INSTRUCTION MANUAL

FRESH WATER GENERATOR


(PLATE TYPE)

1575−6, SONG JUNG DONG, KANGSEA−KU, BUSAN, KOREA

TEL : + 82 51 970−1114 FAX : + 82 51 970 − 1131

Web Site : www.dh.co.kr


INSTRUCTION DATA :
FOR REV.NO. : 0
OPERATION & MAINTENANCE PAGE : 2 OF 27

CONTENTS

PAGE NO
1. SAFETY INTRODUCTION 3

2. SAFETY INSTRUCTIONS AND WARING 4

3. DESCRIPTION OF THE PLANT AND ITS SYSTEM 5


3-1. Working description with engine jacket cooling water heating 5
3-2. Working description with saturated steam heating 6
3-3. Installation description 6
3-4. Installation description of the steam injecor 7

4. OPERATING WITH JACKET COOLING WATER 8


4-1. Starting up the plant 8
4-2. Regulating the capacity 9
4-3. Stopping 9

5. OPERATING WITH STEAM INJECTOR 10


5-1. Starting up the plant 10
5-2. Regulating the capacity 11
5-3. Stopping 12

6. MAINTENANCE & SERVICE 13


6-1. Cleaning with chemical 13
6-2. Cleaning by opening of Fresh Water Generator 13
6-3. The Fresh Water Generator’s cleaning procedure 13
6-4. Renewal of gasket 18
6-5. Maintenance of ejector 18

7. CHEMICAL DOSING 19
7-1. Prevention of Scaling 19
7-2. Feed water ratio 19
7-3. Chemical dosage 19
7-4. Scale inhibitor dosage equipment for feed water 20
7-5. Safety precaution with the use of chemical 21

8. TROUBLE SHOOTING 22

9. MAINTENANCE LIST 26

10. ILLUSTRATION 28

11. TEST REPORT 31

DONG – HWA ENTEC REV. : 0


INSTRUCTION DATA :
FOR REV.NO. : 0
OPERATION & MAINTENANCE PAGE : 3 OF 27

1. SAFETY INSTRUCTION
Before using this item, please read the INSTRUCTION MANUAL.
Follow warning label, instruction and caution procedure in order to us it correctly.
It is also highly recommended to always keeper the INSTRUCTION MANUAL
at the same place for easy access.
Transportation, installation, piping, wiring, operation inspection and maintenance
work must be done by only a LICENSED and/or AUTHORIZED PERSON who has
enough knowledge on health and safety rules and regulations as well as on his or her
profession.
In any respect, we’ll not guarantee for any death, injuries, damages and losses,
which result in modification without our written authorization or using and assembling
unauthorized parts.
During disposing, any accessories, used parts and oil, should be treated as general
industrial waste.
WARNING LABEL and SIGN in the instruction manual are classified into
WARNING, CAUTION and NOTICE as described below.

WARNING : Indicates potentially hazardous situation which, if not avoided,


may result in death or serious injuries.

CAUTION : Indicates potentially hazardous situation which, if not avoided,


may result in damage, defect or injuries.

NOTE : Indicates potentially hazardous situation which, if not avoided,


may result in damages or defect in product.
It will be only used for protecting but not safety.

DONG – HWA ENTEC REV. : 0


INSTRUCTION DATA :
FOR REV.NO. : 0
OPERATION & MAINTENANCE PAGE : 4 OF 27

2. Safety instructions and warning

The user and operator must have to read these instructions and the attached
documents and drawing before the installation, operation and inspection or
maintenance of the plant, so it should be used properly.

1. In operating Steam Injector mode, Steam Condensate valve must be


fully opened and Steam Inlet Valve must be slowly opened by operator.

2. No valve/cocks shall be fitted on steam drain discharge piping to


prevent fresh water generator from being pressurized by steam.

1. Welding or other working with fire should be severely prohibited to


prevent coating and gasket of the plant.

2. The Fresh Water Generator is not to be operated in polluted water or


within 30 kilometers from the coast.

DONG – HWA ENTEC REV. : 0


INSTRUCTION DATA :
FOR REV.NO. : 0
OPERATION & MAINTENANCE PAGE : 5 OF 27

3. Description of the plant and its system


3-1. Working description with engine jacket cooling water heating.

The DongHwa Entec fresh water generator uses the heat from Main Engine Jacket
Cooling Water to produce drinkable water by evaporating sea water due to the high
vacuum, which enables the feed water to evaporate at below 45℃.
Steam can also be used as heat source instead of hot jacket water.

The DongHwa Entec fresh water generator is based on 2 sets of titanium plate
heat
exchangers, acting as an evaporator and a condenser respectively.

The water ejector enables evaporator chamber vacuum condition by driving sea
water pass through water ejector, and sea water supplied by ejector pump to be
delivered to ejector for taking out the brine and air.

The feed water evaporates while entering to the evaporate chamber due to the
vacuum condition. The water spray and droplets are partly removed from the vapor by
the deflector mounted on top of the evaporator and partly by a build-in demister.

The feed water evaporates while entering to the evaporate chamber due to the
vacuum condition. The water spray and droplets are partly removed from the vapour
by the deflector mounted on top of the evaporator and partly by a build-in demister.
The separated water droplets fall back into the brine, which is extracted by the
ejector pump.

The desalted vapour, which passes through the demister, will be sucked into the
plate condenser where it will be condensed by means of incoming cold sea water.

The distilled water will be taken out by integral fresh water pump and controlled
by salinometer and solenoid valve. If it is of high salt content, the solenoid valve
recirculation work starts automatically to the shell or dumping line against high salt
content.
Thermometers are installed for control of sea water to the condenser and engine
cooling water to the evaporator. These thermometers permit control of both heating
and cooling of these units.
The salinometer(salinity indicator) is connected to remote alarm so that very high
salinity is registered immediately at the bridge of the ship or the engine control room.

1. For this plant, please bear in mind that the pressure of ejector inlet side should be
around 3 bar in ballast and around 4 bar in loading.
2. The pressure of ejector outlet should not exceed 0.8 bar.
3. The feed water should be controlled by feed valve. Normally it should be fully

DONG – HWA ENTEC REV. : 0


INSTRUCTION DATA :
FOR REV.NO. : 0
OPERATION & MAINTENANCE PAGE : 6 OF 27

Open to prevent formation of scaling on below 10 ppm.

3-2. Working description with saturated steam heating.

In addition to engine jacket cooling water heating, saturated live steam can
alternatively be used as heating medium for the fresh water generator.

The saturated live steam is being delivered to the heat exchanger of the fresh water
generator through a steam injector.

This steam injector works as a circulating pump and heat up the circulated fresh
water steam condensate, which comes from the outlet branch of the heat exchanger of
the fresh water generator.

As the heat exchanger of the fresh water generator is filled with clean fresh water
or steam condensate by starting the steam heating process. The produced steam
condensate from the supplied saturated live steam escapes from the socket in the
vertical safety blow off pipe. This condensate is led back to the boiler feed water tank
or hot well of the boiler through the condensate outlet placed on the safety blow off
pipe.

3-3. Installation description

Please check the installation drawing and technical specification, overhaul space
in
installation fresh water generator.

Be aware that it must be possible to read the value of thermometer and other gauge.

To avoid the unnecessary pressure drop, the connection pipe should be simple,
because it could effect the specified pump efficiency and produced fresh water
capacity.

Check the specified quantity of jacket water and sea water, steam flow through
the evaporator properly.

The fresh water pipe should be connected to the fresh water tank of the ship.
The counter pressure in the fresh water pipe should not exceed 1.8 bar or
according to specification.

It is recommended that the fresh water outlet line should be used stainless steel or
non-ferrous piping material, because the produced water made by fresh water
generator is of high purity, where dissolved oxygen concentration is of extremely low
level. If dissolved oxygen's quantity is low then oxide film will not be developed by

DONG – HWA ENTEC REV. : 0


INSTRUCTION DATA :
FOR REV.NO. : 0
OPERATION & MAINTENANCE PAGE : 7 OF 27

which it will be very unstable chemically. So this water tends to stabilize itself by
resolving and contacting with other substances. As the result, the color of water may
changes to be red or brownish.

The combined ejector-sea water pump is designed to withstand on a level with and
in close vicinity to the fresh water generator and for a maximum counter-pressure in
the overboard piping of 0.8 bar. If this is impossible, it should be dimensioned for
additional lifting height, and pipe resistance and ejector should be designed
accordingly.

3-4. Installation description of the steam injector

If the back pressure is exerted on the discharge line of the steam drain of the
steam
injector, extraordinary vibration may occur in the injector and there is maximum
possibility that the operation of the system may become impossible.

If the pressure after the steam injector exceed 1 bar, the safety valve will be
opened to secure the plate.

If the supplied steam pressure is lower than the designed pressure, the vibration
may be caused to the system. The fluctuation from the designed value must be within
about ± 5%.

DONG – HWA ENTEC REV. : 0


INSTRUCTION DATA :
FOR REV.NO. : 0
OPERATION & MAINTENANCE PAGE : 8 OF 27

4. Operating with Jacket Cooling water


4-1. Starting up the plant

Before operation, please check the following matter.

■ Please observe instructions for feed water treatment, see “chemical dosing part.“
■ Check the rotating direction of distillate pump.
■ Close in/outlet valves for jacket cooling water of evaporator.
■ Close vacuum breaker valve.
■ Close feed water inlet valve for evaporator.
■ Close the drain valve on the head of water ejector.
■ Open in/outlet valve for condenser cooling water.

Never start the fresh water generator’s distillate pump under dry condition.

Step. 1 : Start the sea water ejector pump.


① Fully open the ejector pump suction valve as well as the overboard
discharge valve.
② Start the ejector pump.
③ Slowly open the ejector pump’s discharge valve.
** Make Sure that the pressure at the water ejector inlet is 3.0 bar or more.

Step. 2 : Wait for sufficient vacuum.(about 92%)

Step. 3 : Open the feed water valve and fed sea waer into the evaporator. Feed water
quantity can be seen by the readings of the comp. gauge in front of the feed
water orifice. The feed valve is to be fully opened to prevent scale on the
evaporator plate.

Step. 4 : Open the inlet and outlet valves for jacket cooling water of evaporator.

Avoid the thermal shock to your main engine. The inlet and outlet valves of jacket
water cooling water to be opened and closed slowly and progressively.
While the obtained vacuum drops to around 85%, the boiling temperature now rises.
This indicates that evaporation has started.

Step. 5 : Open valve for feed water treatment.


Step. 6 : When fresh water is present in the inspection glass on the air suction line,
start the distillate pump and open the valve before flow meter.

DONG – HWA ENTEC REV. : 0


INSTRUCTION DATA :
FOR REV.NO. : 0
OPERATION & MAINTENANCE PAGE : 9 OF 27

4-2. Regulating the capacity.

The procedure amount of fresh water and the amount of engine cooling water for
the evaporator is adjusted by means of the bypass valve til correct capacity is obtained.
In case of production of fresh water in excess of its rated capacity, we recommend
that you should operate the plant at the prescribed quantity of fresh water or less as
production but in excess can involve the risk of scale formation.

4-3. Stopping

Step. 1 : Open the bypass valve for engine cooling water slowly.

Step. 2 : Close the inlet and outlet valves for engine cooling water for the
evaporator progressively.

Step. 3 : Close valve for feed water treatment.

Step. 4 : Stop the distillate pump.

Step. 5 : After cooling the evaporator side as below 50℃, close the feed water valve.

Step. 6 : Stop the ejector pump.

Step. 7 : Close the sea water valve before the ejector pump and the overboard valve
After the ejector.

Step. 8 : Open the vacuum breaker valve.

Step. 9 : Close the valve to fresh water tank.

Step. 10 : Open the drain valve on the head of water ejector.

DONG – HWA ENTEC REV. : 0


INSTRUCTION DATA :
FOR REV.NO. : 0
OPERATION & MAINTENANCE PAGE : 10 OF 27

5. Operating with Steam Injector


5-1. Starting up the plant

Do not open steam inlet valve for the steam injector operation before the ejector
pump has been started and serving feed water to the evaporator.

Open the priming valve and fill the evaporator section with fresh water. If any air is
present in the shell inside, the gasket of evaporator section plate will be damaged by
abnormal rise in temperature. Such air can also cause abnormal noise or vibration due
the cavitation or pulsating movement of inside water.

Do not open the steam valve rapidly. If so, water in the shell will pour into the
drain tank and cause vibration.

If steam pressure is lower than the designed value, inside water will pulsate and
cause abnormal noise and vibration.

The steam arrangement must be filled with fresh water from hydrophore system,
before supplying steam to the system.

No valve at all should be fitted on the pipe from the safety valve as this pipe must
be opened to the atmospheric pressure.

Max. Back pressure in condensate discharge line is 0.8 bar.

When stopping the plant, check that the steam inlet valve is always completely
closed.

To avoid high temperature in the evaporator, as this might cause ;


- Scale formation on the inside of the heat exchanger plates.
- Damage the gaskets in the heat exchanger.

Step. 1 : Close the inlet and outlet valves to jacket cooling water completely, and
open the valves in the drain line for draining jacket cooling water.

Step. 2 : After blowing jacket cooling water, close the drain cock and then fill up
the plant with boiler feed water or clean fresh water until water over flow
the priming checking line.

Step. 3 : The cock at the top of the drain pipe should always be opened because it
serves as a syphone breaker.(Syphone breaker is not necessary when a

DONG – HWA ENTEC REV. : 0


INSTRUCTION DATA :
FOR REV.NO. : 0
OPERATION & MAINTENANCE PAGE : 11 OF 27

drain tank is installed on the higher location than fresh water generator or
on the same floor.)

Step. 4 : Open the two butterfly valves in the steam injector circuit.

Step. 5 : Open the feed water valve and fed sea water into the evaporator. Feed
water quantity can be seen by the readings of the comp. gauge in front of
the feed water orifice. The feed water valve is to be fully opened to
prevent formation of scale on the evaporate plate, but in case the salinity
is some increased, the feed valve is to be closed a bit.

Step. 6 : After the above mentiond preparation, open the steam valve gradually
before the steam injector in order to steam supply initial during 10 min.
Fresh water in the piping is circulated as well as heated by steam. As
heating fresh water is cooled in the evaporator section plate, steam drain
goes up through the drain pipe and then it is exhausted into the drain tank.

The steam supplied to the steam injector must be saturated steam.

5-2. Regulating the capacity.

The fresh water production can be regulated by adjustment of the quantity of


steam supplied to the steam injector.

The steam inlet pressure corresponding to the production of fresh water in


question can be regulated either by means of a manually operated regulating valve
(yard supply) or by an automatic reduction valve(yard supply).

DongHwa Entec recommended that you will operate the plant at the prescribed
quantity of fresh water or less production but in excess hereof can involve the risk of
scale formations.

Steam pressure must be in accordance with pressure stated in “FWG Order


Specification.“

DONG – HWA ENTEC REV. : 0


INSTRUCTION DATA :
FOR REV.NO. : 0
OPERATION & MAINTENANCE PAGE : 12 OF 27

5-3. Stopping.

Step. 1 : Fully close steam inlet valve(yard supply).

Step. 2 : After cooling the evaporator side as below 50℃, close the feed water
valve.

Step. 3 : Stop the distillate pump.

Step. 4 : Stop the ejector pump.

Step. 5 : Close the sea water valve before the ejector pump and the overboard
valve after the ejector.

Step. 6 : Open the valve to fresh water tank.

Step. 7 : Close the valve to fresh water tank.

Step. 8 : Open the drain valve on the water ejector.

During the operating with steam injector, do not close the feed valve, if not so the
saturated steam overboard to steam drain line. In that case, we’ll do not
GUARANTEE FOR FORMATION OF ANY SCALE IN EVAPORATOR AND
INJURIES.

DONG – HWA ENTEC REV. : 0


INSTRUCTION DATA :
FOR REV.NO. : 0
OPERATION & MAINTENANCE PAGE : 13 OF 27

6. Maintenance & Service


6-1. Cleaning with Chemical.

Although the working temperature of evaporator keep 40~48℃, scaling gradually


come into evaporator section plate and the the capacity will be reduced. So the
cleaning of evaporator section plate is necessary.

The cleaning time depends on the working condition, but normally a chemical
cleaning should be 2~3 times per year as well as an opening of the plate pack onec a
year or every second year for total cleaning/inspection will be sufficient.

To reduce the cleaning time and scaling, the feed water quantity is the most important.
So please fully open sea water feed water valve in normal condition as below 10 ppm.

6-2. Cleaning by opening of Fresh Water Generator.

When the plant has been stopped as described under “Stopping the plant“ open the
fresh water generator and inspect Condenser & Evaporator section, Demister and the
interior of the fresh water generator and carry out the required cleaning.

Generally, it is necessary only to separate the evaporator and clean the plates by
means of the chemicals described under “Chemical Cleaning“. The interior of the
fresh water generator should be cleaned at the same time using the same chemicals.

6-3. The Fresh Water Generator’s cleaning procedure.

Step. 1 : Loosen the bolt & nut of Shell Cover.

Step. 2 : Loosen the nuts on the tightening bolt gradually so that no nut will carry
the entire load alone.

Step. 3 : Pull out the end cover and take out the plates one by one and mark the
position in order not to get a “disorganized“ plate pack when you have to
the assembly again.

Step. 4 : Remove the scaling with soft brush or submerge in hot, inhibited acid
bath at maximum 50℃.

DONG – HWA ENTEC REV. : 0


INSTRUCTION DATA :
FOR REV.NO. : 0
OPERATION & MAINTENANCE PAGE : 14 OF 27

Always follow carefully the supplier instructions when using inhibited acid.
Remember to neutralize according to supplier instructions.

Step. 5 : Examine plates and gaskets. If any defective plate is founded, remove the
plate together with the other plates in this group. But the first and last
plate in the plate package can not be removed without being replaced by
a new plate.

Step. 6 : When reassembling a separated evaporator, it should be checked for any


damaged or defective gaskets. If any, then change the gasket with new
one as shown on the plate diagram. Assemble the plates in due succession
according to plate arangement drawing and be aware that they are positioned
correctly. Clamp the plate pack to the correct dimemsion according to the
mumber of plates.

Please refer to Photo. 1, 2, 4, 6 for Evaporator side.


The plate shape and plate gasket shape.
- Please, refer to following Photo(1, 2, 4, 6) and drawng.
- The plate should be numberd(as shown 1, 2, 3, 4) with punching in gasket side.

(1) First Plate : as shown photo. 1 and attached drawing.


(2) No. 2 Plate : as shown photo. 2 and attached drawing,
(3) No. 3 Plate : as shown photo. 4 and attached drawing.
(4) Last Plate : as shown photo. 6 and attached drawing.

The plate arrangement as following.


- Please, refer to the attached drawing.
- Especially “2 PIECE OF PLATE IS CONSIDERED AS 1 SET.“

(1) First SET : First plate – No. 2 Plate – No. 3 Plate.


(2) The next SET : No.2 Plate – No. 3 Plate.
(3) The above combination should be repeatd except the END SET.
(4) END SET : No.2 Plate – No. 3 Plate – End Plate.

DONG – HWA ENTEC REV. : 0


INSTRUCTION DATA :
FOR REV.NO. : 0
OPERATION & MAINTENANCE PAGE : 15 OF 27

*The Plate Of Evaporator & Gasket Shape. *The Plate Of Condenser & Gasket Shape.

Photo.1 First Plate & Gasket Photo.1 First Plate & Gasket

Photo.2 No.2 Plate & Gasket Photo.3 No.2 Plate & Gasket

Photo.4 No.3 Plate & Gasket Photo.5 No.3 Plate & Gasket

Photo.6 The End Plate & Gasket Photo.6 The End Plate & Gasket

☞ The First Plate & No.3 Plate’s shape are same but different in gasket.
☞ The End Plate & No.2 Plate’s shape are same but different in gasket.
☞ The First Plate of Evaporator & The first Plate of Condenser are same.
☞ The End Plate of Evaporator & The End Plate of Condenser are same.

DONG – HWA ENTEC REV. : 0


INSTRUCTION DATA :
FOR REV.NO. : 0
OPERATION & MAINTENANCE PAGE : 16 OF 27

Step. 7 : Check the tightening measurement of each plate section.

The tightening measurement of each plates are as follow;


Please refer to Fig.1 Tightening measurement.
No. TYPE Tightenng Length CASE(ton/day)
1 SFD 7 3.1 mm 10
2 SFD 13 3.9 mm 15, 20, 25
3 SFD 23 3.9 mm 30, 35
4 SFD 35 3.9 mm 40
5 SFD 60 3.9 mm 60

END PLATE

TIGHTENING
BOLT

BASE FLANGE

Fig. 1 The tightening measurement for palte.

For example, “Calculate the tightening measurement for each plate“.


☞ SFD 13/20 : SFD13 means TYPE, 20 means CAPACITY, total plate is 60 ea.
L : 60 ea x 3.9 mm = 234 mm
☞ SFD 23/30 : SFD23 means TYPE, 30 means CAPACITY, total plate is 76 ea.
L : 76 ea x 3.9 mm = 296.4 mm

DONG – HWA ENTEC REV. : 0


INSTRUCTION DATA :
FOR REV.NO. : 0
OPERATION & MAINTENANCE PAGE : 17 OF 27

The orifice size and flow direction are as follow ;


Please refer to Fig.2 The In-Diameter of orifice.
No. TYPE Capacity(ton per day) In-Diamieter
1 SFD 7 10 ton per day 6 mm
2 SFD 13 15 ton per day 7 mm
3 SFD 13 20 ton per day 8 mm
4 SFD 13 25 ton per day 10 mm
5 SFD 23 30 ton per day 12 mm
6 SFD 23 35 ton per day 13 mm
7 SFD 35 40 ton per day 14 mm

Fig. 2 The In-Diameter size of orifice.

Step. 8 : Before closing the Shell Cover, the Hydro-test of the both side should be
done. In case of evaporator, it should be done by slowly opening the by-
pass valve for hot water into normal position and let the water flow through.
In case of condenser, just start sea water ejector pump to circulate.

Step. 9 : After test is done, if there is no leak, then close cover and tight the bolt &
nut properly.

DONG – HWA ENTEC REV. : 0


INSTRUCTION DATA :
FOR REV.NO. : 0
OPERATION & MAINTENANCE PAGE : 18 OF 27

Step. 10 : After all reassembling, the vacuum test should be done by starting sea
water ejector pump at the same time by re-tightening bolt & nut of shell
cover some more.
6-4. Renewal of heat exchanger gasket.

☞ The gasket’s shape


Please kindly find attached drawing.
☞ Glue type
PLIBOND 25/SCOTCHGRIP 847 are nitrile rubber glues on soluble
basis(25%
solid material). The glues are partly thermoplastic so that old gaskets can be
unsticked lease kindly find attached drawing.
☞ Detergent
For cleaning and degreasing new gaskets and gasket grooves use “ACETONE“.
Any remaining charred or loose glue and rubber must be removed by using a
rotation stainless steel brush. It is very important that every detergent is
evaporated before putting glue on.

Solvents are dangerous to inhale.

☞ Gluing
After wiping gaskets and gasket grooves with a cloth moistioned with
degreasing
substance, the gluing itself can begin. The gluing areas must be quite clean-
free from fingerprints also. The gaskets are covered by a brush with a thin coat
of glue on the gluing area and placed on a clean and dry place in order to dry.
The gluing process should be done easily on a solid table. After the gaskets
have been put into the plate gasket grooves, the plates are stacked.

When the gluing is finished, the plates are hung into the unit again and heat
exchanger is clamped together. The heat exchanger can be warmed up by hot
water if the glue is to be dried quickly but without pressure and water!
Drying time : Approx. 2 hours at 80 ~ 100℃.
Approx. 24 hours at 40 ~ 150℃.
Approx. 48 hours at room temperature.

If it is not possible to heat the plate heat exchanger, plates must always be placed
in warm condition.

DONG – HWA ENTEC REV. : 0


INSTRUCTION DATA :
FOR REV.NO. : 0
OPERATION & MAINTENANCE PAGE : 19 OF 27

6-5. Maintenance of Ejector.

The DongHwa Entec ejector consist of Mixing tube and Diffuser, 1’st & 2’nd Nozzle.

Please find attached drawing. There shown the ejector overhaul procedure.

7. Chemical Dosing

Using the more concentrated chemical may cause seriously damage to the plate so the
color of plate is changed.

7-1. Prevention of Scaling.

During the sea water evaporation, there is always a risk of scaling on the heating
surface. This results in reduced K-values of the heating surface and decreased fresh
water production as well an overall reduction of the plant efficiency.
In order to prevent scaling, the operators must be aware of the factors influencing
the scale formation.

7-2. Feed water ratio.

The feed water ratio is an extremely important factor. It is defined by the


relationship between the feed water amount fed into the plant and the produced fresh
water generator.

If the feed water ratio is reduced, the concentration will rise in the plant
subsequently, resulting in scale formations.

The feed valve is to be fully opened to prevnet scale on the evaporator plate. But
in case the salinity is some increased, the feed valve is to be closed a bit.

7-3. Chemical Dosage.

In order to control scale formation on the heating surface and continuous


operation periods without acid cleaning of the plant, it is absolutely necessary to
dose scale control additives to the feed water. The operators must follow the

DONG – HWA ENTEC REV. : 0


INSTRUCTION DATA :
FOR REV.NO. : 0
OPERATION & MAINTENANCE PAGE : 20 OF 27

instructions for chemical additives to the feed water. The operators must follow the
instructions for chemical dosing given by the chemical supplier carefully.

If the distiller is operated at boiling temperatures above 45℃ without chemicals,


frequently cleaning of the evaporator is necessary.

We recommend you not to operate the fresh water generator without


recommended chemical dosage at boiling tempertures above 45℃.

7-4. Scale inhibitor dosage equipment for feed water.

When adding chemicals, mix throughly to ensure a homogeneous blend of


chemicals and water.
Use a fully soluble scale inhibitor, e,g. On polymer basis. The following product
can be recommended :

* NALFEET Evaporator treatment 9-913.


* AMEROYAL EVAPORATOR TREATMENT
* HEXAMETHAPHOSPHATE
* UNITOR LIQUID EVAPORATOR TREATMENT

Step. 1 : Mix the required quantity for 24 hours operation in the tank according to
maker’s instruction.

Step. 2 : Adjust flow-meter to cover the maximum fresh water output from the
distiller.

Step. 3 : Flush the dosage system regulary.

7-5. Safety precautions with the use of chemical.

Step. 1 : Use eye production and gloves. Avoid direct skin contact with skin, eye
and clothes.

Step. 2 : Clean empty containers before disposal.

Step. 3 : If chemicals are spilled on the cloth, rinse with water and dispose off
clothes.

DONG – HWA ENTEC REV. : 0


INSTRUCTION DATA :
FOR REV.NO. : 0
OPERATION & MAINTENANCE PAGE : 21 OF 27

Step. 4 : If chemicals are spilled on the floor, rinse with water and suck remaining
chemicals off with sand. Clean the spot immidiately afterwards.

Step. 5 : Scale inhibitor is hazardous, if consumed in a concentrated solution. If


consumed by mistake. IMMEDIATELY SEEK MEDICAL
ATTENTION.

Step. 6 : If eyes get in contact with the chemicals, rinse for at least 20 minutes
with water. IMMEDIATELY SEEK MEDICAL ATTENTION.

DONG – HWA ENTEC REV. : 0


INSTRUCTION DATA :
FOR REV.NO. : 0
OPERATION & MAINTENANCE PAGE : 22 OF 27

8. Trouble Shooting

Problem Cause Consequence Solution


Low sea water Scale on the eva. Fully open s.w feed valve &
feed rate Plate check the orifice & close the
s.w outlet valve to increase
the back press. Min 0.2 bar &
cleaning the plate.
Solenoid vlave Product water return Check the solenoid valve
is not working to the chamber inside after power off.
Jacket water The difference of Increase the J.W flow rate by
flow rate is not J.W temp. is too high closing by-pass valve or
enough & S.W temp. is too temp. control v/vsetting of
low J.W system.
Sea water flow The water ejector Pls, check the sea water
rate is not inlet press. Is too ejector pump & check the
enough low valve of s.w line as Suc.&
Dis.& overboard line &
discharge the remaining air of
the pipe inside.
Low capacity Rotate direction The discharge press. Change the distillate pump’s
is not correct of of distillate pump is phase, and check the pump’s
distillate pump too low rotate direction.
The outlet line The discharge press. Pls, open the distillate water
valve of of distillate pump is outlet line valve.
distillate water too high
closed
The clogging The discharge press. Pls, cleaning the distillate
the distillate of distillate pump is water outlet line by air.
water outlet line too high
Vacuum Low vacuum Pls, check all of valves on the
condition is no manual & should be closed &
good more tight the bolt & nut of
cover. Pls, check the s.w
ejector pump as the above.
Pls, check the water ejector as
below.
Hot water temp. Increase the J.W temp. as
is low spec. or our drawing.
Flowmeter is Cleaning the flow meter
clogging
Non return Non condensable gas Pls, check the mounting
valve is or brine is not direction and inside condition
malfunction extracted

DONG – HWA ENTEC REV. : 0


INSTRUCTION DATA :
FOR REV.NO. : 0
OPERATION & MAINTENANCE PAGE : 23 OF 27

Problem Cause Consequence Solution


Inside nozzle Re-tighten the nozzle of water
released ejector.
The outlet press. Pls, check the ejector outlet
Is higher than 0.8 bar. piping.
Water Ejector Inside nozzle is worn Change with the new nozzle.
Mal-function or corroded
The discharge press. Close the overboard line valve
of water ejector is and increase the press. as
negative positive.
Leak on the condenser Pls, demount the cover & do it
the leak test in case there is
leak, pls re-tighten the plate
and pls refer to ejector pump
operating manual.
Salinity indicator mal- Salinity Pls, check the salinity sensor &
function fluctuating & controller as manual
worng indication
Salinity high Two much capacity Reduce the capacity
Evaporating temp. is Open the vacuum breaker v/v
too low and increase the eva. Temp
Demister is wrong Check the demister & demount
position it.
Distilled water outlet Cleaning the distilled water
clogging outlet line by air.
Brine extraction is not Check the water ejector as the
sufficient above
Distilled water outlet Cleaning the distilled water
line clogging outlet line by air.
Sight glass Distillate pump is out Check the distillate pump.
overflow on of order
the air suction Distilled water outlet Open the distilled water line
line line valve closed valve
Leaking on the pipe Check the pipe line form
line condensdr to p/p.
Jacket water temp. is Increase the jacket water inlet
Evapoarting too low temp.
temp. low Jacket water flow rate Increase the jacket water flow
is not enough rate

DONG – HWA ENTEC REV. : 0


INSTRUCTION DATA :
FOR REV.NO. : 0
OPERATION & MAINTENANCE PAGE : 24 OF 27

Problem Cause Consequence Solution


Water ejector mal- Brine extraciton Check the water ejector as the
function is no good above
Distilled water line Discharge of Pls, check the distilled water
malfunction Distilled water is outlet line
Evaporating no good
temp. high Condenser mal- Temp. difference Pls, check the condenser plate
Function of s.w side is too
low
S.W flow is not Pls, check s.w line & ejector
enough Pump
Tightening of the Retightening the plate as our
plate is insufficient manual
Gaskets are damaged Change gasket with glue
or deformed
Leak on the The color of plate The plate weak Be careful the solution of
plate changed in chemical chemical don’t dipping on the
cleaning chemicla soluton for long time
Gasket is stretch Pls, change the gasket with
new one
Frequent refill Leaking on the Check the evaporator plate and
of f.w expansion evaporator plate retightening the plate and then
tank due to loss Hydro test at max. 4 bar.
of hot water
Ejector pump’s press. Check the s.w ejector pump.
is too low
The nozzle of water Retightening the water ejector
Brine Ejector release nozzle.
extraction is Check valve is not Examine the check valve and
insufficient Working direction.
Back press. is too high Check the overboard line and
valve.
Orifice of s.w feed Pls, check the orifice inner
line is not correct diameter.
Suction strainer is Clean the s.w strainer.
blocked
Too low front Suc.& Discharge v/v Examine the valve and full
press. of twin closed open
ejector Ejetor pump is mal- Check the s.w ejector pump.
Function
The rotate direction of Change the phase of sea water
s.w pump is opposite ejector pump.

DONG – HWA ENTEC REV. : 0


INSTRUCTION DATA :
FOR REV.NO. : 0
OPERATION & MAINTENANCE PAGE : 25 OF 27

☞ Especially : The pump is out of order.


Problem Cause Consequence Solution
The pump does The motor is out of order Change the motor.
not run The pump has seized Change/repair the pump.
The pump sucks air Repair the leaking part.
The specified The suction pipe and/or Clean it.
flow rate is not Strainer is clogged
reached The impeller is clogged Clean it.
The direction of motor Recover the normal direction of
Rotation is reverse rotation.
The pump sucks air Repair the leaking part.
The revolution speed Check the power source.
The specified has reduced down
head is not The casing ring is worn Replace it with new one.
reached down
The impeller is worn Replace it with new one.
down
starting, water Air remains in the Discharge the remaining air out
discharged but suction pipe of pipe
ps soon The pump sucks air Check the mechanical seal
through the stuffing box
The bearing is defective Replace it with new one.
The motor is The mechanical seal is Replace it with new one.
loaded damaged
excessively The shaft connection is Correct the alignment of the
bad shaft
The impeller is un- Reassemble the pump properly.
balanced
The bearing is Reassemble the bearing
assembled wrongly properly.
The pump The shaft connection is Correct the alignment of the
vibrates bad shaft
abnormally The shaft is bending Replace ti with a new one.
The pump is not Reinstalled the pump.
installed properly
The bearing is worn Replace it with a new one.
down
The bearing is Reassemble the bearing
assembled wrongly properly.
The bearng is The shaft connection is Correct the alignment of the
over-heated bad shaft
The shaft is bending Replace it with a new one.
The thrust is increased Reassemble the bearing.

DONG – HWA ENTEC REV. : 0


INSTRUCTION DATA :
FOR REV.NO. : 0
OPERATION & MAINTENANCE PAGE : 26 OF 27

9. Maintenance List
Item Object Contents Interval
Every Every 3 Every 6 Every
month month or month or year or
2000 hrs 4000 hrs 8000
hrs
Heater Plate Exchanges when the wound
gasket on the both sides of the heat
transfer plate and the crack ○
and the deterioration of the ※1
gasket are confirmed and
there is damage.
Condenser Plate Exchanges when the wound
gasket on the both sides of the heat
transfer plate and the crack ○
and the deterioration of the ※1
gasket are confirmed and
there is damage
Evaporator Baffel Inspect them and if there is
plate & any abnormality, clean them ○
mesh and/or change the defective
seperator one
Corrosion If it is corroded
bar substantially ○ ※2
Replace it with a new one
Feed Feed Clean them and check their ○
water pipe water bore
orifice &
water
inner pipe
Sight glass Glass Clean it ○

Non- Scale for- Cover is removed, housing ○


return mations and non-return valve are
valves mobiity of controlled and cleaned
flap
Water Suction Clean and inspect it ○
meter strainer
Water The inner Inspect and clean the inner ○
ejector surface of surface, and if it is worn
the nozzle down or damaged
& diffuser substantially replace it with
a new one

DONG – HWA ENTEC REV. : 0


INSTRUCTION DATA :
FOR REV.NO. : 0
OPERATION & MAINTENANCE PAGE : 27 OF 27

Item Object Contents Interval


Every Every 3 Every 6 Every
month month or month or year or
2000 hrs 4000 hrs 8000 hrs
Salinity electrode Clean it with care not to
indicator damage the element.
Measure its insulation ○
resistance, and treat it
accoridng to the instrucion
manual for it
Impeller Clean and inspect it ○ ※3
Ejector
pump Casing The gap shall be 2.3 mm ○
ring or less
Mechanica Inspection or replacement ○
l seal
Impeller Clean and inspect it ○
Distillate
Pump Casing The gap shall be 1.2 mm ○
ring or less
Mechanica Inspection or replacement ○
l seal

1. The extent of scaling on the plates and the cleaning interval thereof depend on the
opeating conditions such as the evaporating temperature, capacity, feed water flow
rate, type of chemicals solution, with or without injection, etc. Therefor, User will
modify adequately the inspection schedule from time to time based on its own data
and experience in the actual operations in the ship.

2. The extent of consumption of the Corrosion Bar depends on the property of sea
water and other conditions, so that the inspection schedule for it should be
modified based on the experience and results of the actual operations in the ship.

3. If the material of the Ejector Pump is PBC, it will be worn down with increasing
operating time and the surface of its impeller will get rough. As the pump
continuous rotating at high speed, these phenomena are unavoidable.
User should take notice of these.