Professional Documents
Culture Documents
Project Summary
Project Summary
Certified that the conveyance leads and lifts provided in the data have been verified and are the minimum necessary for the
procurement of materials
Project Engineer
THE KERALA LAND DEVELOPMENT CORPORATION LIMITED
Data Sheet For Panmana and Clappana Panchayath
Per Unit
estimate
Rate Amount
Quantity Description Remarks
Rs. Ps. Rs. Ps.
1 10 m3 Earth work excavation in Ordinary soil and
depositing on bank with initial lead and lift
neat banking etc.Complete
Labour
0.9 Man 240.00 E 216.00
2.063 Man 240.00 E 495.12
Total 711.12
Add 15% , Revised SOR 106.67
Total 817.79
Rate 817.79 818 / 10m3
2 10 m3 Earth work excavation in ordinary soil in
or under water or in liquid mud and
depositing on bank with initial lead and lift
neat banking etc.Complete
Labour
0.7 Man 240.00 E 168.00
Total 168.00
Add 15% , Revised SOR 25.20
Total 193.20
Add 5% Overhead charges 9.66
Rate 202.86 203 / m3
4 m3 Dry stone masonry using dismantled rubble
including labour charges only
Labour
0.8 Rubble Mason 471.00 E 376.80
0.7 Man 240.00 E 168.00
Total 544.80
Add 15% , Revised SOR 81.72
Total 626.52
Rate 626.52 627 / m3
Item no of
Per Unit
estimate
Rate Amount
Quantity Description Remarks
Rs. Ps. Rs. Ps.
5 m 3
Dry stone masonry for retaining wall
including cost and conveyance of rubble
and all labour charges etc. Complete
Material
1.05 m 3
Blasted rubble 420.00 m3 441.00
1.05 m3 Conveyance 607.00 m 3
637.35
Labour
0.8 Mason 471.00 E 376.80
0.7 Man 240.00 E 168.00
Total 1623.15
Add 15% , Revised SOR 243.47
Total 1866.62
Rate 1866.62 1867 / m3
6 m3 Dry stone masonry for retaining wall in or
under water or in liquid mud including cost
and conveyance of rubble and all labour
charges etc. Complete
Labour Charge
0.80 Mason 471.00 E 376.80
0.7 Man 240.00 E 168.00
Add 20% Labour for in or water 108.96
1.05 m3 Conveyance of rubble 607.00 m3 637.35
1.05 m3 Cost of rubble 420.00 m3 441.00
Total 1732.11
Add 15% , Revised SOR 259.82
Total 1991.93
Rate 1991.93 1992 / m3
7 m3 Random rubble masonry in cement mortar
1:6 for retaining wall including
simultaneous pointing of the exposed faces
and conveyance of material and all labour
charges etc. Complete
Conveyance
1 m3 Blasted rubble 607.00 m3 607.00
0.3 m3 Sand 1039.00 m 3
311.70
72 kg Cement 375.00 T 27.00
Cost of Materials
1 m3 Blasted rubble 420.00 m3 420.00
0.3 m3 Sand 2314.00 m3 694.20
72 kg Cement 5940.00 T 427.68
Labour
0.70 Mason 471.00 E 329.70
0.35 Man 240.00 E 84.00
0.70 Woman 377.00 E 263.90
Total 3165.18
Add 15% , Revised SOR 474.78
Total 3639.96
Rate 3639.96 3640 / m3
Item no of
Per Unit
estimate
Rate Amount
Quantity Description Remarks
Rs. Ps. Rs. Ps.
8 10 dm 3
Cement concrete 1:3:6 using 20mm
(nominal size)broken stone including cost
and conveyance of materials and all labour
charges etc. Complete
Cost of Materials
0.009 m3 Broken Stone 942.00 m3 8.48
0.0045 m3 Sand 2314.00 m 3
10.41
2.16 kg Cement 5940.00 T 12.83
Conveyance
0.009 m3 Broken Stone 607.00 m3 5.46
0.0045 m3 Sand 1039.00 m 3
4.68
2.16 kg Cement 375.00 T 0.81
Labour
0.002 Mason 325.00 E 0.65
0.010 Man 240.00 E 2.40
0.035 Woman 240.00 E 8.40
Total 54.12
Add 15% , Revised SOR 8.12
Total 62.24
Rate 62.24 62 / 10dm3
9 Each Supplying at site 1/2 split well matured
coconut posts 3m long including cost
conveyance and all labour charges etc.
Complete
Sub Data
Cost of full size coconut post7.5
1.0 No 406.00 E 406.00
(Average) long
Sawying(4.30sawyer post10m2
2.25 m2 1960.80 10m2 441.18
sawing)
0.02 Man for assisting sawyer 240.00 E 4.80
Total 851.98
Hence for 1Metre 820.05/(7.5x2) 56.80
3.02 1/2 split coconut post 56.80 M 171.53
Add Conveyance LS 25.00
Total 196.53
Add 15% , Revised SOR 29.48
Total 226.01
Rate 226.01 226 /E
10 E Driving down the above coconut posts
to lines and levels 2.5m below bed
level including all labour charges
etc.Complete
0.05 Carpenter for sharpen the post 500.00 E 25.00
0.30 Man for handling fixing in position
113.10
and helping in driving down the posts 377.00 E
0.30 Pile driver for driving the posts 456.00 E 136.80
Hire for tools and plants LS 5.00
Total 279.90
Add 15% , Revised SOR 41.99
Total 321.89
Total 321.89 322 /E
M 100=
Item no of
Per Unit
estimate
Rate Amount
Quantity Description Remarks
Rs. Ps. Rs. Ps.
11 10 m 3
M 100=
Formation of bund using excavated earth
including labour charges for trimming,
dressing and sectioning of berms or slopes
etc. complete.
0.35
Man for trimming, dressing and sectioning
377.00 E 131.95
of berms
DATA SHEET
Item no of
Per Unit
estimate Rate Amount
Quantity Description Remarks
Rs. Ps. Rs. Ps.
1 10 m 3
Earth work excavation in Ordinary soil and
depositing on bank with initial lead and lift
neat banking etc.Complete
Labour
0.9 Man 377.00 E 339.30
2.063 Man 377.00 E 777.75
Total 1117.05
Add 15% , Revised SOR 167.56
Total 1284.61
Rate 1284.61 1285/ 10m3
2 10 m3 Earth work excavation in ordinary soil in
or under water or in liquid mud and
depositing on bank with initial lead and lift
neat banking etc.Complete
Labour
0.7 Man 377.00 E 263.90
Total 263.90
Add 15% , Revised SOR 39.59
Total 303.49
Rate 303.49 303/ m3
4 m3 Dry stone masonry using dismantled rubble
including labour charges only
Labour
0.8 Rubble Mason 471.00 E 376.80
0.7 Man 377.00 E 263.90
Total 640.70
Add 15% , Revised SOR 96.11
Total 736.81
Rate 736.81 737/ m3
5 m 3
Dry stone masonry for retaining wall
including cost and conveyance of rubble
and all labour charges etc. Complete
Material
1.05 m 3
Blasted rubble 420.00 m3 441.00
1.05 m3 Conveyance 607.00 m 3
637.35
Labour
0.8 Mason 471.00 E 376.80
0.7 Man 377.00 E 263.90
Total 1719.05
Add 15% , Revised SOR 257.86
Item no of
Per Unit
estimate
Rate Amount
Quantity Description Remarks
Rs. Ps. Rs. Ps.
Total 1976.91
Rate 1976.91 1977/ m3
6 m3 Dry stone masonry for retaining wall in or
under water or in liquid mud including cost
and conveyance of rubble and all labour
charges etc. Complete
Labour Charge
0.80 Mason 471.00 E 376.80
0.7 Man 377.00 E 263.90
Add 20% Labour for in or water 128.14
1.05 m3 Conveyance of rubble 607.00 m3 637.35
3
1.05 m Cost of rubble 420.00 m3 441.00
Total 1847.19
Add 15% , Revised SOR 277.08
Total 2124.27
Rate 2124.27 2124/ m3
7 m3 Random rubble masonry in cement mortar
1:6 for retaining wall including
simultaneous pointing of the exposed faces
and conveyance of material and all labour
charges etc. Complete
Conveyance
1 m3 Blasted rubble 607.00 m3 607.00
0.3 m3 Sand 1039.00 m 3
311.70
72 kg Cement 375.00 T 27.00
Cost of Materials
1 m3 Blasted rubble 420.00 m3 420.00
0.3 m3 Sand 2314.00 m 3
694.20
72 kg Cement 5940.00 T 427.68
Labour
0.70 Mason 471.00 E 329.70
0.35 Man 377.00 E 131.95
0.70 Woman 377.00 E 263.90
Total 3213.13
Add 15% , Revised SOR 481.97
Total 3695.10
Rate 3695.10 3695/ m3
8 10 dm3 Cement concrete 1:3:6 using 20mm
(nominal size)broken stone including cost
and conveyance of materials and all labour
charges etc. Complete
Cost of Materials
0.009 m3 Broken Stone 942.00 m3 8.48
0.0045 m 3
Sand 2314.00 m3 10.41
2.16 kg Cement 5940.00 T 12.83
Conveyance
0.009 m3 Broken Stone 607.00 m3 5.46
0.0045 m3 Sand 1039.00 m 3
4.68
2.16 kg Cement 375.00 T 0.81
Labour
0.002 Mason 325.00 E 0.65
0.010 Man 377.00 E 3.77
0.035 Woman 377.00 E 13.20
Total 60.28
Add 15% , Revised SOR 9.04
Total 69.33
Item no of
Per Unit
estimate
Rate Amount
Quantity Description Remarks
Rs. Ps. Rs. Ps.
2x10x30
6 M 100=
No.of bamboo posts 100/9=11.11Nos 11Nos
1/2 split bamboo wailing pieces 2x2x10 40M
No.of bamboo required 40/(2x9) 2Nos
1/2 split bamboo struts 11x2 22.00
No.of bamboo required 32/(2x9) 1.00
1/2 split bamboo reapers
30cm c/c 2x10x2/(0.3x4) 33.33M
No.of Bamboo required 33.33/9 4Nos
Totalnos.ofbamboo require(11+2+1+4) 18Nos
18.0 Nos Hire charge of M
bamboo
100=1st class(1/2rate) 105/2 E 945.00
18.0 Nos Conveyance LS 108.00
40x30
30Nos of cudjans madals is required to
120
screen 10m2 area No. of cudjans madals
10
120 Nos Coconut cudjan madals 900.00 100Nos 1080.00
120 Nos Conveyance LS 108.00
2.0 kg Coir Yarn 161.00 kg 322.00
1.0 Nos Carpenter 500.00 E 500.00
10.0 Nos Special man masdoor for driving down the
post laying coconut cudjan madals etc.
Compete. 408.00 E 4080.00
30.0 m3 earth work filling (1x10x0.8x1.5)=12 1340.46 10m3 4021.38
30.0 m3 Conveyance of earth 325.00 m3 9750.00
Labour for dismantling
6.0 Nos Man 377.00 E 2262.00
30.0 m3 Earth work cutting 1340.46 10m3 4021.38
Total 27197.77
Add 15% , Revised SOR 4079.66
Total 31277.43
Total 31277.43
Hence for 1Metre 3127.74 3128/ m
10 1 Hr Bailing out water using 5HP diesel engine
and pump set including hire charge,
conveyance to site and errection cost of
fuel, lubricating oil and other stores, pay of
staff etc. Compete.
Item no of
Per Unit
estimate
Rate Amount
Quantity Description Remarks
Rs. Ps. Rs. Ps.
Cost of 5HP Diesel engine and pump set 25000.00 E
25000x30
Hire charges E 7500.00
100
Hire charges for one month 7500/10 E 750.00
Hire charge for one day 750/20 E 37.50
1 Day Hire charge of engine 70.00 Day 70.00
10 Lt H.S.D oil 45.00 Lt 450.00
Lubricating oil LS 5.00
1 Driver 396.00 E 396.00
1 Cleaner 396.00 E 396.00
Installation charges LS 5.00
Conveyance charges LS 5.00
Total 1327.00
Add 15% , Revised SOR 199.05
Total 1526.05
Total 1526.05 1526/ day
Hence for 1 Hr. =1077.25/8 190.76 191/ Hr.
11 10 m2 Shoring the side of trench using wooden
planks and joists and labour for taking
down after completion including hire and
labour charges for maintaining the
structure until dismantling
10 m2 Form work for cement concrete using
wooden planks joists , bamboo posts and
labour for taking down after completion
including hire and labour charges for
maintaining the structure until dismantling
Per Unit
estimate
Rate Amount
Quantity Description Remarks
Rs. Ps. Rs. Ps.
Add 15% , Revised SOR 522.74
Total 4007.69
Rate 4007.69 4008/ m3
13 1.0 m 3
Cement concrete 1:4:8 using 40mm
(nominal size)broken stone including cost
and conveyance of materials, , curing and
all labour charges etc. Complete
Materials
0.95 m 3
Broken stone 659.00 m3 626.05
0.48 m3 Sand 2314.00 m3 1110.72
171 kg Cement 5940.00 T 1015.74
Conveyance
0.95 m3 Broken stone 607.00 m3 576.65
0.48 m3 Sand 1039.00 m3 498.72
171 kg Cement 375.00 T 64.13
Labour
0.1 Mason 471.00 E 47.10
1.0 Man 377.00 E 377.00
1.4 Women 377.00 E 527.80
Total 4843.91
Add 15% , Revised SOR 726.59
Total 5570.49
Rate 5570.49 5570/ m3
14 1.0 m3 Graded cement concrete 1:3:6 using 60%
of 40mm and 40% 20mm(nominal size)
broken stone including cost and
conveyance of materials , consolidation,
curing, but excluding cost of
reinforcement etc.complete.
Materials
0.57 m3 40mm Broken stone 659.00 m3 375.63
0.36 m3 20mm Broken stone 942.00 m3 339.12
0.47 m3 Sand 2314.00 m3 1087.58
223.2 kg Cement 5940.00 T 1325.81
Conveyance
0.93 m3 Broken stone 607.00 m3 564.51
0.47 m 3
Sand 1039.00 m 3
488.33
223.2 kg Cement 375.00 T 83.70
Labour
0.140 Mason 471.00 E 65.94
1.00 Man 377.00 E 377.00
2.24 Women 377.00 E 844.48
Total 5552.10
Add 15% , Revised SOR 832.81
Total 6384.91
Rate 6384.91 6385/ m3
15 10 dm 3
Reinforced cement concrete 1:2:4 using
20mm (nominal size)broken stone
including cost and conveyance of materials
and all labour charges etc. Complete
Cost of Materials
0.009 m3 Broken Stone 942.00 m3 8.48
0.0045 m3 Sand 2314.00 m 3
10.41
3.30 kg Cement 5940.00 T 19.60
Conveyance
0.009 m3 Broken Stone 607.00 m3 5.46
0.0045 m3 Sand 1039.00 m 3
4.68
Item no of
Per Unit
estimate
Rate Amount
Quantity Description Remarks
Rs. Ps. Rs. Ps.
3.30 kg Cement 375.00 T 1.24
Labour
0.002 Mason 325.00 E 0.65
0.010 Man 377.00 E 3.77
0.035 Woman 377.00 E 13.20
Total 67.48
Add 15% , Revised SOR 10.12
Total 77.60
Rate 77.60 78/ 10dm3
16 10.0 dm 3
Reinforced cement concrete
1:11/2:3 using 20mm(nominal size) broken
stone including cost and conveyance of
materials, consolidation, curing but
excluding steel reinforcement etc.complete.
Materials
0.009 m3 20mm Broken stone 942.00 m3 8.48
0.0045 m 3
Sand 2314.00 m 3
10.41
4.32 kg Cement 5940.00 T 25.66
Conveyance
0.009 m3 Broken stone 607.00 m3 5.46
0.0045 m 3
Sand 1039.00 m3 4.68
4.32 kg Cement 375.00 T 1.62
Labour
0.002 Mason 325.00 E 0.65
0.01 Man 377.00 E 3.77
0.035 Women 377.00 E 13.20
Total 73.93
Add 15% , Revised SOR 11.09
Total 85.01
Rate 85.01 85/ 10dm3
Per Unit
estimate
Rate Amount
Quantity Description Remarks
Rs. Ps. Rs. Ps.
3.80 dm 3
Deduct cost of outer slab @ 25% of log m 3
33063.00 31.41
value
Net 516.94
10.5 dm3 Anjili wood scantling 516.94 10dm3 542.79
10.5 dm3 Conveyance 856.00 m3 8.99
Labour
0.04 Carpenter 500.00 E 20.00
0.04 Man 377.00 E 15.08
Total 586.86
Add 15% , Revised SOR 88.03
Total 674.89
Rate 674.89 675/ 10dm3
a Anjily wood
Cost of Materials
14.400 dm3 Anjily wood 33063.00 m3 476.11
Labour
Man - Put log in position and to assist
0.020 377.00 E 7.54
sawyers
0.330 m2 Sawyer ( 6.40 sawyers for 10m2) 2918.40 10 m2 96.31
Deduct cost of outerslab at 25% of log
3.800 dm3 8265.75 m3 -31.41
value
14.400 dm3 conveyance 856.00 m3 12.33
Total 560.87
Per Unit
estimate
Rate Amount
Quantity Description Remarks
Rs. Ps. Rs. Ps.
Add 10% total labour charge extra 3.51
Total 624.14
Rate 624.14 624/ 10dm3
Rate of Anjily wood
Labour
0.500 Black smith 500.00 E 250.00
0.200 Heavy load Mazdoor 396.00 E 79.20
0.300 Fitter for marking 456.00 E 136.80
0.100 Heavy load Mazdoor 408.00 E 40.80
Cutting the plates, Angles for size
1.250 Black smith 500.00 E 625.00
1.500 Heavy load Mazdoor 396.00 E 594.00
Punching holes
0.500 Black smith 500.00 E 250.00
0.500 Heavy load Mazdoor 396.00 E 198.00
Welding- Vide item No.755
Cost of Materials
100.000 Nos Welding rod (8 gauge) 420.00 Nos 420.00
Labour
1.000 Welder 471.00 E 471.00
1.000 Heavy load Mazdoor 396.00 E 396.00
2.500 Blacksmith for grinding 500.00 E 1250.00
Current charge, hire for welding plant 0.00 LS 55.00
Sundries 0.00 LS 30.00
Grinding stone 0.00 LS 20.00
Total 8961.30
Rate 8961.30 8961/ Qtl
Quantity of steel used for the shutter
Steel plate 5. x 6 mm thick
Front side shutter
Vertical 3 x 1.80 5.40
Horizontal
3 x 1.50 4.50
Diagonal
4 x 0.30 1.20
Back side the shutter
Vertical
2 x 1.80 3.60
Horizontal
2 x 1.50 3.00
Inclined
2 x 2.34 4.68
Total 22.38
Say 22.38m @ 2.40 Kg/m 53.71 54/ Kg
Item no of
Per Unit
estimate
Rate Amount
Quantity Description Remarks
Rs. Ps. Rs. Ps.
Equal angles 50 x 50x 6 mm size
Vertical
2 x 1.80 3.60
Horizontal
2 x 1.50 3.00
Diagonal
4 x 0.30 1.20
Total 7.80
Say 7.80m @ 4.50Kg/m 35.10 35/ Kg
Per Unit
estimate
Rate Amount
Quantity Description Remarks
Rs. Ps. Rs. Ps.
d Painting with shutter of suitable
colour, using quality of paint, two
coats including labour charge etc
complete.
Vide item No.606 (First coat)
1L approved quality of paint 57.00 Litre 57.00
Sundries, brush, Soap,putty Ls 10.00
Labour
0.250 Painter 396.00 E 99.00
Vide item No.607 (Second coat)
0.65 L approved quality of paint 57.00 Litre 37.05
Sundries, brush, Soap,putty Ls 5.00
Labour
0.200 Painter 396.00 E 79.20
Total 287.25
Per Unit
estimate
Rate Amount
Quantity Description Remarks
Rs. Ps. Rs. Ps.
1 Supplying and sitting in position M.S
Shutter of size 2.15m x 2.00m with screw
gear arragement doing M.S plates 6mm
thick over M.S Angle frame width 65 x65
x65 mm allround and that of 2 nos
intermediate vertical and two nos
intermediate horizontal with same angle
section providing screw gear arragement
with 56 mm dia M.S spiral shaft Collar
nuts and sitting over M.S plate of require
size and guide grooves fro rotating . The
collar nut looking arragement with plates
and nuts, supplying one number spanner
with handle to suitable size and shape to
operate the shutter . Painting the whole
with Black Japan paint over a priming coat
etc. complete after dismantling and
removing the existing damaged wooden
shutter including all cost and conveyance
of materials and all labour charges but
excluding cost of concrete.
Cost of Materials
1.050 Qtl M.S. Plate 5000.00 Qtl 5250.00
Conveyance
1.050 Qtl M.S. Plate 323.00 Qtl 339.15
Labour
0.500 Blacksmith 500.00 E 250.00
1.000 Man Mazdoor 377.00 E 377.00
Sundries LS 3.00
Total 6219.15
Rate 6219.15 6219/ Qtl
2 Qtl Sub data for M.S Angles
Cost of Materials
1.050 Qtl M.S. Angles 4410.00 Qtl 4630.50
Conveyance
1.050 Qtl M.S. Angles 323.00 Qtl 339.15
Labour
2.000 Blacksmith 500.00 E 1000.00
Total 5969.65
Rate 5969.65 5970/ Qtl
3 30 m Sub data for welding
Cost of Materials
180.000 Nos Welding Electrode (8 g) 541.00 100 Nos 973.80
Labour
3.750 Nos Welders 471.00 E 1766.25
Consumer charge and hire charges for
LS 10.00
welding plant
Total 2750.05
Hence for 1Metre 91.67
Cost of Materials
1.000 Nos 1 No 56 mm dia shaft 19.34 Kg
Item no of
Per Unit
estimate
Rate Amount
Quantity Description Remarks
Rs. Ps. Rs. Ps.
19.340 Kg 19.34 kg @ Rs.3710/Qtl 717.51
Conveyance
19.340 Kg 1 No 56 mm dia shaft 323.00 T 6.25
Total 723.76
Total 723.76
M 100=
Per Unit
estimate
Rate Amount
Quantity Description Remarks
Rs. Ps. Rs. Ps.
1 M.S Plate 6mm thick for shutter 0.00 0.00
1 x 2.15 x 2.00 x 0.06 0.26
7.90 Kg/m2/mm thick 203.82
Per Unit
estimate
Rate Amount
Quantity Description Remarks
Rs. Ps. Rs. Ps.
2.0 Nos man mazdoor 377.00 754.00
1.0 No Mason 471.00 471.00
Total 2929.00 E
Main Data
1 M.S.Plate
267.13 Kg @ 4430.70/Qtl 16613.17 Rs 16613.00
2 M.S Angle
103.24 Kg @ 4885.70/Qtl 6163.07 Rs 6163.00
3 Welding
36.64 m @ 66.16/m 3358.73 Rs 3359.00
4 M.S rod for spiral shaft
2.00 m @ 633.08/m 1447.52 Rs 1448.00
5 Painting primimng coat
9.68 m2 @ 172.75/10m2 235.01 Rs 235.00
6 Painting Black Japan Paint
9.68 m2 @ 215.30/10m2 292.77 Rs 293.00
7 Spiral threading
100 Nos @ 15/E 1500.00 Rs 1500.00
8 Collar nut, Bolt & Nut
18.19 Kg @ 65/Kg 1364.25 Rs 1364.00
9 Labour for dismantling & stocking
shutter
1 No fitter @ 300/E 456.00 Rs 456.00
2 Nos Heavy load man mazdoor @
792.00 Rs 792.00
270/E
1 No man mazdoor @ 240/E 377.00 Rs 377.00
10 Labour for fitting shutter in position
2 Nos fitter @ 300/E 912.00 Rs 912.00
2 Nos Heavy load man mazdoor @
792.00 Rs 792.00
270/E
2 Nos man mazdoor @ 240/E 754.00 Rs 754.00
1 No Mason @ 325/E 471.00 Rs 471.00
Total 35528.50 Rs 35529.00
Add 15% Revised SOR 5329.28 Rs 5329.00
Grand Total 40857.78 Rs 40858.00
SAY @ RS.30651/E
20 10 m3
Earth work excavation in ordinary soil and
forming bunds to lines and levels with in
all leads and lifts including conveyance
and all labour charges for trimming,
dressing and sectioning of berms or slopes
etc. complete (contractor’s own earth)
10 m3 Earth work excavation 1117.05 10m3 1117.05
10 m 3
Conveyance of earth 325.00 m 3
3250.00
0.35 man for trimming, dressing etc. 377.00 E 131.95
Total 4499.00
2.1 Deduct Woman 377.00 E 791.70
Total 3707.30
Add 15% , Revised SOR 556.10
Total 4263.40
Item no of
Per Unit
estimate
Rate Amount
Quantity Description Remarks
Rs. Ps. Rs. Ps.
Rate 4263.40 4263/ 10m3
THE KERALA LAND DEVELOPMENT CORPORATION LIMITED
DETAILED ESTIMATE
District: Alappuzha
Name of Work: Name of Work: RKVY 2015 -'16 - Drainage and Flood control projects for Alummoottil
padom andChenthitta Padom in Chettikulangara Panchayath in Alappuzha District
Sl.N Measurements
Details Of Work Number Area of Contents
o Length Breadth Depth
Part I - Alummoottil padom
App: A - Construction of Concrete Leadingchal
1 Earth work excavation in Ordinary
soil in or under water or in liquid
mud and depositing on bank with
initial lead and lift neat banking
etc.Complete
1 100.00 1.20 0.60 72.00 m3
Total 72.00 m3
Say 72 m3
2 Rough stone dry packing
1 100.00 1.20 0.30 36.00 m3
Total 36.00 m3
Say 36 m3
3 Cement concrete 1:4:8 using 40mm
(nominal size)broken stone
including cost and conveyance of
materials, , curing and all labour
charges etc. Complete
330.00
Total 1230.00 Kg
Say 1230 Kg
9 Back filling and formation of
road on within side of culvert
using contractor's own earth.
2 5.00 6.00 0.40 24.00
Total 24.00 m3
Say 24 m3
Part II - Chenthitta padom
App: A - Construction of Culvert
1 Earth work excavation in
Ordinary soil and depositing on
bank with initial lead and lift
neat banking etc.Complete.
(av)
Foundation 1 6.30 2.30 1.50 21.74
Wing 4 1.50 0.90 1.50 8.10
Total 29.84 m3
Say 30 m3
Sl.N Measurements
Details Of Work Number Area of Contents
o Length Breadth Depth
2 Shoring the side of trench using
wooden planks and joists and
labour for taking down after
completion including hire and
labour charges for maintaining
the structure until dismantling.
Project Engineer
THE KERALA LAND DEVELOPMENT CORPORATION LIMITED
Office of the Project Engineer, Kayamkulam
Abstract Of Estimate
Name of Work: RKVY 2015 -'16 - Drainage and Flood control projects for Alummoottil padom
andChenthitta Padom in Chettikulangara Panchayath in Alappuzha District
PROJECT ENGINEER
2. Karichal Thodu
App: - A - Construction of Sluice (2m Span)
1 Putting up ring bund using 1st class
bamboo post 3.00m average long 2m
above ground level and driving down
1.00m below ground level at 60cm centre
to centre in two rows at 1.5m apart and tied
with two rows of 1/2 split bamboo strut on
either side and 1./ split bamboo strut on the
top of vertical post and inside screening
with double planted coconut cudjans
madals tied with 1/4th split bamboo
reapers at 30cm centre to centre with coir
yarns and filling with earth excavated from
in or under water including all leads and
lifts involved and maintaining the bunds
leak proof till the completed work including
dismounting the bund and cleaning the site
neatly etc. Complete
2 7.00 14.00 m
Total 14.00 m
Say: 14.00 m
2 Bailing out water using 5HP diesel engine
and pump set including hire charge,
conveyance to site and errection cost of
fuel, lubricating oil and other stores, pay of
staff etc. Complete.
Main portion
1 4.30 3.30 0.50 7.095
Wing wall
4 0.50 1.30 0.50 1.30
Total 8.40 m3
Say: 8.50 m3
6 Cement concrete 1:4:8 using 40mm
(nominal size)broken stone including cost
and conveyance of materials, , curing and
all labour charges etc. Complete
Main portion
1 4.30 3.30 0.50 7.095
Wing wall
4 0.50 1.30 0.50 1.30
Curtain wall 2 3.70 0.50 0.70 2.59
Total 10.99 m3
Say: 11.00 m3
7 Form work for cement concrete using
wooden planks joists , bamboo posts and
labour for taking down after completion
including hire and labour charges for
maintaining the structure until dismantling
Abutment
Vertical faces
2 3.00 2.00 12.00
(1.0 +
Rear side
2 2.0)/2 2.06 6.18
(1.0 +
Edge
4 0.5)/2 2.00 6.00
(1.0 +
Wing wall - slope portion
4 0.5)/2 2.16 6.48
Side wall
Extra height abutment
2 4.00 0.50 4.00
Slab base
1 2.00 1.50 3.00
Slab side
1 9.00 1.50 13.50
Abutment
2 3.00 (1.0 + 0.50)/2 2.00 9.00
Wing walls
2x2 (1.0 x 0.5 + 1 x 0.5)/2 2.00 4.00
Extra height
2 1.50 0.50 0.50 0.75
Total 13.75 m3
Say: 14.00 m3
9 Cement concrete 1:2:4 using 20mm
(nominal size)broken stone including cost
and conveyance of materials and all labour
charges etc. Complete
2 7.00 14.00 m
Total 14.00 m
Say: 14.00 m
2 Bailing out water using 5HP diesel engine
and pump set including hire charge,
conveyance to site and errection cost of
fuel, lubricating oil and other stores, pay of
staff etc. Complete.
Main portion
1 6.30 4.50 0.30 8.505
Wing wall
4 0.50 1.30 0.30 0.78
Total 9.29 m3
Say: 9.50 m3
6 Cement concrete 1:4:8 using 40mm
(nominal size)broken stone including cost
and conveyance of materials, , curing and
all labour charges etc. Complete
Main portion
1 6.30 4.50 0.45 12.758
Wing wall
4 0.50 1.30 0.45 1.17
Curtain wall 2 7.30 0.30 0.70 3.07
Total 16.99 m3
Say: 17.00 m3
7 Form work for cement concrete using
wooden planks joists , bamboo posts and
labour for taking down after completion
including hire and labour charges for
maintaining the structure until dismantling
Abutment
Vertical faces
2 7.20 2.00 28.80
(3.2 +
Rear side
2 2.2)/2 2.06 11.12
(1.0 +
Edge
4 0.5)/2 2.00 6.00
(1.0 +
Wing wall - slope portion
4 0.5)/2 2.06 6.18
Side wall
Extra height abutment
2 9.40 0.50 9.40
Slab base
1 4.00 3.30 13.20
Slab side
1 14.60 0.25 3.65
Centre pillar - Overall 1 3.50 1.50 5.25
Total 83.60 m2
Say: 84.00 m2
8 Graded cement concrete 1:3:6 using 60%
of 40mm and 40% 20mm(nominal size)
broken stone including cost and
conveyance of materials , consolidation,
curing, but excluding cost of reinforcement
etc.complete.
Total
2.000 Nos
Say: 2.000 Nos
13 Lock and Locking arragements
Ls
4. Ward-15, Kumpalathu thodu
Machanical Shutter on existing sluice
1 Putting up ring bund using 1st class
bamboo post 3.00m average long 2m
above ground level and driving down
1.00m below ground level at 60cm centre
to centre in two rows at 1.5m apart and tied
with two rows of 1/2 split bamboo strut on
either side and 1./ split bamboo strut on the
top of vertical post and inside screening
with double planted coconut cudjans
madals tied with 1/4th split bamboo
reapers at 30cm centre to centre with coir
yarns and filling with earth excavated from
in or under water including all leads and
lifts involved and maintaining the bunds
leak proof till the completed work including
dismounting the bund and cleaning the site
neatly etc. Complete
2 7.00 14.00 m
Total 14.00 m
Say: 14.00 m
2 Bailing out water using 5HP diesel engine
and pump set including hire charge,
conveyance to site and errection cost of
fuel, lubricating oil and other stores, pay of
staff etc. Complete.
Total
3.000 Nos
Say: 3.000 Nos
2 7.00 14.00 m
Total 14.00 m
Say: 14.00 m
2 Bailing out water using 5HP diesel engine
and pump set including hire charge,
conveyance to site and errection cost of
fuel, lubricating oil and other stores, pay of
staff etc. Complete.
Main portion
1 6.30 4.50 0.30 8.505
Wing wall
4 0.50 1.30 0.30 0.78
Total 9.29 m3
Say: 9.50 m3
6 Cement concrete 1:4:8 using 40mm
(nominal size)broken stone including cost
and conveyance of materials, , curing and
all labour charges etc. Complete
Main portion
1 6.30 4.50 0.45 12.758
Wing wall
4 0.50 1.30 0.45 1.17
Curtain wall 2 7.30 0.30 0.70 3.07
Total 16.99 m3
Say: 17.00 m3
7 Form work for cement concrete using
wooden planks joists , bamboo posts and
labour for taking down after completion
including hire and labour charges for
maintaining the structure until dismantling
Abutment
Vertical faces
2 7.20 2.00 28.80
(3.2 +
Rear side
2 2.2)/2 2.06 11.12
(1.0 +
Edge
4 0.5)/2 2.00 6.00
(1.0 +
Wing wall - slope portion
4 0.5)/2 2.06 6.18
Side wall
Extra height abutment
2 9.40 0.50 9.40
Slab base
1 4.00 3.30 13.20
Slab side
1 14.60 0.25 3.65
Centre pillar - Overall 1 3.50 1.50 5.25
Total 83.60 m2
Say: 84.00 m2
8 Graded cement concrete 1:3:6 using 60%
of 40mm and 40% 20mm(nominal size)
broken stone including cost and
conveyance of materials , consolidation,
curing, but excluding cost of reinforcement
etc.complete.
7. Ward-12 Pallikadavu
Providing Machanical Shutter on Existing sluice
1 Putting up ring bund using 1st class
bamboo post 3.00m average long 2m
above ground level and driving down
1.00m below ground level at 60cm centre
to centre in two rows at 1.5m apart and tied
with two rows of 1/2 split bamboo strut on
either side and 1./ split bamboo strut on the
top of vertical post and inside screening
with double planted coconut cudjans
madals tied with 1/4th split bamboo
reapers at 30cm centre to centre with coir
yarns and filling with earth excavated from
in or under water including all leads and
lifts involved and maintaining the bunds
leak proof till the completed work including
dismounting the bund and cleaning the site
neatly etc. Complete
2 7.00 14.00 m
Total 14.00 m
Say: 14.00 m
2 Bailing out water using 5HP diesel engine
and pump set including hire charge,
conveyance to site and errection cost of
fuel, lubricating oil and other stores, pay of
staff etc. Complete.
Main portion
1 6.30 4.50 0.30 8.505
Wing wall
4 0.50 1.30 0.30 0.78
Total 9.29 m3
Say: 9.50 m3
6 Cement concrete 1:4:8 using 40mm
(nominal size)broken stone including cost
and conveyance of materials, , curing and
all labour charges etc. Complete
Main portion
1 6.30 4.50 0.45 12.758
Wing wall
4 0.50 1.30 0.45 1.17
Curtain wall 2 7.30 0.30 0.70 3.07
Total 16.99 m3
Say: 17.00 m3
7 Form work for cement concrete using
wooden planks joists , bamboo posts and
labour for taking down after completion
including hire and labour charges for
maintaining the structure until dismantling
Abutment
Vertical faces
2 7.20 2.00 28.80
(3.2 +
Rear side
2 2.2)/2 2.06 11.12
(1.0 +
Edge
4 0.5)/2 2.00 6.00
(1.0 +
Wing wall - slope portion
4 0.5)/2 2.06 6.18
Side wall
Extra height abutment
2 9.40 0.50 9.40
Slab base
1 4.00 3.30 13.20
Slab side
1 14.60 0.25 3.65
Centre pillar - Overall 1 3.50 1.50 5.25
Total 83.60 m2
Say: 84.00 m2
8 Graded cement concrete 1:3:6 using 60%
of 40mm and 40% 20mm(nominal size)
broken stone including cost and
conveyance of materials , consolidation,
curing, but excluding cost of reinforcement
etc.complete.
Unforeseen 1605733.000
Total 71425000.060
Quaity control charges @ 0.65% including GST : 464262.500
Project Engineer
KLDC Ltd., Kayamkulam