DAILY DRILLING REPORT

Date : 07 December 2022 Client : PT. Sarana Mandiri Utama


Day : Wednesday Location : Desa Menjeluntung , Kalimantan Utara
Shift : Day √ Night Rig / Hole : DHGT-06

No From To Activity Photo Activity

1 6:40 7:20 Travel Time Photo 1


2 7:20 7:30 Rig Down
3 7:30 12:36 Prepare Moving (Waiting Support)
4 12:36 13:06 Break (Istirahat)
5 13:06 14:46 Prepare Moving (Waiting Support)
6 14:46 16:36 Next Infomation (Redrill DHGT-06)
7
8
9
10
11
12
13
14
15
16
17
18
19
20 Drilling Activity
Day All
TOTAL DEPTH Open Hole (Meter) - - Activity Times
Coring (Meter) 0.00 37.80 P2H
Consumables Qty Total Hole 188.20/876 (21,48%) Demobilization
PVC Survey Information Moving Rig
POLYMER Depth 100 Set Up Rig & Rig Down 1
AUSGEL Dip Set Waterline
AUSTROL Azimuth Pulling Up & Down Rods
FOAM Freeing Rods
CR 650 Reaming
DIESEL FUEL Changing Bit
GASOLINE Drilling
BENTONIT Tool Box Meeting
Safety Meeting
Conditioning Hole/Flushing
Coral / Instal PVC
Standby (Bad Weather)
Personel Hours Standby (Waiting Support) 1
1. Ayub Bamba (WellsiteGeos) 6. Marthin (Crew) Service - Repair - Maintenance
2. Hadi (Driller) 7. Cecep (Operator Logging) Travel Time 1
3. Hendi (Crew) 8. - Geophysical Logging
4. Encup (Crew) 9. - Making Drillpad
5. Aim (Crew) 10. - TOTAL FOR SHIFT (Hours) 3
Signatures : Moving Distance
From (Hole No) To (Hole No) Total (Meter)
Driller :

Grand Total (Meter)


Supervisor : Issue : Stack Rods (Pipa berhasil di Pull Up 10 batang & 2 bantang + 1 Core Barrel masih tertinggal di lubang)
Plan to Next : Set Up Rig & Redrill DHGT-06