Professional Documents
Culture Documents
Session (17-18) - Cost Management
Session (17-18) - Cost Management
Session (17-18) - Cost Management
3. Estimate Costs
4. Determine Budget
5. Control Costs
Discussion Question
Discussion Question
• On some projects, especially those of smaller scope, cost estimating and cost
budgeting are tightly linked and can be viewed as a single process that can be
performed by a single person over a relatively short period of time
Question
• Processes
Plan Cost Determine budget
Management 2
1 Estimate Costs 3 4
Control Costs
Cost Management Terms
• Opportunity Cost: the loss of other alternatives when one alternative is chosen. For example;
Cost Management Terms
when you have to select between two projects of A=$50,000 and B=$70,000, the opportunity
cost of selecting project B is $50,000.
• Cost Benefit Ratio: This is the amount of money a project is going to make versus how much it
will cost to build it. Generally, if the benefit is higher than the cost, the project is a good
investment.
• Net Present Value (NPV): This is the actual value at a given time of the project minus all of the
costs associated with it. This includes the time it takes to build it as well as labor and materials.
People calculate this number to see if it’s worth doing a project.
Cost Management Terms
Internal Rate of Return:
Cost Management Terms
• This is the amount of money the project will return to the company that is funding it. It’s how
much money a project is making the company. It’s usually expressed as a percentage of the
funding that has been allocated to it.
Depreciation:
• This is the rate at which your project loses value over time. So, if you are building a project that
will only be marketable at a high price for a short period of time, the product loses value as time
goes on.
Exercise
• … the process of defining how the project costs will be estimated, budgeted, managed,
monitored, and controlled.
• It answers the question "how are we going to manage costs during the project“?
• The Triple Constraints (Scope, Time and Costs) are central for Cost Management.
Plan Schedule Management
Plan Schedule Management
• What do we need?
• Which tools to use?
• What will be the outcome?
Inputs Tools & Techniques Output
1. Project Charter 1. Expert Judgement 1. Cost Management Plan
2. Project Management Plan 2. Data Analysis
• Schedule Management Plan 3. Meetings
• Risk Management Plan
3. Enterprise environmental factor
4. Organizational Process Assets
Activity
• … is a quantitative assessment of the likely costs for resources required to complete the activity
• … a prediction that is based on the information known at a given point in time incl. the identification
and consideration of costing alternatives to initiate and complete the project
• … expressed in units of some currency (i.e., dollars, euros, yen, etc.), although in some instances other
units of measure, such as staff hours or staff days, are used to facilitate comparisons by eliminating
the effects of currency fluctuations.
Estimate Cost
• What do we need?
• Which tools to use?
• What will be the outcome?
Inputs Tools & Techniques Output
Techniques
Exercise
• Budget Estimates
• Usually made during planning (-10% to + 25%)
• Definitive Estimate
• Identified when rolling up the WBS (-5% to + 10%)
Estimate Sheet
Determine Budget is …
• A project budget includes all the funds authorized to execute the project. The cost
baseline is the approved version of the time-phased project budget that includes
contingency reserves, but excludes management reserves
Determine Budget
Determine Budget
• What do we need?
• Which tools to use?
• What will be the outcome?
Inputs Tools & Techniques Output
1. Project Management Plan 1. Expert Judgement 1. Cost baseline
• Cost Management plan 2. Cost aggregation 2. Project funding requirements
• Resource Management plan 3. Data Analysis 3. Project Document updates
• Scope baseline • Reserve Analysis • Cost estimates
2. Project documents 4. Historical Information review • Project schedule
• Basis of estimates 5. Funding limit reconciliation • Risk register
• Cost estimates 6. Financing
• Project Schedule
• Risk register
3. Business documents
• Business case
• Benefit Management plan
4. Agreements.
5. Enterprise environmental factors
6. Organizational Process Assets
Cost Baseline, Expenditures, and
Funding Requirements
• … the process of monitoring the status of the project to update the project
costs and managing changes to the cost baseline
• What do we need?
• Which tools to use?
• What will be the outcome?
Inputs Tools & Techniques Output
schedule in a project?
Key Terms
• Budget at completion (BAC): The BAC represents the total cost MTN launches project to upgrade
baseline for the project. E.g. 1,400,000. computer & customer information
system at 10 regional call centers.
• Planned Value (PV): Approved value of work to be completed in
given time. In another words Combined PV = BAC. At any point The upgrade takes 2 weeks per
in the project; Planned Value = BAC X planned % complete call centers and 20 weeks for all
Find PV from the example the work with a total combined
budget of of $1,400,000. You’ve
• Earned Value (EV): Value of work that has been performed and just finished week 12 of the
can be measured at any time. Earned value = BAC X Actual % project.
complete
Let us compute 2 variances and 2 Indexes The upgrade takes 2 weeks per
call centers and 20 weeks for all
• Schedule Variance (SV) is indication of schedule performance the work with a total combined
and is expressed SV = EV – PV budget of of $1,400,000. You’ve
just finished week 12 of the
• - variance indicates work behind schedule
project.
• + variance indicates work ahead of schedule
• 0 Indicates work on schedule – exactly on plan
Key Terms
MTN launches project to upgrade
• Cost Variance (SV) is indication of cost performance and is computer & customer information
expressed CV = EV – AC system at 10 regional call centers.
Cost Forecasts