Professional Documents
Culture Documents
Final Project Report
Final Project Report
A PROJECT REPORT
Submitted by
DEWATHANG
(June, 2022)
འབྲུག་རྒྱལ་འཛིན་གཙུག་ལག་སོབ་སེ།།
འཇིགས་མེད་རྣམ་རྒྱལ་བཟོ་རིག་མཐོ་རིམ་སོབ་གྲྭ།།
Royal University of Bhutan
Jigme Namgyel Engineering College, Dewathang
Certificate
This is to certify that the project report titled ‘RESTORATION PLAN FOR EASTERN GRID
OF BHUTAN AND ISLANDED OPERATION OF BHUTAN POWER SYSTEM’
Submitted by:
In partial fulfilment of the requirements for the award of the BE in Power Engineering.
Supervisor(s):
President: +975-07-260286, Facsimile: +975-07-260289, email: president@jnec.edu.bt , Dean AA: +975-07-260299,Dean SA:
+975-07-260298, Dean RIL: +975-07-260202, Admin.: +975-07-260302, Accounts: +975-07-260205
DECLARATION
We declare that this project titled ‘RESTORATION PLAN FOR EASTERN GRID OF BHUTAN
AND ISLANDED OPERATION OF BHUTAN POWER SYSTEM ’ under the supervision of
Mr. Hemlal, Lecturer, Department of Electrical Engineering is a bonafide report of work done by
us. The report represents our original ideas and words including referred ideas from various
sources. We declare that all the sources referred are adequately cited adhering to the academic
regulation of academic dishonesty reflected in the Wheel of Academic Law (WAL), Royal
University of Bhutan (RUB). The material embodied in the project report has not been submitted
for any other awards.
i
ABSTRACT
The world has become completely reliant on power systems due to rising electrical energy
consumption, contemporary lifestyles, and energy usage patterns. As a result, the operators are
required to ensure high dependability and stability of the power system grid. Typically, the
system is built to manage just one outage at a time. However, multiple large blackouts have
been observed in the recent decade, each of which began with a single outage. Power system
repair and restoration is a novel problem in power system as it is concerned with the reliability.
However, it is a challenge to achieve a highly reliable power system due to various
contingencies occurring in it. These unpredictable events result in overloading of some part of
the system and sometimes it even followed by cascade tripping of transmission line, power plant
and result in a total shut down of the system. Therefore, it’s very important to have black start
plans for the system and prepare a black start operation procedure to recover the system in
minimum duration. This report presents some to strategies to restore the eastern grind of Bhutan
in the event of total black out.
Furthermore, this report presents a complete model of Bhutan Grid and discusses on possibility
of operating Bhutan grid under isolated mode using automatic generation control for frequency
and generation control.
ii
TABLE OF CONTENTS
Acknowledgement ........................................................................................................... i
Abstract ........................................................................................................................... ii
List of figures................................................................................................................. iv
List of Tables .................................................................................................................. v
List of acronyms ............................................................................................................ vi
Chapter 1: INTRODUCTION .............................................................................................. 1
1.1 Project Background .......................................... Error! Bookmark not defined.
1.2 Aim ..................................................................................................................... 1
1.3 Objectives ........................................................................................................... 1
Chapter 2: POWER SYSTEM RESTORATION ................................................................. 2
2.1 Blackouts ............................................................................................................ 2
2.2 Restoration overview .......................................................................................... 5
2.3 The need for restoration ...................................................................................... 6
2.4 Power system restoration procedure ................................................................... 6
2.5 Constraints during restoration ............................................................................ 7
2.6 Restoration Strategies and guidelines ................................................................. 8
Chapter 3: RESTORATION OF THE EASTERN GRID OF BHUTAN ............................ 9
3.1 The eastern grid of Bhutan ................................................................................. 9
3.2 Outages in the eastern grid ................................................................................. 9
3.3 Modelling.......................................................................................................... 10
3.4 Outage creation ................................................................................................. 11
3.5 Restoration plans .............................................................................................. 12
3.7 Results .............................................................................................................. 13
Chapter 4: Islanded operation of Bhutan grid .................................................................... 14
4.1 The Bhutan power system ................................................................................ 14
4.2 Load sizing ....................................................................................................... 17
4.3 Primary governing system ................................................................................ 18
4.4 Automatic generation control ........................................................................... 19
Chapter 5: DISCUSSION ................................................................................................... 21
Chapter 6: CONCLUSION ................................................................................................ 22
Chapter 7: RECOMMENDATION AND FUTURE SCOPE ............................................ 23
References ................................................................................................................................ 24
Appendices ............................................................................................................................... 26
iii
LIST OF FIGURES
Figure 1: Players in the North American power system ............................................................. 2
Figure 2: Satellite image of 2003 US-Canadian blackout .......................................................... 3
Figure 3: Satellite image of 2003 Italy blackout ........................................................................ 4
Figure 4: Images depicting the extent of the 2012 Indian blackout ........................................... 4
Figure 5: Objectives of a power system restoration ................................................................... 5
Figure 6: Overview of restoration process ................................................................................. 6
Figure 7: Power system failures and restoration actions ............................................................ 7
Figure 8: Outages in the eastern grid of Bhutan ......................................................................... 9
Figure 9: Methodology used in the restoration process ............................................................ 10
Figure 10: Eastern grid of Bhutan modelled in DigSilent PowerFactory................................. 11
Figure 11: Frequency deviation upon disconnection with Indian grid ..................................... 11
Figure 12: Static and dynamic bus voltage profile .................................................................. 13
Figure 13: Model of Bhutan power system developed in DigSilent PowerFactory ................. 16
Figure 14: Frequency response of THP during load pickup of 30 MW ................................... 17
Figure 15: Frequency response on 2 %, 4 % and 6 % droop .................................................... 18
Figure 16: Frequency response with and without deadband .................................................... 19
Figure 17: Frequency response with and without AGC ........................................................... 20
Figure 18: Frequency response of THP on addition of 30 MW ............................................... 31
Figure 19:Frequency response of MHP on addition of 40 MW ............................................... 32
Figure 20: Frequency response of CHP on addition of 18 MW ............................................... 32
Figure 21:Frequency response of KHP on addition of 4 MW .................................................. 33
Figure 22:Frequency response of BHP (Upper) on addition of 1.5 MW ................................. 33
Figure 23:Frequency response of BHP (Lower) on addition of 2.5 MW ................................. 34
Figure 24: Frequency response of DHP on addition of 7 MW ................................................. 34
Figure 25 - 27: Bus voltage profile of restoration plan I ................................................... 35 - 37
Figure 28 - 30: Bus voltage profile of restoration plan II .................................................. 37 - 39
Figure 31 - 35: Pictorial representation of restoration plan I ............................................ 40 - 44
Figure 36 - 39: Pictorial representation of restoration plan II ........................................... 44 - 47
iv
LIST OF TABLES
Table 1: Description of restoration plans ................................................................................. 12
Table 2: Check for voltage violation of buses for restoration plans ......................................... 13
Table 3: Maximum allowable pickup load of powerplants ...................................................... 17
Table 4: Sailent features of hydropower plants ........................................................................ 26
Table 5 Reactor data ................................................................................................................. 26
Table 6: Load data .................................................................................................................... 26
Table 7: Generator data ............................................................................................................ 27
Table 8: Transmission line data ................................................................................................ 28
Table 9: Transformer data ........................................................................................................ 30
Table 10: Outage data for 2017, 2018 and 2019 ...................................................................... 31
v
LIST OF ACRONYMS
vi
Chapter 1: INTRODUCTION
1.2 Aim
To develop a restoration plan for eastern grid of Bhutan and to study islanded operation of the
power system of Bhutan.
1.3 Objectives
• Study the power system of Bhutan.
• Develop an understanding of power system restoration and islanded operation of power
system.
• Propose effective restoration plans of the eastern grid of Bhutan.
• Analyze the islanded mode operation of Bhutan power system.
1
Chapter 2: POWER SYSTEM RESTORATION
Extended blackouts of the electric grid can and have been caused by equipment failures,
operator errors, natural disasters, and cyber-attacks as further exampled in this chapter. Even if
such catastrophes are uncommon, being prepared is thus essential, since prolonged power
disruptions put their human lives, national security, energy economy in jeopardy. Because most
of the generating units cannot resume without being connected to a live grid, the system operator
is reliant on a few units that can start. It is expensive to allocate and maintain these units. This
can have a significant impact on the restoration's security and timeliness. While optimizing the
restoration sequence and further studies are important, restoration plans are an absolute
necessity in a power system.[3]
2.1 Blackouts
Cascading failure is a process in which the failure of one or a few elements in a system of linked
parts can cause the failure of other sections, and so on, as seen in power transmission, computer
networking, banking, transportation systems, creatures, the human body, and ecosystems. A
single breakdown in an electric power system can result in a complete system blackout. These
are complex sequences of dependent outages that occur with a low probability yet are not
uncommon. Furthermore, as a source of significant economic loss, this is a problem that needs
to be remedied, or at the very least appropriately addressed, as flaws are unavoidable. To better
understand blackouts, some examples are provided below.
2
2.1.2 2016 Southern California disturbance:
The Blue Cut fire started in the Cajon Pass on August 16, 2016, and immediately spread to an
important transmission corridor consisting of three 500 kV and two 287 kV lines. Because of
the fire, the former experienced thirteen-line faults, while the latter experienced two faults. A
large quantity of solar generation was lost in four of these fault incidents: the most major
occurrence connected to the solar photovoltaic power loss resulted in a loss of almost 1200MW.
[12]
Figure 4: Images depicting the extent of the 2012 Indian blackout. Affected states shown as
red in the Map.
4
2.2 Restoration overview
Modern power systems are designed to have a high level of reliability [15], which is why power
system operation should be closely monitored so that it operates within its safe operating limits.
Despite the high level of reliability, outages in the power system still prevail. Often, an outage
is only in a portion of the power system, and it can be restored using the power from the healthy
section. However, in case of an outage affecting a large area: a blackout, there may not be
neighbor to help the system. In this case, system restoration must begin from pre-selected
generating units with the ability to start themselves [15], called a blackstart generator. The
process of restoring a power plant to operational status without the need of external energy
sources is known as black start. The most common blackstart generators are hydroelectric
generators, diesel generators and gas turbine generator. Hydroelectric generators require small
amount of starting power, and they respond quickly to power other plants which do not have
blackstart capability.
In a primarily hydro system such as in the Bhutanese Power sector, focus is mainly given to
response of the prime mover to sudden load pickups. Off-line dynamic programs and
simulations are done to develop restoration plans depending on the prevailing generation,
transmission, and load data. Large hydroelectric generators are usually linked to on-site diesel
generator sets or a battery bank, which are started and used to power auxiliary buses as well as
start the generator. Small diesel generators can supply enough power to start bigger generators
of several MW capacity, which in turn can start other generators in the same powerplant and
then power other generators. Dispatchers use off-line restoration plans and available black start
capabilities to return the system to normal operation circumstances after a partial or total system
blackout. The supply of auxiliary power to other power stations and offsite power to critical
service loads, such as hospitals and other public health facilities; military facilities; transmission
lines that transport the cranking power to non-black start units or large motor loads; and
transformer units, including setup transformers, are all part of the typical black start scenario
[16].
5
Black start capability is critical for power system restoration to have a quick installation of a
new black start generator. During black start restoration, voltage and frequency management
must be ensure. Both should be kept within their nominal ranges to ensure that no equipment
breakdown would seriously impede the restoration process. As voltage stress is major hinder
for a blackstart during the power system restoration. The black start unit should be able to
absorb the produced reactive power from charging current produced by incoming generators,
transformers, and transmission line. Self-excitation could be caused by a higher charging
current indicating that it will result in an uncontrolled voltage rise. Installing shunt reactors will
reduce the amount of time as well as self-excitation. A blackstart must be tested both in steady
state and transient operating condition for feasibility test to operating voltage and power
flow.[17]
7
2.6 Restoration Strategies and guidelines
According to the restoration stages, restoration strategies can be categorized into six types [22],
that is, build‐upward, build‐downward, build‐inward, build‐outward, build‐together, and serve‐
critical. [23]
• Build upward: Many grids characterize as an island with black start capabilities that
must be resynchronized as the restoration operation progresses. The key tasks involves
black start unit starting, island restoration, and island synchronization.
• Build downward: Some smaller or more closely knit utilities with a lower voltage
network to pool their black start power and provide it to nonblack start units, network
energization, and nonblack start unit startup.
• Build inward: Involves starting of central generation station first.
• Build outward: a ring transmission line is reenergized, and the restoration proceeds from
this ring outward.
• Build together: loads nearer to the generating units is picked up first.
Another way of classification of restoration strategies is as top-down and bottom-up.
• Top down: The high voltage system is energized by using the black start units. In this
method, a high voltage grid is established, and then using the sub-transmission network
selected plant is reached. However, energizing lines in the bulk transmission system first
is more difficult and will usually require larger generating units to be on-line but if
successful, it will generally lead to a faster restoration of critical systems and loads
• Bottom up: The sub transmission is energized by using the black start units and it
energize part to supply cranking power to larger units. Here, several simultaneous,
independent islands are formed which are eventually been synchronized and the extra
high-voltage grids are established when the lager plants are on-line. Although this
method can make used of smaller black start units to restore large grids however, this
method consumed longer duration to restore the system compared to top-down
restoration method.
Standards related to power system restoration are as follows [24]:
• EOP‐005‐1: System Restoration Plans
• EOP‐005‐2: System Restoration from Black start Resources
• EOP‐006‐1: Reliability Coordination – System Restoration
• EOP‐006‐2: System Restoration Coordination
• EOP‐007‐0: Establish, Maintain, and Document a Regional Black start Capability Plan
The key information carried in these standards is outlined as follows:
a) The plans, procedures, and resources should be available to restore the power system on
the occurrences of actual outage events.
b) The transmission operator’s system should have adequate black start resources and
reliable paths that reach the nonblack start units. Personnel should regularly drill the
procedures to start up the black start resources.
c) The control actions taken by various restoration participants must be coordinated to
ensure reliability in each phase of restoration.
d) The regional black start capacity plan plays a central role in enabling sufficient black
start capacity to function as expected, and therefore should be maintained and tested on
a periodical basis.
8
Chapter 3: RESTORATION OF THE EASTERN GRID OF
BHUTAN
In this chapter, the eastern grid of Bhutan is discussed. Two restoration plans developed are
covered including approach and results obtained.
9
3.3 Modelling
High quality modelling of hydro power plants for restoration studies with the continuous
deregulation process, it is becoming increasingly vital to verify existing strategies for network
restoration following blackouts in European electrical energy systems. High-quality computer
models of the electrical system are required for this verification, as well as the ability to generate
exact findings for all potential restoration scenarios. The power plants, which must be built with
extreme precision, are the most significant components of these models [25].
The model of the power system was developed as shown in figure. A rudimentary validation
process was used, i.e., checking the power flow to India in normal operation. The simulated
value resembled closely with the data obtained from Bhutan Power System Operator. Moreover,
the model was verified by various power system analysts.
10
Figure 10: Eastern grid of Bhutan modelled in DigSilent PowerFactory
11
3.5 Restoration plans
Two restoration plans were developed and are discussed. The first plan connects MHP to the
Indian grid and gradually restores the system. The second plan connects both the power plants
and then proceeds with the restoration. In the restoration process, voltage profile of all the buses
and the grid frequency was monitored to not violate its limits.
Plan 1 Plan 2
t1 Start one unit of MHP and Establish connection of MHP to Alipurduar via
establish connection to Alipurduar Jigmeling and KHP to Rangia via Nangkor. Start
via Jigmeling. Energize the 220 kV one unit of both KHP and MHP and gradually
Jigmeling bus as well. raise generation to maximum.
t2 Connect western grid. Connect to western grid. Start one more unit of
both KHP and MHP.
Raise KHP generation to pickup loads of
Nangkor, Kilikhar, Corlung, Kanglung and
Phuentshothang.
t3 Pickup Gelephu load. Start one more unit of both KHP and MHP and
gradually raise generation to half of rated power.
t4 Pickup loads of Yurmo and Establish connection of both MHP and KHP at
Tingtibi. Also establish a radial Jigmeling. Establish connection to Salakati.
loop by connecting Yurmo to Pickup Nganglam load.
MHP.
t5 Pickup Nganglam load. Pickup rest of the load gradually by raising
generation of MHP.
t6 Pickup loads of Nangkor, Kilikhar, Start the two generators remaining and gradually
Corlung and Kanglung loads. raise generation to maximum capabilities.
t7 Establish connection to Rangia and -
pickup rest of the domestic load.
t8 Establish connection to Salakati. -
Start all other generators and
gradually raise generation.
12
3.7 Results
A static graph would not suffice the scope of a restorative process as the voltage profiles of all
buses needs to be checked for violation of it 5 % limits at each step of the restoration process.
If a plot of voltage of all the buses are taken, then the simulation must be done individually and
not cumulatively. To address this, dynamic voltage responses of each bus were taken.
Figure 12: Static and dynamic bus voltage profile (Left – Static :Voltage of all the buses at
an instance & Right – Dynamic : Voltage response of one bus for all instance)
Dynamic bus voltages of all the 20 buses were plotted and are compiled under Appendix x.
With the main aim being to not violate voltage limits at any point, the responses of the
restoration plans are as schemed in table 2 ( refers to voltage within limits).
14
Figure 13: Model of Bhutan power system developed in DigSilent PowerFactory
16
4.2 Load sizing
Load frequency control dictates that frequency drops with addition of load or removal of
generation as vice-versa. The load size and the nadir frequency are inversely related thus
quantifying the load that can be picked up by a powerplant is of importance to both islanding
and restoration of power system. While restoration concerns with load pickup, islanding
resonates more towards sudden loss of generation. However, load pickup and generation loss
of same magnitude results in the exact frequency response. Frequency response such as that of
figure 16 was plotted for all the powerplants to determine the maximum allowable load pickup.
17
4.3 Primary governing system
Governor is one of the most important parts of the frequency control system. By appropriately
configuring three primary parameters in the governor: reset time, temporary droop, and
permanent droop, the governor may considerably improve the stability of the power system
[27]. The other important setting of governor is deadband setting.
The HYGOV model was applied with actual parameters from the hydro power plants. This
model is a conventional mechanical-hydraulic nonlinear governor with a rudimentary hydraulic
approximation of a typical hydro power plant's unconstrained head race and tail race.[27].
Dynamic data of power plants were taken from documents such as [28-29] and a few internal
documents of the powerplants.
18
4.3.2 Deadband Setting
Deadband is inserted deliberately in the governor droop characteristic so that turbine or primary
frequency control will not activate until it reaches a preset value. Figure 16 shows the
comparative plot of frequency response associated with and without the deadband.
Currently, some of power plants in Bhutan set their deadband at ±20 mHz [32] whereas some
other plants set their deadband at ±30 mHz. Thus, simulations were done for the isolated Bhutan
power grid by setting a common ±30 mHz deadband.
Input to AGC will be 𝐴𝑟𝑒𝑎 𝑐𝑜𝑛𝑡𝑟𝑜𝑙 𝐸𝑟𝑟𝑜𝑟, 𝐴𝐶𝐸 = 10 × 𝐹𝑅𝐶 × (𝑓 − 𝑓𝑛𝑜𝑚𝑖𝑛𝑎𝑙 ) where, 𝑓 and
𝑓𝑛𝑜𝑚𝑖𝑛𝑎𝑙 are the actual frequency and scheduled frequency in Hz, respectively.
To bring back frequency to the nominal value of 50 Hz, the calculated ACE signal will be sent
to generators equipped with AGC to adjust their power output setpoints to diminish the ACE to
zero.
20
Chapter 5: DISCUSSION
Although power system blackouts are a rare occurrence, it does occur. A large area blackout is
usually caused due to cascading failure. Most cascading failures are caused due to tripping of
major high voltage transmission lines which is most likely caused by single line-ground faults
on it. Other causes of a system wide outage could be physical harm or cyber-attack on the power
system for reasons mostly relating to socio-politics. These outages cause adverse economic and
social effects. Most outages in the eastern grid as due to line to earth fault: an outage is a
possibility however small it may be. The restoration of a system under blackout is rather a
daunting task. If not planned, a restoration process could lead back to a cascading failure, further
lengthening the restoration time. In actual restoration of power plants in the eastern grid, MHP
is usually started by field flashing and thus is blackstart capable. KHP, on the other hand, is said
to requires around 10 MW of power from other powerplants, thus is a non-blackstart unit.
During the initial stages of this research, the authors had treated KHP as a blackstart unit due
to lack of information on it. However, upon several attempts of parallel restoration starting from
both the power plants, the interconnection failed due to power swings. To choose between
restoration strategies, an outage had to be first created. Keeping in mind that most outages have
happened in the past due to tripping of major transmission lines, Jigmeling to Alipurduar line
was tripped. This sudden loss of load resulted in a frequency overshoot. In absence of a defense
plan or controlled separation scheme, such an event would inevitably trip most/all the
generating units due to rotor pole slip. This was further verified by an official at MHP: to test
for the islanding capability of MHP disconnection with India was coordinated. All the
generating units of MHP and KHP were found to trip due to over-speeding of machine. It was
concluded in the internal documents of MHP as well that islanded mode operation of the MHP
is not possible. This means that a top-down strategy is less likely to fail as compared to a bottom-
up strategy, in the case of the grid under consideration.
Restoration plans were developed by hit and trial method, i.e.., if the dynamic responses of
voltage and frequency are not within limits, that step is re-evaluated. In this way, two bottom-
up restoration plans were finalized. A top-down plan was also tried on but is not a part of the
report as a sustained system was not achieved.
To restore the eastern grid of Bhutan from total blackout, plan II seems more effective. This is
evident in table 2 as a greater number of ‘’ relates to a faster restoration. This is because in
plan II both the powerplants are used right from the first instance whereas in plan I only MHP
is used. Moreso, dynamic responses of plan II were noticed better than that of plan I.
The study now focuses on islanding of not just the eastern grid but of the whole Bhutan grid.
Droop setting and Deadband setting are the two main parameters of a governor affecting
frequency response and thus system stability. It is evident that both nadir frequency as well as
final settling frequency improves with the reduction in droop setting. Moreover, figure 16
clearly indicates that the governor response and frequency nadir improve when there is no
deadband setting. This is however not preferable because the governor control will activate all
the times even under small changes in load, which may cause more stability issues.
It is worth noting that the frequency responses in figures 15 and 16 did not return to nominal
because the governor control only arrests and stabilize the frequency, but its function is not
designed for restoring the frequency back to nominal. It can be clearly observed that AGC action
brings back the system frequency to 50 Hz in both scenarios. The more AGC units, the quicker
frequency is restored. However, too many AGC units’ interactions may potentially cause the
low frequency oscillation.
21
Chapter 6: CONCLUSION
Due to increased electrical energy use, modern lifestyles, and energy usage patterns, the
dependence on electric power have been increasing exponentially. This demands the power
system operators to ensure that the power system grid is very reliable and stable. The entire or
partial failure of the system can occur at any moment owing to a variety of events related with
the electrical system, affecting the system's dependability at any time. Unpredictable
phenomena like as lightning, earthquakes, floods, landslides, and other natural disasters might
cause a system outage at any time of the year. As a result, a comprehensive black start study is
necessary for system restoration to return the system back to normal functioning. The black
start procedure is difficult since the operator must return the system to normal in a short period
of time. The studies that should be included in the system black start planning process are
discussed here. Two restoration strategies have been proposed for the case of total blackout in
Bhutan's eastern grid. Of two proposed plans, plan two seem to have shorter restoration time as
compared to plan one as it facilitates the simultaneous restoration from both MHP and KHP.
Furthermore, a complete model development of Bhutan Power System grid has been presented
and discussed. A comparative study on droop characteristics and frequency control during
islanded operation of Bhutan grid have also been discussed here. It also presents the possibility
of operating Bhutan grid in isolated mode with the use of secondary controller that is Automatic
Generation Control scheme.
22
Chapter 7: RECOMMENDATION AND FUTURE SCOPE
Based on the work carried out in this project, following recommendations are made:
Use different strategies for different outages: Power system restoration is dependent upon
power availability. Therefore, depending on the power availability and the type of outages in
the power system grid, different kind of restoration strategies should be used. Therefore,
implementation of Wide Area Measurements typical of a smart system must be explored.
Furthermore, a restorative approach that is able to devise plans in accordance with the extend
of the outage, such as an intelligent system that generates a restoration plan taking in inputs
from the Wide Area Measurement System, should be looked into.
Preparedness: All the findings in the project is exclusively simulation based. Restoration plans
must be put into test to enable preparedness of operators. Absence of a restoration plan in
Bhutan could render havoc during blackouts, thus must be necessitated in the Bhutan power
system.
Secondary Frequency response scheme: In absence of AGC in Bhutan, India in essence acts
as the AGC for Bhutan. This deprives Bhutan of island mode operation. As recommended in
reports after the 2012 India blackout, Bhutan should explore into frequency control schemes
and controlled separation schemes. The AGC discussed could be used in the development of
such schemes, for disconnecting Bhutan grid from Indian grid under the extreme emergency to
avoid further system outages in Bhutan due to disturbances from Indian power grid. Moreover,
since SCADA is essential for AGC, its implementation must be sped up.
Communication Scheme: Developing a more dependable communication scheme for power
system operators, which could make disaster recovery activities more efficient.
Further studies: Similar work can be done using other platforms for power system studies.
Furthermore, more sophisticated approaches such as Artificial Intelligence.
23
REFERENCES
[1] P. Mukhopadhyay, V. Pandey, A. P. Das, C. Kumar, P. A. R. Bende, and K. K. Parbhakar,
“Black Start Experiences for 400 kV Hydro Power Plant In Western Regional Grid of
India,” 2016.
[2] P. Pentayya, A. Gartia, A. P. Das, C. Kumar, K. B. Out, and B. Start, “Black Start
Exercises Experience in Western Region, India,” 2013.
[3] G. Patsakis, D. Rajan, I. Aravena, J. Rios, and S. Oren, “Optimal black start allocation
for power system restoration,” IEEE Trans. Power System.
[4] North American Electric Reliability Council (2002). 1996 system disturbances
[5] U.S.‐Canada Power System Outage Task Force (2004). Final report on the August 14th
blackout in the United States and Canada. Department of Energy and National Resources
Canada.
[6] UCTE Investigation Committee (2003). Interim report of the investigation committee on
the 28 September 2003 blackout in Italy. UCTE Report, October, 27.
[7] Andersson, G., Donalek, P., Farmer, R. et al. (2005). Causes of the 2003 major grid
blackouts in North America and Europe, and recommended means to improve system
dynamic performance. IEEE Trans. Power Syst. 20 (4): 1922–1928.
[8] Romero, J.J. (2012). Blackouts illuminate India’s power problems. IEEE Spectr. 49 (10):
11–12.
[9] Gailwad, A. (2013). Indian blackouts – July 30 & 31 2012 recommendations and further
actions, in IEEE PES General Meeting.
[10] Rampurkar, V., Pentayya, P., Mangalvedekar, H.A., and Kazi, F. (2016). Cascading
failure analysis for Indian power grid. IEEE Trans. Smart Grid 7 (4): 1951–1960.
[11] Lee, R.M., Assante, M.J., and Conway, T. (2016). Analysis of the cyber attack on the
Ukrainian power grid. SANS Industrial Control Systems.
[12] North American Electric Reliability Corporation (2017). 1,200 MW fault induced solar
photovoltaic resource interruption disturbance report.
[13] Australian Energy Market Operator (AEMO) (2017). Black System South Australia 28
September 2016
[14] Yan R., Al Masood N., Saha T.K. et al. (2018). The anatomy of the 2016 South Australia
blackout: A catastrophic event in a high renewable network. IEEE Transactions on Power
Systems.
[15] J. W. Feltes and C. Grande-Moran, “Black start studies for system restoration,” IEEE
Power Energy Soc. 2008.
[16] Feltes, J.J.W. and Grande‐Moran, C. (2008). Black start studies for system restoration,
Proceedings of the IEEE Power and Energy Society.
[17] K. Sun, Y. Hou, W. Sun, and J. Qi, “Black-Start Capability Assessment and
Optimization,” Power Syst. Control Under Cascading Fail.
[18] J. W. Feltes and C. Grande-Moran, “Black start studies for system restoration,” IEEE
Power Energy Soc. 2008.
[19] P. Pradhan, T. Deki, P. Wangmo, D. Dorji, D. Phuntsho, and C. Dorji, “Simulation and
optimization of blackstart restoration plan in Bhutan using DIgSILENT,” 2015 2nd
Internnational conference on recent advancements in engineering and computer science.
[20] K. Sun, Y. Hou, W. Sun, and J. Qi, “Constraints of System Restoration,” Power Syst.
Control Under Cascading Fail.
24
[21] Adibi, M.M., Borkoski, J.N., and Kafaka, R.J. (Nov. 1987). Power system restoration –
the second task force report. IEEE Trans. Power System.
[22] Fink, L.H., Liou, K.L., and Liu, C.C. (May 1995). From generic restoration actions to
specific restoration strategies. IEEE Trans. Power System.
[23] D. Lindenmeyer, H. W. Dommel, and M. M. Adibi, “Power system restoration - a
bibliographical survey,” Int. J. Electr. Power Energy System.
[24] K. Sun, Y. Hou, W. Sun, and J. Qi, “Restoration Methodology and Implementation
Algorithms,” Power Syst. Control Under Cascading Fail.
[25] H. W. Weber, M. Hladky, T. Haase, S. Spreng, and C. N. Moser, High quality modelling
of hydro power plants for restoration studies, vol. 35, no. 1. IFAC, 2002.
[26] Central Electricity Regulatory Commission, "Report on the grid disturbance on 30th July
and 31st July, 2012," Central Electricity Regulatory Commission, Delhi, India, 2012.
[27] P. Wu, "Stability of hydro power plants in island operation," Norwegian University of
Science and Technology, 2016.
[28] DGPCL, "Report on power system modelling of THP generating unit for islanded/radial
mode of operation," DGPCL, Thimphu, 2015.
[29] DGPCL, "Report on power system modelling of CHP generating unit for islanded/radial
mode of operation," DGPCL, Thimphu, 2016.
[30] L. Sigrist, E. Lobato, F. M. Echavarren, I. Egido and L. Rouce, Island power systems,
CRC Press, Taylor & Francis Group, 2016.
[31] EPRI, "EPRI power system dynamics tutorial," Electric Power Research Institute, Inc,
California, 2009.
[32] DGPC, "Operation & maintenance manual," DGPC, Thimphu, 2016.
[33] P. Kundur, Power system stability and control, McGraw-hill, 1993.
[34] B. Nesje, "The need for inertia in the nordic power system," Norwegian University of
Science and Technology, 2015.
25
APPENDICES
Table 4: Sailent features of hydropower plants
26
Table 7: Generator data
Generating Station Name THP CHP KHP BHP (U) BHP (L) DHP MHP
MVA Rating 200 93.33 20 15 26.5 70 200
MW Rating 170 84 15 12 20 62 180
Rated Voltage in kV 13.8 11 11 11 11 11 13.8
Number of Units 6 4 4 2 2 2 4
Minimum Reactive Power in Mvar -17 -8.5 -1.5 -1.2 -2 127
Maximum Reactive Power in Mvar 100 45 8 6 10 140
Armature Resistance 0.002 0.001979 0.0069 0.00404 0.0037 0.00147
Negative Sequence Reactance 0.13 0.1868 0.147 0.17 0.153 0.15
Zero Sequence Reactance 0.1 0.104 0.037 0.09 0.081 10.77/9.16 0.105
Direct Axis Reactance (Xd) 1.02 0.8656 0.93 1.04 1.05 109.81/98.94 1.01
Direct Axis Sub- Transient Reactance (Xd") 0.14 0.165 0.125 0.155 0.161 23.51/19.98 0.13
Direct Axis Transient Reactance (Xd') 0.24 0.215 0.19 0.275 0.22 29.16/26.93 0.24
Quadrature Axis Reactance (Xq) 0.65 0.6 0.56 0.694 0.75 0.65
Quadrature Axis Transient Reactance (Xq') 0.65 0.23 0.56 0.694 0.694 0.65
Quadrature Axis Sub- Transient Reactance ( Xq") 0.145 0.2083 0.204 0.204 0.2 0.16
Direct Axis Transient Open Circuit Time Constant (T'do) 11.8 8.12 4.73 3.9 6.86 9.32/8.46 12.4
Direct Axis Sub - Transient Open Circuit Time Constant (T"do) 0.07 0.0235 0.055 0.03 0.0199 0.084/0.082 0.078
Quadrature Axis Transient Open Circuit Time Constant (T'qo) 0.5 9 5 0.5 0.5 2.40/2.28
Quadrature Axis Sub - Transient Open Circuit Time Constant (T"qo) 0.1 0.1 0.036 0.036 0.33
Inertia Constant (H) ( Gen. + Exciter +Turbine/engine ) in MJ/MVA 3.8 4.09 4.62 1.1796 1.378 4
Neutral Grounding Resistance in Ohms 0.197
AVR Control Block with details for transient stability studies Type-1 Type-1 Type-1 Type-1 Type-1 Type-ST5B
Governor Control Block with details for transient stability studies. Hydro Hydro Hydro Hydro Hydro Hydro-Digital
27
Table 8: Transmission line data
Line Voltage (kV) Length (km) Line R (pu) Line X (pu) Charging B (pu) R-Zero (pu) X-Zero (pu) B-Zero (pu)
Chukha – Semtokha 220 54 0.007776 0.044388 0.07614 0.0228474 0.148878 0.0477522
Chukha – Malbase 220 29.84 0.00429696 0.02452848 0.0420744 0.0126253 0.08226888 0.026387512
Chukha – Birpara *2 220 70.21 0.01011024 0.05771262 0.0989961 0.02970585 0.19356897 0.062086703
Semtokha – BHP 220 44.9 0.0064656 0.0369078 0.063309 0.01899719 0.1237893 0.03970507
BHP – Tsirang 220 46.6 0.0067104 0.0383052 0.065706 0.01971646 0.1284762 0.04120838
Tsirang – Dagachhu 220 20.2 0.0029088 0.0166044 0.028482 0.00854662 0.0556914 0.01786286
Tsirang – Jigmeling 220 33.8 0.0048672 0.0277836 0.047658 0.01430078 0.0931866 0.02988934
Malbase – Singhigoan 220 1.21 0.00017424 0.00099462 0.0017061 0.00051195 0.00333597 0.001070003
Malbase – Samtse 220 40.15 0.0057816 0.0330033 0.0566115 0.01698747 0.11069355 0.035504645
Malbase – Birpara 220 40.77 0.00587088 0.03351294 0.0574857 0.01724979 0.11240289 0.036052911
Singhigoan – Samtse 220 41.15 0.0059256 0.0338253 0.0580215 0.01741057 0.11345055 0.036388945
Dagapela – Dagachhu 220 9.7 0.0013968 0.0079734 0.013677 0.00410407 0.0267429 0.00857771
Dagapela – Jigmeling 220 57.7 0.0083088 0.0474294 0.081357 0.02441287 0.1590789 0.05102411
Kurichhu – Kilikhar 132 10.06 0.00936586 0.00826932 0.0141846 0.00425639 0.02773542 0.008896058
Kurichhu – Nangkor 132 31 0.028861 0.025482 0.04371 0.0131161 0.085467 0.0274133
Nangkor – Dewathang 132 23.31 0.02170161 0.01916082 0.0328671 0.00986246 0.06426567 0.020613033
Nangkor – Nganglam 132 34.07 0.03171917 0.02800554 0.0480387 0.01441502 0.09393099 0.030128101
Dewathang – Motanga 132 10.5 0.0097755 0.008631 0.014805 0.00444255 0.0289485 0.00928515
Motanga – Rangia 132 46.4 0.0431984 0.0381408 0.065424 0.01963184 0.1279248 0.04103152
Nganglam – Tingtibi 132 83.33 0.07758023 0.06849726 0.1174953 0.03525692 0.22974081 0.073688719
Tingtibi – Yurmo 132 32.63 0.03037853 0.02682186 0.0460083 0.01380575 0.08996091 0.028854709
Tingtibi – Jigmeling 132 45.74 0.04258394 0.03759828 0.0644934 0.01935259 0.12610518 0.040447882
Yurmo – MHP *2 132 1.84 0.00171304 0.00151248 0.0025944 0.0007785 0.00507288 0.001627112
Jigmeling – Gelephu 132 15.4 0.0143374 0.0126588 0.021714 0.00651574 0.0424578 0.01361822
Gelephu – Salakati 132 50 0.04655 0.0411 0.0705 0.021155 0.13785 0.044215
Corlung – Kilikhar 132 45.209 0.042089579 0.037161798 0.06374469 0.01912793 0.124641213 0.039978319
Corlung – Kanglung 132 23.702 0.022066562 0.019483044 0.03341982 0.01002832 0.065346414 0.020959679
Nikachhu – MHP *2 132 10 0.00931 0.00822 0.0141 0.004231 0.02757 0.008843
Kanglung – Phuentshothang 132 58 0.053998 0.047676 0.08178 0.0245398 0.159906 0.0512894
28
Phuentshothang – Motanga 132 22 0.020482 0.018084 0.03102 0.0093082 0.060654 0.0194546
Phuentshothang – Motanga 132 22 0.020482 0.018084 0.03102 0.0093082 0.060654 0.0194546
Motanga – Nganglam 132 34.7 0.0323057 0.0285234 0.048927 0.01468157 0.0956679 0.03068521
Tala – Malbase 400 24.01 0.000432 0.01973622 0.0338541 0.01015863 0.06619557 0.021232043
Tala – Siliguri *2 400 146 0.002628 0.120012 0.20586 0.0617726 0.402522 0.1291078
Tala – Siliguri 400 149.5 0.002691 0.122889 0.210795 0.06325345 0.4121715 0.13220285
Malbase – Siliguri 400 125 0.00225 0.10275 0.17625 0.0528875 0.344625 0.1105375
MHP – Jigmeling *4 400 84.345 0.001518 0.06933159 0.11892645 0.03568637 0.232539165 0.074586284
Jigmeling – Alipurduar *2 400 4.76 0.000044 0.00391272 0.0067116 0.00201396 0.01312332 0.004209268
Chukha – Watsa 66 21.88 0.081481 0.01798536 0.0308508 0.00925743 0.06032316 0.019348484
Chukha – Gedu 66 20.4 0.07597 0.0167688 0.028764 0.00863124 0.0562428 0.01803972
Watsa – Chumdo 66 15.1 0.056232 0.0124122 0.021291 0.00638881 0.0416307 0.01335293
Chumdo – Paro 66 24.01 0.089413 0.01973622 0.0338541 0.01015863 0.06619557 0.021232043
Chumdo – Jemina 66 11.78 0.043869 0.00968316 0.0166098 0.00498412 0.03247746 0.010417054
Jemina – Olakha 66 17.66 0.065766 0.01451652 0.0249006 0.00747195 0.04868862 0.015616738
Olakha – Semtokha 66 1.7 0.006331 0.0013974 0.002397 0.00071927 0.0046869 0.00150331
Semtokha – Dechencholing 66 11.5 0.04264 0.009453 0.016215 0.00486565 0.0317055 0.01016945
Semtokha – Lobesa 66 24.33 0.090605 0.01999926 0.0343053 0.01029402 0.06707781 0.021515019
Lobesa – Kewathang 66 21.8 0.081183 0.0179196 0.030738 0.00922358 0.0601026 0.01927774
Kewathang – BHP (L) 66 1.5 0.005586 0.001233 0.002115 0.00063465 0.0041355 0.00132645
BHP (L) – BHP (U) 66 3.08 0.01147 0.00253176 0.0043428 0.00130315 0.00849156 0.002723644
Gedu – Phuentsholing 66 16.7 0.062191 0.0137274 0.023547 0.00706577 0.0460419 0.01476781
Phuentsholing – Malbase 66 8.98 0.033442 0.00738156 0.0126618 0.00379944 0.02475786 0.007941014
Phuentsholing – Gomtu 66 26.9 0.100176 0.0221118 0.037929 0.01138139 0.0741633 0.02378767
Gomtu – Samtse 66 14.8 0.0551152 0.0121656 0.020868 0.00626188 0.0408036 0.01308764
Jemina – Changedaphu 66 9.7 0.010443699 0.0079734 0.013677 0.00410407 0.0267429 0.00857771
Jemina – Changedaphu 66 9.7 0.010443699 0.0079734 0.013677 0.00410407 0.0267429 0.00857771
Pangbisa – Chumdo 66 13.07 0.014072077 0.01074354 0.0184287 0.00552992 0.03603399 0.011557801
Pangbisa - 66 23.78 0.025603213 0.01954716 0.0335298 0.01006132 0.06556146 0.021028654
29
Table 9: Transformer data
From Bus To Bus No. MVAR Specified R (pu or watts) Specified X (pu) Rate A Rate B R01 (pu) X01 (pu)
Chukha 11 Chukha 220 4 105 0.0031 0.1142 105 105 0.0031 0.1142
BHP (U) 11 BHP (U) 66 2 15 0.0481 0.8653 15 15 0.0481 0.8653
BHP (L) 11 BHP 220 2 30 0.0173 0.433 30 30 0.0173 0.433
Dagachhu 11 Dagachhu 220 2 72 0.005 0.12 72 72 0.005 0.12
Kurichhu 11 Kurichhu 132 4 20 0.0281 0.6184 20 20 0.0281 0.6184
Tala 13 Tala 400 6 210 0.0015 0.0686 210 210 0.0015 0.0686
MHP 13.8 MHP 400 4 225 0.0013 0.0667 0 0 0.0013 0.0667
Chukha 220.00 Chukha 66 2 20 0.0267 0.5864 10 20 0.0267 0.5864
Semtokha 220 Semtokha 66 2 50/63 0.0061 0.1961 50 63 0.0061 0.1961
Tsirang 220 Tsirang 66 2 10 0.053 0.8473 10 10 0.053 0.8473
Jigmeling 220 Jigmeling 132 2 63/80 0.0049 0.1565 63 80 0.0049 0.1565
Jigmeling 220 Jigmeling 400 3 167 0.0017 0.0748 167 167 0.0017 0.0748
Malbase 220 Malbase 400 1 200 0.00276154 0.124269 200 200 0.0083 0.2499
Malbase 220 Malbase 66 3 50/63 0.0066 0.1983 0 0 0.0066 0.1983
Singhigoan 220 Singhigoan 66 2 50 0.01 0.2996 50 50 0.01 0.2996
Samtse 220 Samtse 66 2 50/63 0.0061 0.1951 50 50 0.0061 0.1951
Kilikhar 132 Kilikhar 33 2 5 0.008097 0.097163 5 5 0.008097 0.09716
Kanglung 132 Kanglung 33 2 5 0.008097 0.097163 5 5 0.008097 0.09716
Nangkor 132 Nangkor 33 2 5 0.008097 0.097163 5 5 0.008097 0.09716
Dewathang 132 Dewathang 33 2 5 0.008097 0.097163 5 5 0.008097 0.09716
Nganglam 132 Nganglam 33 2 3 0.009751 0.097514 0 0 0.009751 0.09751
Tintibi 132 Tintibi 33 2 3 0.009751 0.097514 3 3 0.009751 0.09751
Yurmo 132 Yurmo 33 2 20 0.009751 0.097514 0 0 0.009751 0.09751
MHP 132 MHP 400 3 67 0.0058 0.1865 67 67 0.0058 0.1865
Gelephu 132 Gelephu 66 2 25 0.0171 0.3928 25 25 0.0171 0.3928
30
Table 10: Outage data for 2017, 2018 and 2019
31
Figure 19:Frequency response of MHP on addition of 40 MW
32
Figure 21:Frequency response of KHP on addition of 4 MW
33
Figure 23:Frequency response of BHP (Lower) on addition of 2.5 MW
34
PLAN 1 VOLTAGE PROFILE
35
Figure 26: Bus voltage profile of restoration plan 1
36
Figure 27: Bus voltage profile of restoration plan 1
37
Figure 29: Bus voltage profile of restoration plan II
38
Figure 30: Bus voltage profile of restoration plan II
39
PLAN 1
t0
t0
t1
t1
40
t2
t2
t3
t3
41
t4
t4
t5
t5
Figure 33: Pictorial representation of restoration plan I
42
t6
t6
t7
t7
Figure 34: Pictorial representation of restoration plan I
43
t8
t8
Figure 35: Pictorial representation of restoration plan I
PLAN 2
t0
44
t1
t1
t2
t2
45
t3
t3
t4
t4
Figure 38: Pictorial representation of restoration plan II
46
t5
t5
t6
Figure 39: Pictorial representation of restoration plan II
t6
47
Glossary
Restoration: Is the process of restoring a part of or a total electric power grid into normal
operation after a partial or total blackout.
Blackout: A total loss in power generation in the system or in grid due to internal or external
factors.
Cascading Failure: is the process in a power system of interconnected parts in which the failure
of one or few parts can trigger the failure of other parts and so on.
Outages: Is a short term or long-term state of electric power loss in each area or section of power
grid.
Overload: A system is said to be overloaded when the connected electrical loads exceed the
ability of the source to maintain supply continuously.
Nadir: It is defined as the minimum value of frequency reached during the transient period.
Excitation: Is the process of generating magnetic field by the means of electric current.
Transient: Power system transient is the outward manifestation of a sudden change in circuit
conditions as when a switch opens or closes, or a fault occurs in a system.
Dynamic stability: Is the ability of power system to return to steady state of operation after
significant disturbances.
Islanding: Is the intentional isolation of a part of power system during external grid
disturbances.
48