Penstocks Manufacturing Schedule

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

MANUFACTURING SCHEDULE :

Manufacturer's Ref# SQ0007835


Product: PENSTOCKS Manufacturer's Work Order# WO3818
Project Name: NEW PUMP STATION PS-56A AND FORCE-MAIN TO SWTP-9 MACO PO# 58415
Client: MARAFIQ | ALMANAR ARABIAN CORPORATION

MONTH-1 MONTH-2 MONTH-3 MONTH-4


Target Actual Finish
SN ACTIVITY SEPTEMBER OCTOBER NOVEMBER DECEMBER
Start Date Start Date Date
WK-1 WK-2 WK-3 WK-4 WK-1 WK-2 WK-3 WK-4 WK-1 WK-2 WK-3 WK-4 WK-1 WK-2 WK-3 WK-4

1 RECEIPT OF OFFICIAL PO WITH FABRICATION CLEARANCE 19/Aug/20 31/Aug/20


2 CUTTING LIST 1/Sep/20 2/Sep/20 10/Sep/20
3 PROCUREMENT
AUMA Operators 2/Sep/20 2/Sep/20 31/Dec/20
Raw Materials 2/Sep/20 2/Sep/20 24/Sep/20
4 PRODUCTION 27/Sep/20 27/Sep/20 19/Nov/20
5 READY FOR INSPECTION 29/Nov/20 30/Nov/20 30/Nov/20
6 READY FOR DELIVERY 1/Dec/20 2/Dec/20 3/Dec/20

Technology Products and Services Company | Al Kuhaimi Metal Industries Ltd. Prepared by: KMI-PMU Dated: 01-09-2020 Sheet 1/1
Disclaimer: This document is strictly confidential and personal to its recipients and should not be copied, distributed
or reproduced in whole or in part, nor passed to any third party without the express written permission.

You might also like