ESCALATION FOR INCREASED COST OF BITUMEN

Name of Work: - Widening & Reconditioning of Dual Carriageway Road from Therhi Bridge to Zulfiqar Ali Bhutto Bus Terminal at
Therhi Overghead Bridge i/cs: with Treated Berms for Masonry Structure Mile 0/0-1/7 (3.0 K.m)

Name of Firm/Agency: - M/s, Meesam Construction Company

Work Order No: - CMO.Khp/Engg/416 Dated: - 14-09-2017.

Date of Bitumen Rate Rate


Qty: of Date of Difference/ Rate Amount of
Record as per Inreases/ M.B Amount
S# Bill No: Bitumen Notification by Escalation Deducted in Escalation/ Total Diffrenece Remarks
Bitumen in Schedule-B Decreased by difference
As per M.B Refinery Rate per Ton M.B Refinery Rate
M.B (Rs.) Refinery (Rs.)

1 2 3 4 5 6 7 8 9 10 11 12 13
1 3rd: R/A 16.970 8/5/2018 86213 82639 6/7/2018 -3574 29860 506724.20 -60650.78 446073.42
2 4th:R/A 23.760 31/08/2018 86213 94339 6/8/2018 8126 29860 709473.60 193073.76 902547.36
3 6th: R/A 27.150 12/11/2018 86213 93871 2/10/2018 7658 29860 810699.00 207914.7 1018613.70
4 9th: R/A 7.270 15/03/2019 86213 91598 2/10/2018 5385 29860 217082.20 39148.95 256231.15
5 10th: R/A 26.520 29/04/2018 86213 91598 11/4/2019 5385 41285 1094878.20 142810.2 1237688.40
6 10th: R/A 5.303 29/04/2018 86213 91598 11/4/2019 5385 29860 158347.58 28556.655 186904.24
7 11th: R/A 36.166 10/5/2019 86213 91598 11/4/2019 5385 41285 1493113.31 194753.91 1687867.22
8 12th: R/A 5.515 1/10/2019 86213 94377 17/05/2019 8164 26860 148132.90 45024.46 193157.36
9 12th: R/A 14.466 1/10/2019 86213 94377 17/05/2019 8164 41285 597228.81 118100.424 715329.23
10 13th: R/A 4.596 29/10/2019 86213 94377 17/05/2019 8164 29860 137236.56 37521.744 174758.30
11 13th: R/A 31.345 29/10/2019 86213 94377 17/05/2019 8164 41285 1294078.33 255900.58 1549978.91
12 14th: R/A 7.950 12/11/2019 86213 94377 17/05/2019 8164 29860 237387.00 64903.8 302290.80
13 14th: R/A 54.250 12/11/2019 86213 94377 17/05/2019 8164 41285 2239711.25 442897 2682608.25
14 15th: R/A 3.712 26/12/2019 86213 94377 17/05/2019 8164 29860 110840.32 30304.768 141145.09
15 15th: R/A 25.316 26/12/2019 86213 94377 17/05/2019 8164 41285 1045171.06 206679.824 1251850.88
16 16th: R/A 0.883 12/11/2020 86213 94377 17/05/2019 8164 29860 26366.38 7208.812 33575.19
17 16th: R/A 6.027 12/11/2020 86213 94377 17/05/2019 8164 41285 248824.70 49204.428 298029.12
18 17th: R/A 8.297 2/12/2020 86213 94377 17/05/2019 8164 29860 247748.42 67736.708 315485.13
19 18th: R/A 3.358 7/6/2021 86213 94377 17/05/2019 8164 29860 100269.88 27414.712 127684.59
20 18th: R/A 22.905 7/6/2021 86213 94377 17/05/2019 8164 41285 945632.93 186996.42 1132629.35
TOTAL : - 331.759 12368946.62 2285501.08 14654447.69