Professional Documents
Culture Documents
Electrical Safety Guide
Electrical Safety Guide
Contents
Appendices 24
They are intended to serve as a basis for local procedures, competence requirements, learning
material and contract requirements and to support those accountable and responsible for
implementation.
This guide is not mandatory, but provides recommendations based on proven practices with
learning from across the Lines of Businesses. The guide is therefore regarded as an effective
and efficient means to fulfil the requirements of the HSSE & SP Control Framework.
This guide will also be of use for people who own or develop documents on behalf of managers
such as local procedures, competence requirements and learning material or contract
requirements for Electrical Safety.
1. Use a Subject Matter Expert for electrical safety to develop and maintain Electrical Safety
Rules for each site or business unit. The Electrical Safety Rules of the site or business unit
must be in line with Internationally Recognised Standards and local legislation.
WHO: The Manager is Accountable.
The main objective of the Electrical Safety Rules (ESRs) is to ensure that all work and
testing/fault finding on electrical equipment is carried out safely.
ESRs should be developed and maintained by an SME for Electrical Safety. They should be
published within the HSSE management system by the Manager as nominated Owner.
It is recommended that ESRs be:
communicated and kept readily accessible to everyone who could be involved in sponsoring,
supervising or performing electrical work; and
used to determine the risk barriers during job planning and Permit to Work (PTW)
preparation, as described in the guidance for requirement 3.
Electrical Safety Guide
2/29
Shell HSSE & SP Control Framework Guidance
Electrical Safety Restricted
Version 2
The SME appointed to develop and maintain the Business Unit’s (BU’s), company’s, or site’s
ESRs should be the designated Senior Electrical Authority (SEA) or, in the absence of a SEA, a
Senior Authorised Electrical Specialist (SAES).
The SME is the overall senior authority for all matters of electrical safety. His/her
responsibilities include:
developing the asset or site’s electrical safety rules;
overseeing:
o assessment of electrical competence;
o training and experience of persons operating and working on electrical equipment;
o preparation, approval and issue of Electrical Safety Operational Procedures (ESOP) to be
implemented in BUs.
The ESRs should comply with applicable local legislation and regulations. Due to variation in
regulations, the SME will need to research and/or consult with local authorities regarding
mandatory legislation in a particular jurisdiction. If national and/or local regulations have more
stringent requirements than the ESRs of the Business, the SME should determine how to best
comply with regulation while meeting the intent of BU requirements.
Having an electrical safety programme encompassing ESRs, procedures, qualifications, and
training applies to all types of facilities (i.e., refinery, chemical plant, terminal, gasoline service
station, etc.). The details of the programmes, however, will vary depending on the size,
operations and level of complexity of the different facilities.
The scope of the ESRs should include:
General requirements for electrical safety.
Accountabilities and responsibilities for electrical power systems.
Competency requirements.
Authorisation of personnel.
Switching, isolating and earthing procedures.
Measuring and testing.
Personal protective equipment.
Electrical safety documents.
Precautions before working on or testing on High Voltage (HV) and Low Voltage (LV)
electrical equipment.
Precautions for special equipment.
Electrical work at construction sites.
Portable electrical equipment.
Precautions before excavating.
Assurance and auditing of the ESRs.
Additional detailed guidance on the development of BU, company, or site ESRs and supporting
electrical safety procedures, is in Shell DEP 80.64.10.10 – Electrical Safety Rules.
Examples of ESRs developed within Upstream can be viewed on the following links:
HSE0161 UAU and UAH Electrical Safety Standard (developed in accordance with Canadian
and US legislation and associated guidance)
Shell UIO Engineering Reference Document, COP Electrical Safety Rules – EA/082.
(developed in accordance with UK Statutory Legislation and associated guidance)
No one should be allowed to work on or test any part of the electrical power system unless
they have been evaluated to meet the requirements of the competency programme and are
authorised to perform the task.
The BU or site should have defined roles for individuals working on electrical equipment. The
roles should specify what tasks an individual is authorised to perform and the associated
responsibilities. In addition, the BU or site should have a documented system for appointing
individuals into those defined roles. See the guidance for requirement 2 and Appendix 1 for
more details regarding roles and responsibilities, competency, and Appointed Persons.
1.2 Set responsibilities and requirements for operation, maintenance, identification (labelling)
and Inspection of electrical equipment.
WHO: The Manager is Accountable.
1.3 Identify the Internationally Recognised Standards, legislation, or requirements to use for
equipment design and for control of electrical craftwork.
WHO: The Manager is Accountable.
Electrical safety at construction sites may be governed by the BU ESRs or those developed by
the project (e.g. such as ‘Greenfield’ sites).
If ESRs are developed for ‘Greenfield’ projects then they should address all the topics given in
the Control Framework requirement 1.
Any interface with the existing electrical power system, and the related operational
responsibilities, should be clearly defined before any commissioning takes place.
1.5 Require use of Personal Protective Equipment to prevent contact with exposed, energised
equipment and to protect people from arc flash.
WHO: The Manager is Accountable.
The term ‘protective equipment’ has wide application, but typically includes: special (insulated)
tools, protective clothing, and insulating materials needed to work safely on energised (or
potentially energised) electrical equipment.
Managers, supervisors and workers are responsible for providing the protective equipment
identified in the task-specific risk assessment and verifying that it is:
suitable for the use for which it is provided;
maintained in a condition suitable for that use, which may include periodic testing; and
used properly.
In terms of Hierarch of controls, proper de-energisation and isolation should always be
considered more effective when working on or near electrical equipment. PPE is the last line of
defence, and is for personnel protection not control of the inherent hazard. Appendix 2 reviews
control measures in order of effectiveness.
Tools/Meters as PPE
Employees should use insulated tools and/or handling equipment when working inside the
restricted approach boundary of exposed energised parts, where tools or handling equipment
might make accidental contact. Voltage rated PPE and tools should be rated at or higher than
the maximum anticipated voltage of the equipment.
Insulated Tools
Below is an example of typical ratings and certifications for hand-held insulated tools.
ASTM F1505
OSHA 1910.333(c)(2)
Tested to 10,000V
Max Use 1000V
Two-colour coating if coated tool for
two dip process
Shows symbol for use in live voltage
situation
Insulating Gloves
Figure 8 – Example of PPE using face shield and coveralls (Up to 8 cal/cm2 or 33 J/cm2)
NOTE: Some legislation requires use of arc rated balaclava sock hood when using a face shield.
Figure 9 – Example of use of PPE Flash Suit (15-111 cal/cm2 or 63-466 J/cm2)
See the PPE Guide for additional details on electrical safety PPE.
NOTE: The PTW above refers to the Electrical Permit to Work (EPTW), not the safe work
permit. The EPTW acronym is also not to be confused with ePTW (electronic Permit to Work).
Electrical hazards to workers include electric shock, electrical burns, and electrical arc flash.
The provision of a safe system of work is fundamental to the effective control of risks.
It is a common industry requirement for additional electrical safety documents to be used in
conjunction with the site’s general PTW system. This system should include an electrical safety
permit, such as EPTW. Any electrical safety documents required by the ESRs, such as the
EPTW, are always additional to those required by the business or site’s PTW System. These
are typically used as supplementary controls, and would be cross-referenced to a normal Work
Permit, which remains the main controlling document. These supplementary controls are used
to identify and control discrete electrical hazards and include:
1. EPTW
2. Limitation of Access (LOA)
3. Sanction for Test (SFT)
Electrical Permit to Work
The EPTW is a supplemental document to the BU or site’s PTW System. The EPTW should
address the electrical hazards associated with working on or near electrical equipment and
additional approvals if required by the site or BU ESRs. The PTW and EPTW are integral parts
of safety management arrangements covering a wide range of activities and hazards. The
EPTW normally applies to the following types of work:
Work on any HV electrical equipment connected to the HV electrical power system.
Work on a LV switchboard’s bus bars or its incoming connections, which are directly fed
from a HV/LV transformer and where it may be considered necessary to apply a circuit main
earth. Generally this refers to non-routine energised electrical work and complex LV
systems which may have backfeed potential.
The EPTW is normally signed by a SAEP and given personally to the Competent Electrical
Person (CEP) in charge of the work to be carried out. The EPTW states the electrical equipment
that has been isolated and the circuit main earths that have been applied.
The EPTW should be issued at the place where the work is being performed. The designated
competent person in charge of the work can then explain the work and agree the accuracy and
completeness of the details with the person doing the work before they both sign the permit.
The person issuing the permit should verify all necessary controls have been implemented to
make the electrical equipment safe.
Limiting Access
It is good practice to limit access to electrical equipment (e.g. barriers, signs, or a LOA form).
A LOA can be used when work is carried out in close proximity to exposed energised electrical
equipment.
An example is ground level work in a HV substation with exposed live overhead conductors
from which safe working clearance distances are needed. If an LOA is used:
An Authorised Electrical Person should issue the LOA to the CEP in charge of the work to be
carried out.
The LOA will provide the means to identify the work to be done and the safety precautions
to be taken when working near exposed energised conductors.
The LOA should remain at the worksite at all times while work is being carried out.
2. Use only Authorised Persons to work on electrical equipment and to carry out the assigned
work in line with the Electrical Safety Rules.
WHO: The Manager is Accountable.
Electrical hazards are unseen and severe. Specialised training and authorisation is required for
people working on or near electrical equipment, to identify the hazards and employ safe work
practices to protect themselves.
No one is allowed to carry out operations, work or testing on any part of the electrical power
system unless they meet the competence requirements and are authorised to perform the task.
An Authorised Person (AP) is a person trained and normally appointed by SEA and/or SAES
to carry out authorised duties. This appointment should be in writing. Contractors performing
electrical work should have a documented electrical competency programme, reviewed and
approved by the SEA and/or SAES.
An example of APs related to electrical equipment and systems from the Shell UK ESRs is
provided in Appendix 3 along with typical roles and responsibilities (see also the guidance for
requirement 1 and DEP 80.64.10.10 Electrical Safety Rules). The title of roles may vary from
the DEP 80.64.10.10 Electrical Safety Rules or other BUs based on local terminology and the
size of the electrical installation. Sub-roles or specialty roles with narrower scope may also be
appropriate, while meeting the control framework.
Competence
Before a person is appointed as an AP, we must assure that they are competent to fulfill their
range of responsibilities. For general guidance on competence refer to the HSSE & SP Control
Framework Competence Manual Section and Competence Guide and Appendix 1.
Appointment of Authorised Persons
The SEA or SAEP would normally be responsible for appointing APs (Shell or contractor),
following satisfactory assessment and assessor recommendation. For guidance on the
appointment process and documentation, please refer to Appendix 1.
The ESRs and supporting electrical safety procedures are required to cover the control
framework requirements for control of work on or near electrical equipment and provision of
safe isolation. These should be approved by an SME for Electrical Safety, normally the SEA.
The requirements should be communicated to everyone who could be involved in sponsoring,
supervising or performing electrical work, as required by the ESRs.
Recommendations for how each of these requirements should be implemented are given below.
3.1 Provide a permit prior to work that could expose people to harmful electrical energy as
specified by the Electrical Safety Rules, see requirement 1.6 above, and following the
requirements in the Permit to Work Manual Section.
WHO: The Manager is Accountable.
NOTE: “Permit” may also refer to an EPTW, an Electrical certificate, or an Energised Electrical
Work Permit (EEWP) depending on the PTW system in place and local terminology. For
consistency purposes we use the term EPTW in this document.
Recommendations on when to require an EPTW in support of the ESRs is in Section 1.6.
Under the ESRs, work which could expose people to harmful electrical energy requires an
EPTW be issued and signed by an SAEP, and given personally to the CEP in charge of the work.
Further details on these documents are provided in Section 1.6, and ESR DEP 80.64.10.10,
Electrical Safety Rules.
3.2 De-energise and isolate equipment as required in the Safe Isolation – Lock Out Tag Out
Manual Section and verify that there is no voltage and when required use Earthing.
3.2.1 Use physical barriers, protective equipment, special tools or other Controls to prevent
harm to people when it is not possible to de-energise equipment.
WHO: The Manager is Accountable.
Before carrying out any maintenance, repairs, alterations, cleaning or testing on electrical
equipment, the equipment should be isolated (de-energised) from its power source.
Isolation is disconnecting from energised conductors by either by an open isolator (switch) or
adequate physical gap from all sources of supply, so as to prevent electrical equipment from
becoming energised in error.
Provided that safe methods are used and that approved equipment, tools and instruments
required for testing are properly insulated for the rated voltage of the circuit, electrical
isolation of LV electrical equipment may not be required for diagnostic testing or adjustments.
All electrical equipment is regarded as being energised until properly isolated and proved to be
de-energised. The operation of switching out a circuit and de-energising it from all sources of
supply does not by itself provide proper isolation of that circuit.
The methods of de-energising and isolating electrical equipment should be described under the
ESRs and detailed in supporting electrical procedures, for specific types of equipment.
Electrical isolation and de-isolation should normally be under the control of the PTW System,
enabling effective overview and control along with other energy isolations (see also the guidance
for requirement 1.6).
Securing Isolations
Safety padlocks used for isolating purposes should be of a non-standard or unique type with
only one key for each lock, i.e. with no master key supplied or available. Each lock should be
marked with a clearly readable individual number or name. It is considered good practice to
differentiate between LV and HV padlocks. Craft locks, where multiple people hold a common
key, are not to be used for personal isolations.
All points of isolation from which electrical equipment can be made energised should also be
tagged with Caution notices in accordance with the site’s LOTO procedures. They warn persons
that:
work or testing/fault finding is in progress; and
no attempt should be made to interfere with the electrical equipment, or the controls, to
which it is attached.
The label should contain essential details of the isolation and the Isolating Authority.
Figure 10 provides an example of an isolation tag incorporating a tear-off stub, which can
accompany the isolation certificate and/or PTW to provide control over electrical isolations. Tag
requirements may differ based on local regulations.
Figure 10 – Example of Isolation Tag Electrical Caution Notice with tear-off stub
Maintaining Control of Keys
Lock out Boxes
An effective method for controlling multiple lock-out points or complex lock
out procedures is the use of lock-out boxes. Lock-out boxes are usually
located in main sub-stations, or other suitable ‘operational’ locations.
Lock-out boxes should be used in accordance with the ESR for the secure
retention of all the keys to the safety padlocks used to secure means of
isolation, earthing or other safety devices. Ideally, the lock-out boxes should
be provided with the facility for two (or more) unique locks with keys to be
used to secure the Lock-out Box.
The ESRs or site’s LOTO procedures should describe the procedures for using
a lock box.
If Lock Out Boxes are not available
If lock-out boxes are not readily available, and Safety Documents are to be
issued, for example for work on HV systems and main LV systems the SAEP
should apply two safety padlocks to each point of isolation and earthing.
Specially designed multi-hasp padlocking devices that have provision for
several locks to be fitted to prevent them opening can be used for this
purpose.
One of the two safety padlocks can be issued to, and retained by, the recipient of the Electrical
Safety document (under PTW control). The other being retained by the SAEP until the Electrical
Safety Document is cleared and cancelled. Where electrical isolations are only for mechanical
work, a 2nd padlock would not normally be required for control by the SAEP, although multi-
hasp arrangements may still be required.
Verification of Voltage
Before work is performed on isolated electrical equipment, properly rated test equipment
should be used to verify that the circuit elements and equipment parts are de-energised. The
test should also determine whether any energised condition exists as a result of inadvertently
induced voltage or unrelated voltage back feed. This should be done even if specific parts of
the circuit have been de-energised. The approved test equipment should be checked
immediately before and after use, on a known source, to make sure it is working correctly.
If mechanical work is to be carried out on plant equipment driven by electrical equipment, e.g.
motors, the circuit incorporating the electrical equipment concerned should be isolated in
accordance with the requirements of the ESR.
Earthing (or grounding) is required when electrical work is to be carried out on electrical
equipment and systems.
High Voltage: Before work or testing is carried out on HV electrical equipment that is part of
the electrical power system, the equipment concerned should be:
de-energised,
isolated,
absence of voltage verified and earthed (grounded); and
an Electrical Safety Document issued to allow work, or any testing/fault finding.
HV equipment should be earthed using a circuit main earth. This circuit main earth can be
applied either through switchgear with adequately rated earthing capacity, or by using
approved portable earthing leads (sometimes known as temporary protective grounds).
Whenever practicable, the HV electrical equipment should be earthed by the SAEP in the
presence of the intended recipient of the EPTW or SFT.
Low Voltage: If work is to take place on a LV switchboard’s isolated bus bars or its incoming
connections, which are directly fed from a HV/LV transformer, a circuit main earth should be
applied on the HV side of the transformer circuit. If necessary for operational safety reasons,
the earth may be applied on the LV switchboard’s bus bars.
The isolated conductors of a low voltage switchboard's bus bars should be effectively proved
de-energised before an Electrical Safety Document can be issued to allow work, or any
testing/fault finding to take place.
LV electrical equipment isolation and earthing should be performed by a CEP, or more senior
electrical person.
Earth notices are intended to indicate where equipment earthing (grounding) is applied. They
warn people not to interfere with the circuit main earth. Sites should implement procedures
that account for the application and removal of earthing (grounding) connections to minimise
the likelihood of these remaining in place during re-energisation. The use of magnetic signs on
the front and/or rear of electrical equipment indicating portable earthing leads (temporary
protective grounds) are installed is recommended.
The ESRs and PTW System should address the hazards associated with working on or near
energised electrical equipment. EPTWs are issued for energised work – typically on “higher
risk” systems such as MV and LV incomer circuits, where the SAEP is overseeing and verifying
proper isolation, de-energisation, voltage verification and earthing/grounding when applicable.
In the Americas, the use of an Electrical Energised Work Permit requires both electrical and
management approval when energised work is performed.
Persons working on or near energised electrical equipment should conduct appropriate pre-job
planning discussions in order to identify the hazards involved and special precautions to be
taken to protect the workers from the hazards. The PTW system should also include provisions
for limiting access to energised electrical equipment using the Limitation of Access (LOA)
form (see the guidance for requirement 1.6).
Tools and Equipment: Unless they have been verified as being safe for use at a particular
voltage, tools and equipment should be considered conductive. In general, tools such as
wrenches and screwdrivers should not be used on equipment energised at over 1000 V.
For work on equipment energised at less than 1000 V, any tools that touch or may possibly
touch the energised equipment should have handles insulated from the working parts of the
tool and rated for the application. Hand taping of tools to provide insulation does not meet this
requirement.
Tools should be inspected before use and retested (e.g. according to ASTM F1505) or replaced
if any damage beyond permitted manufacturer’s instructions is observed.
To prevent accidental contact, Guarding should be used, as necessary, when performing
electrical work in close proximity to exposed energised electrical equipment. Examples of
guarding include the use of covers, shields, barriers, screens or mats to minimise the
possibility of inadvertent contact by persons or objects to exposed energised parts.
If barriers or ropes are necessary to define the safe area of work, verify that these are clearly
visible and are not tied or supported by any structure carrying live electrical equipment or
conductors. The safe area should be clearly identified and danger notices attached to adjoining
live electrical equipment outside the safe working area.
Danger notices are intended to warn persons that it is dangerous to approach or interfere
with live conductors. These notices are used to indicate to persons, working or testing, that
adjacent electrical equipment is live.
Each business should provide details of approved PPE for specific types of electrical work.
Examples of good practice on Electrical PPE can be seen by clicking on links to the following
documents in Upstream Americas (UAU and UAH) Electrical Safety Standard HSE0161:
HSE0161-TO.11 Electrical Specific PPE, Tools, and Equipment
HSE0161-TO.12 Electrical Specific PPE, Tools, and Equipment and Standards Tables
HSE0161-TO.13 Electrical Specific PPE, Tools, and Equipment Recommended Care, Use, and
Maintenance Tables
General guidance on how to comply with HSSE & SP CF requirements for PPE is in the Control
Framework PPE Guide. However this is more focused on general PPE than electrical specific
PPE for shock and arc flash.
3.3 Obtain signed authorisation from a person designated by the Electrical Safety Rules for
switching, testing and work on electrical equipment.
WHO: The Manager is Accountable.
3.4 Manage work and equipment near underground and overhead electrical Hazards to prevent
contact with energised lines or equipment.
WHO: The Manager is Accountable.
Certain types of equipment may have electrical hazards that need extra precautions:
overhead lines with exposed conductors underground feeders
Avoiding the use of mechanical diggers, graders or other mechanical means for the removal
of topsoil, grass or vegetation, prior to digging pilot trenches.
Using hydro-excavation or air excavation techniques such as hydro-vac trucks or air digging
tools to expose underground services.
Restricting the use of the cable locators (cable avoidance tools) to trained persons.
Marking the location of underground services with posts or equivalent markers indicating
the types and size of services.
Not limiting scanning to the trench width, but including any additional areas used for drain
points, sloping, benching or shoring used to prevent collapse (see the guidance for
requirement 4.6 in the HSSE & SP Control Framework Excavation Guide for more details).
Where the excavation is to be greater than 1 metre wide, it is recommended to scan at both
sides of the proposed excavation and at every 5 metres along the trench.
The ESRs and supporting ESPs are required to cover the control framework requirements for
control of electrical work in design and construction.
The requirements should be communicated to everyone who could be involved in sponsoring,
supervising or performing electrical work under control of the local PTW System or
Construction PTW System and Electrical PTW Safety documentation that supports it.
Recommendations for how to meet these HSSE & SP CF Manual requirements are given below.
4.1 Provide a system to review and approve the design, installation and bringing into service of
permanent or temporary electrical systems and facilities.
WHO: The Manager is Accountable.
4.2 Approve whether newly constructed electrical equipment may be connected to electrical
power distribution and generation systems.
WHO: The Manager is Accountable.
Maintenance of Documentation
Key documentation required to safely operate and maintain electrical assets should be kept up
to date as part of the site’s Management of Change process.
Periodic reviews should be conducted to verify the accuracy required for the safe operation and
maintenance of the electrical assets.
The ESRs and supporting ESPs are required to specify controls for ignition of
flammable/explosive atmospheres caused by electrical equipment or static electricity.
Requirements should be communicated to everyone who could be involved in specifying,
installing, or maintaining electrical equipment within hazardous (classified) locations. For
additional static electricity guidance, also see RMP 80.64.10.50 Static Electricity Operation &
Maintenance.
5.2 Use equipment and work practices that manage static electricity.
WHO: The Manager is Accountable.
The Electrical Safety Rules (ESRs), and supporting procedures, must cover the control
framework requirements for control of ignition of flammable atmospheres caused by electrical
equipment or electrical phenomenon.
The requirements should be communicated to everyone who could be involved in sponsoring,
supervising or performing electrical work under control of the local PTW System (and Electrical
PTW Safety documentation that supports it) as required by the ESRs.
NOTE: Electrical Arc Flash is the release of thermal energy, acoustical energy, pressure waves,
and shrapnel due to an arcing electrical fault through air and is not related to static electricity.
Recommendations for how each of these requirements should be implemented are given
below.
General Principles
An effective method of avoiding hazards due to static electricity is to bond all conductors
together and to earth/ground. This will reduce the charge on a conductor and the potential
release of stored energy as a single spark, to earth/ground or to another conductor.
The terms ”earthing” (”grounding”) and “bonding” are often used interchangeably. They are, in
fact, two different and complementary components of an effective barrier against static
discharge. Bonding is intentionally electrically connecting two conducting materials to bring
them to the same potential. Earthing (grounding) is intentionally connecting systems or
equipment to earth.
System earthing is essential to the proper operation of the electrical system. Equipment
earthing and bonding are essential to the safety of personnel. A key function of equipment
earthing is to prevent the build-up of static electricity, thus reducing the risk of electrical
discharge in potentially hazardous (flammable) environments. A resistance to earth/ground of
1 MΩ (106 Ω), or less, will provide safe dissipation of static electricity.
For additional information refer to DEP 80.64.10.11-Gen. Static Electricity, RMP 80.64.10.11-
Gen Static Electricity Operation and Maintenance, and the Operational Safety GET Static
Electricity Campaign Site. Note that this DEP contains mandatory requirements to mitigate
process safety risks in accordance with Design Engineering Manual DEM 1 – Application of
Technical Standards.
Preventing Harm to People
Electrostatic discharges are considered to be a direct health hazard if the discharge energy
exceeds 350 mJ or the charge transferred exceeds 50 μC. Sparks to the person can be
unpleasant and may cause accidents from involuntary reactions.
Shocks can be avoided by having a conducting or dissipative floor and ensuring that persons
wear dissipative clothing and footwear.
Preventing Harm to HSSE Critical Equipment
Sensitive electronic instruments can be damaged by static discharge, for example while
undertaking maintenance work, e.g. routine maintenance on Distributed Control Systems
(DCS) and within instrument marshalling racks. This type of work should have: specific work
instructions including controls for preventing static discharge; and a PTW.
There is a range of anti-static tools, instruments and specialised equipment to control
undesired electrostatic discharge. This includes wrist straps and antistatic table mats, ground
cords, workstations, common grounding points, and anti-static tools.
Anti-static wrist straps Anti-static table mats Mats and Work stations Anti-static tools
Use equipment and work instructions to control static electricity such as:
Do not use plastic or non-conductive containers.
Avoid splash filling when possible.
Bond and earth equipment to allow static charge to
dissipate, and monitor that the earthing is effective.
Eliminate flammable atmospheres.
Reduce flow rates.
Allow charge settling time.
Increase conductivity of materials through additives.
Eliminate spark promoters.
Ensure PTW requirements address static electricity
concerns and include precautions.
Examples of correct locations for earth connections:
Appendices
APPENDIX 1 - Competence Assessment and Appointment of Authorised
Persons
Competence Assessment
Competence should be assessed by an appointed assessor for:
1) Academic Competence [i.e. qualifications]
o An Engineering Degree, Technical diploma, National Certificate or Trade Certificate, etc.
2) Technical Skill and Electrical System Competence
o Technical knowledge and operational experience that involves safe and effective
operation of the electrical equipment/electrical systems for which they may be
responsible in an Installation.
o Knowledge and practical experience of the sites ‘Permit to Work’ system and the rules
applying for work, or testing/fault finding, in hazardous areas.
3) Electrical Safety Rule Competence
o The knowledge and experience required to be considered competent to safely operate,
carry out work, or testing/fault finding. This should be in accordance with the ESRs and
electrical safety procedures for the high/low voltage electrical equipment installed on an
Installation's electrical system.
o competence in other duties, such as:
i. the preparation and checking of switching programmes;
ii. the operation of all types of electrical equipment they may have to operate or
maintain;
iii. the application/removal of circuit main earths (temporary protective grounds); and