Name Of Work : Construction of Six Lane Link Road (NH-166S) with Paved Shoulder configuration to Mopa Airport in the state of Goa on EPC Mode

Name Of Client : Chief Engineer (NH)Government of Goa on behalf of Ministry of Road Transport & Highways (MoRT & H)
Name Of Auth. Engineer : M/s TPF Engineering Private Limited
Name Of Contractor : M/s Ashoka Buildcon Limited

ESCALATION SUMMARY
WORK DONE FOR THE COMPLETION OF A STAGE UNDER
DATES
THE FOLLOWING ITEMS OF SCHEDULE-H
RA Bill 3 MONTHS WORK DONE
IPC NO BASE DATE Culverts, Minor REMARKS
DATE PRIOR TO AMOUNT Earthwork, Granular Cement Concrete Major Bridges and
IPC BILL Bituminous Work Bridges and other
Work and Other Works Pavement Structures
Structures
1 W.E.F Interchange Foundations,Viaduct foundations
Jun-22 Feb-22 56,59,85,339.00 - 56,59,85,339.00
31-07-2021 & Girders casting
Interchange Foundations &
2 W.E.F Substructures,Viaduct -1 & 2 foundations &
Aug-22 Apr-22 20,48,41,087.00 - 92,36,972.00 19,56,04,115.00
31-07-2021 Girders/Segment casting,Box culverts,ROB
fabrication
TOTAL = 77,08,26,426 - - - - 76,15,89,454.00

Escalation Summary Item Wise


Sr. No. Items Amount Remarks
1 Labour 15,11,337.05
2 Cement 34,43,275.71
3 Steel 1,69,41,281.37
4 Fuel -29,19,948.29
5 Other 1,46,30,826.01
6 Plant and Spars 40,02,015.00
7 Bitumen
Total upto Escalation Bill-02 3,76,08,786.86 (A)
Paid in previous Escalation:-
Esc. Bill No. -1 2,06,38,655.39
Net Amount to paid Esc Bill No-2= 1,69,70,131.48
Note :- (1) Base Date is taken 28 days prior to the BID submission Date 23-08-2021 is no the last day of month,Hence july 2021 indices considered
(2)Bill date 31.08.2022-3 Months prior to the month to which IPC relates i.e April -2022 Incides

Team Leader
Project Head Authority Engineer Assistant Engineer VII
M/s Ashoka Buildcon Limited M/s TPF Engineering Private Limited National Highway Sub-Div II.
EPC Contractor

Page 1 of 1