S.

no Equipment Model Validity Issued by


1. Glass Lined Reactor 12 months from the date of commissioning or 18 months Standard Glass Lining Technology Pvt. Ltd
Date Of Dispatch: 19-12-2020 from the date of dispatch whichever is earlier
2. MEE With Integrated Stripper 12 months from the date of commissioning or 18 months Protech Engineers
Column from the date of dispatch whichever is earlier
Date Of Dispatch: 27-06-2020
3. 96 Trays Capacity Vacuum Tray 29.01.2021 SVSENGINEERING
Dryer (GMP Model)
Date: 22.01.2020
4. SS304 + HC-22 Explosive 12 months After the date of commercial BEW ENGINEERING PVT. LTD
Bonded Agitated Operation of the plant or eighteen (18) months from the
Pressure Nutsche Filter date of completion of delivery of the goods whichever is
the short period
5. Hand Pallet Truck (GPT 2500) 6 months from date of supply Godrej & Boyce MFG. co. Ltd.
Date: 19.03.2021
6. Pulverizer 12x6 GMP Model PHAREQUIP ENGINEERS
Date: 16.05.2020
7. Glass Lined Reactor 12 months from the date of commissioning or 18 months Standard Glass Lining Technology Pvt. Ltd
Date Of Dispatch: 25 12 2020 from the date of dispatch whichever is earlier.
8. 3000 Ltrs SS316 Agitaied Nutsch 12 months from the date of dispatch S2 Engineering Services
Filter (M0noBlock)
Date.24.08.2020
9. 20 Sq.M Ss Condenser Either 18 months from till date Of The dispatch or 12 iPharrm Process Technologies Pvt Ltd
Date Of Dispatch: 25.09.2020 months from the date of installation whichever is earlier
10. 3000 Ltrs Ss 316 Receiver 12 months from the date of commissioning or 18 months iPharrm Process Technologies Pvt Ltd
Date Of Dispatch: 25.09.2020 from the date of dispatch whichever is earlier.

11. 20 Sq.M Ss Condenser 18 months from the date Of the dispatch Or 12 months iPharrm Process Technologies Pvt Ltd
Date Of Dispatch: 25.09.2020 from The Date of Installation
whichever Is earlier.
12. All Godrej Forklift Truck GX 300E 12 months from date of commission or 15 months from Godrej & Boyce MFG. co. Ltd.
excluding engines. date of dispatch
Date of delivery- 24.02.21
13. Glass Lined Reactor 12 months from the date of commissioning or 18 months Standard Glass Lining Technology Pvt. Ltd