Construction Schedule
Construction Schedule
Not Started
In Progress
Complete
On Hold
6/1/2023
10/06/2023
AAN STRUKTUR ATAP
PERSIAPAN
iapan & Mob Demob
NO Pekerjaan Satuan Volume Harga Satuan Harga Total durasi bobot (%)
1
1 PEKERJAAN STRUKTUR BAJA DAK ATAP Rp 44,544,815.07 9 100.00
2 HWF 200X200 kg 224.55 Rp 28,540.00 Rp 6,408,657.00 2 14.39
3 IWF 150X75 (Inc Shea kg 551.32 Rp 30,995.00 Rp 17,088,163.40 2 38.36
4 Chemical Angkur Baut H bh 20 Rp 32,815.00 Rp 656,300.00 2 1.47
5 End Plate 15 mm kg 8.2425 Rp 26,710.00 Rp 220,157.18 2 0.49
6 Base Plate 15 mm kg 10.5975 Rp 26,710.00 Rp 283,059.23 2 0.64
1 Baut 1/2' A325 bh 118 Rp 4,965.00 Rp 585,870.00 2 1.32
2 Cat Konstruksi Baja kg 794.71 Rp 2,750.00 Rp 2,185,452.50 2 4.91
3 Bondek T=0.75 m2 21.6 Rp 331,635.00 Rp 7,163,316.00 2 16.08
4 Wiremesh M7-150 (1lap m2 21.6 Rp 59,435.00 Rp 1,283,796.00 2 2.88
5 Beton K-300 (fc'=20) (f m3 1.4256 Rp 2,133,620.00 Rp 3,041,688.67 1 6.83
6 Screed Adukan untuk k m3 1.107 Rp 934,985.00 Rp 1,035,028.40 1 2.32
1 Water Proofing Coating m2 22.14 Rp 48,905.00 Rp 1,082,756.70 1 2.43
2 Biaya Bobok dan Bongka ls 1 Rp 3,510,570.00 Rp 3,510,570.00 1 7.88
hari
Chart Title
2 3 4 5 6 7 8 9 10 11 12
11.11 11.11 11.11 11.11 11.11 11.11 11.11 11.11 11.11
7.19 7.19
19.18 19.18
0.74 0.74
0.25 0.25
0.32 0.32
0.66 0.66
2.45 2.45
8.04 8.04
1.44 1.44
6.83
2.32
2.43
7.88
1.00
1.00
1.00