Construction Schedule STR DAK ATAP BETON HG @PURI

Project Name: Strart Date: 6/1/2023

Project Manager: End Date: 6/10/2023

TASK DESCRIPTION Unit QTY STATUS START DATE


PEKERJAAN STRUKTUR ATAP 6/1/2023
PERSIAPAN 6/1/2023
Persiapan & Mob Demob Not Started 6/1/2023

PEKERJAAN STRUKTUR BAJA DAK ATAP 6/2/2023


HWF 200X200 kg 224.55 Not Started 6/2/2023
IWF 150X75 (Inc ShearConnector&Pelat Sambun kg 551.32 Not Started 6/3/2023
Chemical Angkur Baut Hilti/Setara M16 bh 20 Not Started 6/3/2023
End Plate 15 mm kg 8.2425 Not Started 6/3/2023
Base Plate 15 mm kg 10.5975 Not Started 6/3/2023
Baut 1/2' A325 bh 118 Not Started 6/3/2023
Cat Konstruksi Baja kg 794.71 Not Started 6/3/2023
Bondek T=0.75 m2 21.6 Not Started 6/5/2023
Wiremesh M7-150 (1lapis) m2 21.6 Not Started 6/5/2023
Beton K-300 (fc'=20) (fc'=25) Ready Mix (Incl Gro m3 1.4256 Not Started 6/6/2023
Screed Adukanuntuk kemiringan Dak Beton (5cm m3 1.107 Not Started 6/8/2023
Water Proofing Coating Polyurethane Rebbar m2 22.14 Not Started 6/9/2023
Biaya Bobok dan Bongkar Finishing untuk Chems LS 1 Not Started 6/10/2023
House keeping LS 1 Not Started 6/7/2023
ETON HG @PURI (R1)
Total Duration: 10 Days

END DATE DURATION COMMENTS 6/1/2023


6/10/2023 10 PEKERJAAN STRUKTUR ATAP
6/2/2023 2 PERSIAPAN
6/2/2023 2 Persiapan & Mob Demob

6/10/2023 9 PEKERJAAN STRUKTUR BAJA DAK ATAP


6/3/2023 2 HWF 200X200
6/4/2023 2 IWF 150X75 (Inc ShearConnector&Pelat Sambungan-Las+Chamber)
6/4/2023 2 Chemical Angkur Baut Hilti/Setara M16
6/4/2023 2 End Plate 15 mm
6/4/2023 2 Base Plate 15 mm
6/4/2023 2 Baut 1/2' A325
6/4/2023 2 Cat Konstruksi Baja
6/6/2023 2 Bondek T=0.75
6/6/2023 2 Wiremesh M7-150 (1lapis)
6/6/2023 1 Beton K-300 (fc'=20) (fc'=25) Ready Mix (Incl Grouting Non Shrink)
6/8/2023 1 Screed Adukanuntuk kemiringan Dak Beton (5cm ~ 2cm)
6/9/2023 1 Water Proofing Coating Polyurethane Rebbar
6/10/2023 1 Biaya Bobok dan Bongkar Finishing untuk Chemset dan Support temporary saat pengecoran
6/10/2023 4 House keeping
START DATE DU
STATUS

Not Started
In Progress
Complete
On Hold

6/1/2023
10/06/2023
AAN STRUKTUR ATAP
PERSIAPAN
iapan & Mob Demob

KTUR BAJA DAK ATAP


HWF 200X200
ungan-Las+Chamber)
aut Hilti/Setara M16
End Plate 15 mm
Base Plate 15 mm
Baut 1/2' A325
Cat Konstruksi Baja
Bondek T=0.75
mesh M7-150 (1lapis)
Grouting Non Shrink)
k Beton (5cm ~ 2cm)
Polyurethane Rebbar
ary saat pengecoran
House keeping
START DATE DURATION
KURVA S PEKERJAAN STR DAK ATAP BETON H

NO Pekerjaan Satuan Volume Harga Satuan Harga Total durasi bobot (%)
1
1 PEKERJAAN STRUKTUR BAJA DAK ATAP Rp 44,544,815.07 9 100.00
2 HWF 200X200 kg 224.55 Rp 28,540.00 Rp 6,408,657.00 2 14.39
3 IWF 150X75 (Inc Shea kg 551.32 Rp 30,995.00 Rp 17,088,163.40 2 38.36
4 Chemical Angkur Baut H bh 20 Rp 32,815.00 Rp 656,300.00 2 1.47
5 End Plate 15 mm kg 8.2425 Rp 26,710.00 Rp 220,157.18 2 0.49
6 Base Plate 15 mm kg 10.5975 Rp 26,710.00 Rp 283,059.23 2 0.64
1 Baut 1/2' A325 bh 118 Rp 4,965.00 Rp 585,870.00 2 1.32
2 Cat Konstruksi Baja kg 794.71 Rp 2,750.00 Rp 2,185,452.50 2 4.91
3 Bondek T=0.75 m2 21.6 Rp 331,635.00 Rp 7,163,316.00 2 16.08
4 Wiremesh M7-150 (1lap m2 21.6 Rp 59,435.00 Rp 1,283,796.00 2 2.88
5 Beton K-300 (fc'=20) (f m3 1.4256 Rp 2,133,620.00 Rp 3,041,688.67 1 6.83
6 Screed Adukan untuk k m3 1.107 Rp 934,985.00 Rp 1,035,028.40 1 2.32
1 Water Proofing Coating m2 22.14 Rp 48,905.00 Rp 1,082,756.70 1 2.43
2 Biaya Bobok dan Bongka ls 1 Rp 3,510,570.00 Rp 3,510,570.00 1 7.88

Jumlah Rp 44,544,815.07 100 - 1 2


jumlah akumulatif
R DAK ATAP BETON HG @PURI (R1)

hari
Chart Title
2 3 4 5 6 7 8 9 10 11 12
11.11 11.11 11.11 11.11 11.11 11.11 11.11 11.11 11.11
7.19 7.19
19.18 19.18
0.74 0.74
0.25 0.25
0.32 0.32
0.66 0.66
2.45 2.45
8.04 8.04
1.44 1.44
6.83
2.32
2.43
7.88

1 7.19 2 30.79 3 23.59 49.48 16.31


5 6- 2.32
7 2.438 7.889 - -
7.19 38.0 61.6 71.1 87.4 87.4 89.7 92.1 100.0 100.0 100.0
Schedule Manpower PEKERJAAN STR DAK ATAP BETON HG @PURI (R

hari / Crew (Grup)


NO Pekerjaan Satuan Volume durasi
1 2 3 4 5 6
1 PEKERJAAN STRUKTUR BAJA DAK ATAP 9 11.11 11.11 11.11 11.11 11.11
2 HWF 200X200 kg 224.55 2 2.00 1.00
3 IWF 150X75 (Inc Shea kg 551.32 2 0.50 1.00
4 Chemical Angkur Baut H bh 20 2 0.10 0.20
5 End Plate 15 mm kg 8.2425 2 0.10 0.20
6 Base Plate 15 mm kg 10.5975 2 0.10 0.20
1 Baut 1/2' A325 bh 118 2 0.10 0.20
2 Cat Konstruksi Baja kg 794.71 2 0.10 0.20
3 Bondek T=0.75 m2 21.6 2 1.00 0.25
4 Wiremesh M7-150 (1lap m2 21.6 2 1.00 0.25
5 Beton K-300 (fc'=20) (f m3 1.4256 1 1.50
6 Screed Adukan untuk k m3 1.107 1
1 Water Proofing Coating m2 22.14 1
2 Biaya Bobok dan Bongka ls 1 1

Jumlah - 2.00 2.00 2.00 2.00 2.00


jumlah akumulatif 2.00 4.0 6.0 8.0 10.0
P BETON HG @PURI (R1)

hari / Crew (Grup) Catatan 1 Grup: 1 Tukang & 1 kenek


7 8 9 10 11 12
11.11 11.11 11.11 11.11 Total ada 2 Grup dengan Kumulatif Grup adalah 13 Gr

1.00
1.00
1.00

- 1.00 1.00 1.00 - -


10.0 11.0 12.0 13.0
Tukang & 1 kenek

engan Kumulatif Grup adalah 13 Grup atau 26 Manpower