 10 km) of high
the offshore oil and gas industry, as well as the voltage submarine cable in a landlocked lake.
offshore wind turbine generator industry. Some However, there are plans for a 47 km long
can be fitted with turntables or carousels of about submarine cable in Lake Como, Italy, as part of
7,000 tonne capacity and would be suitable for the 150 km long 400 kV DC GreenConnector
delivering 100 km lengths of submarine cable to Project between Italy and Switzerland, as well as
Montreal, Prince Rupert or Vancouver without for a 320 kV DC installation in Lake Champlain,
coiling. An example is shown in Figure 24. as part of the Champlain-Hudson interconnector
project between Quebec and New York.

Figure 24: North Ocean 102 (Source: www.oceanteam.nl)


During the Panel’s deliberations, four different
concepts or proposals to transport long lengths
of submarine cable by rail were studied. Detailed
descriptions of all the proposals are included in
Appendix 4.

After a thorough review of each concept, Proposal


1 was considered by the Panel to have the highest
potential for success, primarily because no part
of the operation would coil or apply a twist to
cables, which could be particularly damaging to
the tightly applied insulating tapes of MI cables
and possibly to XLPE cables as well.

66 - Manitoba Hydro
Figure 25: Looped cables on train (Proposal 1), four cars are shown for simplicity

Proposal 1 presents a concept on how long this case. Both the Montreal and Powerview-Pine
sections of 500 MW 500 kV DC submarine Falls locations meet this requirement.
cable with either MI or XLPE insulation might
be transported by train. MI cable would be When the ship with cable arrives in Montreal,
approximately 130 mm (five inches) in diameter the cable would be immediately transferred
with single-wire armour, have a supported onto a turntable positioned on or near the dock
bending diameter of approximately three metres and adjacent to a railway track. It is necessary
(nine feet, 10 inches) and weigh about 45 kg/m. to quickly unload the ship to avoid expensive
500 kV AC XLPE cable would be about 150 mm port costs estimated at about $200,000 per day
in diameter and weigh approximately 65 kg/m. for a cable ship. The turntable would be at the
This procedure could be used for both AC and midpoint of the required 1.2 km of track. From
DC cables, but this example continues with MI the turntable, the end of the cable would be
cable to illustrate the concept. lifted to the top of a 10-metre gantry, propelled
by a “caterpillar” (a special traction machine for
Cable could be loaded on the unit train at the this purpose). The gantry would overhang the
port of Montreal, for example, and unloaded at railway track and from there the cable would be
Powerview-Pine Falls, where the track is 300 m lowered onto the floor of the first flatcar. The
from a bay on the Winnipeg River that flows into train would then advance along the track and
Lake Winnipeg. The total distance between these the cable would continue to be released and laid
two locations is about 2500 km. on all following cars until the end of the train.

In this proposal it would take 29 flatcars to When the cable reaches the end of the last car,
transport 50 km of cable. A 29 flatcar train is a steel rim, three metres in diameter would be
almost 600 m in length. The procedure to load or fitted on the cable and pressed up to the vertical
unload the cable requires a track at the dockside length of cable extending from the top of the
to be twice the length of the train, or 1.2 km in gantry. At this point the train would back up,

Report of the Concepts Review Panel - 67


with the result that the cable would be draped are required to address congestion or delay
over the rim and then descend to the floor to contingencies in the supply chain and to meet
form the second row and continue to be laid on schedules.
the flatcars as they proceed down the track.
Modified end cars, cable rims, tie downs and
On reaching the end car, the cable would once fastenings would need to be engineered for the
again be fitted with a steel rim, and with the same stress and forces of moving the train and cable.
procedure as described above, it would double The systems to load and unload the cable onto
back to form the third row. In this manner, with the train would also have to be engineered for this
the train going back and forth, the entire 50 novel concept. System testing would have to be
km of cable could be loaded in about a week. conducted to verify that the procedures outlined
A second section of cable could be hauled by in this concept would work in practice, and would
loading another set of cars with 50 km cable. In be acceptable to the cable manufacturer, railway
this case the total train would consist of 58 cars company and insurance underwriters.
and would transport 100 km of cable.
In total a cable would be handled six times before
On each car there would be 22 rows of cable and the cable is laid. In ocean waters cables are usually
it would be necessary to have four layers of cable handled twice.
extending along the length of the train. The end
As stated previously, four different concepts
cars would contain the loops of cable with steel
to transport the cable were considered. In its
rims supporting each loop end. Each 22-row layer
deliberations, the Panel decided that Proposal
would result in 11 loops at each end of the train.
1 had the highest merit for further research and
With four layers of cable there would be four sets
development, and potential implementation.
of rim-held loops positioned about 4.5 m from
Although apparently superior to the others, all
each other on the end cars. See Figure 25.
are presented in Appendix 4 for information.
Proposals 3 and 4 require that the cables be
Flatcars at each end of the train would be 28.6 m
coiled, whereas Proposals 1 and 2 do not. With
long (94 ft), and the intervening cars would have
advances in cable technology, especially with
a length of 19.5 m (64 ft). The end cars would
respect to greater tolerance of torsional twist,
carry approximately 81 tonnes of cable and the
Proposals 3 and 4, or additional proposals, may
shorter cars would carry about 77 tonnes.
be developed in future.
Unloading the cable would take place at
Powerview-Pine Falls, where the railway track is
about 300 m from a bay where a barge would be
moored. A special gantry system would remove
the cable from the train in a manner similar to
the way in which the cable was loaded, with
the train moving 600 m forward and 600 m
back. During the unloading process, the cable
would be directed along a conveyer system of
rollers leading to the dock and onto a turntable
on a barge. The barge would then be towed to
Lake Winnipeg where the laying of the cable
would take place. Cable storage facilities with
two additional turntables at the rail siding

68 - Manitoba Hydro
4.3 Transportation of short lengths of Figure 26: Equipment to move 500kV AC cable reels in the
submarine or underground cable factory (Photo from IEEE ICC 2007, Nexans France)

This investigation began with suggestions to


install submarine cables in Lake Winnipeg as an
alternative to overhead line construction. It was
postulated that long continuous submarine cables
could be successfully transported using multiple
rail cars, as described previously. Although
investigations so far indicate feasibility, the entire
procedure needs to be researched by mechanical
engineers familiar with power cable engineering,
as well as railway professional engineers who
could evaluate the possible negative effects on
train dynamics and stability. This proposal must
also be reviewed by insurance underwriters to
determine the risk acceptance. There must be a
high degree of confidence that the relatively stiff
group of cables spanning several rail cars would Figure 27: Lifting cable reels at site (source: www.neptunerts.
not cause any issues during transportation. com)

An alternative to the transportation and use of


long lengths of cable could be shipping shorter
lengths of cable on large reels for use in both
underground and submarine applications,
recognizing that hundreds of field installed joints
would be necessary. The length limits for cables
on reels must also consider the whole supply
chain from manufacturing to site, as follows.

• Moving cable reels around cable factory


(Figure 26)

• Fitting cable reels into degassing ovens or


tanks at factory (XLPE cables).

• Moving cables into high voltage testing


lab for routine tests on each shipping
length at factory.

• Lifting reels onto trucks, rail cars and ships


(Figure 27)

• Transportation to site (underpass


clearances, bridge loadings, road width
and bearing capacity, etc.).

• Capacity of reel carriers at site ( Figure 28)

Report of the Concepts Review Panel - 69


For rail transport, the maximum allowable reel Figure 28: Reel carrier at site (Photo from IEEE ICC Spring
weight for typical flat cars would be about 100 2008, Prysmian)
tonnes. Deducting an allowance for the empty
reel weight would leave about 85 net tonnes for
cable. The maximum cable length per reel can be
calculated for the assumed 500 kV AC and DC
submarine cables, as follows.

The outside dimensions of a cable reel are limited


by the flange diameter and the axial reel length.
Maximum flange diameter is usually less than 4.2
m. This allows an additional 0.05 m for protective
lagging or battens over the reel circumference. The
combined outside diameter of 4.3 m is a typical
maximum width for North American rail cars
and road vehicles. The reel axial length is usually
governed by the maximum allowable gross
reel weight when loaded with cable. The other
critical dimension is the barrel diameter, which is
determined by the minimum bending diameter of
the cable.

Applying these limits provides the following reel


dimensions.

Table 15: Reel dimensions for maximum submarine cable length for rail transport (approximate)

Minimum Bending Maximum


Cable External Reel Dimensions
Cable weight Diameter (24 x cable Cable Length
Cable Description Diameter Barrel x Flange x
(kg/m) diameter) per Reel
(m) Axial Length (m)
(m) (m)

500 kV AC XLPE 1600


65 0.160 3.6 1200 3.6 x 4.2 x 8.0
mm2

500 kV DC MI 1000
44 0.120 2.8 1800 2.8 x 4.2 x 3.5
mm2

70 - Manitoba Hydro
Once the cable reels are transported to With this procedure the number of joints in
Powerview-Pine Falls near the dock where the Routes 4, 5 and 6 would be as follows:
barge would be moored, the jointing of these
short lengths of cable could proceed – AC lengths • Route 4 – 534 km/1.8 km = 297 joints
being 1.2 km and DC 1.8 km. A large jointing • Route 5 – 861 km/1.8 km = 478 joints
house would be constructed at this location,
• Route 6 – 960 km/ 1.2 km = 800 joints
large enough to contain three jointing assembly
lines. Outside this structure there would be
The time that it would take to install the cable in
three approximately 20 km capacity turntables
Routes 4, 5 and 6 would be as follows (see Table
dedicated to each of the assembly lines. Nearby,
17):
there would also be a large 50 km storage
turntable. • Route 4 – 3 summers

The jointing procedure would be carried out by • Route 5 – 5 summers


three jointing crews, working simultaneously, • Route 6 – 6 summers
whereby each crew would complete the joints
for one-third of a 50 km length of cable. In
the course of this procedure, the ensuing three Figure 29: Transport of spare 500 kV DC submarine cable
lengths of cable would be loaded onto the three (Photo from IEEE ICC Mar 21-24 2010, Prysmian)
separate small turntables. Afterwards, there would
be two alternatives. These three lengths could be
transferred directly to the barge where they could
be jointed in the barge jointing house and the
completed 50 km length would be laid on the
barge turntable. Alternatively, if the barge were
not available, the three approximately 17 km
lengths could be transferred as separate pieces
onto the storage turntable. Later they would be
transferred onto the barge for jointing and storage
on the barge turntable.

In the case of DC cable, a 50 km length would


have 27 joints, i.e., 50/1.8 = 28 pieces (27 joints).
At five days to construct each joint, the time to There are several examples of long underground
assemble 50 km would be 27 x 5= 135/3 equals cable circuits joined together from shorter cables
45 days or approximately seven weeks. shipped on reels, as shown in Table 16.
In the case of AC cable, a 50 km length would
have 41 joints, i.e., 50/1.2= 42 pieces or 41 joints.
At five days to construct each joint, the time to
assemble 50 km would be 41 x 5 = 205/3 equals
68 days or 10 weeks (2 ½ months).

Report of the Concepts Review Panel - 71


Table 16: Examples of long 300-500 kV underground cable applications, shipped on reels and joined in the field
(completed and planned)

No. of Longest Total


Route
Voltage Cable Shipping Reel Cable Number
Application Year Length
kV Insulation Lengths per Length Length of Joints
(km)
Application (m) (km)

Tokyo ‘Shin-Toyosu’ (2
2000 500 AC XLPE N/A 1800 40 2 x 3 x 40 N/A
circuits)

Greece-Italy (land SCFF (in


2002 400 DC N/A N/A 43 43 N/A
segment) Italy)

Neptune (New Jersey


– Long Island) (land 2007 500 DC MI 24 975 22.5 22.5 23
segment)

DolWin1 2012-
320 DC XLPE N/A N/A 90 2 x 90 N/A
(land segment) 13

Skagerrak IV (land
2014 500 DC MI N/A N/A 90 90 N/A
segment)

Maximum underground cable lengths can also be calculated using the same methods as used for
submarine cables, but with a net 65 tonne limit due to road weight restrictions, not considering
special conditions along final right-of-way.

Reel dimensions can be determined using the same methods as for submarine cables.

Table 17: Reel dimensions for maximum underground cable length for truck transport

Cable Description Cable Cable External Minimum Bending Maximum Cable Reel Dimensions
weight Diameter Diameter (24 x cable Length per Reel Barrel x Flange x
(kg/m) (m) diameter) (m) Axial Length
(m) (m)

500 kV AC XLPE 1400 mm2 25 0.131 3.1 1800 3.1 x 4.2 x 5.5
copper

500 kV DC XLPE 1000 mm2 11 0.105 2.5 4000 2.5 x 4.2 x 6.0
aluminum

Compared to the submarine cable alternatives, into prepared trenches or use of many serial
the above four kilometre lengths for DC cables powered rollers and cable pushers to assist
would require substantially fewer joints and they end pulling machines. Results of cable system
could be of the pre-molded type, leading to faster reliability calculations summarized in Table
installation times for underground applications. 13 indicate that the extra effort to ship four
For Routes 2 and 3 approximately 131 and 197 kilometre lengths of underground DC XLPE
joints would be required respectively. Installing cables may not provide a significant increase in
four kilometre lengths of underground cables reliability, although there could be savings in
would require novel methods, including use of jointing costs.
travelling reel carriers to side-load cables directly

72 - Manitoba Hydro
5 Cable Installation When fully loaded, such a barge would have a
draft of about 2.5 m. The boat builder could
This section describes both submarine and land build such a barge as a modular structure, with
cable installations, the equipment required, several possibilities, e.g., a 25 x 25 m section in
schedule and processes. the middle, flanked by 20 x 25 m sections at each
end, or three 15 x 25 m sections flanked by 10 x
25 m sections. These sections would be bolted
5.1 Submarine Cable Installation and welded together to compose a single rigid
The laying of submarine cable in Lake Winnipeg unit, with a solid deck on the top. The sections
would be conducted from a barge, with its base would also be suitably reinforced to carry the
at a dock in a bay of the Winnipeg River at weight of the turntable and cable. The exact
Powerview-Pine Falls – only a few kilometres dimensions and structure of the barge would
from the lake. Three potential submarine cable have to be determined and designed by a naval
routes have been identified for illustrative architect.
purposes.
To tow a large barge of this size as well as the
The procedure for laying cable underwater is necessity to keep the barge stationary in rough
complex. A cable laying vessel, a barge in this weather during the jointing operation may
instance, is the heart of a cable laying operation. require both a dynamic positioning (DP) system
Hence it is useful to provide a description of the and one or more tugboats. A DP system by itself
barge and its wide variety of equipment. The might be sufficient to propel the barge and keep it
procedure for jointing and burying the cable stable, together with anchors, during the jointing
in a trench on the lake floor is described to aid operation, but the cable installation contractor
understanding. may decide to use tugboats as well. This may be
for purposes of safety and the necessity to move
the barge as quickly as possible from the loading
5.1.1 Cable Laying Barge dock to the cable laying area, with the final and
furthest destination being about 370 km.
The cable barge is a specially equipped marine
vessel for the express purpose of delivery Central to what would be required on the barge
and installing submarine cable on site. The is a motorized 20 m diameter steel turntable,
cable turntable, jointing equipment, gantries, weighing about 200 tonnes, which would be
navigation systems, power plant and thrusters, located at the midpoint of the barge. It must be
wheel house, living quarters and cranes, are all capable of transporting 50 km of cable, where the
contained on the barge. DC cable would weigh approximately 2,250 tonnes
and an AC cable approximately 2,500 tonnes.
A local boat building company at Lake Winnipeg
could be capable of building such a barge suitable A specially designed “jointing house,” measuring
for laying cable, with expert advice from a cable about 4 x 17 m [1], would need to be constructed
laying company.4 The parameters of the barge are along one side of the barge at the stern end.
calculated below as part of this discussion.

The total weight to be transported, including the 4 A naval architect has provided an estimate of $10 million for
the barge, including some of its basic equipment, but
weight of the cable, the barge, the turntable, and
excluding a dynamic positioning system and thrusters.
all the associated equipment, would be about
4,000 tonnes. The estimated dimensions for a 5 A naval architect at Transport Canada considered this to be
barge to carry this weight are 65 x 25 x 4 metres.5 reasonable, but a full study by a naval architect would be
required for any official approval.

Report of the Concepts Review Panel - 73


It would have to be constructed in such a manner Together with a DP system, it is usual for cable
that a narrow section of the entire structure on laying barges to employ four to eight anchors to
one side could be opened to allow the jointed maintain position. During the laying operation,
cable to be removed from the inside of the the DP system with its thrusters would maintain
jointing house and transferred to the laying the barge’s propulsion and position. However,
equipment and then over the stern laying tugboats may also be used to deploy anchors for
wheel into the water. An alternative would be stability during jointing operations.
to construct a “splitable” structure so that the
upper part could be tilted to one side to allow the A bridge and living quarters for the crew would
jointed cable to be removed. need to be constructed including sleeping berths,
a galley and common area. Alternatively they
The jointing house would have to be equipped could be provided on a separate barge. Storage
with an electric power supply, air-conditioning, of supplies, extra fuel and additional equipment
air-drying facilities and hoisting and cable could be accommodated in the hold of the barge.
handling equipment, as well as other equipment A helicopter landing pad may be required.
required for the jointing operation.

As on a dedicated cable laying vessel, the barge 5.1.2 Submarine Cable Trenching
must be equipped with a variety of equipment,
Sometimes the laying of the cable and its
some of it quite bulky. A large wheel or chute is
subsequent burial in a trench are conducted
required at the stern of the barge for deploying
simultaneously from the cable laying vessel. An
cable into the lake. Cable tensioners or linear
alternative would be to bury cables as separate
cable engines (caterpillars) are necessary for the
operations utilizing different vessels, as described
movement of cable on board and for applying
below. In this case, especially because the cable
tension during laying or temporary recovery.
is being laid from a barge with limited space, it
appears advisable to conduct these as separate
Each cable laying operation is different so the
operations.
cable manufacturer and installation contractor
would have to determine the required support
A small barge or other support vessel is therefore
equipment for cable laying.
assumed to be used to operate a cable trenching
machine. For a Lake Winnipeg application in
Of critical importance is a dynamic positioning
bottom sediments, trenching machines would
(DP) system to enable the barge to move along
be relatively small, both in size and weight, e.g.,
a pre-determined course or to remain in a
Nexans Capjet 50 measures 8 x 4 x 2.5 m and
stationary position. This would utilize a GPS-
weighs 12.5 tonnes. The exact size and nature of
supported navigation system. The system would
the support vessel would have to be determined
involve the installation of azimuth thrusters at
by the cable laying contractor. As an alternative, it
each corner of the barge. Four self-contained
may be possible to use a cable trenching machine
diesel-hydraulic power units would be positioned
in conjunction with a new vessel, such as the
on deck at each corner, and a DP navigation
Pumpemaron, specially designed to operate the
control room would be installed at the top of
Nexan’s Capjet. This vessel has a power unit
the barge’s bridge. A video of the assembly of
which operates an engine for its own propulsion,
such a system can be viewed at reference [10].
and for the water pumps to the Capjet. From this
Within certain limits, a DP system should be able
vessel the Capjet is operated by remote control
to maintain a barge’s position even when wind,
and would not need any diver-based operation.
waves or currents threaten to move it off course.

74 - Manitoba Hydro
Figure 30: Nexans Capjet (source: Nexans Norway, Marine Installation Department)

Its first successful operation took place in the When lowered into the water, the Capjet machine
spring of 2010 with the burial of the Valhall cable is connected by an umbilical cable to the surface
(292 km) in the North Sea. vessel in order to provide power and data
communication. It carries high-pressure water
Nexans Capjet is one example of an advanced pumps to create large water flows at high pressure,
form of cable burial equipment that uses the jetting swords, cable tracking equipment, process
water-jetting principle for both trenching and monitoring sensors, positioning systems and
propulsion. Unlike other systems that employ powerful lights and cameras. The machine is
heavy equipment which could damage the cable, neutrally buoyant in water but can be ballasted
no force is applied to the cable minimizing the during the trenching operation. It can create a
likelihood of damage. Also, the machine can start narrow trench to a depth of one to three metres,
and stop at any point along the route. depending on the need and the type of sediment.

Report of the Concepts Review Panel - 75


The machine would be lowered to the lake Figure 32: Hydro-Plow burial machine for simultaneous laying
bottom where it would straddle the already laid and burial (source: www.neptunerts.com, Prysmian)
cable. A narrow projection or “sword” carrying a
row of water nozzles would be pushed alongside
the cable into the lake sediment. Water at
extreme high pressure shoots from the nozzles
fluidizing the sand, silt, mud and clay as the unit
moves along the cable. The cable would sink into
the slurry by gravity and over time, the slurry
would re-solidify.

With excellent sediment conditions along


the central part of Lake Winnipeg, the Capjet
machine should be able to bury the cable in a
trench about a metre deep at a faster rate than the
average of 100 to 200 m per hour,6 so a burial rate
of 1.5 to 2 km per day might be possible.
A video of the Capjet machine in simulated Another alternative machine for very deep burial
operation can be viewed at reference [11]. is the Sumitomo HydroJet which was used for the
There is a wide variety of equipment available for 500 kV DC Kii Channel cables between Honshu
burying power cables, and alternative solutions and Shikoku (Figure 33).
are shown in Figure 31 and Figure 32.

Figure 31: Light duty sled type cable burial system (source: Figure 33: HydroJet Machine (source: Sumitomo Electric USA)
Cabletricity)

6 Information provided by Georg Balog, retired Senior Engineer


from Nexans Norway.

76 - Manitoba Hydro
5.1.3 Cable Jointing Operation 7 specialized equipment would include welding
materials and apparatus for MI cables, a semi-
In only one part of the lake is it possible to lay a automatic lapping machine for the application
length of cable without joints – the 50 km section of insulation tapes, equipment to have the joints
between Traverse Bay and Riverton. Elsewhere, the vacuum-dried and a semi-automatic armouring
routes are too long for the length of cable that can machine.
be transported, and therefore these shorter pieces
must be jointed or connected together. Rigid joints cannot be used for MI DC cable,
but for Lake Winnipeg they could be used for
In these areas, after the first section of cable is cable with extruded insulation and for AC
laid, the end of the cable would be carefully cables. Hence, if XLPE AC cables were to be
capped with a cable seal equipped with a pulling installed, steel casing tubes would be required.
eye and hooking arrangement to which a strong The following descriptions are for flexible joints
wire would be attached. The cable would then applied to MI DC cables.
be lowered to the lake bottom with a marking
buoy attached. Later, when the barge arrives with Jointing is a highly specialized procedure that
another section of cable, the cable in the water requires a team of highly skilled technicians. It
would be pulled onboard over the laying wheel would take approximately five days to make each
and into the jointing house. The end of the cable joint on the cable laying vessel. Certified jointers
on the turntable would be pulled into the jointing for 500 kV cables are scarce and it may not be
house from the opposite entrance where the two possible to find any in North America. Therefore
cables would then be joined. it may be necessary to bring skilled workers from
Europe or Asia.
The newly-joined cable would be removed from
the jointing house either through the opening of Before the onset of a jointing operation, there
a slot along the side of the house or by raising the must be some assurance of reasonable weather
upper part of the house to allow the cable to be conditions for several days. However, Lake
removed. If the joint is a flexible joint, the cable Winnipeg is notorious for sudden storms,
could be transferred through the ordinary laying 8
despite good weather forecasts. Hence, weather
equipment of the barge and passed over the stern may prove to be a hazard, especially during
wheel into the water. The cable would need to be the jointing sessions. Heavy weather imposes
kept under suitable tension in order to preserve a risk for the jointing crew and the cable. The
the joint from undue bending at the touchdown greatest danger would occur if a severe storm
point on the lake bottom. should cause the cable tensioners to slip or
the securing devices to break and the cable
If the joint design is rigid, it could not be pulled becomes unfastened in the jointing room.
through the ordinary on-barge cable route and Once the jointing process is started it cannot be
over the stern wheel. With a rigid joint, the cable interrupted, so the cable would have to be cut
would have to be carefully lifted with cranes and and the process restarted, resulting in lost time
winches to deploy it into cable laying machinery. and money.
This would be a complicated procedure since
great care must be taken to avoid sharp bends of 7 In this section, reference has been made to sections of
the cable near the rigid joint area, and equal care Thomas Worzyk, Submarine Power Cables, Berlin: Springer,
must be exercised in laying it on the lake bottom. 2009 [1]

In addition to what has already been mentioned 8 Information provided by Captain Curtis Grimolfson, an
to be provided in the jointing house, other experienced fisherman, operator of tugboats, and captain
on cruise ships on Lake Winnipeg and the Red River.

Report of the Concepts Review Panel - 77


The procedure for making a flexible joint is Figure 34: Submarine MI Cable Flexible Joint
essentially the same as occurs in the production (Source: Cabletricity)
of a factory joint. This is a time-
consuming and exacting task that
requires highly trained personnel.
The joints must have the same
mechanical and electrical properties
as the cable itself.

The jointing process begins with


welding the conductors of the two
cable ends. Stranded conductors are
welded either with a single welding
seam across the entire diameter,
or wire-by-wire. Great skill must
be exercised to avoid defects such
as discontinuities, cracks, porosity,
incomplete fusion or penetration
and nonmetallic inclusions. Ideally,
the weld quality should be checked
by X-rays. The electrical conductivity
of the weld must be sufficiently high to avoid a Before the conductor welding takes place, a lead
hotspot in the cable. sheath, in the form of a cylinder and slightly larger
than the cable, is slid over one of the cables and
The next step is to apply the insulation, normally “parked” there until it is time to install it. When
the same structure as the cable insulation. The the insulation process is completed, the lead
existing insulation on the two cable ends must sheath is pushed over the jointed area and the
be tapered to form conical surfaces. The new ends are tapered or swaged to fit tightly over the
insulation material is applied between the two insulation. The excess is trimmed and the sheath
tapered ends, and is usually thicker than the cable is soldered to the cable’s lead sheath. Next, the
insulation in order to reduce the electric stress. joint is vacuum-dried and hot-oil impregnated to
The insulation on a flexible joint has a similar achieve fully saturated paper-oil insulation. Then,
structure to that of the cable, and is comprised a protective polymetric shrink tube is applied over
of a conductor screen, the electric insulation the lead sheath and adjoining area.
and an insulation screen. The screens are made Finally, the gap between the armouring of the
from carbon-black paper tapes. The paper two cables is closed with pre-spiraled wire. The
tapes are pre-impregnated and can be applied wires are welded on one side of the joint and then
manually, but preferably with a semi-automatic twined around the joint and connected to the
lapping machine. It is critical that the joints wires on the other side where they can be welded
be manufactured in a humidity-controlled and or be connected by special screw connectors. In
temperature-controlled jointing room. the course of connecting the wires, it is necessary
to maintain the tensional forces in the armouring.
The procedure can be simplified by using a
patented semi-automatic portable armouring
machine.

78 - Manitoba Hydro
The completed flexible joint can be transferred The winch would haul in the pull wire and the
through the ordinary laying equipment and cable to its destination at the terminal. During the
passed over the stern laying wheel into the water. pull-in, the cable would be guided on a system of
rollers, either within the trench or alongside it. In
the case of the latter, the cable would be pushed
5.1.4 Cable Laying Procedure into the trench afterwards. Once in its proper
position, the cable should be anchored and as the
Long before the cable is laid, the cable routes
floatation devices are removed, it would settle on
must be precisely determined and carefully
the lake bottom. The barge could then proceed
surveyed to avoid crossing underwater
with the regular cable laying operation.
obstructions, if possible, and to ensure that
there would be no obstacles in the sediment. For At the end transition station, a somewhat different
example, over the years there have been a number procedure would be followed. The barge would
of shipwrecks on the lake, as well as lost fishing be brought as close as possible to the shore. The
gear and anchors. Given the amount of sediment remaining cable on the barge would then be
in the lake from both glacial Lake Agassiz and equipped with floatation devices. At this point the
Lake Winnipeg itself, it would be unusual to find barge would change direction and proceed a short
rocks in the sediment. distance parallel to the shore while the rest of the
cable is played out. A pull wire would be attached
A careful survey would have to be conducted to to the cable end and the floating cable would be
determine the depth and extent of ice scour and pulled ashore by a winch positioned on shore or
impact of other natural hazards, for the complete near the terminal station (see Figure 52).
cable routes. This would determine the depth
to which the cable would have to be buried in It is necessary to have properly trained personnel
various locations. operating the cable laying equipment. Various
procedures, including the speed of the barge,
It would be prudent to dig or excavate the must be synchronized, otherwise damage could
trenches at the terminal points for the onshore occur to the cable. A series of operations would
three (DC) or four (AC) lines of cable during the be involved. From the motorized turntable, the
fall before the laying operation. The trench profile cable would run over a moveable pickup arm with
must be engineered with respect to thermal cable rollers, through a cable tensioner (or a linear
properties, and the trenches would extend as far cable engine), and then over the laying wheel and
inland as necessary to reach a suitable location for finally into the water. The pickup arm has the
the terminal station. Alternately, conduits could shape of a gooseneck, and in the gap between the
be pre-installed through the littoral zone and turntable and the gooseneck, the cable could hang
cables pulled through them into land trenches loose. The slack is necessary to absorb possible
when the cable laying barge arrives. temporary speed differences between turntable
and tensioner engines. The gooseneck is highly
When all the land preparations are completed,
maneuverable, being pivotal and adjustable in
the barge with a load of cable would be towed as
height.
close as possible to the landing site and remain
anchored or maintained in place by its DP system. The cable could not be let down to the lake
On the shore, a winch would be installed with a bottom vertically because of possible looping
pull wire extending to the barge and connected to and violation of minimum bending radius limits.
the cable end. The cable could then be extended Instead, the cable would have to be positioned
over the laying wheel, and where it would enter in a well-defined catenary line from the laying
the water, floatation devices would be attached wheel to its point of contact on the lake sediment.
so it could be more easily pulled onto the shore.

Report of the Concepts Review Panel - 79


This would be done by the correct forward about 10 km per day9 , so it would take about five
movement of the barge which would cause days to lay one length of cable. Each cable joint
the cable to hit the bottom at an acceptable would take about five days as well. The barge may
angle. An inappropriate catenary line or bottom have a speed of about six knots, so it could take
tension could be corrected by a temporary extra up to two days to tow the barge from the dock at
pay-out from the turntable, or by a temporary Powerview–Pine Falls to the construction site.10
acceleration of barge speed. The bottom tension Trenching and burial of cable could be done at
is a critical factor in successful laying. a rate of about two km per day under favourable
conditions.
Variations in equipment speeds (barge,
turntable, tensioners, etc.) can cause a cable
kink, loop or damage to both cable and 5.1.5 Cable Laying Schedule
deck equipment. Hence, the necessity for an
To determine how long it would take to lay
experienced and properly trained crew. Lake
the cable at the potential submarine cable
Winnipeg’s ideal sediment conditions and
routes, it was necessary to work out a ship-train-
shallowness would facilitate cable laying
barge schedule for each. In the case of Route
operations. On the other hand, sudden storms
4, the schedule (Appendix 8) shows that, with
could prove to be a hazard for which the crew and
favourable weather and no disruptions or delays,
operators must be prepared.
it might be possible to lay the 534 km of cable
in about 1 ½ seasons (approximately mid-
Once the jointing operation begins, a different
May through to the end of October). However,
type of work schedule would ensue. The laying
because of the certainty of disruptive storms and
and jointing crews would take turns on the
the possibility of some delays involving ship,
barge. After the first length of cable is installed,
train or barge, the required contingency time
on the barge’s return with the second length, on
may very well take up the remaining part of the
board would be the jointing technicians and not
second season.
the laying crew. On the fifth day when the joint
is about to be completed, the laying crew would
Similar schedules show that cable installation for
arrive at the barge and the jointing technicians
Route 5 would take three seasons, and up to four
would return to home base at the dock. Since
seasons for Route 6.
the procedure to bury the cable takes longer
than laying the cable, the trenching operations
Table 18 provides a comparison, based on the
would operate continuously as soon as cable
above mentioned schedules, of the time that
laying begins.
would be required to lay the cable in Routes 4,
5 and 6. It also provides a comparison of the
The logistics and a time schedule must be
number of cable joints that would be required
carefully worked out. The sequence of events
in these three routes if the cable is transported to
at the lake begins with the loading of the cable
Lake Winnipeg in long lengths (Section 4.2) or in
on the barge turntable. This is a slow process
short lengths on reels (Section 4.3).
and the speed to transfer cable from a storage
turntable to a ship’s turntable ranges from 500
to 1200 m per hour. To load 45 or 50 km of
cable might take three or four days. As for laying
the cable, in good weather conditions, it may
9
be possible to lay about 15 m per minute or Information provided by Georg Balog.

10 Information on speed provided by Thrustmaster of


Texas and by Captain Curtis Grimolfson.

80 - Manitoba Hydro
Table 18: Cable Installation Durations

Route 4 – DC Route 5 – DC Route 6 – AC


Cable Transport Alternatives
(534 km) (861 km) (960 km)

Rail cars 2 3 4
Installation Time (summers)
Reels 3 5 6

Rail cars 9 12 8
Number of joints
Reels 297 478 800

Summer is defined as mid May through to the end technicians could be employed, and that they
of October. would be prepared to work for about five months,
with periodic rotations with relief crews. The
There are many uncertainties in preparing cable contractor would provide an experienced captain
installation estimates and weather conditions are and crew for cable laying barge operations.
a major factor. The estimated time for the various
procedures in cable laying has not taken into And finally, it should be noted that this cable
consideration any delays that could be caused by laying operation is in many ways a unique
bad weather. Normally, there are many storms construction project. Never has a major power
during the course of a summer – some which transmission cable system been laid in an inland
might cause serious disruption. lake of this size so there are no precedents for this
type of project.
Along with the uncertainty of weather conditions,
there is the added uncertainty of ice conditions
on Lake Winnipeg in the spring. In recent years
5.2 Underground Cable System Installation
the lake has sometimes been free of ice at the
beginning of May. But, on average, the ice-free 5.2.1 Civil Work
period in the south basin begins about mid-May
and in the north basin the beginning of June.11 The most extensive work for installing
underground cables would be trenching over
Aside from weather and ice conditions, there are long distances, in some cases through areas of
a number of other uncertainties – so over all, it exposed bedrock, if unavoidable. Construction
may take longer to install the cable than indicated equipment and methods would be similar to
in these schedules. It is estimated that 90 to 100 those used throughout North America for oil and
km of cable could be loaded on a turntable in a gas pipelines, mainly using large tracked hydraulic
minimum of five days (seven were allowed in the excavators with rippers and rock hammer
schedule), so to load half this amount on a barge attachments where necessary. In some areas,
turntable may take about a minimum of 3 ½ days. drilling and explosive rock fracturing methods
There is also the assumption that 10 km of cable might be required. Other mechanized equipment
could be laid per day by a barge. It has also been would be used, where practical, for example as
assumed that qualified and experienced jointing shown in Figure 35. Typical trench depth would
be about 1.5 m, as indicated in Figures 13 and 18.
Only one trench is anticipated.
11Information on ice conditions in Lake Winnipeg has been
provided by Robert T. Kristjanson, a commercial fisherman,
with over 50 years of experience on Lake Winnipeg. Captain
Curtis Grimolfson is in agreement with these dates.

Report of the Concepts Review Panel - 81


Figure 35: Trenching machine (IEEE ICC Spring 2007) 5.2.2 Cable Transportation
One of the biggest challenges would be delivering
long lengths of cables to the trenches on reels by
truck. Long cable lengths are desirable because
they reduce the number of cable joints, which
are relatively expensive and labour-intensive.
This results in use of reels with the largest
dimensions transportable on Manitoba roads
(with permits) and weighing about 65 tonnes as
explained elsewhere in this report. Use of 10 to
13 axle tractor trailers is anticipated. Therefore,
temporary roads and water crossings built along
For transmission cable applications, it is necessary the underground right-of-way must be of suitable
to provide high quality engineered backfills quality. Figure 38 shows typical transportation of
around the cables to conduct heat to the surface 60-tonne cable reels on highways, which would
without drying out surrounding materials. For also need to be accommodated on temporary
remote locations it may be necessary to provide construction roads. Figure 39 identifies some of
custom aggregate and concrete batch plants. the associated risks.
Typical trenching and backfilling operations in
ideal conditions are shown in Figure 36. Figure 38: Transportation of 60 tonne cable reels on highway
(IEEE ICC Spring 2006)
Figure 36: Typical trench excavation and backfill operations in
ideal conditions

Conditions more likely to be encountered at


the sites, as experienced during installation of
an INROCS fibre-optic cable from Gillam to
Winnipeg in 2004, are as shown in Figure 37.
Figure 39: Tipping hazards when trucking large cable reels on
Figure 37: Trenching for installation of INROCS cable in 2004 uneven roads (IEEE ICC Spring 2006)

82 - Manitoba Hydro
5.2.3 Cable Installation Figure 41: Cable pulling (IEEE ICC Spring 2008)

Before cables are delivered to site, joint bay


locations would be accurately determined and
built so that arriving cable reels could be quickly
set up (Figure 40), cables pulled between joint
bays (Figure 41) and backfilled. Joints would be
made by specially qualified tradesmen with high
attention to precise workmanship, in weather-
resistant and climate-controlled housings, as
shown in Figure 42. For 500 kV AC underground
cables, there would be a single joint bay at each
jointing location and it would be necessary to
make four joints altogether, including for the
spare cable (see Figure 43). For 500 kV DC
alternatives, it is anticipated that there also be a
single joint bay, containing three joints including Figure 42: Jointing housing over joint bay
for the spare cable.

Figure 40: Cable reel set up on site pulling (IEEE ICC


Spring 2008)

Figure 43: Completed joints in joint bay

Report of the Concepts Review Panel - 83


5.2.4 Cable Jointing and Terminating
It is anticipated that one-part premoulded joints
would be used, because the main components
can be factory tested, they are relatively
inexpensive and can be installed quickly. Several
manufacturers have developed joints for 500 kV
AC, however the present limit for DC is about
320 kV. It is assumed that by 2025, when a new
post-Bipole III line is contemplated, they would
also be available for 500 kV DC. Each joint would
take about three to five days to complete, and
with multiple crews working together, all joints at
a jointing location should be completed in about
one week.

Cable terminating is done in climate-controlled


shelters within the transition stations.
Completion of each termination would take
about a week if using only one crew. Multiple
crews would allow several to be done at once.

84 - Manitoba Hydro
6 Transition and Compensation Stations
For both AC and DC systems employing Figure 45: Another example of 500 kV AC Double circuit cable
underground or submarine cables, equipment terminal – Side View
is required to make the transition from
underground/submarine to overhead lines, and to
provide for switching and isolation. For AC cable
and submarine systems, additional equipment in
the form of compensation stations is required,
to provide reactive support to transmit useable
power and control the voltage. This chapter
describes this equipment, and its role in the
context of the routes described in this report.

6.1 Transition Stations – 500 kV AC

Where transitions are made from overhead lines


to underground or submarine cables, fenced
transition stations are required. Figures 43 and A spare cable would be required to keep outage
44 provide an example for a 500 kV AC double durations to acceptable operational limits.
circuit transition station with a spare seventh Repairs would not be possible in winter due to
cable. A Manitoba Hydro application would frozen surface conditions, difficulty with fault
require only one overhead line to nominally locating and inhabitable site conditions for
transmit 1000 MW, with one cable per phase and workers on the lake. Instead repairs would be
a spare. Figure 44 and Figure 45 show a manually carried out the following summer. It is assumed
connected transfer bus to allow replacement of that a manual transfer bus would not be
any cable with the spare (at left of Figure 43 and appropriate for remote locations and that motor-
right of Figure 44). operated disconnects would be used instead.
This would probably require de-energization
of the overhead circuit in order to operate the
Figure 44: Example of 500 kV AC Double Circuit Terminal – disconnects, due to their inability to interrupt
End View load or cable charging current, resulting in a
temporary loss of 1000 MW of transmission
capacity from northern generation.

A possible 500 kV AC submarine cable transition


station configuration using disconnects, a spare
cable and shunt reactors is shown in Figure 46.
Detailed system studies would be needed to
determine switching needs for the reactors and
optimum sizes for each cable segment. Outside
dimensions of the fenced and graded area would
be about 72 m by 100 m, not including external
drainage, ground grid extensions beyond the fence
and tree clearing to prevent vegetation growth into
the station.

Report of the Concepts Review Panel - 85


Figure 46: Overhead Conductor to Underground or Submarine
Cable AC Terminal Transition Station

For submarine-reactor-submarine transition 6.2 Transition Stations – 500 kV DC


stations, as would be required where AC
submarine cable lengths would exceed about 500 kV DC overhead-submarine cable transitions
50 to 70 km, Figure 49 configuration would would be similar to AC, except that there would
be significantly different. Detailed descriptions only be three cables instead of four and only
are beyond the scope of this report, but space two overhead line conductors would terminate
would be required for two sets of four cable on the dead-end structure (positive and negative
terminations, a switched transfer bus arrangement poles), assuming a ground electrode return
for the spare cable and several sets of shunt path. Disconnects would allow substituting the
reactors. Detailed system studies would be needed spare cable for a failed one, using the transfer
to determine switching needs for the reactors and bus. Dimensions of the fenced station would
optimum sizes for each cable segment. be reduced to about 80 m by 72 m. Figure 47
illustrates a typical DC transition station.
For underground-reactor-underground AC cable
transition stations, layouts would be similar to Figure 47: Overhead Conductor to Underground or Submarine
those for submarine cables, as described above. Cable DC Terminal Transition Station

86 - Manitoba Hydro
DC overhead-underground transition stations would be severely limited for long cable lengths
would be similar to the overhead-submarine and over-voltage conditions could be excessive
transition stations. under some operating conditions.

Figure 48 shows a 400 kV DC 500 MW overhead- For overhead-submarine transition stations,


underground transition station with a single considering transportation difficulties to remote
monopolar cable. An equivalent overhead- sites, it is assumed that the optimum location
underground 500 kV DC 1000 MW station with for shunt reactors would be within or adjacent to
three cables would be about five times as large. the stations, since the large, heavy shunt reactors
could be delivered via landing barge from Lake
Figure 48: 400 kV DC single cable transition station (courtesy Winnipeg. Referring to Figure 50, it appears that
of Prysmian) adding several sets of reactors on the line side of
the dead-end structure would be simplest. Some
could be fixed and others switched, for cases
when one cable circuit was out of service, due to
faults, for maintenance or to reduce reactor losses
under favourable loading conditions. However,
it is not electrically necessary to install the shunt
reactors right at the transition stations and there
could be installation, operating and maintenance
benefits by installing them near an existing road
intersection with the overhead lines, provided
distances from transition stations were within
limits determined by system studies. Figure 49
schematically represents what equipment would
be installed at a typical compensation station for
6.3 Compensation Stations – 500 kV AC AC underground or submarine cable options.

As described in the preceding sections, shunt


reactors would be required to compensate for the Figure 49: Underground or Submarine Cable to Underground
leading reactive power of the cable capacitance. or Submarine Cable AC Intermediate Reactive Power
Otherwise, real power transmission capacity Compensation Station

Report of the Concepts Review Panel - 87


Overhead-underground transition stations would 6.4 Shore Landing
be similar, except that delivery of reactors would
be overland. At some point, all submarine cables come ashore
to be connected to their respective transmission
Submarine-reactor-submarine transition stations paths in the power system. The shore landing
and underground-reactor-underground transition requires careful planning and is typically trenched
stations would be as described in the previous for mechanical protection against water hazards.
section on Transition Stations. The former would Ice is of particular concern on Lake Winnipeg as
be more complex because of the need for spare shown in Figure 51.
cable switching capabilities. It is envisioned that
one set of reactors would be fixed and the other
switched. The reactors for these stations would 6.5 Ice Scouring
need to be about twice the capacity of overhead-
underground cable transition stations because Lake Winnipeg is a shallow lake with a long fetch
they would need to provide compensation for of 240 km in the north basin and 80 km in the
cable charging current in both directions. south basin. In some years, this results in large
volumes of ice being driven along the lake by
Figure 50 shows a 500 kV 135 MVAr 3-phase force of the wind. According to the Geological
shunt reactor, weighing over 200 tonnes. Several Survey of Canada Lake Winnipeg Project: Cruise
would be required at each terminal station. Report and Scientific Results [9], “Furrows in the
Alternatively, single phase reactors could be used. lake sediments caused by ice keel scours associated
Reactors of this capacity are filled with insulating with wind-driven ice pressure ridges have been
fluid and special containment systems are found to be in the order of one metre deep, tens
required around their bases. of metres wide and several kilometres long”.

In some years, based on wind direction, the ice


Figure 50: 500 kV 135 MVAr 3 phase shunt reactor is driven onto the shoreline. This phenomenon
(www.siemens.com) occurred in the spring of 2010 with ice
accumulating in places on the shore to a height of
10 m or more.

Figure 51: Wind Driven Ice on the Shore of Lake Winnipeg


(source: D. Farlinger)

88 - Manitoba Hydro
Submarine cables would have to be buried to
a sufficient depth to avoid damage from wind-
driven ice, also considering installation cost
constraints. Further detailed study is required to
determine the extent and depth of the ice keels.

Figure 52: Cable landing at a 300 kV DC terminal station


(source: Cabletricity)

Report of the Concepts Review Panel - 89


90 - Manitoba Hydro
7 Cost Comparisons
One of the important requirements of the Budgetary quotes were requested from cable
Panel’s Terms of Reference was to: ‘… address suppliers and rail transportation companies.
cost implications of any concepts that may have Other costs were obtained from Panel members’
merit.’ The Panel chose to develop this topic experience on past projects. Quantities were
by selecting possible illustrative routes from determined from the selected route layouts, as
northern generation to the Winnipeg area using summarized in Table 6. Cost estimates were then
combinations of hybrid lines, i.e. overhead lines prepared using a spreadsheet covering all route
combined with submarine cables or underground and shipping alternatives, including entirely
cables. Cable types were selected based on overhead AC and DC alternatives, to serve as the
reasonable expectations for availability by about base cases. Results are summarized in Table 19.
2025 when a post-Bipole III link would be The estimates are for labour and material only.
required, and in accordance with the other items
in the Terms of Reference.

Table 19: Cost estimate summary for route concepts (direct costs only; long length submarine cable shipping by rail
assumed feasible for this table)

Route Lengths
(km) Cost Premium
Cost Estimate
Route Type Description above Base
(M$)
Over- Cable (M$)
Total
head System

1 DC All overhead via Cedar Lake 1,273 0 1,273 635 (DC Base)

O/H with U/G along east side of


2 DC 1,025 175 1,200 1,076 441
Lake Winnipegosis

O/H with U/G along west side of


3 DC 830 262 1,092 1,236 601
Lake Winnipeg

O/H along west side of Lake


4 DC Winnipeg with submarine 812 178 990 995 360
section (long length shipping)

O/H with two submarine sections


5 DC exiting at Traverse Bay (long 704 287 991 1,319 684
length shipping)

1 AC All overhead via Cedar Lake 1,273 0 1,273 809 (AC Base)

O/H with U/G along east side of


2 AC 1,025 175 1,200 1,942 1,133
Lake Winnipegosis

O/H with U/G along west side of


3 AC 830 263 1,092 2,387 1,579
Lake Winnipeg

O/H with two submarine sections


6 AC exiting at Traverse Bay (long 703 240 993 2,268 1,459
length shipping)

Report of the Concepts Review Panel - 91


Assumptions and notes: Sources for Cost Estimates:

1. Costs are expressed in 2010 CAD dollars. • Cable supply costs were based on budgetary quotes
2. 500 kV AC overhead line is single circuit capable of from suppliers.
1000 MW. • Overhead line costs were based on Manitoba Hydro
3. 500 kV DC overhead line is similar to Bipole I-II 500 kV AC and DC line cost estimates
construction. • Overhead line costs were based on Manitoba Hydro
4. DC underground cables are XLPE. 500 kV AC line costs.
5. DC submarine cables are MI due to maturity • Stations and local service were based on Manitoba
6. AC underground cables are XLPE. Hydro cost estimates.
7. AC submarine cables are XLPE. • Transportation costs by rail were estimates from CN
8. For underground options, cables would be shipped logistics.
from Thunder Bay to site by truck (4.0km cable/truck • Trucking costs were supplied by a Manitoba trucking
for DC; 1.8 km cable/truck for AC). firm.
9. For submarine options with no long train shipping, • Transportation of underground cables by sea were
cables would be shipped from Thunder Bay to based on a per diem cost of $250k per day. Submarine
Powerview/Pine Falls by rail (1.8 km cable/car for DC; cable transportation by sea was based on $5M per 100
1.2 km cable/car for AC). km (or one ship load).
10. For submarine options with long train shipping, cables • Tunnel cost estimates were derived from a similar
would be shipped from Montreal, Prince Rupert or project in Vancouver.
Vancouver, a maximum distance of about 2500 km.
11. MH Project Management and Engineering costs not
included.
12. Contingencies not included.
13. Interest during construction not included.
14. Insurance for cable transportation not included.
15. Converter costs for DC alternatives not included.
16. Static VAR compensator for AC alternatives not
included.
17. Cable manufacturing capacity is assumed available.
18. Taxes and import duties not included.
19. Estimates are Class 5, as defined by AACE
International, to be used only for concept screening
purposes with low project definition. Class 5 estimates
typically have accuracies in the following range:
Low: -20% to -50%
High: -30% to +100 %”
20. All estimates contain only labour and material.

92 - Manitoba Hydro
A table of cost premiums for submarine cabling
over an equivalent length of overhead line for
1000 MW is presented below in the Table 20: Cost
Premiums for Equivalent Line Lengths.

Table 20: Cost Premiums for Equivalent Line Lengths

1000 MW Transmission System - Submarine Cable Premium when compared to similar length OH line

Route Total Total OH OH Submarine Submarine # of Submarine Submarine Ratio


Submarine Overhead Cost segment segment + OH Cables segment segment Submarine/
Cable Route per Cost ($M) cost ($M) segment cost per cost per OH
Route Length route Cost ($M) route km cable km per route-km
Length (km) km ($M/km) ($M/km)
(km) ($M)

4 DC 178 812 0.499 405.2 589.8 995.0 3 3.3 1.1 6.6

5 DC 287 704 0.499 351.3 967.7 1319.0 3 3.4 1.1 6.8

6 AC 240 703 0.6355 446.8 1821.2 2268.0 4 7.6 1.9 11.9

These are represented as ratios:



submarine segment (cost per route km)
overhead segment (cost per route km)

These estimates and ratios that express the


premiums include labour and material only.

Report of the Concepts Review Panel - 93


7.1 Interpretation of Estimate Results The exercise has helped to illustrate how care
must be taken when quoting comparative costs
Referring to Table 19, it is clear that the base case between overhead and underground/submarine
DC overhead line solution (1 DC) is the least cable solutions. If comparing, for example, 10
costly at approximately $0.635B, not including km of overhead versus 10 km of cables, cost
converters. premiums for cables expressed in $/km would be
considerably higher as shown in Table 20. But
A comparative AC overhead line solution (1 AC) when comparisons are made with actual hybrid
would cost about $0.809B, which is less than the solutions, such as when overhead line length is
DC base case if converter costs were included. much longer, overall cost premiums for solutions
with cables are reduced.
The least costly hybrid DC or AC route would be
approximately 1.6 and 2.4 times more expensive
respectively, than the base overhead route.

The least costly DC alternatives with submarine


cables would be Routes 4 DC and 5 DC through
the Eastern Interlake or Traverse Bay routes,
costing about $0.995B or $1.319B respectively.

The least costly AC alternatives with submarine


cables would be Route 6 AC along the east side of
Lake Winnipeg, costing about $2.268B.

The next least costly alternatives to overhead lines


would be to use underground cables instead of
submarine cables.

Notwithstanding the assumed estimating


accuracy, which reduces the ability to resolve
comparative costs for similarly priced alternatives,
it is clear that an overhead AC or DC solution is
the lowest cost. Any alternative solutions using
cables would result in an increased cost of at least
$0.360B and as high as $1.579B, and assumes
that submarine cables could be successfully
transported to Lake Winnipeg in continuous
lengths on long trains. Evidence shows that if this
was not possible, costs would be higher.

94 - Manitoba Hydro
8 Regulatory Issues
8.1 Licencing Other Federal reviews required would include
the Department of Transport under CEAA to deal
The project will require a licence under The with impacts under the Navigable Waters Protection
Environment Act of Manitoba as a Class 3 Act and a Comprehensive Study requirement that
development. Projects of this nature always would involve the Major Projects Management
involve a public review and if there is significant Office. All of this may then require a federal panel
public interest, a project may be referred by the review of the project under CEAA.
Minister of Conservation to the Manitoba Clean
Environment Commission. A major transmission Part of the problem with submarine transmission
project would almost certainly involve a public for regulators in this Province is that it will be
hearing prior to the issuance of a licence by the new technology applied at a fairly large scale. This
Minister to construct. will mean that regulators will need assurance that
the project is feasible, minimizes environmental
effects and has limited risk of failure that could
Aboriginal Interests cause continuing lifetime environmental damage
(e.g. release of contaminants into Lake Winnipeg,
The project will almost certainly involve disturbance of lake bottom and marine habitat).
discussions and negotiations with First Nations This will likely increase the challenge and time
and other Aboriginal peoples in the vicinity of to get environmental approvals as regulators
the transmission route. Supreme Court rulings may impose commitments with respect to future
have clarified that the Crown has a legal duty to submarine cable repairs as part of the initial
consult with Aboriginal people about any action project approval.
that might affect the exercise of an Aboriginal
or Treaty right before taking any action. The There will be other legislation that will need to
Crown must reasonably accommodate concerns be dealt with including Species at Risk Act for
about the effects of a project like the one under threatened and endangered species.
review. Discussions on these matters have
typically involved substantial negotiations about New approvals may be required for each repair
economic opportunities associated with a project. operation and an Environmental Management
Plan may need to be provided with the original
application that describes how submarine cable
8.2 Regulatory Issues with Lake Winnipeg repairs would be carried out.
Routing

One of the largest environmental regulatory


issues for submarine cable alternatives will be
to obtain a license from Fisheries and Oceans
Canada due to the potential disturbance/harm
to fish habitat when installing cables. This will
trigger a Canadian Environmental Assessment
Agency (CEAA) review due to having to issue
a permit under Section 35 of the Fisheries Act
(Harmful Alteration Disruption or Destruction of
fish habitat (HADD)).

Report of the Concepts Review Panel - 95


96 - Manitoba Hydro
9 Project Risks
9.1 Design Risks Number of joints

Extreme ambient temperatures Cable joints are subjected to the same


development and prototype tests as cables,
As described in the foregoing, ambient so in theory, they should be at least as robust
temperatures can get very low at the site, and reliable. However, there is always some
approaching -50 °C for air and -1 °C at a cable uncertainty about projecting installation quality.
burial depth on land of about one metre. Industry Installation quality assurance can be improved
standard cable system tests do not cover operation by use of detailed checklists, ensuring workers are
at such low temperatures, hence there is no proof adequately trained and supervised, and following
by test that joints and terminations will perform the best work practices.
adequately at such low temperatures. New cable
system custom tests would be required to prove
suitability of any of the concept cable systems Largest single contingency
for applications at the site. Until such tests are
conducted, it cannot be assumed that cable Since there are spare cable provisions for both
applications at the site are feasible. submarine and underground solutions, the
largest single contingency for AC alternatives
would be loss of a 1000 MW overhead line. For
Cable System reliability DC alternatives the largest single contingency
would be loss of an entire 1000 MW bipolar
Calculations based on broadly gathered industry overhead line. The next biggest would be loss
statistics show that underground cable system of a 500 MW pole. Special protection systems
failures could be expected between every three to may be required to maintain stable operation
seventeen years on average, depending on selected of the Manitoba Hydro power system for the
cable solution. For the least costly underground largest contingency. The North American Electric
solution, Route 2 DC, a failure could be expected Reliability Corporation (NERC), who defines
about once every four years. Frequency of performance standards, continues to advance the
failures would not only present a high financial elimination of special protection systems in the
and system reliability risk, it would also pose market place due to the large interdependencies
a permitting and public relations risk, since with neighbouring utilities.
repetitive environmental impacts would occur
with every repair.
Manufacturer warranty
Since there are presently no 500 kV AC XLPE
submarine cable systems in service, it was It is possible that for a project of this scope and
not possible to predict performance with value, and considering overall risks, contractors
confidence for such long lengths studied as part may not be willing to provide a five year warranty,
of this report. Cable system reliability is directly which is preferred.
proportional to length, so care must be taken in
predicting performance of very long lines based
on that of shorter lines. Notwithstanding the lack
of data, submarine cable failures can be expected.

Report of the Concepts Review Panel - 97


Route siting curves, the cable would be laid loosely enough
on the train cars so that each line of cable would
Route siting in northern Manitoba imposes a have numerous wiggles along its entire length,
number of constraints on the physical location thereby enabling it to have flexibility. Regardless,
of a transmission line, underground cable, the cables would have an inherent flexural
submarine cable, and associated compensation stiffness that would need to be quantified and
and transition stations because of terrain and taken into account when combined as a group
environmental conditions. Risks for site access, between rail car couplings. If it were deemed
site suitability and natural hazards, such as lake necessary to have additional flexibility, the cables
ice island scouring effects on submarine cables, could be loaded with a sufficient upward curve
need to be factored into design processes for at the junction between each of the cars, which
effective and practical mitigation during project would provide additional manoeuvrability. It is
implementation stages. critical that the cable be loaded in an appropriate
manner. Otherwise, without the necessary
flexibility and support, a train derailment could
Transportation Risk occur.
Perhaps the greatest risk of installing long lengths
of submarine cable in a large land-locked lake The likelihood of damage to the cable during rail
is the number of times that the cable must be transport is unknown at this time. Transformer
handled, and thus the number of occasions equipment is regularly damaged during rail
during which the cable could be damaged. transport and because of this, steps are taken
Conventionally, cables are installed between to mitigate and monitor the apparatus during
two ocean-based locations. The cable may be transport. Extensive analysis and testing would
loaded onto a cable laying vessel at the site of the have to be carried out to warranty this method of
manufacturer, transported to the origin of the shipment.
line and then laid on the ocean bottom to the
terminus. In this way the cable is only handled Transportation of cable on reels by truck or
twice, during loading and then for laying. In train has its associated risks, but this method
the case of a land-locked location such as Lake is used today and smaller sections of cables
Winnipeg, with long train transportation the are transported, inherently minimizing the
cable would be loaded onto an ocean-going consequences and therefore risk of loss. However
vessel, shipped to a port in Canada such as more joints are required, which introduce
Montreal, transferred to a large turntable, loaded offsetting reliability risks and jointing costs.
onto a train and then delivered to a lakeside
location in Manitoba such as Powerview-Pine
Falls. There it would be transferred to another Transportation schedule delays
turntable or a cable laying barge for laying on the There is the possibility that delays could occur
lake bottom. In this case the cable would have to occasionally in loading long lengths of submarine
be handled five, or as many as six times, resulting cable on a ship’s turntable or in unloading it on a
in a greater probability of damage. turntable at the receiving dock. Also, since a single
cable manufacturer may not be able to supply
Each of these transfers subjects the cable to stress sufficient cable to meet the needs of the project, a
and possibility of human or equipment error, and second manufacturer may be required. Problems
there would be the added stress of hauling it 2500 may occur in meeting exact schedules with two
km on the train. To enable the cable to have manufacturers.
the necessary flexibility for the train to navigate

98 - Manitoba Hydro
Laying separate complete lines with cable from Jointing workmanship
two different manufacturers should not present a
technical problem, but there could be a liability Each joint must be professionally produced
problem in attempting to joint cable from so that its mechanical strength and electrical
different producers, especially if joint failures properties would be equal to the cable itself,
should occur. Such eventualities must be taken otherwise a line failure could occur.
into consideration. It appears that there are differing views among
the manufacturers on the reliability of cable
Once a routine is established in loading lines with a large number of joints, depending
submarine cable on a train and unloading, it strongly on manufacturer and cable type. For
would be expected that the procedure should be example, there is evidence that DC MI cable joints
flexible in order to meet any expected delivery have performed very well, whereas failures have
schedule. occurred for AC XLPE cable joints.

Transporting underground or submarine cable 9.2 System Operation Risks


on reels by truck could be subject to a variety
of delays, ranging from loading to unloading A power system with long cables has electrical
problems, mechanical breakdowns and problems characteristics that differ from a system with
with traffic congestion or road conditions, overhead lines. For hybrid transmission (overhead
especially on roads near the installation sites. coupled with submarine or underground cable)
to be installed in Manitoba, care must be
Weather conditions have ramifications at all levels taken to determine what impact the electrical
of the delivery schedule. Severe storms could delay characteristics of cables have on the transmission
the arrival of the cable ship in port or interfere system, and to design for these impacts to
with the unloading of cable at a port Weather control voltage, allow efficient power flow
could also impact loading cable onto a train, and operational effectiveness. With the AC
train movement, or unloading at its destination. transmission options, the risks are even greater
Storms on Lake Winnipeg could also seriously when the transmission path is integrated into the
affect the barge cable laying schedule. Maps show grid. Very long high voltage AC cables are now
areas of shallow water in Traverse Bay near the being considered for more projects worldwide
mouth of the Winnipeg River, which presumably but their behaviour and impact on the grid, and
could pose problems for a barge with a draft as an operating element, are still being studied by
of 2.5 metres. However, municipal officials at industry organizations such as CIGRE.
Powerview-Pine Falls have provided assurance
that barges with heavy loads of pulpwood have
been brought through the area with no problems,
and that sailing boats with deep keels sail in
this area. Nevertheless, this should be further
investigated. Dredging equipment is available
on Lake Winnipeg if necessary, but using it may
increase permitting risk.

Report of the Concepts Review Panel - 99


100 - Manitoba Hydro
10 Benefits and advantages of underground and submarine
cable installations

Some general benefits of underground and


submarine cable lines are noted as follows.
Submarine and underground cables:

• are better protected from the


immediate effects of storms.

• may have reduced capital costs for


rights-of-way.

• minimize negotiations with


private property owners and other
land entitlements particularly for
submarine applications.

• would not involve cutting of boreal


forest or encroachment on agricultural
land.

• would have minimal impact on


agricultural operations.

• have minimal visual impacts to the


environment.

Report of the Concepts Review Panel - 101


102 - Manitoba Hydro
11 Findings and Conclusions
1. System studies indicate that with Bipole 8. A hybrid 500 kV AC line with several cable
III (LCC) in service, the Manitoba Hydro sections and associated multiple transition
power system would experience network and compensation stations would be
frequency stability problems with an difficult to operate.
additional LCC HVDC transmission
9. A hybrid 500 kV AC line may degrade
link. Therefore it is very unlikely that a
system reliability, as compared to an
fourth HVDC (LCC) bipole would be
overhead line. This potential degraded
implemented in Manitoba [19].
level of reliability may impact the
2. The same studies have concluded that reputation and value of Manitoba Hydro’s
additional north-south 500 kV AC product.
transmission would be recommended
to integrate the next major northern 10. An underground AC or DC cable system
generation plant [19]. failure can be expected approximately
once every 3 to 17 years. A lack of
3. With current cable technology and meaningful industry data for AC and DC
unproven cable transportation methods, an submarine cables prevents determination
AC submarine cable under Lake Winnipeg of statistical failure rates.
is not a viable option at this time.
11. The repair time for underground cables
4. Assuming in the foreseeable future that is considerably less than for submarine
the Manitoba Hydro system develops to cables. A spare cable for submarine and
accommodate a fourth Bipole of any mode underground options would minimize
(overhead or hybrid), and together with forced outage times.
further research and technological advances,
a DC submarine or underground cable may 12. All hybrid options have cost premiums
be a viable option. compared to overhead lines. Any of the
solutions using cables result in incremental
5. Future transmission development cost increases of about $0.36B and could
should proceed on the basis of overhead, be as high as $1.58B, assuming that long
underground and submarine in that order submarine cables could be successfully
of preference. Studies and circumstances transported by train.
at the time would determine the actual
A reference of cost premiums for
choice.
submarine cabling over an equivalent
6. Once all overhead and underground length of overhead line is presented in
options have been exhausted, Section 7, Table 20: Cost Premiums for
further research on long length Equivalent Line Lengths.
cable transportation by train, related These are represented as ratios:
transportation handling and installation submarine segment (cost per route km)
may be initiated.
overhead segment (cost per route km)
7. Based on years of operating experience For Route 4 DC the ratio is 6.6, for 5 DC
with long transmission lines in Manitoba, it is 6.8 and for Route 6 AC it is 11.9. This
an overhead transmission line should have means that on an equivalent length basis
a higher reliability than a hybrid line. the submarine options are 6.6 to 11.9
times costlier than an overhead line.

Report of the Concepts Review Panel - 103


These estimates and ratios that express 19. The world’s ocean going cable laying fleet
the premiums include labour and does not have access to Lake Winnipeg.
material only. A suitably equipped cable laying barge
would need to be constructed locally and
13. Routing through Grand Rapids would launched.
require detailed engineering studies.
Underground segments, including a 20. A dock and cable handling facilities
tunnel, are required to alleviate issues would need to be constructed on a Lake
with congestion and proximity to existing Winnipeg harbour.
Bipole lines. 21. The life expectancy of an overhead line is
approximately 100 years. Life expectancy
14. With present technology, estimates for an underground or submarine cable is
indicate that short length submarine approximately 40 to 50 years. Therefore a
cables shipped on reels would take twice complete cable system replacement could
as long to splice and lay compared to be anticipated about half way through the
long train shipping methods. Using reels life of overhead line sections.
for shipping submarine cable would be
more expensive, impractical and is not
22. VSC HVDC technology, if only
recommended.
implemented as a future fourth HVDC
Bipole transmission line, would not
15. The least costly hybrid DC or AC route
improve the vulnerability to common
would be approximately 1.5 and 2.8
mode faults. Assuming that there are no
times more expensive respectively, than
technological developments or system
the base case overhead route, assuming
developments that would remove system
long train shipping is feasible.
constraints to allow a fourth Bipole
16. The base case DC overhead line is the and given the operating complexities
most economic option, despite being and reliability risks of a hybrid AC
longer than other DC conceptual routes. transmission line, an overhead AC line
A base case AC overhead line would cost should be considered first.
approximately 27% more than the base
case DC overhead line. 23. With a low probability of HVDC being
implemented, and the costs, reliability,
17. Installation time of DC submarine complexity and operating difficulties
cable would range between 2 to 3 years, associated with hybrid AC lines, the
depending on route alternative and preferred post-Bipole III option is
assuming long train transportation. For therefore overhead 500 kV AC.
AC submarine cable it would be about 4
years.

18. The complete manufacturing capacity of


two cable suppliers may be required to
meet this schedule for submarine cables.

104 - Manitoba Hydro


12 References
[1] T. Worzyk (2009), “Submarine Power [10] Portable Dynamic Positioning
Cables”, Springer, ISBN 1612-1287; 978-3- Systems (PDPS), Thrustmaster,
642-01270-9 Retrieved from http://www.
thrustmastertexas.com/products/
[2] Teshmont Consultants (October 2006), portableDynamicPositioningSystems.html
“A weather Risk Assessment of the Existing
and Proposed HVDC Transmission Lines”. [11] Capjet trenching system [movie],
Nexans, Retrieved from http://www.
[3] “Specification for Impregnated Paper- nexans.com/eservice/Corporate-en/
Insulated Metallic-Sheathed Cable, Solid navigateref_224957/Capjet_trenching_
Type”, AEIC Specification CS2, Association system.html, MDI-Ltd. Norway.
of Edison Illuminating Companies, 11th
edition, 1997. [12] J. Ryan. “Lake bottom line – Hydro
transmission cable under Lake Winnipeg
[4] E. Stern et al. (August 2008), “The explained,” Part 1, February 9, 2008;
Neptune Regional Transmission System “From ship to shore – Two-kilometre
500 kV HVDC Project”, CIGRE 2008 paper train needed to move transmission cable,”
B4-118, Paris. Part 2, February 10, 2008; “Barge at Gimli
would lay cable in lake,” Part 3, February
[5] A. Nyman et al. (1996), “The Baltic Cable 11, 2008, Winnipeg Free Press.
HVDC Project”, CIGRE 1996 paper 14-
105, Paris. [13] D. Reske “Manitoba Hydro memo: Initial
Class I Cost Estimates of Underground or
[6] N. Yonemoto et al. (2003), “Construction Submarine Cable to Overhead Conductor
of the World’s First Long Distance 500 Transition Stations for 500kV AC and
kV XLPE Cable Line”, Fujikura Technical DC Transmission Lines Proposed by the
Review. 500kV Cable Concepts Panel”, September
13, 2010
[7] T. Yamanaka et al. (August 2003),
“Development of DC extruded cables and [14] Underground Transmission Systems
factory joints in Japan”, Jicable ‘03 paper Reference Book, 2006 Edition, Electric
A.7.3., Paris. Power Research Institute Report 1014840,
March 2007.
[8] G. Evenset et al. (August 2007),
“Qualification, Supply and Installation of [15] Electric Cables Handbook, Third Edition,
the World’s First 420 kV XLPE Submarine BICC Cables, edited by G.F. Moore,
Cable System in Norway”, Jicable ’07 Blackwell Science, 1997, ISBN 0-632-
paper A.9.3., Paris. 04075-0

[9] Brian J. Todd, C.F. Michael Lewis, L Harvey [16] CIGRE Working Group B1.10, Update of
Thorleifson (2006), “Geological Survey of Service Experience of HV Underground
Canada, Open File 3113, Lake Winnipeg and Cable Systems, CIGRE, April 2009.
Project Cruise Report and Scientific
Results”.

Report of the Concepts Review Panel - 105


[17] RAM – Study Phase 2 NorNed Kable
HVDC Project, Statnett Doc. No. N 126
JA2/16, April 15, 1998. (http://www.
energiekamer.nl/images/12_24746_tcm7-
4788.pdf Accessed July 2010)

[18] Manitoba Hydro website: http://www.


hydro.mb.ca

[19] Ultimate HVDC Development in


Manitoba, SPD 2010/14, Transmission
Planning & Design Division, System
Planning Department, Manitoba Hydro.
Ron Mazur/Pei Wang. Issued October 14,
2010.

[20] Lake Winnipeg Shoreline Management


Handbook, March 2001 – Lake Winnipeg
Shoreline Erosion Advisory Group/
Manitoba Water Stewardship.

[21] An Independent Review of Shoreline


Erosion along the Shorelines of the
South Basin of Lake Winnipeg and
Related Issues – Lake Winnipeg Shoreline
Erosion Advisory Group/Manitoba Water
Stewardship.

Additional References listed in Appendix 3

106 - Manitoba Hydro


Appendices

Appendix 1: Concepts Review Panel Terms of Reference

Appendix 2: Panel Members

Appendix 3: Long AC Cable Compensation

Appendix 4: Cable Transportation

Appendix 5: 500kV Global Cable System Applications

Appendix 6: Differences Between AC and DC Cable Technologies

Appendix 7: Grand Rapids Bottleneck

Appendix 8: Cable Laying Schedule

Appendix 9: Pole I and Pole II Reliability, 1993 - 2008

Report of the Concepts Review Panel - 107


108 - Manitoba Hydro
Appendix 1: Terms of Reference
Concepts Review Panel for Potential Future Use of Underground or
Underwater Cables for Long Distance Transmission in Manitoba

Purpose:
The overall purpose of this review panel is to produce a concepts-based report that includes discussion
of the reliability of 500kV high voltages cables and the feasibility of underground and underwater
installation for possible use in a future North-South Transmission line in Manitoba, post-Bipole III.

Items of Concern:

• The Panel shall review the maturity of the state-of-engineering of 500kV cable technologies in
use world-wide today

• The Panel shall research the performance of cables operating at 500kV

• The Panel shall research the causes of failure of 500kV cable systems world-wide

• The Panel shall review the literature on current cable research for 500kV and the effects of very
long cable lengths on the power system

• The Panel shall discuss concepts for transporting very long sections of cable on land and over
landlocked inland waterways

• The Panel shall identify the concept with the highest feasibility for transportation and
installation that may need to be advanced for further research and investigation by world
experts

• The Panel shall address cost implications of any concepts that may have merit

Report of the Concepts Review Panel - 109


110 - Manitoba Hydro
Appendix 2: Panel Members

David A. Farlinger, P.Eng., F.E.I.C. (Panel Chair)


Principal, CMC Consultants Inc.

David Farlinger is a Civil Engineer and a Principal with CMC Consultants Inc. His interests are
divided into two principal areas, energy and water.

With respect to energy, he was involved for a number of years as a pipeline technical advisor for the
Province of Nova Scotia, in the technical review of proposed natural gas systems for the awarding of
franchises in Mexico as well as two World Bank funded electricity regulatory projects, one in Russia
and the other with the Palestinian Energy Authority.

In 2007 he served as Study Manager for the Manitoba Bipole III Study “Review of Environmental
Considerations” which examined the issues related to alternatives routes.

Previously he served as study manager of a Canadian East-West Electrical Transmission Grid Study
conducted for the fourteen Provincial, Territorial and Federal Energy Ministers and took a leading
role in an External Review of Qulliq Energy Corporation, the electricity provider in Nunavut.

Much of Mr. Farlinger’s water related work involves bringing diverse interest groups to a common
understanding. He served as Chair of the Manitoba Water Commission reviewing the actions
taken during the 1997 Flood of the Century, as Chair of the Lake Winnipeg Shoreline Erosion
Advisory Committee and subsequently as Chair of the Lake Manitoba Regulation Review Advisory
Committee. He also served as Technical Advisor to the Clean Environment Commission with
respect to licencing of the construction of the 200 MW Wuskwatim dam and the expanded
Winnipeg Floodway.

Mr. Farlinger has been active in the Consulting Engineering Industry for many years. He was a
founding Director of CEM, the Consulting Engineers of Manitoba and served as President of the
Association of Consulting Engineers of Canada.

For 28 years Mr. Farlinger was a Director of Teshmont Consultants LP, specialists in High Voltage
Transmission Systems, including a number of years as Chairman. He also served two terms as a
member of the National Research Council representing industry with his expertise in energy.

Report of the Concepts Review Panel - 111


Ed Tymofichuk, P.Eng.
Vice President, Transmission
Manitoba Hydro

Ed Tymofichuk, graduated from the University of Manitoba in Electrical Engineering in 1966. He


has held management positions in Thompson, Brandon and Winnipeg in a variety of operating and
engineering functions.

Most of his career has been in transmission and includes eleven years as Division Manager of
Transmission System Operations which included a time of dynamic industry change involving de-
regulation, market developments, and establishment of enforceable reliability standards.

Mr. Tymofichuk managed and oversaw new interconnection transmission lines to Saskatchewan and
the U.S. including the 500 kV AC line from Winnipeg to Minneapolis (Manitoba portion only), and
many transmission projects in Manitoba.

He has been active in national industry organizations such as Canadian Electricity Association,
Canadian Standards Association, in North American organizations such as the Midwest Reliability
Organization (Chair of Board for 2011), Chair of the North American Electrical Corporation
Members Representatives Committee for 2010, and internationally as past member of the
International Electro-technical Commission (IEC) Standardization Management Committee.

He has consulted on international electricity industry re-structuring in several Balkan countries early
in this decade.

Since March 2009 he has held the position of Vice-President Transmission Business Unit,
comprised of four divisions of approximately 1 400 employees, responsible for the cradle-to-grave
management of transmission assets.

112 - Manitoba Hydro


John Ryan, Ph.D. (Retired Professor of Geography & Senior Scholar University of Winnipeg)

John Ryan, B.A., B.Ed., M.Ed., M.A., Ph.D., is a retired professor of economic geography and
Senior Scholar at the University of Winnipeg where he taught from 1964 to 1996. He specialized
in courses on energy, resources, economic development, and the economic geography of Canada,
the USSR, and Monsoon Asia. His research and travels have taken him to more than 50 countries.
His numerous publications include a pioneer work on the agricultural economy of Manitoba
Hutterite Colonies and a best-selling art and biography book. Since retirement he has continued to
publish in journals and on the Internet on a wide range of subjects, including articles on Canada-
US trade relations, Afghanistan, Iraq, Israel-Palestine, US foreign policy, and Canadian political
affairs. His latest efforts have involved a steep learning curve in engineering and he has acquired
expertise on the nature of HVDC submarine cable, its transport by rail and its possible use in Lake
Winnipeg.

Report of the Concepts Review Panel - 113


Allen MacPhail, P.Eng.
Cabletricity Connections Ltd.

Allen MacPhail has a Bachelor of Applied Science degree (Electrical Engineering) from the
University of British Columbia and is a registered professional engineer in BC and Alberta. He
began his career at British Columbia Hydro as a Distribution Engineer, with an early interest
in underground systems for high load density urban areas. Later he transferred to BC Hydro’s
Transmission Engineering Department, specializing in design, installation and maintenance
of many underground and submarine cable systems, from 69 to 525 kV. He was also an
engineering leader for many external submarine cable projects through BC Hydro’s consulting
subsidiary BC Hydro International, taking him to assignments in Egypt, Jordan, Northern
Ireland, Belize, Alaska and Washington.

In 2006 Allen retired from BC Hydro and began Cabletricity Connections Ltd., to further his
interests in high voltage power cable applications. He is active with a variety of domestic
and international power cable engineering activities and has affiliations with several other
consulting companies specializing in power cables and HVDC systems. Presently he
participates in the IEEE Insulated Conductors Committee as well as CIGRE B1 Working
Groups.

114 - Manitoba Hydro


Paul Wilson, P. Eng.
Managing Director, Subsidiary Operations
Manitoba Hydro International Ltd.

Paul Wilson is currently the Managing Director of Manitoba Hydro Subsidiary Operations,
Manitoba Hydro International Ltd. and the past Managing Director of Manitoba HVDC
Research Centre. The Manitoba HVDC Research Centre is the the engineering arm of MHI
and developer of the advanced Power System Simulator PSCAD®/EMTDC™ used by utilities,
manufacturers, consultants, research centers and universities worldwide to solve technical
problems.

Paul has worked his entire career in the utility industry with Manitoba Hydro and has enjoyed
the challenges associated with Software Development, Distribution Engineering Protection,
System Protection Maintenance and commissioning, and the Y2K project. The Engineering
group of the HVDC Research Centre is very active in power system studies for grid integration
of renewables, HVDC engineering, operational planning studies and electro-magnetics
transient analysis.

A graduate from the University of Manitoba in 1987, in Electrical Engineering, he is an


active member of the IEEE (M 2000) and CIGRE, and a licensed practicing member of the
Association of Professional Engineers and Geoscientists of the Provinces of Manitoba and
Saskatchewan. Paul is President of the Energy Service Alliance of Manitoba, an association of
energy service consultants active in both domestic and international services work.

Report of the Concepts Review Panel - 115


116 - Manitoba Hydro
Appendix 3: Long AC Cable Compensation
Thermal Properties and Ampacity of Cables For long land cables that can be exposed to high
through fault currents, cross bonding or single
Cable ampacity must be carefully calculated point bonding are the best choices as they provide
so that conductor temperature does not rise both voltage mitigation during faults and reduce
above a certain level where cable damage would circulating currents in the sheaths which would
occur reducing the life expectancy of the cable reduce the available ampacity. A cable system
or destroying the insulation integrity. AC XLPE is cross-bonded if the arrangements are such
cables have a design limit of 90 ºC, and are that the circuit provides electrically continuous
specified to operate at some acceptable level sheath runs from earthed termination to earthed
below limit. The ampacity of a cable depends on termination but with the sheaths so sectionalized
many factors including the environment in which and cross-connected in order to eliminate the
it is installed (i.e. water, land with thermal soil, sheath circulating currents. In such case, a voltage
or air), the conductor spacing, cross-bonding will be induced in between screen and earth, but
configurations and cable configuration or no significant current will flow. The maximum
geometry after installation. induced voltage will appear at the link boxes
for cross-bonding. This method permits a cable
The ABB cable users guide list several ampacities current-carrying capacity as high as with single-
for the 1600 mm2 500 kV AC XLPE cable for 65 point bonding but longer route lengths than the
o
C and 90 oC, in flat or trefoil configuration, or latter. It requires screen separation and additional
cross bonded configuration. link boxes. This solution is widely used on
underground land cables and the cross bonding
is accomplished in a link box specially designed
Trefoil and flat formation for this purpose which contains the connecting
bars and surge voltage limiters. However,
The three cables in a 3-phase circuit can be placed cross-bonding is impractical for underground
in different configurations. Typical configurations applications when a spare cable is used, due to
include trefoil (triangular) and flat formations. The difficulties with switching the spare cable and
choice depends on several factors such as screen making the cross-bonds at the junction box
bonding method, conductor area and available terminations. Therefore, for this application the
space for installation. Trefoil configurations have single point bonding method is recommended.
the advantage of having balanced voltages and At least one ground conductor would be provided
currents in phases compared to flat configuration between cable terminals to provide a return path
for fault current.

Bonding of the metallic screens For submarine cables, no cross bonding


The electric power losses in a cable circuit are arrangement exists today. This would be a new
dependent on the currents flowing in the metallic technology that would need to be developed.
sheaths of the cables. Therefore, by reducing or Submarine cables can be either single core or
eliminating the metallic sheath currents through three core designs. Three core submarine cable
different methods of bonding, it is possible systems usually have lower AC losses, mainly
to increase the load current carrying capacity due to lower mutual reactance between phases
(ampacity) of the cable circuit. The usual bonding and less eddy and hysteresis heating in armour. 
methods are bonding at ends, single point But the cores’ closer proximity results in mutual
bonding, or cross-bonding. heating effects, which reduces ampacity. Long

Report of the Concepts Review Panel - 117


single core submarine cables almost always have Cable Sizes - AC Submarine Cable
their sheaths and armour systems solidly bonded
at both ends, otherwise if they were open at For AC submarine cables, the panel has assumed
one end, the voltages induced in them would the conductor size would be 1600 mm2 copper,
exceed withstand levels of insulating components on the following basis.
(jackets). The same is true for 3-core submarine
cable designs. The end result is that there are For 1000 MW/circuit, required deliverable real
circulating currents in the sheath and armour current per cable would be:
which cause additional heating lowering the Ampacity = 1000 MW / (√ 3 * 500 kV)
ampacity. As cross-bonding of sheaths/armour Ampacity = 1155 Amps.
wires is impractical for submarine cables, other
measures must be taken to reduce the effects of Charging current would be approximately 23
high AC losses for solidly bonded systems.  One A/km and it's assumed that it would flow equally
is to use copper armour wires, thereby reducing into each cable end. This is a realistic assumption
eddy current and hysteresis losses compared to considering the rated voltage would be connected
steel (magnetic) armour. Another is to retain at both ends of the cable under normal
steel armour wires but introduce a large copper circumstances.
concentric return conductor under the armour, Ampacity (70km) = sqrt (11552 +
thereby substantially cancelling the magnetic (70*23/2)2) = 1408A
field experienced by the armour. Semi-conducting
jacket materials are commonly used over the Required ampacity for a 70 km distance between
sheath to control induced voltage for both 1-core reactors would be a vector summation of the
and 3-core designs. power and capacitive current. This current could
be carried by a 1600 mm2 copper conductor
submarine cable, if it had copper armour wires,
Transmission Route Assumptions which would be rated at about 1500A. With
100% compensation for a 70 km section, reactor
Manitoba Hydro contemplates that the next capacity should be approximately Reactor Size
transmission corridor will be HVAC in order to (MVAr) = √ 3 * 500 kV * (70 km*23 A/km) /2 =
provide grid strength to alleviate the weak short 700 MVArs This value requires further study as it
circuit ratio for HVDC operations on the existing ignores any shunt reactance from the overhead
two Bipoles and planned new Bipole III [19]. The transmission lines which form part of this circuit.
next corridor may come down, or partially down
Lake Winnipeg and this report has identified Therefore, there would be some capacity margin,
a number of possible routes which are used as for example if a reactor is out of service, or if one
concepts herein. of the parallel circuits is out of service, ignoring
possible voltage regulation problems. That
means it might be possible to use 500 MVAr
Electrical Assumptions reactors on the 70 km segment.

• Power level: 1000 MW


• Voltage level: 500 kV AC
• One AC cable per phase plus one spare
cable
• Reactive compensation stations on shore.

118 - Manitoba Hydro


Cable Sizes – AC Underground Thus the longest cable section possible without
compensation is 92 km at 500 kV, 1000 MW
For AC underground cables, the Panel has making certain assumptions about cable size.
assumed the conductor size would be about 1400 However, losses and voltage regulation would be
mm2. The required capacity for a 50 km cable, poor so compensation is still required.
the estimated distance between reactors would be:
Ampacity (50km) = √ (11552 +
(50*23/2)) = 1290A Figure A3-1: Compensation diagram

This could be carried by a 1400 mm2 copper


conductor direct buried underground cable which
would be rated at about 1300A.

Compensation of Long AC cables


As described in the body of the report, long
AC cables require compensation in the form of
reactors to eliminate or reduce the capacitive
effect of the cable. Cable compensation is
necessary to minimize losses in transmitting
power across a cable, and to control the voltage The diagram in Figure A3-1 depicts the concept
which would otherwise exceed equipment ratings. of compensation [22]. In order to move power
Ps through the cable to result as Pr power at the
There is a critical cable length (MCLTL) that when receiving end, compensation Qs at the sending
reached the cable’s full ampacity at the sending end and Qr at the receiving end is required to
end is consumed by the capacitive current; thus release the losses generated by the capacitance
no active power transport is possible. One must of the cable. If these losses are not released, the
either install a larger cable with higher ampacity entire cable current carrying capacity is consumed
must be installed, or the capacitive current would by losses and there would be no room left for
have to be reduced by installing compensation actual power transmission.
devices at the ends of the cables, and if required
along the cable route. During normal operation of an electrical power
system, the transmission voltages are normally
The theoretical maximum operable length of the maintained within a small range, typically, from
line at thermal limit (MCLTL) without reactive 0.95 to 1.05 pu of rated value [23]. Due to the
power compensation based on the formulations load variations, shunt reactors and capacitors have
by Colla et al. [22], been applied in power systems to compensate
excess reactive power (inductive for heavy

Table A3-1: Maximum theoretical cable length at power

Active Power transferred 0 1000 1500 2000


(MW)

MCLTL (km) 102 92 78 49

Report of the Concepts Review Panel - 119


load conditions, and capacitive for light load
conditions). Shunt reactors are commonly used
to compensate the capacitive reactive power
of transmission and distribution systems and
thereby to keep the operating voltages within
admissible levels.

For no load operation with 100% compensation,


the cable system will require a much greater
amount of compensation to maintain no load
voltage. When power is transmitted, some of
the compensation must be switched off as less
compensation is required when transmitting at
the design level.

Figure A3-2: Arrangement of shunt reactors on a long distance high voltage AC transmission line

Compared with overhead lines, inderground/ Operation of EHV long AC cables requires a
underwater cables are characterized as having high degree of inductive shunt compensation.
low surge impedance (Z0, 40 to 60 Ohms) The sudden voltage change due to routine
and relatively limited implicitly (Iz). The main manoeuvres (e.g. no-load energization or
problem of underground/underwater cables is disconnection for weak system) and rated cable-
that the cable generates far more reactive power charging breaking current of line circuit breakers
than it absorbs. I.e. ampacity of the cable is (for strong systems) dictates a high minimum
lower significantly (several times) than Surge compensation degree (usually over 95%).
Impedance Loading (SIL = V2 /Z0) of the cable.
For a 530 km overhead line section
Under these circumstances, the current
transmitted through the cable is limited to the • 1.3 MVA charging per kilometre, total 728
large charging current (capacitive) of the cable. MVA reactive compensation.
When the cable is fully loaded, the reactive • Surge impedance: 235 ohms
power absorbed by the series reactance is only
about 10% of the reactive power produced by Ferranti effect is a rise of voltage at the open
the cable capacitance. The local shunt reactors receiving end of a transmission line. On a 300 km
(inductances) are installed to compensate for this line the voltage rise is only 8.8% which is not
capacitive charging current.

120 - Manitoba Hydro


enough to cause operational concerns provided
limits are not exceed. However, voltage rise on an
unloaded line of 640 km would be 1.579 pu which
is unacceptable for the insulation systems and
exceeds normal design limits. For a 1250 km line
(a quarter wavelength) the voltage rise would be
infinite without some means of compensation [24].

Voltage distribution along the cable without


shunt compensation is shown in Figure A3-3
assuming that voltages at either-end of the line
are maintained at nominal voltage. The maximum
voltage is 1.2 pu. This will be significantly
reduced if shunt compensation is used.

Figure A3-3: Voltage profile along a transmission line/cable with ends at 1 per unit voltage

1.25

1.2
Voltage [p.u.]

1.15

1.1

1.05

1
0 50 100 150 200 250 300
Length (km)

It is desirable to limit open-circuit voltage rise to connected capacitors are used to maintain the
about 25% at the sending end, and about 40% at voltage levels by compensating the reactive power
the receiving end under worst conditions – that to transmission line.
is with all parallel lines connected, minimum
generators connected, and before the excitation There are many types of shunt compensation
systems on the generators can be reduced to a safe systems which provide varying degrees of control.
level [24].Shunt compensation, especially shunt Fixed and switch compensation shunt reactors
reactive compensation has been widely used offer a coarse level control, where thyristor switch
in transmission system to regulate the voltage reactors/capacitors (TCR/SVC) and STATCOM
magnitude, improve the voltage quality, and devices provide excellent compensation control.
enhance the system stability by employing active TCR/SVC and STATCOM are much more
variable compensation [25]. Shunt-connected expensive and are typically employed to improve
reactors are used to reduce the line over-voltages voltage and transient stability of the power
by consuming the reactive power, while shunt- system.

Report of the Concepts Review Panel - 121


Table A3-2: Reactive compensation for various power levels

Overhead line Underground cable Overhead line


( Double Circuit ) ( Double Circuit ) ( Double Circuit )
(100 km) (280 km) (530 km)

Inductance, L (mH/km) 0.4408 0.2705 0.4408

Capacitance, C (μF/km) 0.02587 0.46 0.02587

Maximum Power transfer capability (MW) at 15,084 5,580 3,065


1.0 pu voltage (both-ends)

Reactive power required for 1000 MW 88 3,351 504

For the proposed cable route, the above table Using the formulations by T.J.E. Miller [24], it is
indicates that 3351 MVAr of compensation would possible to calculate the required shunt reactor
be required for each circuit in order to transmit sizes along each cable (pages 97-101) to control
1000 MW of power across the cable interface. the open-circuit voltage during energization.
Calculations indicate that the minimum reactor
size is 161.5 MVAr per phase at each terminal
Transmission Line and cable electrical point per cable along the line. Note: when two
analysis cable segments join the reactors are doubled to
2 times 161.5 MVAr. Five line segments were
The Concepts Review Panel studied options of selected (48 km each) for the total 240 km cable
underground cables for the next north-south run. Using PI section models in a simulation
transmission corridor. The corridor will bring with capacitance of 0.22 uF / km, confirms the
1000 MW of power to the Winnipeg area and reactor size is 500 MVAr (3 phase) for each PI
destinations south for export from new generation section end.
built in the north (the amount of this generation
is unspecified at this time). This analysis does not take into account any
parallel path or resonance analysis.
A number of assumptions were made so that
some simple engineering calculations could be
performed to determine typical reactive power
requirements for an AC cable option.

Figure A3-4: Three phase 500kV cable compensation stations per circuit

Total circuit length - 240 km


Reactive Compensation Required: 5000 MVar
P = 0.4133 P = 0.4133
Q = 11.6 Q = 11.6
Ph: 0.0 deg

Ph: 0.0 deg


Source1

Source2

V = 500.2 C1 C2 C3 C4 C5 V = 500.2

A PI PI PI PI PI A
V V

Cable Section Cable Section Cable Section Cable Section Cable Section
48 m 48 m 48 m 48 m 48 m

500 1000 1000 1000 1000 500

122 - Manitoba Hydro


When a load is suddenly dropped, or a circuit Switching Transients and Transient Recovery
breaker is opened unloading a long cable, an Voltage
overvoltage can appear due to the resonance
between inductances of the power system Switching transients result from the energy
(generators and transformers) and capacitance in exchange between capacitors and inductors
the cable system. Previous work by Dr. Ametani and are initiated by the operation of breakers
has investigated the overvoltages that occur and switches in a power system. The switching
immediately after a fault and load rejection operation itself represents three main categories:
[26]. The maximum transient and temporary
• Energization of transmission lines, cables,
over voltage was 2.2 pu due to the switching
and transformers (connection)
transient and 2.0 pu due to the load rejection.
• De-energization of transmission lines and
The former occurs due to the resonance between
cables (disconnection)
the inductance and capacitance of the system. The
later occurs due to the load rejection only when • Re-closure after clearing a fault
load is suddenly dropped off a loaded generator.
An overvoltage appears on the cable in the • Switching (connection/disconnection) of
following manner: capacitors or reactors

1. The generator terminal voltage increases The energization phenomena includes charging
to the inductive electromotive force. of system elements like transmission lines or
cables, transformers, reactors, capacitor banks, etc.
2. The generator speed increases. with no trapped charge. However, in the case of
re-closure, the transmission line may have been
3. When the transformer inductance and left with a trapped charge after the initial breaker
capacitance of the cable are in a resonant opening and this affect is more pronounced on
condition, a resonant overvoltage will a cable. In such a case the transient overvoltages
appear. can reach very high values up to 4.0 pu [26]. De-
energization includes transient phenomena as a
The temporary overvoltage will sustain longer result of fault clearing and load rejection.
until voltage control equipment reacts
to lower the exciter voltage rectifying
the situation. Transmission line reflections
Vabs Vbcs Vcas
400
300
200
Sending (kV)

100
0
-100
-200
-300
-400
Vabr Vcar Vbcr
600
400
Receiving (kV)

200
0
-200
-400
-600

A52a
A52b
Figure A3-5: Transient Switching A52c

Overvoltages Time 0.7250 0.7300 0.7350 0.7400 0.7450 0.7500 0.7550 ...
...
...

Report of the Concepts Review Panel - 123


The previous graphic depicts a typical switching Pre-insertion resistors can be employed as a
transient that occurs on a transmission line due mitigation strategy this phenomenon.
to energization of a capacitor bank.
Because of the large capacitive reactive power of
Transient Recovery Voltage is the voltage HVAC cables, shunt reactors are needed for power
that appears across the breakers terminals compensation. For unloaded cable systems,
immediately after opening. The stray capacitance the shunt reactor current is almost in phase
and inductance of the bus work and connected opposition to the current in the cable, reducing
equipment govern the response of the system the amplitude of the resultant AC component
on the breaker terminals. Typically, inductors through the circuit breaker. As the current in the
coupled with the stray bus capacitance create shunt reactor has a transient DC component, the
very fast transients that may exceed the transient resulting current in the circuit breaker may have
recovery envelope of the circuit breaker. The Rate a DC component larger than its AC component.
of Recovery Voltage rise is very fast and is a design When this happens, the current passing through
factor in the selection of circuit breakers. Cables the circuit breaker does not cross zero until the
have high capacitance so by themselves are not DC component becomes smaller than the AC
expected to be problematic with circuit breakers, component [27].
other than that the breaker must be rated to
switch capacitive current. However, switching
line reactors used to compensate cables are Ferroresonance
inductive and may produce very high transient Ferroresonance occurs due to interaction between
recovery voltages. capacitors and saturable iron-core conductors,
thus this phenomenon can occur in systems
FigureA3-6: Transient Recovery Voltage (TRV) with long cables connected to transformers and
reactors. Ferro-resonance
TRVEnvA : Graphs

40
emax TRVa TRVb TRVc is similar to series
resonance except that
30
a non-linear inductor,
20
the transformer, can
10
produce a chaotic and
0 unpredictable response.
kV

-10 Ferroresonance is
-20 characterized by large
-30
phase voltages and
currents that may exceed
-40
x 0.2750 0.2760 0.2770 0.2780 0.2790 0.2800 0.2810 0.2820 0.2830 0.2840 ... system ratings damaging
...
... equipment.

Zero-miss phenomena The following figure shows some Ferro-resonant


responses on the primary side of a transformer
Zero-missing can happen for a cable when shunt initiated due to a breaker phase open failure.
compensation exceeds 50% and is characterized
by having a current that does not cross zero over
several cycles. In the case of a fault in the cable,
and re-energization, it may not be possible to
open the circuit breaker without risk of damage.

124 - Manitoba Hydro


FigureA3-7: Ferro-resonance can generate over voltages that Fault Levels
exceed equipment ratings Cables typically have a lower overall reactive
component providing
Main : Graphs
E1 increases to the fault level
800
600
current contributions
400
through the cable circuits.
200 A high penetration
0 of underground or
y

-200 submarine cable in


-400 an electrical network
-600 (for example, if a large
-800 percentage of overhead
...
0.460 0.480 0.500 0.520 0.540 0.560 0.580 0.600 0.620 0.640 0.660
... lines were replaced with
...
similar-sized cables), the
fault levels would generally increase providing
Series Resonance an extra burden on the switching elements and
The inductance of a transformer may create protection systems.
a series resonance circuit together with the
capacitance of a cable. This situation is Generator self-excitation
characterized by low impedance for harmonic Cable energizing can cause terminal voltages at
currents at the resonance frequency that the generators to increase, with a potential threat
may result in high current distortions and to the safety of equipment. Prior to energizing
overvoltages. Series resonance is important to the cable from a generator bus, the open circuit
consider since long cables have a large shunt voltage of the generator terminal to the nominal
capacitance producing a lower resonance voltage rating. The exciter supplied field voltage is
frequency. adjusted to the required value to maintain these
conditions. When the breaker is closed energizing
Parallel Resonance the cable, the cable capacitance will feed reactive
On a system with long HVAC cables, the power into the machine. This may result in
inductance of the shunt reactors and the cable a sudden increase of the machine terminal
capacitance form a parallel resonance circuit. voltage. The excitation system will respond to the
Parallel resonance is characterized by a large increased terminal voltage by reducing the field
impedance for the resonance frequencies, leading voltage to bring back the terminal voltage to its
to overvoltages when in presence of currents with set point.
a frequency equal to the resonance frequency.
The overvoltage duration and magnitude is
During a transformer energization an inrush determined by the cable capacitance (length) and
current containing all the harmonic components the response and characteristics of the machine
may be generated. If one or more of these excitation system. Unless properly designed, the
harmonic frequencies are near a system over voltage may violate the temporary (power
resonance point, transient overvoltages may be frequency) over voltage capability of surge
produced. Since the resonance circuit impedance arresters and other equipment. In the extreme
is very high, the current only flows to the case, when the cable capacitance is excessive, the
resonance circuit if it has nowhere else to go, exciter can reach its minimum excitation limits,
leading to overvoltages. thus failing to control the terminal voltage.

Report of the Concepts Review Panel - 125


References
[22] “Steady-state operation of very long EHV
AC cable lines”,Colla, L.; Gatta, F.M.;
Geri, A.; Lauria, S.; Maccioni, M.,
PowerTech, 2009 IEEE Bucharest,
Volume , Issue , June 28 2009-July 2 2009
Page(s):1 – 8.

[23] Areva Tech News, Shunt Reactors in


Power Systems, Areva T&D,
Products-L4PS-Shunt reactor-71695-V1-
EN- © - AREVA – 2007.
http://www.arevausitr.com/pdf/TECH%20
NEWS_SHUNT_71665.PDF

[24] T.J.E. Miller, “Reactive Power Control in


Electric Systems”. 1982 Wiley
Interscience ISBN 0-471-86933-3

[25] “Shunt compensation of EHV Cables and


Mixed Overhead cable lines”, Stefano
Lauria, IEEE, Fabio M. Gatta and Luigi
Colla,

[26] Takashi, K., Takeshi G., Ametani, A,


“An Abnormal Overvoltage due to
Load Rejection on EHV Underground
Transmission Line”, IPST 1995, Lisbon.

[27]
F. Faria da Silva, C. L. Bak, U. S.
Gudmundsdottir, W. Wiechowski and
M. R.Knardrupgård, “Methods to
Minimize Zero-Missing Phenomenon”,
IEEE PES
Transactions on Power Delivery,
TPWRD-00683-2009.

126 - Manitoba Hydro


Appendix 4: Cable Transportation

Proposal 1
Transporting long sections of submarine cable by train
by John Ryan, Consultant

Figure A4-1: Four layer vertical loop proposal for cables on flat cars

The purpose of this paper is to present a concept The dimensions of DC cables would be
on how to transport submarine cable from a approximately:
sea port to Lake Winnipeg where it would be • Diameter 130 mm (5 in)
part of a 500 kV transmission line from the • Weight 45 kg/m (30 lb/ft)
power stations in the north of Manitoba to the • Bending diameter 3 m (9 ft 10 in)
Winnipeg area.  • A single layer of steel armour wires

It is proposed that long sections of 500 MW 500 The dimensions of AC cables would be
kV DC submarine cable, with mass impregnated approximately:
(MI) insulation, be transported by train. • Diameter 145 mm (5.7 in)
Although not discussed specifically, this concept • Weight 50 kg/m (35 lb/ft)
and the same procedure applies equally well to • Bending diameter 4.4 m (14.3 ft)
cable with greater weight and larger diameters, • One or two layers of copper armour wires
such as 500 kV AC or DC XLPE cable.

Report of the Concepts Review Panel - 127


The restrictions on the railway from Montreal to Procedure for loading cable on a train
Powerview-Pine Falls:
• Total height above the rails As described below, on a 29-flatcar train,
<6.1 m (20 ft) measuring 584 m, it should be possible to
• Conventional flatcar height above rails transport 50 km of cable – 27 flatcars would
1.2 m (4 ft) be required for a 46 km length of cable. The
procedure to load or unload the cable would
The total height of the looped cable plus the require a track at the port or a dock to be twice
rail car must be less than the height restriction. the length of the train, or 1.2 km in this instance.
There is also the possibility to employ special low Although the track at Montreal is exceptionally
height flatcars at both ends of the train to increase long, the track at Powerview-Pine Falls allows for
the loop diameter above the minimum. this, but limits a train to a maximum length of
600 m, plus additional space for locomotives.
As shown on the accompanying map, in this
concept the plan is to lay cables in two sections To avoid expensive port costs of about $200,000
of Lake Winnipeg – a 230 km line and a 50 km per day for a cable ship, it would be advisable to
line. The 1000 MW DC transmission line would make arrangements with the harbour authorities
require two 500 MW cables and one spare cable, to install a turntable in a suitable location on
so the total length of cable would be 840 km. For or near the dock and adjacent to a railway track.
these two sections 15 lengths of 46 km cable and The ship carrying the cable could then transfer
three lengths of 50 km cable would be required. the cable, without delay, to this turntable. Space
In the longer section there would be four joints in on a deep water dock would come at a premium,
each line of cable or a total of 12 joints in the five and the dock may not be able to accommodate a
cables. turntable of about 20 m in diameter. Therefore,
using a roller system it would be possible to
There are several overseas cable suppliers and the move the cables to a turntable some distance
cable could be brought to a port on either the east from the dock, where space may be more readily
or west coast. By way of example, in this concept available, but nevertheless near a railway track.
the cable would be transported by ship to the
port of Montreal, where it would be loaded on a The turntable would have to be positioned at the
train and then hauled 2500 km to be unloaded midpoint of the required 1.2 km of track.  From
at Powerview-Pine Falls, a small Manitoba town the turntable the end of the cable would be lifted
where the track is 300 m from a deep bay on the to the top of a 10-m high gantry/conveyor system,
Winnipeg River that flows into Lake Winnipeg. propelled by a “caterpillar” (a special traction
machine for this purpose). The gantry would
Montreal was chosen as an example because of overhang the railway track and from there the
its long harbour and because it can accommodate cable would be lowered onto the floor of the first
larger shipments of cables. The alternative flatcar. The train would then advance along the
eastern port of Thunder Bay would be limited track and the cable would continue to be released
by dimensions of the St. Lawrence Seaway and and laid on all following cars until the end of the
Welland Canal (each with vessel limits of: length, train. The pick-up speed from the turntable and
222.5 m; breadth, 23.8 m; draught, 8 m; height the movement of the flatcars would have to be
above water level, 35.5 m). synchronized.

128 - Manitoba Hydro


When the cable reaches the end of the last car, To transport the cable, as already noted, would
a steel rim, with its axis perpendicular to the require either 27 or 29 flatcars. The first and
tracks, would be fitted on the cable and pressed last cars must be 28.6 m in length (93 ft 10
up to the vertical length of cable extending from in, including the space between cars) and the
the top of the gantry. This would be a specially intervening 25 or 27 cars would be 19.5 m in
designed concave steel rim, approximately 3 m in length (64 ft). For further clarity, the deck of these
diameter and slightly larger than the 130 mm (5 shorter cars measures 18.6 m (61 ft), but with
in) diameter of the cable. At this point the train the 3 foot 2½ inch space between cars for the
would back up, with the result that the cable coupling mechanism, the effective length for our
would be draped over the rim and then descend purposes is 19.5 m (64 ft). The space between the
to the floor to form the second row and continue cars would be covered by a steel plate that could
to be laid on the flatcars as they proceed down swivel as the train goes around curves.
the track.
On the trains carrying either 46 or 50 km of cable
On reaching the end car, the cable would once there would be four 22-row layers. To prevent the
again be fitted with a steel rim, and with the same layers from rubbing against each other during
procedure as described above, it would double transit, it would be advisable to have some type
back to form the third row.  In this manner, with of separation barrier between each of the layers.
the train going back and forth, the entire 46 or Sheets of plywood might serve this purpose.
50 km of cable could be loaded in about a week. The short flatcars would require a row of steel
This is a complex procedure, still to be more fully supports along the sides, approximately 0.6 m
explained, but even at this stage, reference to the (2 ft) in height. Sheets of plywood at this height
attached diagrams may be helpful. placed along the supports would prevent damage
to the cable.  However, the long first and last cars
A second section of cable could be hauled by would require approximately 3-m (10-ft) high
loading another set of cars with either 46 or 50 steel supports that would form a rigid frame along
km cable. In this case the total train would consist the sides and at the end. It is on these end cars
of either 54 or 58 cars and would transport either that 3-m high loops would be formed as the cable
92 or 100 km of cable, as required. It might be is laid over the rims on the cars.
more economical to haul the two sets of cars in
one trip, but, if desired, the two sets could be As already explained, to provide support for these
transported separately, as soon as each would be loops a 3-m diameter steel rim would be inserted
loaded. into each loop. Each 22-row layer would create 11
sets of vertical loops – on each of the end cars –
Although it could be possible to have locomotives so four layers would form a series of four sets of
move the train of flatcars back and forth, a loops, with a space of about 4.5 m between each
different means of doing this might be preferable. of them. A 28.6-m (94-ft) car could accommodate
As an alternative, the flatcars could be moved by this series of loops, and it is for this reason that
powerful winches attached to the front and rear these longer cars would be required. The attached
of the line of flatcars. Moving the row of cars by diagrams illustrate this explanation.
winches could be done more smoothly and more
reliably, especially with respect to the speed at
which the cars would be moved. As previously
stated, it is important that the speed of the
moving flatcars be synchronized with the speed at
which the cable is removed from the turntable.

Report of the Concepts Review Panel - 129


Figure A4-2: End of train and loop assembly for cable supports

The steel rims that support the loops would have Once the first layer of cable is laid, a steel
to be firmly fastened to each other and to the 3-m platform, about a metre wide and positioned
high steel frame surrounding the end and the two about 4.5 m from the first row of rims, must be
sides of the long cars. This could be done by a attached to the sides of the flatcar, high enough
series of narrow metal plates or anchors bolted to to clear the height of the layer of cables (probably
the rims. These would keep the rims at the correct 150 mm or 6 in). The second row of loops
distance apart and firmly in place. To be more (with the rims inside them) would be placed on
specific, at the time the rims are manufactured, this platform, where the rims would be firmly
four strong bolts should be put through the rims attached to each other and to the platform and
and welded in place – equidistant from each the side supports. The same type of platform
other and at the midpoint of the interior concave would have to be installed for the third and
surface. The heads of the bolts should have a fourth rows of loops containing the rims, at
welded steel patch over them to prevent possible heights that would clear the underlying layers of
abrasion to the cable. When the rims are fitted cable.
over the cable they should be so positioned that
two bolts would be vertically aligned – one at It should be pointed out that if the cable is left
the top and one at the bottom – and two would unsupported from the top of the rim to the
be on the sides, opposite each other. Once in floor of the car it would sag in a catenary shape.
position, steel anchors would be fitted over Vibration of the suspended cable could cause
the bolts from the previously installed rim and concentrated sheath fatigue, resulting in loss of
attached to the bolts on the rim being installed – cable life and early failure. To prevent this from
keeping the rims about 130 mm (5 in) apart. In occurring, immediately after the rim is installed
this manner the 11 rims would be firmly fastened and the loop is formed, a specially fashioned
together and they would also be fastened to the support would be inserted in the void between
steel support structure on the sides of the flatcar. the edge of the rim and the curved slope of the

130 - Manitoba Hydro


cable. The support would act as a wedge to models to prove procedural concepts. For added
prevent the tendency of the cable to sag and certainty it may very well require an actual train
vibrate during train movement. This would have and reasonable lengths of cable for appropriate
to be done for each cable within the four series tests. Testing might reveal that some different
of loops and rims as soon as the cable is laid – at approaches may be necessary.
both ends of the train. The attached diagrams
illustrate this feature. There is a possibility that a problem may exist
with the matter of sheath material fatigue within
Although the short flatcars are 3.05 m (10 ft) the cable when the rail cars move through bends
wide and could actually accommodate 24 rows in the railway and because of the vibration of
of 130 mm (5-in) cable, only 22 rows would the cars during transit. However, by using the
be installed. This is to allow a small amount of appropriate sheath alloy and design, this problem
space between the cables and thereby each line of on other types of cable has been successfully
cable would contain a series of small sinusoids or circumvented, as per the experience of Canada
wiggles along the course of its length. This would Wire and Cable, shipping cables with F3 alloy
enable each line of cable to have the necessary from Toronto to Vancouver for decades. This
flexibility that would be required when the train alloy is available as well as designs where weaker
navigates curves. It should be noted that the long alloys are reinforced. Such designs have been
end cars are only 2.9 m (9 ft 6 in) wide, but they successfully employed on ship transport from
could still accommodate 22 rows of cable, with a Scandinavia as far as Alaska and New Zealand.
bit of space between them.

In transporting cable of either 46 or 50 km Unloading the cable from the train


lengths, each of the long end cars (with the
loops of cable) would carry 1.8 km of cable or As previously stated, near Lake Winnipeg, at the
approximately 81 metric tonnes. The intervening town of Powerview-Pine Falls, the railway track
short cars would carry 1.7 km of cable or about is about 300 m from a deep sheltered bay in the
76.5 tonnes. Central Manitoba Railway, that Winnipeg River. A dock would have to be built
operates the line from Winnipeg to Powerview- at this location, and a narrow conveyer system of
Pine Falls, has advised that a train with this rollers (stretched out along a mainly downhill
weight per car would be within their allowed slope) would be needed to convey the cable from
weight limits. the train to the dock and onto a turntable on
the barge. Near the railway track, a gantry system
Testing would have to be conducted to see if this would have to be built to unload and convey the
procedure for loading the cable on a train would cable from the train onto the downhill conveyer.
work in practice, and to determine if damage The gantry system would require caterpillars
could occur to the cable in transit. Also, some on it to pick up the cable and to control the
form of testing would have to be conducted to progression of the cable down the slope. 
determine if the wiggle in each line of cable as it
stretches across the entire length of the flatcars For the sake of precaution, it would be advisable
would provide sufficient flexibility for the train to have at least two cable storage turntables
to navigate curves. If there should be a question positioned probably near the gantry. Normally
about this, each line of cable could perhaps be the cable would be unloaded from the train and
lifted about 0.5 m into an upward curve at the transferred directly to a turntable on the barge,
junction between cars to provide additional but conditions may arise when this might not
flexibility. Some testing could be done by be possible. For instance, in the event of bad
computer modelling or by small-scale working weather the laying of cable in the lake could be

Report of the Concepts Review Panel - 131


delayed, and without an accumulator/buffer
system of extra turntables, this could paralyze the
chain of cable delivery, i.e., ship-train-barge, and
lead to very high delay costs. In any event, extra
turntables could result in better coordination
with ocean shipping, train loading/unloading and
cable laying.

The cable would be unloaded in a reverse


process to the one used to load it. To begin the
unloading process, the end of the cable would be
diverted from the train onto an overhead gantry
and directed along the roller/conveyer system.
After this, as the train would move about 600 m
forward and then 600 m back, a caterpillar system
would gently propel the cable from the rows on
the cars onto and along the roller/conveyer to
the rotating turntable, as the rims were removed
sequentially.  

In this manner the entire 46 or 50 km of cable


could be unloaded from the train and loaded
onto a turntable on the barge. A second section
of cable on another set of cars or unit train
could be unloaded onto one of the storage
turntables. Regardless, optimizing barge size,
barge turntable capacity, number of trainloads
per barge, separation distance between individual
cables on the lake bottom, etc., would be subject
to further investigations and innovation by cable
installation contractors, independent from the
main train transportation logistics. 

In summary, it appears technically feasible to


transport long lengths of submarine cables
to Lake Winnipeg, using conceptual methods
described above. However, the transportation
procedure and the laying of cable will require in
depth engineering and some tests to assure a safe
and low risk operation.

________________________
John Ryan, Ph.D., is Retired Professor of Geography and
Senior Scholar at the University of Winnipeg.

February 10, 2008; latest revision Dec 8, 2010

132 - Manitoba Hydro


Figure A4-3: Proposed Overhead and Submarine Cable HVDC Transmission Line

Report of the Concepts Review Panel - 133


Proposal 2, while not the Panel’s preferred proposal for transporting long lengths
of submarine cable by train, is one of four concepts Dr. Ryan initially developed for
consideration by the Panel for inclusion in this report.

Proposal 2
Transporting Long Lengths of Submarine Cable by Train
by John Ryan, Consultant

This proposal outlines an alternative concept days. A second section of cable could be hauled
on how long lengths of 500 MW 500 kV DC by loading another set of cars with either 46 or
submarine cable can be transported by train. The 50 km cable. Hence the total train would consist
proposal is suitable for cable with either mass of either 54 cars or 58 cars and would transport
impregnated (MI) or extruded insulation (XLPE. either 92 or 100 km of cable, as required.
These cables would be approximately 130 mm
(5 in) in diameter with single-wire armour, have It should be noted that the cable lies in a
a bending diameter of approximately 3 m (9 ft horizontal position on the ship’s turntable and
10 in), and weigh about 45 kg per metre. This that it would be lifted and conveyed to form a
proposal is unsuitable for AC cable because of its horizontal loop on the flatcar. Because the cable
larger bending diameter. would be transferred from a horizontal position
on the ship to a horizontal position on the train
As presented in Proposal 1, the cable would be there should be no torsional twist exerted on
designated for Lake Winnipeg, and the same the cable. That is the main advantage of this
amounts of cable would need to be transported. alternative proposal.
Also, by way of example, Montreal would be the
arrival port for the cable, and the procedure at the As in Proposal 1, the same number and type
dock for loading the cable on the train would be of flatcars would be required. However, in this
identical to that presented in Proposal 1. However, proposal the flatcars would require 0.6 m (2 ft)
in this alternative concept, the procedure for high steel supports along the sides, but the first
loading the cable on the long cars at each end of and last cars would require 1.8 m (6 ft) high
the train would differ. steel supports. At the ends of the first and last
cars, there would be, bolted to the floor, specially
In this alternative proposal, when the cable designed 1.5 m (5 ft) high aluminum drums,
reaches the end of the last car it would be carefully measuring 3 m in diameter. It is around these
looped horizontally around a vertically positioned drums that the cable would be looped, allowing
3-m diameter aluminum drum (bolted to the it to double back. For each 22-row layer there
car floor), enabling the cable to double back and would be 11 loops around the drum, which
form the second row. At this point the train would would measure about 1.4 m (4 ½ ft) high. The
go in reverse and back up while the cable would drum for the second layer should be positioned
continue to be laid on the cars as they pass by. On about 4.5 m from the first drum, and it would
reaching the end car the cable would once again be bolted on supports above the first layer (so as
be looped around a 3-m drum and thereby double not to exert any weight on the cables in the first
back to form the third row. In this manner, with layer). The drum for the third layer should be
the train going back and forth, the entire 46 or 50 positioned about 4.5 m from the second drum,
km of cable could be loaded in a matter of several and again it would be bolted on supports above

134 - Manitoba Hydro


the two layers of cable. Likewise, the drum for the Aside from the above differences in loading the
fourth layer should be positioned about 4.5 m cable on the cars, all other aspects in the transport
from the third drum. With the exception of the of cable on a train would be identical to that
first drums on the two end cars, the remaining outlined in Proposal 1, including the unloading
drums would be installed and bolted to the procedure.
supports only after the relevant preceding layer of
cable would be laid. A 28.6-m (94 ft) car could _________________________
accommodate the four sets of loops on drums, John Ryan, Ph.D., is Retired Professor of Geography and
and it is for this reason that these longer cars Senior Scholar at the University of Winnipeg.
would be required. The attached sketch shows the
layout of this design. February 20, 2010; latest revision June 15, 2010

Figure A4-4: Proposal 2 rail transport with vertical drums

Report of the Concepts Review Panel - 135


Proposal 3, while not the Panel’s preferred proposal for transporting long lengths
of submarine cable by train, is one of four concepts Dr. Ryan initially developed for
consideration by the Panel for inclusion in this report.

Proposal 3
Transporting long sections of DC submarine cable
with extruded insulation by train, coiled on widened flatcars
by John Ryan, Consultant

In this proposal an additional concept is these would not involve sharp bends this may
presented on how long sections of 500 MW 500 not be detrimental to the cable. Nevertheless,
kV DC submarine cable with extruded insulation this procedure should be tested to ensure that
(XLPE) can be transported by train. The no damage could occur to these short sections
procedure involves coiling the cable on a series between the cars.
of specially widened flatcars. Cable with extruded
insulation may tolerate a certain degree of coiling Since the bending diameter of the cable is 3 m (9
and twisting so this procedure may be feasible. ft 10 in) and the standard flatcar is 3.05 metres
However, because of the coiling and torsional (10 ft) wide, to accommodate four rows of 130
twist involved in this concept, this process would mm (5 in) diameter cable, both ends of the car
not be suitable for cable with mass impregnated would have to be widened to 4.3 m (14 ft) by the
(MI) insulation since this cable cannot be coiled addition of 0.6 m (2 ft) extensions on each side of
or twisted. the car. This additional width at each end of the
car should extend along the length of the car for
As presented in Proposal 1, the cable would be 4.3 m (14 ft). Hence the car would have a type of
designated for Lake Winnipeg, and the same hour-glass configuration, as shown in the attached
amounts of cable would need to be transported. diagram.
Also, by way of example, Montreal would be the
arrival port for the cable. A support structure, measuring 1.2 m (4 ft) in
height, would have to be built on all four sides
In this proposal, a 46 or 50 km length of cable of the car. These supports could be made of steel
would be loaded on a series of flatcars, with bars at intervals of about 0.6 m (2 ft), and sheets
supports for sides, by means of coiling the cable of plywood or some other material would be
in several rows along the outer edges of each installed to prevent the bars from damaging the
car. Once the first car is loaded, the cable would cable. The extensions to the floor on each side of
be extended to the adjoining car – a distance of the car at both ends could also be made of steel
almost a metre (3 ft 2 ½ in) – and then with the bars and covered with plywood or some other
same procedure the second car would be loaded material. Steel bars would be far less expensive
and all other succeeding cars. The connecting than the use of solid steel plates.
cable between the cars should be enclosed in
a specially designed and correctly curved rigid The adaptation would have to be made to 30 cars
protective case. This would protect the cable for a 50 km length of cable. It should be possible
from vibration and possible damage. This to haul two lengths of cable per trip so the
section of cable would still be subjected to slight adaptation would have to be made to 60 cars.
bends as the train navigates curves, but because

136 - Manitoba Hydro


On a 61-foot car (18.6 m), four rows of cable With this system of transporting the cable there
could be stacked 10 layers deep. With a cable would be the expense to adapt 60 cars, i.e., to
diameter of 130 mm (5 in) the 10 layers would extend the width of the cars to 4.3 m (14 ft) for a
have a height of 1.3 m (50 in), hence the lengthwise distance of 4.3 m (14 ft) at each end,
necessity for 1.2 m (4 ft) sides all around the car. and the necessity to build 1.2 m (4 ft) sides with
These could probably be made of steel bars at 0.6 steel bars on all four sides of the car. Also some
m (2-foot) intervals, with sheets of plywood laid type of support system would be required at the
against them to prevent damage to the cable. mid-point of the car to ensure that the stack of
cables along each side would stand upright, with
The outer row of cable would be the longest in no slippage.
length, i.e., 42.8 m, and the three succeeding
rows would be 42.2 m, 40.6 m, and 40 m. The A further drawback to the system of coiling the
four rows, stacked 10 layers deep, would have an cables in each car is that it would take longer
overall length of 1.656 km and at 45 tonnes per to load and unload the cable as compared to
km the total weight would be 74.5 tonnes per car. Proposals 1 and 2.
A train with this weight per car would be within
the weight limits for the track from Winnipeg to Both CN and CP have been apprised of this
Powerview-Pine Falls. concept and the matter of car adaptation and
both railways affirmed that they have clearance
With 1.6 km of cable on each car we would need for 14 foot wide rail cars.
30 cars for a 50 km length. A 46 km length of
cable would require 28 cars. A 30-car train would Although XLPE cable can tolerate a degree of
measure 585 m, and 28 cars would be 546 m. torsional twist, there are conflicting views on
The 600 m track at Powerview-Pine Falls could whether this cable could be coiled in the manner
accommodate trains of this length. described in this proposal.

A gantry on the ship with the appropriate lifting


and pulling apparatus would load the cable onto
the cars. A second gantry with the associated
lifting and pulling apparatus would be loaded ________________________
on an extra car and hauled with the cable cars John Ryan, Ph.D., is Retired Professor of Geography and
to Powerview-Pine Falls. At this destination, the Senior Scholar at the University of Winnipeg.
gantry would be assembled on a concrete pad
beside the track in order to unload the cars. December 18, 2009; latest revision June 15, 2010

Report of the Concepts Review Panel - 137


Figure A4-5: Proposal 3 rail transport with widened flatcars

138 - Manitoba Hydro


Proposal 4, while not the Panel’s preferred proposal for transporting long lengths
of submarine cable by train, is one of four concepts Dr. Ryan initially developed for
consideration by the Panel for inclusion in this report.

Proposal 4
Transporting DC cable with extruded insulation
on widened flatcars in a figure 8 pattern
by John Ryan, Consultant

This is a further concept on how long sections cross over diagonally to the other end where it
of 500 MW 500 kV DC submarine cable with would form another 180 degree curve but in
extruded insulation (XLPE) may be transported by the opposite direction, thereby eliminating any
train. overall twist to the cable. As such, this would
eliminate the cumulative torsional stress that
As presented in Proposal 1, the cable would be would occur if the cable were coiled on the car.
designated for Lake Winnipeg, and the same
amounts of cable would need to be transported. Since the bending diameter of the cable is 3 m
Also, by way of example, Montreal would be the (9 ft 10 in) and the standard flatcar is 3.05 m (10
arrival port for the cable. ft), to accommodate four rows of 130 mm (5 in)
diameter cable, both ends of the car would have
In this proposal, it should be possible to load a 46 to be extended to a width of 14 feet (4.3 m) by
or 50 km length of cable on a series of flatcars by the addition of 2-foot (0.6 m) extensions on each
loading it in a prescribed manner on individual side of the car. This additional width at each end
cars. Once the first car is loaded, the cable would of the car should extend along the length of the
be extended to the adjoining car – a distance of car for 14 feet (4.3 m). Hence the car would have
almost a metre (3 ft 2 ½ in) – and then with the a type of hour-glass configuration, as shown in
same procedure the second car would be loaded the diagram.
and all other succeeding cars. The connecting cable
between the cars should be enclosed in a specially The main restricting feature and drawback of this
designed and correctly curved rigid protective case. proposal is the limitation on the height of cable
This would protect the cable from vibration and where it criss-crosses at the midpoint of the car.
possible damage. This section of cable would still In crossing diagonally from one corner of the
be subjected to slight bends as the train navigates car to the other the cables cross each other at
curves, but because these would not involve sharp the midpoint section. The height restriction on
bends this may not be detrimental to the cable. trains from Montreal to Winnipeg is 6.1 m (20 ft).
Nevertheless, this procedure should be tested to Since the flatcar has a height of 1.2 m (4 ft), this
ensure that no damage could occur to these short leaves 4.9 m (16 ft) for the cable. With the cable
sections between the cars. being 130 mm (5 in) in diameter, this would
theoretically allow for 38 layers of cable. However
The cable would not be coiled within the some type of material, perhaps about a ¼ of an
individual cars – instead it would be laid in a inch thick would have to be inserted between
type of figure eight configuration, as shown in the cables to prevent rubbing damage and to
the accompanying diagram. After forming a 180 alleviate the weight from the upper layers on the
degree curve at one end of the car the cable would lower layers of cable. Considering this, plus a

Report of the Concepts Review Panel - 139


small margin for safety, means that the probable The problem is compounded because this would
maximum number of cables would be 32 and no not only involve train transport but ship transport
more than 36, i.e., 13.3 or 15 ft in height. as well. Overall, the additional costs for this
proposal would be significantly greater.
Four rows of cable on each side of the car would
result in 8 criss-crosses per layer at the midpoint, A gantry on the ship with the appropriate lifting
so 4 layers would total 32 cables, for a height of and pulling apparatus would load the cable onto
13.3 ft. An extra two rows on a fifth layer would the cars. A second gantry with the associated
result in 36 cables or 15 ft. lifting and pulling apparatus would be loaded
on an extra car and hauled with the cable cars
Two-foot (0.6 m) high supports would have to to Powerview-Pine Falls. At this destination, the
be constructed along the sides of the 14-foot gantry would be assembled on a concrete pad
extensions at both ends of the car. These supports beside the track in order to unload the cars.
could be made of steel bars at intervals of about
0.6 m (2 ft), and sheets of plywood or some other This procedure for transporting cable poses a
material would be installed to prevent the bars problem at Powerview-Pine Falls because the
from damaging the cable. The two-foot extensions current track near the unloading area is only 600
to the floor on each side of the car at both ends metres in length. A 62-car train would be 1.2 km
could also be made of steel bars and covered with and a 67-car train would be 1.3 km in length.
plywood or some other material. Steel bars would This would necessitate the double-tracking of
be far less expensive than the use of solid steel this section, with a siding system to shunt off the
plates. Probably a type of rack could be made of excess cars as they would be unloaded.
steel bars and then attached to the floor at each
end of a car. Both CN and CP have been apprised of this
concept and the matter of car adaptation and
On a 61- ft car (18.6 m), the outer row of cable both railways affirmed that they have clearance
would be the longest in length, i.e., 42.8 m, and for 14 foot wide rail cars.
the three succeeding rows would be 42.2 m, 40.6
m, and 40 m. The four rows, stacked 4 layers deep, Although XLPE cable can tolerate a degree of
would have an overall length of 0.662 km. If two torsional twist, there are conflicting views on
additional rows were added as a partial fifth layer, whether this cable could be coiled in the manner
the length would be 0.7474 km, and at 45 tonnes described in this proposal.
per km the total weight would be only 34 tonnes
per car.

With this short length per car, to transport 46


km of cable would require 62 flatcars and a 50
km length would need 67 cars. Considering that
Proposals 1, 2 and 3 would require only 27 to 30 ­­­­­________________________
cars, the transport costs for this method would John Ryan, Ph.D., is Retired Professor of Geography and
be more than double. With the other proposals Senior Scholar at the University of Winnipeg.
the plan is to transport two lengths of cable per
trip, utilizing 50 or 60 flatcars. With this method December 22, 2009; latest revision June 15, 2010
only one length of cable could be transported.

140 - Manitoba Hydro


Figure A4-6: Proposal 4 rail transport with figure 8 cable coiling

Report of the Concepts Review Panel - 141


142 - Manitoba Hydro
Appendix 5: 500 kV Global Cable System Applications
Table A5-1: 500 kV AC XLPE Underground Cable System Applications

Cct. Length Installation Capacity Insul. Conductor


Supplier Location Year I/S Joints
(km) Type (MW) Type (mm2)

Grand Coulee
J-Power Systems 1977 20.0/3 Tunnel SCFF
Dam; USA

Tsuruga P/S;
J-Power Systems 1985 0.7/3 SCFF-PPL 2500
Japan

Imaichi P/S;
J-Power Systems 1987 0.615 XLPE 1400
Japan

Shimogo P/S;
J-Power Systems 1988 0.19 XLPE 800
Japan

Shimogo P/S;
J-Power Systems 1990 0.381 XLPE 800
Japan

Shiobara P/S;
Viscas 1992 0.46 XLPE 1400
Japan

Reihoku P/S; SCFFF-


J-Power Systems 1994 0.9/3 2500
Japan PPL

Okukiyotsu 2nd
J-Power Systems 1995 2 x 0.280 XLPE 800
P/S; Japan

Okumino P/S;
J-Power Systems 1996 1.4 XLPE 800
Japan

Okumino P/S;
J-Power Systems 1996 2.4 XLPE 800
Japan

Matsuura P/S;
J-Power Systems 1996 1.246 XLPE 1200
Japan

1996,
Viscas; J-Power Shinkeiyo- XLPE 27
1997, 2 x 40.0 69 Tunnel 1200 2500
Systems Toyuso; Japan km
2000

1996,
Viscas; J-Power Shinkeiyo- XLPE 27
1997, 2 x 40.0 69 Tunnel 1200 2500
Systems Toyuso; Japan km
2000

Okutataragi P/S;
J-Power Systems 1997 1.459 Tunnel XLPE 800
Japan

Kashiwazaki P/S;
J-Power Systems 1997 4.6/3 SCFF-PPL 2500
Japan

Okutataragi P/S;
J-Power Systems 1997 4.4/3 XLPE 800
Japan

Kazunogawa P/S;
Viscas 1997 2.2 XLPE 1000
Japan

Report of the Concepts Review Panel - 143


Table A5-1 (continued)

Cct. Length Installation Capacity Insul. Conductor


Supplier Location Year I/S Joints
(km) Type (MW) Type (mm2)

Tianhuangping
J-Power Systems 1997 3 x 0.697 XLPE 800
P/S; China

Tachibanawan
J-Power Systems 1998 2 x 1.614 XLPE 1000
P/S; Japan

Tachibanawan
J-Power Systems 1998 4.8/3 XLPE 1000
P/S; Japan

Anan Converter
J-Power Systems 1998 0.219 XLPE 1200
Station; Japan

Anan Converter
J-Power Systems 1998 0.272 XLPE 800
Station; Japan

Anan Converter
J-Power Systems 1998 0.289 XLPE 800
Station; Japan

Anan Converter
J-Power Systems 1998 0.202 XLPE 1200
Station; Japan

Kihioku S/S;
Viscas 1998 6 x 0.600 XLPE 800
Japan

Tachibanawan
J-Power Systems 1999 1.015 XLPE 800
P/S; Japan

Tachibanawan
J-Power Systems 1999 1.023 XLPE 1000
P/S; Japan

Echizen P/S;
Viscas 1999 1.2 XLPE 1400
Japan

Kihioku S/S;
Viscas 1999 2 x 0.360 XLPE 1500/800
Japan

Viscas Futtsu P/S; Japan 2000 1 XLPE 800

Viscas Futtsu P/S; Japan 2001 1 x 0.210 XLPE 800

Hitachi-Naka P/S;
J-Power Systems 2001 0.547 XLPE 2500
Japan

Dachaoshan HPP;
Suedkabel/ABB 2002 0.77 No XLPE 800
Yunnan, China

Kannagawa S/S;
Viscas 2003 1 x 1.750 XLPE 1000
Japan

Zheijang P/S;
Viscas 2003 1 x 0.814 XLPE 800
China

J-Power Systems Hirono P/S; Japan 2003 1.11 XLPE 800

Viscas Futtsu P/S; Japan 2004 1 x 1.124 XLPE 2500

144 - Manitoba Hydro


Table A5-1 (continued)

Cct. Length Installation Capacity Insul. Conductor


Supplier Location Year I/S Joints
(km) Type (MW) Type (mm2)

Bureskaya HPP:
Suedkabel 2005 0.8 No Tunnel ? XLPE 800
Russia

Omarugawa P/S;
Viscas 2005 1 x 1.480 XLPE 800
Japan

Sanbanxi P/S;
J-Power Systems 2005 0.477 XLPE 1200
China

Suedkabel Sudan 2006 1.3 XLPE 1200

Suedkabel Sudan 2006 1 XLPE 800

Viscas Shangxi; China 2006 1 x 1.554 XLPE 800

J-Power Systems Yixing P/S; China 2006 2 x 0.716 XLPE 800

Yunan Huaneng
Viscas Xiaowan P/S; 2007 1 x 2.050 XLPE 1000
China

Henan
Viscas 2007 1 x 1.050 XLPE 800
Heimifeng; China

Shanghai Expo; 5 x 1.440 + 1


Viscas 2007 XLPE 2500
China x 0.240

Boaquan P/S;
J-Power Systems 2007 2 x 0.734 XLPE 800
China

Huizhou P/S;
J-Power Systems 2007 2 x 0.500 XLPE 800
China

Bailianhe P/S;
J-Power Systems 2007 2 x 0.372 XLPE 800
China

Omarugawa P/S;
J-Power Systems 2007 1.328 XLPE 800
Japan

Xilongchi P/S;
Viscas 2008 0.850/3 Tunnel XLPE 800
China

Kashiwazaky
Viscas 2008 1 x 0.550 XLPE 2500
Kariwa; Japan

Yunan Huaneng
Viscas Xiaowan P/S; 2008 1 x 2.478 XLPE 1000
China

Huizhou P/S;
J-Power Systems 2008 4 x 0.627 XLPE 800
China

0.810 +
Nexans France Ochakova; Russia 2009 0.720; 1.820 DB 660 XLPE 2500; 800
800 sq mm

Report of the Concepts Review Panel - 145


Table A5-1 (continued)

Cct. Length Installation Capacity Insul. Conductor


Supplier Location Year I/S Joints
(km) Type (MW) Type (mm2)

Kashiwazaky
Viscas 2009 1 x 0.640 XLPE 2500
Kariwa; Japan

Shimane P/S;
Viscas 2009 1 x 1.504 XLPE 2000
Japan

Luoyang P/S;
Viscas 2009 1 x 0.493 XLPE 800
China

Kashiwazaky 1 x 1.720 + 1
Viscas 2009 XLPE 800
Kariwa; Japan x 1.577

Liaoning Pushihe;
Viscas 2009 1 x 1.066 XLPE 2500
China

Kashiwazaki P/S;
J-Power Systems 2009 2 x 0.834 XLPE 2500
Japan

Shibo - Sanlin;
Nexans France 2010 17 Tunnel 1560 XLPE 2500
Shanghai; China

Porce 3 P/S;
Suedkabel 2010 2 x 0.7 No Tunnel 600 XLPE 800
Colombia

Shibo - Sanlin;
Viscas 2010 17 Tunnel 1560 XLPE 2500
Shanghai; China

Kashiwazaki P/S;
J-Power Systems 2010 2 x 0.520 XLPE 2500
Japan

Beskudniko:
Nexans France ? 3 x 0.2 No ? 2000 XLPE 2500
Russia

146 - Manitoba Hydro


Table A5-2: 500 kV AC SCFF Underground Cable System Applications

Cct.
Installation Capacity Insul. Conductor
Supplier Location Year I/S Length Joints
Type (MW) Type (mm2)
(km)

Grand Coulee
BICC 1973 20.0/3 Tunnel SCFF
Dam; USA
1990
Honshu-Shikoku; Bridge and
J-Power Systems and 22.0 SCFF–PPL 2500
Japan DB
1994
Grand Coulee
J-Power Systems 1977 20.0/3 Tunnel SCFF
Dam; USA

J-Power Systems Tsuruga P/S; Japan 1985 0.7/3 SCFF-PPL 2500

J-Power Systems Reihoku P/S; Japan 1994 0.9/3 SCFF-PPL 2500

J-Power Systems Kashiwazaki P/S;


1997 4.6/3 SCFF-PPL 2500
Japan

500 kV AC XLPE Submarine Cable System Applications

None presently exist.

The highest voltage XLPE submarine cables are the Gossen Island 420 kV cables installed for the Ormen
Lange offshore gas production project.

The next highest will be a new 345 kV submarine cable crossing between New Jersey and Brooklyn, to be
in-service in 2011.

Table A5-3: 500 kV AC SCFF Submarine Cable System Applications

Cct.
Year Installation Capacity Insul. Conductor
Supplier Location Length Joints
I/S Type (MW) Type (mm2)
(km)

Nexans/Viscas Hainan Island; China Submarine; SCFF–


2009 31.0 600 800
100 m deep PPL

Mainland BC to
2 x (30.0 Submarine; SCFF
Nexans/Prysmian Vancouver Island; 1984 1200/cct 1600
+ 8.0) 400 m deep -kraft
Canada

500 kV DC XLPE Underground Cable System Applications

None exist. The highest voltage system for a completely underground DC application using XLPE cables is
+/- 150 kV (MurrayLink).

Report of the Concepts Review Panel - 147


Table A5-4: 500 kV DC SCFF Underground Cable System Applications

Cct. Length Installation Capacity Cable


Supplier Location Year I/S Joints Sheath
(km) Type (MW) type

St. Lawrence
River crossing, SCFF- Lead
Sumitomo/JPS 1991 5.1 Tunnel
Quebec; kraft alloy
Canada

500 kV DC MI Underground Cable System Applications

None exist for a completely underground application, but there are underground sections associated with
the 500 kVdc ‘Neptune’ submarine cable project from New Jersey to Long Island (36 cable reels, weighing
up to 54.4 kg, 4 m diameter). The underground length is 22 km. There are also underground sections
associated with the 500 kV DC Italy-Sardinia project, with 15 km on land.

500 kV DC XLPE Submarine Cable System Applications

None exist. The highest voltage system presently in service is 150 kV dc.

In 2010 Prysmian will commission a new 200 kV dc system in the San Francisco Bay area.

In 2010 J-Power systems will commission a new 250 kV dc XLPE cable system between Honshu and
Hokkaido in Japan, which will be designed for LCC converters.

Table A5-5: 500 kV DC SCFF Submarine Cable System Applications

Cct.
Installation Capacity Cable
Supplier Location Year I/S Length Joints Sheath
Type (MW) type
(km)

4 x 50
Honshu- Submarine, 1400 initial SCFF- Lead
Viscas/JPS 2000 km
Shikoku; Japan 75m deep 2800 final PPL alloy
cables

Table A5-6: 500 kV DC MI Submarine Cable System Applications

Cct.
Installation Capacity Cable
Supplier Location Year I/S Length Joints Sheath
Type (MW) type
(km)

2 x 390
Italy-Sardinia; 2009, Submarine, Lead
Prysmian km 2 x 500 MI
Italy 2010 1600 m deep alloy
cables
New Jersey – NY
Submarine, 75
Prysmian (Long Island); 2009 82 600 MW MI
m deep
USA

148 - Manitoba Hydro


Table A5-7: DC MI Submarine Cable Installations at all Voltages, 1956 – 2010

Length Max. Water Depth


Name of Link Date Voltage (kV) Power (MW) Type
(cable-km) (m)

Sweden (Gotland 1) 1956 100 20 100 160 MI

Italy – Sardinia 1965 200 100 2 x 118 450 MI

Sweden-Denmark (Konti-
1965 285 300 64 80 MI
Skan 1)

Canada (Vancouver Island 1) 1969 300 156 3 x 27 200 MI

Norway-Denmark
1976 263 250 2 x 125 600 MI
(Skagerrak 1,2)

Canada (Vancouver Island 2) 1976 300 185 2 x 35 200 MI

Sweden (Gotland 2,3) 1983 150 160 2 x 100 160 MI

England-France (Cross-
1986 270 250 8 x 50 55 MI
Channel 2)

Sweden-Denmark (Konti-
1988 285 300 2 x 64 80 MI
Skan 2,3)

Finland-Sweden (Fenno-
1989 400 500 200 117 MI
Skan)

New Zealand (Cook Strait 2) 1991 350 500 3 x 40 300 MI

Norway-Denmark
1993 350 500 125 500 MI
(Skagerrak 3)

S. Korea (Jeju Island) 1993 180 150 2 x 96 160 MI

Sweden-Germany (Baltic
1994 450 600 250 60 MI
Cable)

Sweden – Poland (SwePol) 1999 450 600 253 90 MI

Greece-Italy (GRITA) 2001 400 500 1 x 160 1000 MI

Scotland-N. Ireland (Moyle) 2001 250 500 2 x 55 100 MI

Australia (BassLink) 2005 400 500 1 x 290 75 MI

Norway-Netherlands
2007 450 700 1 x 580 410 MI
(NorNed)

USA (New Jersey – Long


2007 500 660 1 x 84 25 MI
Island –Neptune)

2008 500 1 x 420


Sardinia-Italy (SAPEI) 500 1620 MI
2010 500 1 x 420

Report of the Concepts Review Panel - 149


150 - Manitoba Hydro
Appendix 6: Differences Between AC and DC Cable Technologies

Introduction Figure A6-1: AC cable insulation stress versus radius


There is little difference in appearance between
AC and DC transmission cables, as the basic
components look to be very similar. They are
both comprised of:
• A metallic conductor (copper or
aluminum)
• Insulation (laminar or extruded)
• Metal sheath
• Inner Jacket
• Armour (in the case of submarine cables)

However, there are major differences in the


electrical insulation design, which is more
complex for DC cables than for AC cables.

Electric Field Distribution in an AC Cable

The electric field distribution in an AC cable is


dependent on the capacitance of the insulation,
which is in turn dependent on the insulation
geometry. The permittivity of the insulation is Electric Field Distribution in a DC Cable
usually uniform with radius and constant with
temperature. The electric field distribution in a DC cable is
dependent primarily on the insulation resistance,
Electric field strength, or stress, is determined by which is temperature dependent, and secondarily
the following equation. by the electric field stress. When a DC cable is
first energized, the temperature of the insulation
is constant throughout, and the maximum stress
is at the inside of the insulation, as with an AC
cable. However, as load is applied, the conductor
Where: emits heat and a temperature gradient arises
Er = Electric field strength at radius r (kV/mm) across the insulation. The result is a non-uniform
V = AC voltage across insulation (kV) insulation resistivity, such that the maximum
r = Radius at any point in insulation (mm) stress is no longer at the inside of the insulation.
ri = Radius at inside of insulation (mm) At full load the insulation can therefore
ro = Radius at outside of insulation (mm) experience a higher stress at the outside than
inside, as shown in Figure A6-1.

Report of the Concepts Review Panel - 151


Figure A6-2: DC cable insulation stress versus radius and Where:
temperature Er = Electric field at radius r (kV/mm)
V = DC voltage across insulation (kV)
r = Radius at any point in insulation (mm)
ri = Radius at inside of insulation (mm)
ro = Radius at outside of insulation (mm)
Wc = Losses in conductor (W/m)
T = Thermal resistivity of insulation
(K-m/W)
a = Electrical resistivity temperature
coefficient (per °C)
b = Electrical resistivity stress coefficient
(per kV/mm)

DC Instead of AC Cables

Effect of Capacitance
Cable insulation has a capacitance, C, given by
Calculation of DC insulation stress is far more the following equation:
complex than for AC cables, as reflected in the
following equations.

Where:
C = Insulation capacitance (μFarads/km)
e = Insulation permittivity

Effect of Charging Current


Applying an AC voltage results in a current
flowing into the cable to charge the capacitance.

Where:
Ic = Insulation charging current (A/km)
Xc = Capacitive reactance (μOhms/km)
f = Frequency (Hz)

152 - Manitoba Hydro


From the above equation it can be seen that the Effect of Dielectric Losses
charging current is cumulative with cable length.
If cables are sufficiently long, the charging current Applying an AC voltage to an insulation also
can heat the cable to its maximum allowable results in dielectric losses, as defined by the
operating temperature, such that no usable power following equation.
can be transmitted.

Since the equation shows that charging current


is dependent on voltage, it is clear that charging Where:
current is independent of load and is present Wd = Dielectric losses due to internal
whenever the cables are energized. heating of the insulation (W/km)
tandelta = Dielectric loss angle (also known as
It can also be seen that as the frequency goes to dissipation factor or power factor)
zero, as is the case for DC, the cable charging
current also goes to zero, highlighting one of the From the above equation it can be seen that the
great advantages of DC cables compared to AC dielectric losses are proportional to the square of
cables. the AC voltage, so that these effects become much
more pronounced at EHV levels. They are also
frequency-dependent, so that DC cables have no
dielectric losses.

Table A6-1: Comparative Losses of AC versus DC Cables

AC Cables DC Cables

Ohmic losses in conductor Ohmic losses in conductor

Induced losses in conductor nil

Induced losses in sheath nil

Induced losses in armour nil

The implications of the above are that DC cables


can transmit power for very long distances with
low losses. Of course the low DC cable losses
are offset by their converter losses, which don’t
exist for AC cables. And the negative aspects
of AC cable transmission that limits effective
transmission distance and capacity can be
overcome with shunt reactive compensation
systems, to somewhat neutralize the effects of
capacitance.

Report of the Concepts Review Panel - 153


154 - Manitoba Hydro
Appendix 7: Grand Rapids Bottleneck

Introduction flows into Lake Winnipeg via the Saskatchewan


River. This is an area where the separation
To construct an electrical link from northern between Lake Winnipeg and Cedar Lake narrows
generation to a future termination point in the to mere metres. In this bottleneck section,
south, there needs to be consideration over the Manitoba Hydro has all of its DC transmission,
problems with the Grand Rapids area. If a link and a significant amount of AC travelling through
is built, whether it be underground, overhead, this narrow corridor. Specifically, the following
underwater, or a combination of the three and AC and DC lines:
brought through the Grand Rapids area, issues
exist. • G1A/G2A AC Transmission
• G31V AC Transmission
The ground conditions consist of fractured • G9F AC Transmission
limestone bedrock at surface. This has caused • G8P AC Transmission (which
difficulties in the past for the installation of a runs north to Ponton
fibre optic link. During the construction of the Station)
fibre optic cable through Grand Rapids, the cable • Bipole I & II DC Transmission
could not be drilled under the river due to the
leakage of drilling fluid through the fractures into In addition, there is buried fibre optic cable
the ground water and surface water. Ultimately, in this section. The fibre optic cable travels
the cable was trenched in at a high cost with from Winnipeg, north to Gillam to provide
consequences to the surface water. Further cables communications for northern generation
would be trenched in as well. activities.

The proximity of the underground cable or This bottleneck has always caused concern due to
above ground cable to existing transmission the concentration of assets in this location. Some
lines needs to be reviewed. To go overhead, the solutions suggested in the past have included the
potential from a storm knocking out the major creation of islands in Cedar Lake for transmission
transmission of power to the South has to be towers to be placed on.
factored. An option is to bury the cable, leaving
little chance of a storm to damage it; however, While the bottleneck section is quite congested,
terrorism or electrical interference may cause there is opportunity for routing further HVAC or
issues. DC transmission through the area. There is a risk
associated with this due to the concentration of
The use of the Grand Rapids corridor is not transmission in the area and events damaging
free of significant issues as it relates to the numerous lines simultaneously, storm, terrorism,
performance of a transmission link to southern etc. Underground cables may provide a greater
load centers from northern generation. level of protection as the cable is not subjected
to problems associated with transmission towers.
Further studies would be required to determine
Background the effects of locating new HVAC and DC cables
so close.
Grand Rapids is an area approximately 400 km
north of Winnipeg, Manitoba where Cedar Lake

Report of the Concepts Review Panel - 155


Figure A7-1: Location of Grand Rapids

The black lines on the green map are the major


Manitoba Hydro transmission lines in the
province. The two small red lines refer to the
spillway and dam at the generating station.

Figure A7-2: Grand Rapids Reserve Location

The Grand Rapids reserve is identified above in


the green shaded area.

156 - Manitoba Hydro


Figure A7-3: Grand Rapids Infrastructure

Transmission Lines

Roads

Highway PTH #6

The above map shows the infrastructure that exists


in the vicinity of the Grand Rapids Generating
Station

Overview

Grand Rapids lies on the Saskatchewan River, Winnipeg (downstream of Grand Rapids). Two
approximately 400 kilometres north of Winnipeg, communities live in the area immediately below
Manitoba, Canada. The rapids have been the dam site; the community of Grand Rapids on
replaced by an excavated channel and dam for the west side of the river, and the Grand Rapids
the production of electricity. The old riverbed First Nation on the east. The following aerial
contains the spillway structure. The dam is photograph shows the communities along either
located at a narrow strip of land between Cedar side of the river below the dam site.
Lake (upstream of Grand Rapids) and Lake

Report of the Concepts Review Panel - 157


Figure A7-4: Grand Rapids in an aerial photo

North

The aerial photograph is a visual presentation


illustrating the congestion in the Grand Rapids
area.

Grand Rapids Topography and Geology Figure A7-5: Trench at Grand Rapids

The Grand Rapids area is a low-lying area


consisting of lakes, creeks and boreal forest.
Ground conditions consist of nearly no humus
and fractured bedrock at or near the surface.
The bedrock is limestone and the area has been
affected by past glaciations.

The above photos show trenching for a fibre optic


project in the same material as Grand Rapids.

158 - Manitoba Hydro


Figure A7-6: Trenching machine

Area Land Use

The area is primarily used for hunting, trapping


and fishing by the local population. In addition,
there is logging occurring in the area, but no
significant industry exists.

Conclusion

Options for installing an HVAC or DC link


through the Grand Rapids area are limited due
to the bottleneck effect from the congestion of
existing transmission lines. One option may be
to install underground cables through the area.
This would entail one trench for either an AC or
DC system. Issues with this installation would be
environmental (water turbidity and fish habitat)
and physical room (the area is currently congested
as shown in previous aerial photos). Further
issues may exist due to ground temperatures,
proximity of overhead lines, etc. However, for this
report they have been limited to environmental
and physical. Other opportunities to route an
additional transmission line, whether above or
below ground or below Lake Winnipeg should be
looked at in conjunction with the Grand Rapids
area.

Report of the Concepts Review Panel - 159


160 - Manitoba Hydro
Appendix 8: Cable Laying Schedule
Cable Installation Schedule (Ship, Train, Barge) 1st Summer
Route 4, as example (540 km or 12 45-km lengths of cable)
Activity Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Load 2 45-km lengths of cable onto vessel at factory
Vessel transit to Montreal
Transfer cable to train at Montreal
Vessel returns to factory
Train travels to Powerview and transfers cable to turntables
Train returns to Montreal
Lay cable -- 1 wk for 45 km; 2 wks, if joint required
Lay cable -- 2 wks for 45 km, joint required
Train idle time
Barge idle time

Explanatory Notes:

Although the cable manufacturer(s) will be This remaining length of cable would be laid at
producing cable continuously during the shipping the beginning of the next summer.
season, this might not be enough to meet the
demands of a regular shipping schedule, so it During the first summer, because of having to
is assumed that an adequate amount of cable wait for the arrival of cable, the train would
would have been produced and stored during the remain idle for 6 weeks and the barge would be
preceding period to provide sufficient cable for idle for 8 weeks.
the entirety of the shipping season, and not cause
any delays due to shortage of cable. According to this schedule, during the first
summer, the first cable line consisting of four
It is assumed that a vessel such as North Ocean 45-km segments would be laid and three
103, fitted with a turntable, would be used to segments of the second line – the remaining
transport the cable. It travels at 16 knot and could fourth segment would be stored on a spare
cover the approximate 6000 km from Europe to turntable and would be laid at the beginning
Montreal in about nine days, which should leave of the second summer.
sufficient time in the two-week slot to transfer the
cable from the ship to a turntable on the dock.

In this schedule the laying of cable would begin


at Week Six, which would be the second week of
May, if the lake is ice-free.

The cable laying season would end at Week 25,


the last week of October, but this would leave one
45-km length of cable on a spare turntable.

Report of the Concepts Review Panel - 161


Cable Installation Schedule (Ship, Train, Barge) 2nd Summer
Route 4, as example (540 km or 12 45-km lengths of cable)

Activity Month 1 Month 2 Month 3 Month 4


1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Load 2 45-km lengths of cable onto vessel at factory
Vessel transit to Montreal
Transfer cable to train at Montreal
Vessel returns to factory
Train travels to Powerview and transfers cable to turntables
Train returns to Montreal
Lay cable -- 1 wk for 45 km; 2 wks, if joint required
Lay cable -- 2 wks for 45 km, joint required
Train idle time
Barge idle time

Explanatory Notes:

In the second summer, starting the second week


of May if the lake is ice-free (Week Six), the laying
of cable would begin with the single length of
cable that was stored on a spare turntable at the
end of the first summer. This section of cable
would complete line two.

Line three would be completed at the end of


Week 15, the third week of August.

Because of having to wait for the arrival of cable,


the train would be idle for three weeks and the
barge one week.

In the event of disruptive storms or any other


disruptions or delays involving ship, train or
barge during the 1 ½ summers to lay the cable
for Route 4, the required contingency time would
be available in the remaining part of the second
summer.

162 - Manitoba Hydro


Appendix 9: Bipole I and Bipole II Reliability 1993 - 1998

Table A9-1: Bipole I and Bipole II Reliability 1993 - 1998 *

Combined Bipole I
Bipole I Bipole II
+ Bipole II
Year
No. of Forced Duration of Forced No. of Forced Duration of Forced Average No. of forced
Outages/900km Outages (hrs) Outages/1000km Outages (hrs) outages/100 km/year

2008 2 2.1 4 0.6


2007 0 0 1 0.2
2006 0 0 0 0
2005 2 0.3 2 0.3
2004 0 0 2 0.1
2003 2 0.6 3 44.8
2002 0 0 0 0.3
2001 2 0.9 3 0.3
2000 0 0 2 0
1999 0 0 0 0
1998 0 0 1 0.1
1997 0 0 18 0.4
1996** 1 117.5 10 182.7
1995 NA NA 10 0.6
1994 NA NA 2 0.3
1993 NA NA 9 0.9

Average
1996-2008 0.0909 10.6818 0.9091 16.6091
/900km
Average
1996-2008 0.0101 0.1010
/100km/year
Average
1996-2008
0.0556
/100km year
for both Bipoles

* Based on CIGRE1996-2010 papers on ‘A Survey of the Reliability of HVDC Systems Throughout the World’.
** 19 towers damaged by downburst

Report of the Concepts Review Panel - 163


164 - Manitoba Hydro

You might also like