Professional Documents
Culture Documents
Exihibit B - SCC (NO Tracking)
Exihibit B - SCC (NO Tracking)
BANDRA MUMBAI
2. Schedule
3. Commercials
3.1 Contract Value
3.2 Quantity Variations
3.3 Statement at Completion
3.4 Mobilization
3.5 Performance Guarantee
3.6 Mobilization advance
3.7 Running Account Bills
3.8 Defect Liability period
3.9 Correction of certificates
3.10 Final Running Account Bill
3.11 No dues Certificate
3.12 Bonus / Penalty
3.13 Escalation / Validity of Rates
3.14 De-scoping Penalty
3.15 Contra Charges
3.16 Taxation
3.17 Payment against tax variations
4. Manpower
4.1 Construction labours
4.2 Technical personnel
6. Compliances
6.1 Statutory Compliances, Indemnity and Labour Laws
6.2 Illegal Immigrants
6.3 Documents to be submitted
6.4 Insurance
6.5 No Poaching
6.6 Contractor’s key staff
Sr. Building Name Approx No. Of floors Approx Total BUA (sqft)
No.
1 Link Komal 4th floor to 15 floors + 1,18,578.81
Infra+ Tower Car Parking+
++
The Employer will hand over the site in stages after completion of mass excavation as sufficient
work area is made available to the contractor. The scope of work under terms of this contract
shall include, but be not limited to carrying out all civil works for the main building as shown in
drawings prepared by Architect & consultant and described in specification and any variations
thereto including all preparatory works and protective measures for completed works in full
compliance with conditions of this tender document and as directed by concerned Employer’s
representative, including maintenance/ rectification of the works till the completion of Defects
Liability Period as specified in the Contract Form, and inclusive of:-
a) Excavation: Manual excavation as required in any strata after general excavation carried out by
the Employer to an average depth not exceeding 0.15m including dressing and cleaning of the
strata before pouring the concrete for PCC, levelling of the final strata at required depth, clearing
and taking out the excavated materials etc. including carting away the surplus earth (after
backfilling) within the plot as per direction. Any additional excavation shall be paid as per agreed
rate.
Survey: Setting out including marking of Control points and grid points and making of centreline
marking.
b) Backfilling and Compaction: Approved quality murum to be brought by contractor and carry
out backfilling work by mechanical or manual means. filling required for attaining the required
levels/ slopes in the lift pits, service trenches, plinth and other pits as mentioned on drawings
shall be done by contractor. Scope shall include filling in layers, levelling, and compaction with
earth compactor. Compaction should be done in layers of 200 to 300 mm thick to achieve
compaction density of 95%
d) Plain Cement Concrete: Laying plain cement concrete including centring, vibrating, shuttering,
compacting, curing, de-watering etc. below foundation and plinth level including Reinforcement
if any in plinth.
e) Plum Concrete: Laying plum concrete course in plain cement concrete and evenly distributed
plums including mechanically vibrating, compacting, centring etc. (No plums shall be allowed to
be projected / protruded within 150mm from top level of plum concrete). Maximum quantity
under contractor’s scope shall be 100 Cum (Below/Above Raft and Foundation). Any additional
requirement shall be paid to contractor per the Item rate quoted by Contractor in the agreed rate.
g) Reinforcement:
For RCC Elements, Steel will be issued by employer at site. Employer may supply steel
in truck load or in full length.
The contractor’s scope shall include preparation of bar bending schedule, straightening, cutting ,
bending, shifting to the required location, and fixing of steel reinforcement for RCC including
fabricating, transporting, storing, de-coiling, spirally hooping and placing in position at all levels,
including all labour, equipment’s, supplies and incidentals including tying with the binding wire
and providing proper cover as specified and shown in the drawings or as directed by the
Employer’s Representative.
The contractor alone shall remain responsible for the correctness of the bar bending schedule and
any wastage of the steel due to erroneous cut lengths in the contractor’s BBS shall be to the
contractor’s account.
In both cases, the contractor’s scope of work shall include supply and fixing of cover blocks and
binding wire as per specifications. The scope of work shall also include welding of reinforcement
with low hydrogen low heat welding electrodes for the welding length mentioned in the drawings
in place of conventional laps, wherever consultants recommend, for which no extra cost shall be
claimed. Replacing conventional laps with welding splices will be entirely at consultant’s
discretion. Such unclaimed welding will also include welding of reinforcement to already fixed
insert plates, structural steel members etc. Shear connectors prepared from the reinforcing steel
welded to structural steel members.
The scope shall also include protecting the reinforcing bars – in their virgin form or in the
fabricated form, or when placed and tied up in position or as dowels left for future continuation of
work or at construction joint – against corrosion due to exposure to weather if left exposed and
un-encased for more than three weeks from the date of delivery to the site. These bars will be
treated as per employers recommended process all material required for the treatment will be
given by the Employer All the main reinforcement bars in column with diameter 20mm and
above shall be necessarily spliced using Type II parallel threaded cold forged couplers.
Mechanical couplers shall be provided by the Employer however, fixing of the couplers shall be
in the Contractor’s scope. Threading of bars for couplers will be carried out by the Employer’s
agency; the Contractor shall provide labour for lifting and shifting of the bars to and from the
threading facility for threading. In case of missing/ displaced/ misplaced dowels, the contractor
shall drill and grout new dowel bars using approved method.
In case Employer arranges to issue readymade cut steel to contractor for work as per bar bending.
Contractor shall have to include transportation of steel from steel yard, bending, lifting & fixing
of steel in his scope. In this case contractor shall pass rebate as - Rebate for readymade cut steel
– Rs. 5 psft of BUA of the relevant slab or Rs.1000 per ton whichever is lower.
h) Sleeves: Placing/Welding of GI Sleeves of various diameters during concreting at locations as
shown in drawings with or without flanges within the formwork.
i) Formwork: The scope of work for providing Shuttering shall be as per Clause 1.4 [Formwork].
l) If the slab-ceilings are not completed to the required quality standards (permitted variance only
+/- 5MM), the contractor shall ensure that the variation is corrected with putty within the original
stipulated timelines at his own cost. Window and door openings shall be completed as per the
dimensions in the drawing. Maximum allowable variation of +/- 5MM.
+/- 50mm chipping in RCC / masonry wall, RCC Floor shall be done by contractor to achieve
proper line and level.
m) Brick work/ Block work: Internal & external Brick/Block masonry work in the building. The
scope shall include but not limited to –
a. Shifting of Bricks/blocks from 150m lead to respective location, watering/ soaking of
bricks, raking of joints etc.
b. Screening and washing of sand for masonry and plaster, if required
c. Fixing of chicken mesh at RCC Masonry joints
d. Scaffolding/staging (M.S. only). No bamboo scaffolds allowed for work.
n) External Plaster/Internal Plaster: The scope shall include but not limited to:
a) Crushed sand based pre-mix plaster for 1st coat
b) For 2nd coat - to go with natural sand based ready mix / hand mix plaster.
c) In case if external plaster mixing machine is required for 2nd coat of external plaster,
then the same shall be in the scope of the contractor
d) Internal plaster along with plastering the sides of staircase flights and the risers of the
stairs. Internal plaster shall also include other areas like toilet Dado, lift lobby dado etc
and other utilities.
e) Internal plaster along with retaining wall/Shear wall in basement area.
f) Gunny rolls, green screen to be installed before external plaster.
o) Fixing of door frames and window sub frames: Included in the scope of the contractor.
p) Insert Plates: Installing inserts in the concrete.
q) Water proofing: excluded but Coordination with water proofing agency, giving Workfront, is in
the scope of the contractor.
r) PT Slab: excluded but Coordination with PT agency, giving Workfront, making PT strand stool,
scaffolding, grouting labour if required is in the scope of the contractor.
s) Other Civil Works: Any other civil work in building as per working drawings. In addition to the
above-mentioned work, contractor shall also carry out all civil works wherever required at the
discretion of the Employer in the building/project layout at an agreed item rate amounting up to
10% of the Contract value.
t) Grinding of ceilings
u) Repairing of electrical zari & conduit sides - Electrical conduit, DB, Electrical box mortar filling
& repairing work in the scope of contractor (This work shall be done by civil contractor till the
contract period)
-v) Contractor to provide scaffolding in passenger elevator shafts and car parking system shafts for
Tie rods filling, grinding of RCC as well as electrical works and white wash before dismantling
and handover to Elevator companies for installation
w) Inspection of Work: Contractor will assist (labour supply) in providing safe approach, ladders
with proper railing to building under construction for architects, consultants’ inspection and also
to contractor’s workmen.
x) Rain Water drainage Arrangement: Keeping working area dry is contractor’s responsibility.
Contractor shall make necessary arrangement so that rain water/ surface runoff cannot enter the
working area with Employer supplied materials. During monsoons the Contractor shall submit a
detailed monsoon protection plan and get it approved by the Employers Representative. The Cost
for the same shall be deemed to be included in the rates quoted by the Contractor.
x) The contractor is required to dig up and fill 8 to 10 nos of earthing pits as per specifications of
the electrical contractor. The contractor shall dig up and construct all pits/trenches/chambers/
manholes/service chambers required for RWH/Drainage/Sewage/ SWD as per the client’s
plumber’s, Fire fighting and electrician’s requirements. All these works are included in the scope
of work of the Contractor.
y) Auxiliary: Following scope of activities will be required during the course of the project:
a. Concrete Testing: Concrete Testing (casting of cubes, handling and transportation of
cubes from casting site to the specified laboratory, thereafter conducting testing at lab
provided by the Employer and reporting appropriate strength to the Employer) shall be in
the scope of the civil contractor.
b. Construction of Water tank for cube curing
c. Formation of pits for drainages
d. Supply of labour for carrying out miscellaneous activities at site at an additional rate as
agreed with the Employer.
e. Cleaning/ Housekeeping
f. Removal of Tie rods, PVC pipes/PVC cones, plugging tie rod holes with approved
cement mortar/cement grout
g. Drilling and Grouting – to be paid separately for the reasons not attributable to the
Contractor
h. Collection of debris from each floor and disposal of debris through the debris chute &
carting away all generated debris and dumping it on approved location by MCGM.
j. Supply of Labours for Spraying of surface retarder, curing compound and other
construction chemicals
k. Lighting fixtures in the common areas of the building shall be provided by the Contractor
free of cost. Contractor shall install sufficient floodlights/ halogens for illumination of
working area.
l. Providing spray paint, chalk line, line thread, nails, hammer, markers etc. for survey
works with application of the same
m. Contractor shall erect, removal, shifting & re-fixing of the edge protection on each floor
n. Approach roads for the working area shall be constructed by the Employer
z) Safety
a. Contractor shall follow the provisions of GCC for Safety Precautions
The contractor shall be solely responsible for providing and operating all equipment,
tools and implements (save and except those that the Employer has specifically agreed to
provide as per the terms of this Contract) which are required for the implementation of
the contracted works as per the schedule stated in the contract and as per the quality
standards acceptable to the Employer. In case of any dispute in this matter, the decision
of Sorriso developers LLP Director/Partner shall be binding on all parties. In the event
that the Contractor fails or neglects to provide and/or operate the said equipment(s),
tool(s) and implement(s) as required, same shall constitute a default on part of the
contractor and the consequences as laid out in this contract shall follow.
1.4 Formwork:
Conventional/System/Aluminium Formwork (for Non-typical & Typical floors):
The Contractor shall provide required quantity of specified shuttering material for all RCC
Members to achieve the progress of work and as agreed in the construction schedule. Minimum
shuttering requirement is as below –
a. 100% of wall shuttering at one level
b. 100% of the column/Shear wall/lift wall/Core wall etc shuttering for one level of the
building (Aluminium formwork)
c. 100% of one level worth of slab shuttering
d. 200% of one level of slab propping (M.S)
e. Two level equivalent of beam bottoms and props (M.S.)
f. No wooden props (bamboos) shall be allowed
g. Only channels (no spans) shall be allowed
h. Staging for all double height areas
i. Outer working platform with edge protection for top two floors and one floor above top
floor design/onsite samples as approved by employer representative for installation and
shifting along progressive floors to be done by contractor. All material required will be
provided by contractor without any extra cost.
j. Access and egress to all level with suitable ladder with handrails to be provided by
contractor.
Contractor shall provide details of shuttering and shall get it approved from Employer’s
Representative. The Contractor shall provide detailed shuttering design which shall be approved
by the Structural Consultant.
Any conventional shuttering requirement for additional areas, required to achieve the
construction program, shall also be brought by the Contractor without any additional cost to the
Employer. The formwork and false work shall be erected at the site after the Employer’s
Representative checks and inspection of the entire lot of shuttering and centring materials
including type, thickness and repetitions proposed. Contractor shall use plastic coated Plywood of
12mm/18 mm thickness or as recommended by structural Consultant or the Employer’s
Representative. Only 10 repetitions for plywood shall be allowed including both sides (5
repetitions from each side). The plywood of first quality of specified/ recommended quality,
variety and brand are to be used for form finish shuttering. All wooden shuttering shall be new.
The MS materials shall be of acceptable quality and shall be used only after the approval of
the Employer.
All shuttering and formwork shall be designed and provided to obtain form finished
concrete surface for all RCC works.
MS Props, MS Channels, H-Frames, Cup-locks shall be used. Other equivalent may be allowed
as specified/approved by Employer’s Representative. Yokes, shrinkages, bolting and other
mechanical devices will be used for tightening and fastening of the Form/ False work. The use of
nails and wires shall not be allowed.
Contractor will erect the form/ false work in line, level and the Plumb shall be checked and
maintained in form work at all heights and levels without fail. The bracing will be provided in
both the directions and in case of heights greater than 3 meters, diagonal bracing shall also be
provided in addition to the former as directed by Employer’s Representative. No steel
reinforcement to be used for bracing. The entire responsibility of Form/false work lies on the
Contractor for any kind of failure. At every use of formwork, the surfaces of shuttering/
formwork shall be cleaned neatly and washed with water, then the recommended oil or grease
need to be applied before it is erected in position.
Contractor shall be required to provide MS formwork for round columns (if applicable), elevation
treatment/ features. The outside scaffolding shall be of steel and no lateral supports shall be
allowed from any wall.
The planks shall be tied with the benches perfectly. Tie-rod holes need to be immediately grouted
after de-shuttering; grouting material shall be provided by the contractor without any extra cost.
1.6 Water
The cost for construction & drinking water shall be borne by contractor at his own cost also
distribution shall be done by the contractor at his own cost. Contractor shall ensure that there
shall be no leakage or improper use of the said water during the course of transition from the
common point to the place of requirement. The Contractor shall be liable for any pilferage or
misuse of the water. Water Tank for storage of construction Water shall be constructed by the
Contractor with his labour free of cost.
In case Employer arrange water to construction & drinking purpose & Any wastage in excess of
the norms prescribed by the Employer’s Representative shall be debited to the Contractor’s as per
Contra charges mentioned in the GCC.
Employer shall allow labour camp after completion of Ground floor roof slab, to build
temporary labour camp. Contractor shall build the labour camp in accordance with the
Employer’s prevalent policy temporary labour camp.
a) Reinforcement Steel: Reinforcement Steel is supplied in total Load. Steel for all column
and shear wall vertical bars (16mm dia and above only) may be supplied in order length
& for other members viz. slabs, beams, Pardi etc shall be supplied in lengths available in
market. The contractor shall satisfy himself of the total quantity of steel received at site
after unloading before acceptance from Employer and before being put to use. Contractor
shall make provisions for adequate and safe storage of steel issued to him.
The Reinforcement Steel in case of total load shall be supplied at the nearest point to the
building. Reconciliation of the Steel, Couplers and Threaded bars is to be done through
subsequent RA bill after completion of every 4th running account bill and along with
final bill. All the scrap material shall be returned to the Employer.
b) Ready Mix Concrete: Ready mix concrete shall be supplied for concreting work at a
nearest point to the work site, co-ordination with concrete plan to be done by contractor.
RMC for slabs should be unloaded using stationary pumps within 90 minutes of delivery
of concrete at site. Minimum order quantity from RMC plant shall be minimum 3 cum.
100% of concrete required for column work need to be unloaded using tower crane/boom
placer as applicable (to achieve unloading within 90 minutes of delivery of concrete at
site)
Contractor shall give schedule for concreting well in advance. Every Saturday, the
Contractor must submit the program for concreting for the next week. In case the
contractor is not ready for concreting after indenting for RMC and RMC has to be taken
back from site after delivery, then the costs paid to the RMC supplier by the Employer
shall be debited from the Contractor’s bills at actual + 25%. Contractor shall not retain
Transit mixer for more than 1 hour for unloading. Extra retaining of transit mixture will
be debited as per actual. RMC reaching site should be used within 90 minutes.
c) Cement: Storing cement in proper condition at site is contractor’s responsibility and any
damage of the same shall be debited to the contractor at basic rate +25% handling
charges. Shifting of material is in contractor’s scope. Contractor shall return all empty
cement bags to the Employer. Contractor can use 25% cement bags but these will be
reissued to contractor after contractor return 90% bags to the stores. Although Cement is
purchased by Employer from known brands and from reputed dealers, shall be
responsibility of the Contractor to satisfy himself regarding quality of cement by physical
inspection prior to use.
d) Rubble, Sand, Bricks, Blocks and Aggregates: Rubble, Sand, Bricks, Blocks and
Aggregates shall be supplied in lots of truckload.
e) Other Miscellaneous materials: Retarders, curing compound & other construction
chemicals shall be supplied by the Employer along with the following:
The Contractor shall ensure the following in case of free issue material:
a. The Contractor shall properly store the material provided by the Employer and maintain
proper records of materials receipt, issues, consumption and balance to be maintained by
the Contractor at the site. The Employer will have the right to inspect storage and safety
facilities provided and records of the Contractor.
b. The material, consumed in excess of the wastage limits due to bad workmanship,
negligence or mishandling by the Contractor’s employees, the materials issued for
rectification will be recorded at landed cost or prevailing market price whichever is
higher and value of the same will be debited from the Contractor’s payment.
c. The Contractor shall provide details of the total quantities of the stipulated materials
required for the completion of the work in writing within a fortnight of issue of work
order, in a phased manner i.e., month wise requirement according to construction
program for completion of the work. Any lapse/ delay on the part of the contractor/
agency in this regard will be to his account.
d. For the material which will be issued at the Employers store/ yard, the contractor will
have to make its own arrangement for loading, unloading and shifting of the material to
worksite at leads up-to 150mm and all lifts. The Contractor shall be responsible for any
damage/ loss to the material.
e. The material issued by the Employer shall at all times remain the property of the
Employer and no part of it shall be used by the Contractor for the purpose other than
execution of the work entrusted under the work order.
f. Excess, unused material supplied by the Employer or obtained by recommendations of
the Employer which in the opinion of the Employer’s representative are likely to be
useful to the Employer, will be returned in good condition at the original cost paid for, if
so, decided by the Employer.
g. None of the equipment and materials shall be removed by the Contractor from the site
without the permission of the Employer’s representative.
h. The Contractor shall not remove unfixed material from sites without the permission of
the Employer’s representative.
Material Reconciliation: The contractor shall minimize the wastage on all free issued material.
Wastages of the materials should be within specified limits mentioned below, if it exceeds these
percentages then actual cost of material at the time of execution will be recovered from contractors’ RA
bills at the rate of purchase price plus + 25% incidental cost. Breakages and pilferages, if any, shall also
be recovered accordingly. Contractor shall submit Reconciliation of cement, reinforcement every bill and
also along with the final bill which shall be checked and approved by the Employer’s Project-in-Charge
before certification of bill. Reconciliation of RMC shall be submitted after every pour, the Contractor
needs inform Employer’s representative in case of any discrepancy of supplied volume as against the
quantity mentioned in the RMC supplier’s Challans. Otherwise, any such discrepancy has to be borne by
the Contractor and Contractor shall be debited as per the wastage norms as mentioned in the table below.
Note: - Cement consumption for all concrete shall be considered on the basis of Mix design based on IS
456:2000. Cement consumption norms for other activities shall be as per Annexure-III (Cement
consumption norms).
Debit for excess Steel Wastage in case steel is issued in truck load: Amount to be debited to the
Contractor for excess Steel wastage shall be calculated as following:
• NI: (Net Issue) – Net amount of steel issued in tons (Total issue – steel return in full
length bars as issue)
• B: (BBS quantity) – Theoretical quantity of steel required in tons as per BBS (prepared
by Detailer)
• C: (chairs & pins quantity) – Quantity of steel required for chairs and pins -1.5% of BBS
Qty
• W: (allowable scrap expected) – allowable scrap expected to be generated (%) -2.5% of
BBS quantity
• w: Allowable scrap expected to be generated (in tons)
• s: (scrap returned) – Amount of scrap returned in tons
• P: (price of steel) – Weighted average price of steel over duration of the project
Notes:
• Contractor shall segregate higher dia bars (>=20 mm dia) into individual dia wise groups
while returning to stores
• In case bar bending schedule (BBS) is prepared by Employer’s site engineers, the BBS
must be checked and any disagreements must be highlighted by the Contractor within 7
days of receipt of the BBS from site. In case the BBS is prepared by the Contractor, the
Employer’s Representative shall approve the bar bending schedule or highlight
disagreements within 7 days of receipt of the same.
• Cost of steel to be computed as the average cost of purchase of all steel by the Employer
during the course of the project. In case of any dispute, documentation provided by the
Employer for procurement done during the course of the project will serve as the final
figure.
• Rolling margin does not play a role in determination of penalties as computed above and
no Adjustment for rolling margin is to be allowed for this purpose.
The Contractor shall ensure the following for material in his scope:
a. Materials supplied/ obtained should be of standard and acceptable quality as per the
Employers specifications. Defective materials, if any, shall be replaced immediately by
the Contractor at no extra cost. The discretion of the Employers representative in this
regard shall be final and binding.
b. Materials to be used including their make and type shall be pre-approved by the
Employer’s representative on site.
c. Material of sub-standard/ defective quality brought to the site shall be removed, as per
instruction of Employer’s representative, failing which, the Contractor will not be entitled
to any payment whatsoever on this account. The Contractor undertakes to provide the
additional material in place of such rejected material at its own costs and expenses.
d. In case of Contractor delaying delivery of certain equipment or material, the Employer
reserves the right of getting the material delivered at site at the Contractor’s risk. The
material cost and an additional 15% of cost shall also be recovered from the Contractor.
e. Employer’s or his representatives will have right of access to the Contractor’s workshops.
1.10 Housekeeping
Housekeeping shall be carried out by the contractor at every stage where one stage of the work is
completed and second stage is to start or when the area of work has to be handed over to another
agency. Failing which, the Employer’s Representative will deploy another agency to carry out
such works and an amount equalling 125% of the actual charges incurred shall be levied to the
failing contractor. Contractor shall make sure that the safety net is cleaned at least once a week.
2. Schedule
The following table shows the timelines for buildings to be executed.
Milestones:
The following milestones shall be considered for calculation of bonus and penalty:
1. Interim Milestone: Completion of Gr. Floor Roof slab– 165th day from the start of works
2. Final Milestone: Final completion of works under contractor’s scope i.e 550th day from
start of works
The above milestones shall be used by the Employer to track the proposed construction program.
Based on the Commencement Date and the agreed program, the Contract Duration will be arrived
at for the purpose of this Contract. The contractor shall be deemed to have taken into
consideration the statutory byelaws, conditions surrounding the site and requirements for the
commencement of the work at each stage and shall be deemed to have considered fulfilment of
such requirements in his completion schedule.
The contractor is also required to account in his completion schedule, reasonable time for
procurement of such permissions and shall have no claim for additional time for completion of
the work.
a. The contractor to consider following requirement -Part areas/ floors will have to be
handed over from time to time for 'fit outs and finishing works ' as per requirements of
the Employer.
b. The Sequence of work may have to be changed to suit requirements and phased
completion schedule at no extra cost to the Employer and no additional amounts shall be
payable to the Contractor by the Employer.
3. Commercials
3.1 Contract Value
Civil construction of units mentioned below for sub structure and super structure above
plinth with contractor supplied formwork for all the slabs and required plant equipment
as per the scope mentioned in the document on BUA labour rate basis including all taxes,
cesses, duties, Octroi, transportation, any other levies by government (including GST),
safety measures and insurance, including all overheads and profits etc.
Sr. No. Building Name No. Of floors Total BUA Rate Amount
(sqft) (INR/Sq.ft)
GST –
Total Contract Amount in Rs.
• The areas mentioned above is as per the drawings attached and Area reconciliation will
be done only in case of revision in Drawing areas shall be calculated as per norms for
measurement of built-up area as stated in Annexure - I (Norms for Measurement of
Built-up Area).
• Individual milestone variance is 14 days and Final completion milestone variance is 30
days
• If any interim milestone is not achieved, the respective additional payment shall be
withheld. Those withheld payment shall only be paid back if the Contractor is able to
achieve the final completion milestone.
It is understood that the Contractor has understood well the norms of measurement and furnished
rate accordingly and will not take any objection for area calculation, percentage agreed etc. as per
the Contract agreement and also for future amendments, if any.
3.4 Mobilization
Though the entire mobilization period shall be 15 days starting from the date of handing over the
building from the Employer, Contractor shall mobilize partially and start work at site with
required labour, material and equipment by the Commencement date as mentioned in Clause 2
[Schedule].
The following activities shall be completed in the Mobilization period:
By the Contractor:
a) Commencement of construction of site office, store and other site infrastructure required
by execution of the works.
b) Bank guarantee needs to decide for mobilization advance
c) Mobilization of required resources (Men and Equipment) for the works that needs to be
executed over the next 3 months.
d) Completion site labour toilet, water tanks construction.
e) Mobilizing the required labour force and deployment of his staff at site
f) Submission of Mobilization schedule of major and minor equipment’s in Contractor’s
scope.
g) Mobilization of Dewatering pumps.
h) Mobilization of Rebar Bending and cutting machines.
By the Employer:
a)
Payment of Mobilization advance against Bank Guarantee as per the payment terms.
b) Hand over to and grant possession of the portion of site on which the works need to
commence.
c) Issue of GFC/VFC drawing for Plinth.
d) Issue of Form ‘V’
Any payments to be made against submission of bill, prior to final certification of the bill, shall
be stopped / discontinued if it is found that the submitted bills exceed the actual certified bills by
a significant amount on a repeated basis.
• Audit
Client shall have the right to audit the relevant records and accounts of the contractor or its Sub-
Contractors in relation to reimbursable items paid for by Client under the order at any time until
the expiry of eighteen (18) months following the settlement of the final account. Any incorrect
payment(s) made by Client shall be adjusted in accordance with the findings of the audit. The
Contractor shall make all relevant records and accounts available and give the auditors all
reasonable assistance and ensure that it’s Sub-Contractor(s) comply with such provisions.
Setoff: All claims for money due or to become due from Client shall be subject to deduction or
set off by the Client by reason of any counterclaim arising out of this or any other transaction
with Contractor.
Percentage Payment stages mentioned in Annexure II are only indicative and may not
represent actual value of work completed
Any EHS violation recorded and penalized will be debited from the running bill.
Contractor should submit the RA bill as per approved format by Employer representative.
In case the Contractor fails to perform as per the agreed time schedule, provided in this
Order and as per the directions of the CLIENT, the Contractor shall pay to the
CLIENT agreed amount of liquidated damages for each calendar week of default
or delay or part thereof, the sum(s) equivalent to 1% (one percent) of the total
value of this ORDER per week. The balance work / supplies shall be carried out
by Client, by appointing another agency at the cost and risk of the Contractor.
Amount thus due from the Contractor shall be recovered from the amount
payable to the Contractor on this work or any other work with the Client and
shall be without prejudice to the rights of the Client.
Payments of liquidated damages shall become due immediately upon the failure of the
Contractor to make the Supplies / work within the time frame specified by the
CLIENT and as mentioned in this Order. Nothing in this clause shall operate to
restrict any other rights and remedies available to the CLIENT at law or under
this ORDER.
Actual Cost incurred x 125% for the different categories of such works/rectification:
Contractors shall be provided copy with debit note for each debit at the time of payment of the
bill in which the debit is made to the Contractor.
* In case of the amounts under (a to g) x 125% exceeds 12.5% of the contract value, the
Employer shall be entitled to terminate contract and appoint new contractor vendor for balance
scope work.
3.16 Taxation
Only GST as applicable shall be paid extra on quoted rates as per the prevailing government rules
and regulations. T.D.S shall be deducted from each R.A. bill. Relevant Tax Registration number
needs to be clearly mentioned on the contractor’s bill. The Contractor shall furnish all the
documentary details pertaining to the tax rules. The Contractor is solely responsible for payment
of taxes to the Government Authorities. Contractor is required to submit their GST payment
challans along with 2nd R A bill onwards.
The Contractor shall provide its permanent account number (PAN) to the Company before
releasing its first payment, as provided in the Agreement. The Company shall issue a
consolidated TDS certificate to the Contractor for such tax deducted during the whole of financial
year from April to March. A request letter should be issued by the Contractor to the Company for
such consolidated certificate.
Income tax clearance certificate for last three years needs to be furnished along with the Tender
submission.
4. Manpower
4.1 Construction Labour
The labour strength requirement is subject to variation from time to time, which the
Contractor should be prepared to meet at short notices and no extra claim for this shall be
considered. Below mentioned is the minimum labour requirement to complete the work
within agreed timeframe.
Contractor will have to increase the same as per requirement of site with 3 days prior
notice from Employer.
5.1 Definitions
“Employer” means a company registered under the Companies Act 1956, as detailed in the
Instruction to Tenderer and includes the Employer/Employer’s Representatives, successors and
assigns.
“Contractor” means a company registered under the Companies Act 1956, who has been
employed by the Employer to conduct the Works under the Contract and includes its legal
Representatives and successors.
“Architect” means the firm nominated by the Employer for designing the works and designated
as such by the Employer.
“Structural Consultant” means the firm nominated by the Employer for designing the works
and designated as such by the Employer.
“Contracting Authority” shall mean the Authorized Signatory appointed by the Employer to
award the contract on his behalf.
“Works” shall mean the work(s) to be executed, items and / or activities to be provided / carried
out, and / or services and activities to be performed in accordance with the Work Order issued to
the Contractor or part(s) thereof as the case may be and shall include all extra or additional,
altered or substituted or temporary works as required for performance of the Work Order and
urgent measures which in the opinion of the Employer become necessary during the process of
work to obviate any risk of accident or failure.
“Letter of Award” means the award of Works by the Employer of the Contractor’s Tender
(including any deviations or changes agreed to in writing) and instructing the Contractor to
mobilize and commence the work.
“Work Order / Agreement” shall mean the Work Order placed on the Contractor by the
Employer for the execution of the specified portion of the Work(s), in accordance with the
Specifications, terms & conditions, workmanship as per requirement of satisfactory completion of
Works and Priced Bill of Quantities.
“Specifications” shall mean the directions, technical specifications, requirements and provisions
furnished or approved in writing by the representative(s) of the Employer as the case may be
during the course of the project duration.
“Contractors Equipment” means all appliances and things of whatsoever nature (other than
Temporary Works) required for execution and completion of the Works and the remedying of any
defects therein, but does not include plant, materials or other things intended to form or forming
part of the Permanent Works.
“Disruption/s” shall mean and include all stoppages of work caused by temporary suspensions of
work duration one day or more caused due to power failure, want of drawings, want of decisions,
unprecedented climatic conditions stopping all work, or any of the force majeure conditions.
For terms that are not defined in the above section, the meanings for the same may be as
reasonably inferred from the usage of the term in the relevant clause. In case of any further
clarification required, the meaning of the term as defined in the FIDIC guidelines may be referred
to.
“Commencement Date” means the date agreed upon between the Employer and the Contractor
for start of Works and defined as such in the Work Order.
“Time for Completion” means the time for completing the execution of and passing the Tests of
the Works in full under the scope entrusted to the Contractor, or as extended under the Contract
and calculated from the Commencement Date.
- Contractor needs to Allow usage of material hoisting elevator for use by other agencies to
hoist materials when not in use and provide operator for hoisting.
5.5 Workmanship
The Contractor will carry out the work in workmen like manner as per architect’s approved
drawings/ specifications and instructions of the Employer’s representative. All the work shall be
carried out as per the relevant I.S. codes. If the Work is rejected by the site engineer for material
quality or poor workmanship, then the cost of redoing the work and the cost of the materials shall
be recovered by the Company from the Contractor’s bills at the sole discretion of the Company, if
the Contractor does not rectify as per the satisfaction of the company.
5.7 Drawings
The drawing stamped as “For site Execution” or “Valid for Construction” or “Good for
construction” only shall be used for execution. Contractor has to carry out work as per stamped
drawings issued during construction.
All drawings will be issue in stages. drawings issued for work shall be Employer’s property and
remain at site with contractor’s site staff and same should be returned to Employer upon
completion of work. Proper records will be kept for all the working and structural drawings
issued by Employer separately. All the deleted and revised drawings shall be returned to
Employer’s representative promptly.
Contractor shall be liable for the misuse of any Architects/ Consultants working and structural
drawings, details and sections.
Any changes in drawings/ specifications shall not be considered as increase in scope of work.
5.8 Interpretation and use of Drawings
Drawings, specifications and description specified in the scope of contract are explanatory and
complementary to one another, representing together the work/ installation to be carried out.
The Contractor should adhere to the latest drawings/ specifications/ supplementary drawing
issued by the Architects and the instructions issued by the Project-In-Charge.
Drawings, schedule of rates, specifications, other contract documents and all copies thereof
furnished by the Project-In-Charge shall be the Employer’s property. The same shall not be used
by the Contractor on any other work and shall be returned to the Company immediately on
request or at the completion of the Contract without making any copies, reproductions
whatsoever.
Provisions of this clause shall not be applicable in the case of any work which becomes essential
to carry out by rotary or double shifts in order to achieve the progress and quality of the part of
the works being technically required/ continued with the prior approval of the Employer’s
Representatives.
All work at night shall be carried out without unreasonable noise and disturbance and with the
approval of the Employer’s Representatives and in addition that of the local authority, if so
applicable. The Contractor shall indemnify the Employer from and against any liability for
damages on account of noise or other disturbance created while or in carrying out the work and
from and against all claims, demands, damages, penalties, fines, compensation, proceedings,
costs, charges and expenses whatsoever in regard or in relation to such liability. Safety supervisor
is must from contractor for any night activity. Adequate supervisory of staff should be arranged
by contractor during night work. Further details for works during nights is presented in the GCC.
6. Compliances
6.1 Statutory Compliances, Indemnity and Labour Laws
The Contractor undertakes to comply with all provisions of the labour laws and the
Employer shall not be responsible for the same. Contractor will be required to comply
with all Statutory Stipulations with regard to Contract Labour Regulation and Abolition
Act, the Minimum Wages Act, Workmen’s Compensation Act, the ESI Act, the Provide
Fund Act and/or any other Act or Law in force during the period of execution of work
under this contract. Further the Contractor shall indemnify the Employer from any or all
kind of claims towards any of the above during the subsistence of the contract. Contractor
has to subscribe to and keep alive requisite Workmen’s Compensation Policy from the
date of commencement of work till the date of satisfactory completion of the work as per
the certificate issued by the Employer’s representative and till complete demobilization
and vacation from the site. A copy of the said policy subscribed shall be furnished to the
Employers for record at the Employers head office and site office prior to
commencement of work. The Contractor agrees to comply with all labour laws,
regulations or any law effecting Contractor – Employers relationship and the Contractor
further agrees to comply and secure compliance of all sub-contractors with all applicable
laws.
The Contractor shall comply with the provision of the Apprentices Act, 1961 and the
rules and orders issued there under from time to time. If the Contractor fails to do so, its
failure will be a breach of the contract and the Employer’s Representative/Employer may
in its discretion cancel the contract. The Contractor shall also be liable for pecuniary
liability arising on account of any violation of the provisions of the Act.
Contractor undertakes to comply with all applicable statutory provisions in relation to the
implementation/execution of the works contract, including but not limited to provisions
of:
i. ESIC Act
ii. PF Act
iii. Workmen’s compensation Act
iv. Factories Act
v. Not employing any illegal immigrants and/or child labour
vi. Micro, small and medium enterprises as per MSME Act, 2006
vii. Minimum wages Act
And indemnifies the owner/developer from any liability/penalty on account of its
failure/negligence/inability to comply with the same
Payment related to any slab (x) shall become due only if the brickwork / blockwork (if any) is
completed below x-4 floors and internal plastering works completed below x-6 floors
Annexure III: Cement Consumption Norms
Item Cement
Brief Description Per
No. Consumption
1. P.C.C. 1:4:8 9 bags 100 cft
2. P.C.C. 1:3:6 12 bags 100 cft
3. Concrete (for reference only)
M15 6.2Bags Or as per Cum
M20 6.8Bags design Mix. Cum
M25 7.0Bags Cum
M30 7.4Bags Cum
M35 8.0Bags Cum
M40 8.2Bags Cum
4. 300mm wide channel in Podium 0.9 bags Rmt
5. 9” Brickwork in cm 1:6 3 bags 100 sft
6. 9” Brickwork in cm 1:5 3.75 bags 100 sft
7. 9” Brickwork in cm 1:4 4.5 bags 100 sft
8. 6” Brickwork in cm 1:5 2.5 bags 100 sft
9. 41/2” Brickwork in cm 1:4 1.70 bags 100 sft
10. Brick on edge 3” thk. (1:3 cm) 1.70 bags 100 sft
11. Block masonry 100mm thk. (1:5 cm) 0.60 bag 100 sft
12. Block masonry 140mm (1:5 cm) 0.75 bag 100 sft
13. Block masonry 150mm (1:5 cm) 1.1 bag 100 sft
14. Block masonry 200mm (1:5 cm) 1.5 bag 100 sft
15. AAC masonry 100mm (1:5 cm) 0.75 bag 100 sft
16. AAC masonry 150mm (1:5 cm) 0.75 bag 100 sft
17. AAC masonry 200mm (1:5 cm) 1.00 bags 100 sft
18. 12mm thick. internal cement plaster to 1.5 bags 100 sft
slabs/beams, walls (1:4 cm)
19. ½” thick. Backing coat plaster in C.M. 1:4 1.5 bags 100 sft
20. Sand faced plaster in 2 coats (20mm thick.) 3.5 bags 100 sft
21. Sand faced single coat plaster (20mm 2.0 bags 100 sft
22. 50mm thick. IPS Layer in M15 grade 3.5 bags 100 sft
Note: - Cement consumption for all concrete items shall be considered on the basis of Mix design
based on IS 456:2000.