Refer to
Project 1 on the OLS and
the sketching guidelines, to help you complete the questions below.
Sketching guidelines
This assessment contains a number of tasks requiring you to prepare
sketches of relevant construction details. The sketches are to be prepared to
a standard acceptable to allow communication of a detail as would occur on
a construction site. Many details are communicated in this manner and
everyone involved with building sites should be skilled in the preparation of
sketches.
Sketches are freehand drawings. Line work and proportion are important
considerations that must be satisfied in the assessment. Select a scale/size
appropriate to the detail.
It is not expected everyone will have these skills at the commencement of
this assessment. This first assessment may be presented with a mix of
freehand sketches and ruled drawings. All should be completed in pencil on
A4 size paper. Refer to the project documentation before commencing the
drawings to clearly identify and comply with the documents. This question
may require you to carry out research of the topics to broaden your
knowledge before attempting the answers.
Submissions, which are assessed to be not of an acceptable standard, will
be returned with a request to resubmit the assessment.
Question 1
The reinforced concrete ‘slab on ground’ flooring system for the 2 storey dwelling detailed in
the plans is to be constructed. The site will be excavated to provide a level ‘bench’
incorporating cut and fill. Piers will be required to support the slab on an even foundation.
a) Prepare a sketch of the plan view of the slab indicating the possible location of the
piers. You can assume the piers are 300mm in diameter. (Hint: position piers at all
corners/beams intersections, then place between these at maximum 1800 centres)
Question 2
Prepare a sketch of the joint between the external wall frames and the first floor joists. Fully
label the sketch and provide dimensions and member sizes. Clearly show the fitout of the
building on this sketch including:
Ceiling and wall linings
Full external wall detail
Flooring
Skirting boards etc
The clay extends from below the topsoil on the site to a depth of approximately 750mm. By
providing a sketch, propose an alternative footing system for the construction of the cottage.
Fully detail the footing specifying concrete and reinforcement. Provide all relevant
dimensions.
Should the clay, after excavation commences, prove to be at a greater depth, say an
average of 1500mm below the cleared site, propose another footing system and fully sketch
the detail.
detail.
Floor system 1:
a platform floor incorporating bearers and joists with particle board flooring and including a
suitable insulation system.
Floor system 2:
a concrete floor system to replicate the qualities of the slab on ground and suitable for the
new footing systems. Australian Standard 2870 – Residential Slabs and Footings may be
useful if you need to research this detail.