Professional Documents
Culture Documents
Ep-Gis 18-013
Ep-Gis 18-013
24 May 2016
ETP
Engineering
Specification for Weld Overlay, Integral Cladding, and Limited Loose Lining of Pressure Vessels and Other Components
Table of Contents
Page
Foreword ........................................................................................................................................ 4
1 Scope .................................................................................................................................... 5
2 Normative references............................................................................................................. 5
3 Terms and definitions............................................................................................................. 6
4 Symbols and abbreviations .................................................................................................... 7
5 Order of precedence .............................................................................................................. 8
6 General requirements ............................................................................................................ 8
6.1 Materials selection ...................................................................................................... 8
6.2 Corrosion resistant alloy (CRA) barrier application ...................................................... 8
6.3 Internal attachments ................................................................................................... 9
6.4 Clad tubesheets, tube to tubesheet joints. .................................................................. 9
6.5 Nozzles ....................................................................................................................... 9
6.6 Storage and fabrication ............................................................................................... 9
6.7 Health, safety, and environmental (HSE) for welding and NDT operations ................ 10
7 Loose or strip linings ............................................................................................................ 10
7.1 General ..................................................................................................................... 10
7.2 Loose lining of nozzles .............................................................................................. 11
8 Integral clad linings .............................................................................................................. 11
8.1 Stainless steels and nickel alloys .............................................................................. 11
8.2 Integral cladding with titanium ................................................................................... 12
8.3 Integral cladding with zirconium ................................................................................ 13
9 Weld deposited overlay ........................................................................................................ 14
9.1 Welding processes.................................................................................................... 14
9.2 Cladding re-instatement ............................................................................................ 14
9.3 Welding equipment ................................................................................................... 15
9.4 Welding consumables ............................................................................................... 15
9.5 Welding gases .......................................................................................................... 17
9.6 Weld overlay requirements ....................................................................................... 17
9.7 Welding procedures .................................................................................................. 17
9.8 Weld overlay with Alloy 400 UNS N04400 (such as MONEL™) for hydrofluoric acid
service ...................................................................................................................... 20
9.9 Weld overlay for valves ............................................................................................. 20
10 Production welding .............................................................................................................. 21
11 Post weld heat treatment (PWHT)........................................................................................ 21
12 Nondestructive testing (NDT) of weld deposited overlay ...................................................... 21
12.1 Nondestructive testing (NDT) procedures ................................................................. 21
12.2 Extent of nondestructive testing (NDT)...................................................................... 22
List of Tables
Table 1 - Typical filler metal requirements for weld overlay of vessels and equipment .................. 16
Table 2 - PT inspection acceptance criteria................................................................................... 23
List of Figures
Foreword
This specification contains the same technical content as GPO-EN-SPE-18013 Rev B02.
1 Scope
2 Normative references
The following documents are referenced in one or more requirements in this document. For dated
references, only the version cited applies. For undated references, the latest version of the referenced
document (including any amendments) applies.
Company documents
EP-GIS 36-103 Specification for Positive Materials Identification (PMI).
For the purpose of this Specification, the following terms and definitions apply:
Back cladding
Application of weld overlay on the exposed base metal at the longitudinal, circumferential, and nozzle
weld seams of integrally clad or weld overlaid equipment.
Company
BP p.l.c., an associate or subsidiary, or other organisation acting as owner, purchaser, or customer as
designated in the Purchase Order.
Integral cladding
Metallic lining material that forms a metallurgical bond with the base metal during manufacture.
Loose lining
Metallic lining that is not integrally bonded with the base metal.
Supplier
Entity entering into a contract with Company to provide materials, goods, supplies, equipment, or
plant and includes the successors and (or) permitted assigns of such entity.
Weld overlay
Metallic lining material deposited by welding.
For the purpose of this Specification, the following symbols and abbreviations apply:
CV Curriculum vitae.
FN Ferrite number.
Hv Vickers hardness.
SS Stainless Steel.
UT Ultrasonic testing.
VT Visual testing.
5 Order of precedence
a. The order of precedence of the codes and standards quoted in the specifications shall be:
1. International and local statutory regulations.
2. Project data sheets.
3. Project specifications.
4. This Specification.
5. Referenced Company documents.
6. Referenced national and international codes.
b. Areas of apparent conflict between documents shall be brought to the attention of
Company for resolution.
c. In the event of a conflict between this document and a relevant law or regulation, the
relevant law or regulation shall be followed. If the document creates a higher obligation, it
shall be followed as long as this also achieves full compliance with the law or regulation.
d. Design, engineering, procurement, and construction for equipment shall comply with the
statutory laws and regulations of the final location of the asset. Refer to documents
identified in the Purchase Order for a list of these regulations.
e. For projects where the final location of the asset is in the EU:
1. Products supplied shall be confirmed to comply with applicable EU directives.
2. A Declaration of Conformity shall be provided.
3. The CE mark shall be affixed to the package nameplate.
4. Components supplied shall be listed together with the EU directives with which they
comply and the rationale by which compliance has been achieved.
5. A Technical File in compliance with applicable EU directives shall be compiled and
retained for a period of 10 years.
6 General requirements
6.5 Nozzles
a. Nozzles may be manufactured from clad plate or, except for titanium or zirconium,
internally weld overlaid.
b. Use of loose liners shall be subject to approval by Company responsible engineer.
c. Small diameter nozzles, typically less than or equal to DN 50 (NPS 2), may be solid CRA,
instead of internally clad, subject to approval by Company responsible engineer.
e. Paint or any other compound used for marking shall be free from:
1. Low melting point metallic components.
2. Sulphur.
3. Chloride.
4. Other halogens.
f. Fabrication and welding activities shall be controlled in conformance to an international
standard such as ASME or NORSOK, or any other document included in the Purchase
Order, and shall be subject to review and approval by Company responsible engineer.
g. Welding engineers, welding inspectors, and NDT personnel:
1. Shall be currently qualified to a standard, which shall be subject to review and
approval by Company responsible engineer.
2. CVs, job descriptions and certifications shall be available for review and if requested
by Company may be subject to review and approval by Company responsible
engineer.
3. Shall conform to any other requirements included in the Purchase Order.
h. Fabrication procedures, WPS and PQR, and NDT procedures shall be subject to approval
by Company responsible engineer prior to the commencement of any work.
i. Temporary welded attachments made to CRA surfaces shall be subject to approval by
Company responsible engineer prior to the commencement of any work.
6.7 Health, safety, and environmental (HSE) for welding and NDT operations
a. Welding, cutting, NDT, and associated operations shall be performed in a safe manner and
with due regard to individual health and safety and the minimisation of environmental
impact in conformance to Company requirements included in the Purchase Order.
b. Welding, cutting, NDT activities, and associated operations shall be included in Supplier
and sub-suppliers, if applicable, operational safety planning and in the safety audit
schedule.
c. Rooms where welding operations will be performed shall be ventilated and quality of
breathing air during welding operations shall be controlled.
d. As a minimum, radiography operations shall comply with local regulations.
7.1 General
a. Application of loose or strip linings for the repair of existing equipment and or new
construction shall be subject to the approval by Company responsible engineer.
b. If loose or strip liners are used in the construction of new equipment, or for the repair of
existing equipment, the effect of process fluid breaching the liner, or associated fabrication
welds, and being trapped between the liner and base metal shall be considered.
c. Design of loose or strip lining shall be subject to approval by Company responsible
engineer prior to the start of any fabrication.
d. Venting of the cavity between the lining and base metal to the outside of the vessel
insulation shall be reviewed with Company responsible engineer.
e. If specified in the applicable materials specification, post forming stress relief heat
treatment of loose liners prior to welding into the vessel or nozzle shall be performed.
f. PT of loose linings in vessels and nozzles (fillet and plug welds) shall:
1. Be performed following completion of the hydraulic test.
2. Conform to the acceptance criteria in Table 2
g. Loose or strip linings shall not be used in the following applications:
1. Non-vented liners in hydrogen or hydrogen rich service.
2. Vessels subject to PWHT, unless special procedures for design and installation can be
used.
3. Vessels with design temperature greater than 371°C (700°F), or lower than -50°C
(-58°F).
4. Vessels that operate at negative pressure, or undergo pressure cycling, particularly
between positive and negative pressures.
5. Vessels that are designated as “lethal service” in conformance to ASME IX.
6. Vacuum conditions (refer to 7.1g.4).
7. Fatigue (pressure cyclic) conditions (refer to 7.1g.4).
8. High pressure gas service with design pressures greater than 60 barg (870 psig).
g. Welding consumables for SAW and ESW cladding shall not transfer alloying
elements by means of the flux to achieve the specified weld metal composition. If
deviations are unavoidable, the issues involved shall be raised with Company responsible
engineer for approval of Supplier proposed welding processes.
h. Flux may be recirculated and re-conditioned using a procedure which shall be subject to
approval by Company responsible engineer.
i. Flux that has been fused and become “slag” shall not be ground and reused as flux.
j. Overlay consumables to be used for common CRA barriers shall be as shown in Table 1.
Use of alternative consumable compositions shall be subject to agreement by Company
responsible engineer.
k. Columbium (niobium) to carbon ratio for deposited weld metal of columbium (niobium)
bearing grades of austenitic SS (e.g., types 347 and 309Cb) shall not exceed 16:1.
l. Welding consumables batch test:
1. Welding consumables shall be subjected to batch testing as required by the applicable
AWS specification for the consumable type. (ASME IIC also details the AWS
consumable batch tests per type).
2. Each batch of welding consumables shall be deposited in conformance to the
approved WPS and PQR to ensure that the resultant overlay conforms to the specified
microstructure and chemical analysis, as required in 9.7.
3. Each batch of submerged arc or electroslag flux shall be batch tested with the same
batches of wire and/or strip to be used in production.
4. Corrosion testing shall be included in the batch testing, if specified for PQR welds.
Table 1 - Typical filler metal requirements for weld overlay of vessels and equipment
5. Hardness measurements:
a) Hardness measurements in weld metals and HAZs shall be performed using the
Vickers pyramid method (Hv 5 kg or 10 kg) and shall not be converted from
other scales.
b) For each traverse, the initial hardness measurement shall be located in the base
material HAZ within 0,5 mm (0,02 in) of the fusion boundary.
c) Subsequent hardness impressions shall be made on a vertical path at 1 mm
(0,04 in) intervals into the base material and the overlay deposit.
d) Measurements shall be numbered and reported in tabular or diagrammatic form.
6. Company responsible engineer will specify any hardness limitations associated with
the overlay process. If no hardness limits are specified, the measurement requirements
in 9.7p.5 shall not apply.
7. An original digital photograph of the metallographic specimen, showing the location
of each hardness impression, shall be presented in the PQR.
8. This metallographic specimen may be used for the ferrite point counting required by
9.7q.
q. Microstructural assessment and ferrite content measurement:
1. Microstructural assessment and ferrite content measurement shall be performed on
austenitic SS overlays.
2. On the metallographic sample in 9.7p, ferrite content shall be determined by point
counting in conformance to ASTM E562.
3. Point counting shall be performed within the top 2 mm to 3 mm (0,08 in to 0,125 in)
of the overlay. Results shall be tabulated and supported by original digital
photographs of the microstructures.
4. Ferrite measurements:
a) Ferrite content for austenitic SS shall lie in the range specified in 9.7o.3.
b) An instrumental technique, such as a Feritscope, shall be used to make a series
of 10 measurements on the as welded surface of the PQR plate.
c) Instrument shall be calibrated in conformance to AWS A4.2M.
d) Average figure shall be calculated.
e) Average value shall lie in the range specified in 9.7o.3.
r. If autogenous welding will be used to blend the weld overlay, technique shall be qualified
to include weld deposit chemical analysis and ferrite determinations, as required in 9.7o
and 9.7q.
s. Company responsible engineer will specify if corrosion testing of PQR overlay and
production overlay is required.
9.8 Weld overlay with Alloy 400 UNS N04400 (such as MONEL™) for hydrofluoric
acid service
a. Overlay chemistry shall not exceed a maximum of 5% iron content in the top 1,5 mm
(1/16 in) of the final deposit.
b. Overlays deposited with a manual process shall have at least three layers as follows:
1. First layer of buffer pure nickel (E/ERNi-1).
2. Followed by two layers of E/ERNiCu-7.
10 Production welding
a. Welding consumables for weld overlay, back cladding, or the repair of integral clad plates
shall be selected to minimise the effects of thermal degradation during PWHT.
b. In multilayer weld overlays, application of PWHT following deposition of the first layer
should be considered. Second layer of overlay may then be deposited without the need for
further heat treatment.
c. 300 series austenitic SS consumables shall be either “L” grade or stabilised grade.
d. Titanium clad equipment:
1. A heat treatment holding temperature at the lower end of the allowable heat treatment
range should be selected.
2. Between 200°C (390°F) and the hold temperature, heating and cooling rates shall not
exceed 55°C (100°F) per hour.
3. Below 200°C (390°F), equipment may be air cooled.
e. Where austenitic stainless steels form part of a vessel of which the ferritic base material
thickness is greater than or equal to 100 mm (4 in) and PWHT is required, a corrosion test
shall be carried out for evidence of sensitisation unless agreed otherwise by Company
responsible engineer. Refer to 8.1.
e. Acceptance criteria for PT shall be as detailed in Table 2 and the following apply:
1. Rounded indications: indications of circular or elliptical shape with the length less
than or equal to three times the width.
2. Linear indications: indications with a length greater than three times the width.
f. Presence of relevant linear indications shall be reported to Company for review and repair
options shall be subject to agreement by Company responsible engineer.
Indications ≤ 1,5 mm (0,06 in) shall Indications ≤ 3,0 mm (0,12 in) shall
Cladding deposited using any be accepted. be accepted.
welding processes in
≥ 3 layers. Indications > 1,5 mm (0,06 in) shall Indications > 3,0 mm (0,12 in) shall
not be accepted. not be accepted.
Notes:
1. Grinding of clad layer may be performed to remove rounded indications, provided that the grinding does not reduce
the thickness of the cladding to less than the minimum specified. Cladding thickness remaining on completion of
grinding shall be confirmed by UT. Following completion of grinding, PT shall be performed to confirm that the
indication has been completely removed.
2. Supplier shall demonstrate by examination of at least five representative indications that depth of defect associated
with the indication is such that it does not penetrate into the first layer of cladding. Depth of these indications may
be determined by layer grinding combined with intermediate depth measurement following PT to confirm the
presence or, otherwise, of the indication, subject to approval by Company responsible engineer.
3. Single layer welding processes shall be subject to approval by Company responsible engineer after relevant review
of supporting data to establish corrosion protection equivalent to two layer systems or as required by application.
14 Ferrite measurements
a. Ferrite content of austenitic SS weld overlay and back cladding shall be checked using an
instrumental technique (e.g., Fischer Feritscope).
b. Instrument shall be calibrated in conformance to AWS A4.2M or BS-EN-ISO 8249.
Secondary standard FN blocks shall be available to confirm calibration of instrument.
c. Testing shall be performed both before and after any PWHT in nominally the same
locations.
d. Ferrite content of 300 series austenitic SS:
1. Ferrite content of 300 series austenitic SS, including 321 and 347, shall be in the
range of 3% to 8% (3 FN to 10 FN).
15 Quality management
The quality management system shall conform to BS-EN-ISO 9001, API Specification Q1, or other
agreed internationally recognised standard to ensure that the products and services provided conform
to the requirements for supplier quality identified in the Purchase Order.
Bibliography
Company documents
[3] GIS 18-014, Specification for Heat Exchanger Tube-to-Tubesheet Joints.
[4] GIS 18-015, Specification for Weld Deposited Overlay of Subsea Production (API 17D, API 6A)
Equipment, Linepipe, Fittings, and Valve Bodies.
[15] API Spec 17D, Design and Operation of Subsea Production Systems - Subsea Wellhead and
Christmas Tree Equipment.