Download as pdf or txt
Download as pdf or txt
You are on page 1of 7

17th International Conference on Protection & Automation

in Power System
Shahid Beheshti University
January 17, 2023 - January 18, 2023

Comparison of Load Shedding Methods for


Mitigating FIDVR

Mahdi Ghotbi-Maleki Reza Mohammadi Chabanloo Hamid Javadi


Dept. of Electrical Engineering Dept. of Electrical Engineering Monenco Iran Consulting Eng.
Shahid Beheshti University Shahid Beheshti University and Dept. of Electrical Eng. SBU
Tehran, Iran Tehran, Iran Tehran, Iran
m_ghotbi@sbu.ac.ir re_mohammadi@sbu.ac.ir javadi.hamid@monencogroup.com

Abstract- Fault-induced delayed voltage recovery (FIDVR) implementation of network-side methods is costly, and these
occurs after a fault in a network with high penetration of induction methods are not suitable for all networks. The used converter in
motor (IM) loads. Load shedding (LS) is one of the appropriate [1] disconnects the IM from the network and feeds it from an
methods to reduce the destructive effects of FIDVR on the emergency source if FIDVR is detected. However, it cannot be
network, and for this reason, the authors have previously
presented three LS methods to deal with FIDVR. The first method
expected that all IM loads act in this way; therefore, load-side
uses the index of IM loads’ power change. The second method is methods have been directed towards load shedding (LS). Ref.
an optimization problem and the third method introduces [2] has presented a local LS scheme that uses an index
indicators based on sensitivity analysis to find the location and consisting of active and reactive powers of IM load. Monitoring
amount of LS. The purpose of this paper is to examine the the imaginary part of admittance seen from the beginning of
strengths and weaknesses of those three methods, and to determine feeders is the used method in [3] to detect critical FIDVRs. The
each of these methods is suitable for use in what specific positive value of presented index indicates the angular speed
conditions. The proposed methods obtain less LS amounts, also, recovery of IM loads, and LS will not be required in such
the number of LS locations and moments of proposed methods are conditions. Also, the instability of DGs has been considered as
fewer than previous ones. However, these methods have different
execution times which are related to the speed of utilized
a criterion for LS.
processor, and a suitable method to deal with FIDVR must have Under-voltage load shedding (UVLS) relays are the
the ability to shed the load in the initial moments of this common protection installed in networks against voltage drops,
phenomenon. however, studies have shown that this protection does not have
the ability to effectively deal with the FIDVR phenomenon;
Keywords- Fault-Induced Delayed Voltage Recovery (FIDVR); therefore, researchers have tried to improve this protection. It
Induction Motor; Wide-Area Load Shedding; Voltage Estimation. has been proposed in [4] that UVLS relays should measure
voltage changes in addition to monitoring the voltage values.
I. Introduction The slope of voltage is compared with the threshold value in
this scheme using (1). In this equation, (𝑉1 ,𝑡1 ) and (𝑉2 ,𝑡2 ) are
The power network is exposed to new phenomena due to its two points on the voltage-time coordinate plane which are used
ever-increasing expansion. With occurring a fault in a network to determine the slope. The point (𝑉𝑐𝑟𝑡 ,𝑡𝑐𝑟𝑡 ) indicates the critical
with high penetration of induction motor (IM) loads, the speed condition of FIDVR and it means that the voltage must reach
of IMs will decrease during the fault. After clearing the fault, it the critical voltage 𝑉𝑐𝑟𝑡 at the critical time 𝑡𝑐𝑟𝑡 when FIDVR
is expected that the voltages will quickly return to their levels occurs. If the obtained slope is greater than its threshold, the
before the fault; however, the reactive power required by IM voltage will return to the 𝑉𝑐𝑟𝑡 in less time than 𝑡𝑐𝑟𝑡 and there will
loads increases due to the increase in the ratio of reactance to be no need to LS. The authors in [5] have suggested that UVLS
resistance of IM loads. The increased demand for reactive relays are equipped with a fuzzy controller to improve their
power prevents fast voltage recovery, and voltage collapse may performance during FIDVR. UVLS relays have been improved
even occur. This phenomenon is called fault-induced delayed in [6] so that these relays have the ability to detect the operation
voltage recovery (FIDVR). There are different methods to of IM loads in their stable or unstable regions by using the
control the FIDVR phenomenon, which are categorized into relative slip index. If the value of this index greater than 1 it
two categories: network and load side methods. The network means that the IM loads are entering the unstable area of their
and load side methods try to increase the reactive power operation, and it is necessary to shed those loads.
generation capability, and shed the loads, respectively. 𝑉2 − 𝑉1 𝑉𝑐𝑟𝑡 − 𝑉1
𝑆𝑙𝑜𝑝𝑒 = < 𝑆𝑙𝑜𝑝𝑒𝑚𝑖𝑛 , 𝑆𝑙𝑜𝑝𝑒𝑚𝑖𝑛 = (1)
The use of distributed generators (DG), energy-storage 𝑡2 − 𝑡1 𝑡𝑐𝑟𝑡 − 𝑡1
equipment, and the installation of capacitor bank, SVC, and It is also possible to implement centralized scheme to deal
STATCOM for injecting reactive power are some of the with FIDVR if the studied network is equipped with PMUs.
network-side methods for dealing with FIDVR. However, the Considering that LS from one bus also affects the voltage

1
17th International Conference on Protection & Automation
in Power System
Shahid Beheshti University
January 17, 2023 - January 18, 2023

recovery of other buses, therefore, checking all buses at the involve the factors affecting FIDVR in the proposed LS
same time using centralized schemes will have better results methods for more precisely determining the amount of load that
than checking the buses separately when using decentralized can be shed. In this case, the suggested LS will be more
ones. A wide-area LS scheme based on the impedance deviation effective and efficient to control the critical FIDVR.
of load has been presented in [7]. The bus with the highest The network information is sent by PMUs to the central unit
impedance deviation will be a candidate for LS, and the amount in the wide-area LS scheme shown in Fig. 1, and the central unit
of load that can be shed is determined in advance by the decides about the amount, location and moment of applying LS.
operator. A central and online LS scheme has been presented in Every LS scheme must answer these three important issues in
[8] which uses the kinetic energy of IM to determine the addition to identifying critical conditions. In the proposed LS
effective loads. It is necessary that the inertia 𝐻𝑀 and the scheme, initial amount of load that can be shed is obtained at
angular speed 𝜔𝑟 to be known for calculating the kinetic energy the beginning, then, the voltage estimation tool is used to
through 𝐻𝑀 𝜔𝑟2 . The inertia is obtained using the load parameters validate the obtained initial LS. The LS amounts are sent to the
estimation methods, and (2) is used in order to obtain the motor switches through telecommunications if the estimated voltages
speed. In this equation, 𝑉𝑀0 , 𝐼𝑀0 , 𝑉𝑀 (𝑡) and 𝐼𝑀 (𝑡) are the voltage meet the critical conditions after applying LS. Otherwise, new
and current of IM load before and after the fault. 𝑠𝑀0 is the slip amounts are calculated, and the voltages are estimated using
of equivalent IM before the fault, which is obtained through the new LS parameters. This process continues until the critical
load parameters estimation methods. conditions are addressed.
𝜔𝑟 (𝑡 + ∆𝑡) = 𝜔𝑠 × …
𝑉
𝑅𝑒 ( 𝑀0⁄𝐼 )
𝑀0
1 − 𝑠𝑀0 ×…
𝑉𝑀 (𝑡) Power Network
𝑅𝑒 ( ⁄𝐼 (𝑡)) (2)
𝑀
𝑉𝑀 (𝑡)
∆𝑡 𝑑Re ( ⁄𝐼 (𝑡))
𝑀
(1 + × )
PMU

PMU
𝑉 (𝑡) 𝑑𝑡
Re ( 𝑀 ⁄𝐼 (𝑡))
[ 𝑀 ]
An evolutionary strategy based on physical laws along with
Central LS Unit
Markov decision tree is presented in [9] as a voltage control
method to deal with critical FIDVRs. This evolutionary strategy
which is a data mining method, includes inputs such as voltage Fig. 1. Communication links of proposed LS scheme
and amount of load of each bus, and its outputs are the amount
of load that can be shed. The machine learning tool is used in A. Amount and Location of LS
[10] for online LS during the FIDVR. The training data are The first proposed method detects the LS location using the
different states of load, and the location and amount of LS power changes of IM loads. The amount of LS is obtained by
corresponding to each state. The trajectory sensitivity analysis pre-determined LS steps and the voltage estimation process is
method is used to determine the location and amount of LS. the validation tool for determining total LS amounts [11]. The
LS for dealing with FIDVR is modeled as an optimization
II. Proposed Load Shedding Methods problem in the second proposed method, and the results of this
linearized optimization problem are the location and amount of
Some issues of above-mentioned LS methods are: not LS [12]. The location and amount of load that can be shed are
paying attention to all affecting parameters on FIDVR, calculated through sensitivity analysis in the third method [13].
improper voltage estimation during FIDVR, and not accurately
1) LS based on IM Loads’ Power Changes
determining the amount of LS. Therefore, the authors of this
paper have presented comprehensive LS schemes in [11-13] In this method, the location of LS is obtained through an
whose main basis is formulating and modeling the FIDVR index based on the changes in powers of IM loads according to
phenomenon based on the dynamic equations of IM loads (3) and the amount of LS is obtained by applying pre-
which is named as voltage estimation tool, for addressing the determined LS steps to the selected bus. The highest change in
issues of previous methods. The presented voltage estimation IM load power indicate that the selected bus is close to the
process is based on the combination of transient IM model and location of fault. It also illustrates that the network is weak in
conventional Gauss-Seidel load flow; and its goal is to obtain a that bus to provide the required power of loads, or the large IM
relationship between voltage and time for estimating the loads connect to that bus. The data received in the past moments
voltage at any moment during the FIDVR. A comparison has are used to perform calculations in the previous methods
been made in [11] between the results of using one- and three- because those methods do not have the ability to estimate the
order model of IM in the voltage estimation process. Obtaining voltage in the future; however, it is possible to access the
initial values of the state variables of IM loads for use in the network conditions in the future moments due to the use of
voltage estimation process has been investigated in [12]. Also, voltage estimation process in the proposed method. It is better
[13] contains an approach for modeling the shed of a part of to use the power values at the critical time 𝑡𝑐𝑟𝑡 in (3) to perform
solid load in the voltage estimation process. The next step is to calculations.

2
17th International Conference on Protection & Automation
in Power System
Shahid Beheshti University
January 17, 2023 - January 18, 2023

After determining the LS location, the remaining issue will 𝑉 𝑎𝐿𝑆 − 𝑉 𝑏𝐿𝑆 = 𝑍(𝐼𝑎𝐿𝑆 − 𝐼𝑏𝐿𝑆 ) → ∆𝑉 = 𝑍∆𝐼 (9)
be the amount of LS. The accuracy of proposed method will be
It can be understood through ∆𝑉 = 𝑍∆𝐼 that the sensitivity
reduced if LS step is chosen a large value; in other hand, small
of voltage of bus 𝑗 to load current of bus 𝑖 (∆𝑉𝑗 ⁄∆𝐼𝑖 ) is equal to
step increases the volume of calculations. The location of LS is
selected through (3) at first, then, the hypothetical LS equal to the parameter |𝑍𝑗,𝑖 |. The goal is to shed the load in such a way
the considered LS step is applied to the selected bus and it is that maximum effect is achieved on the voltage recovery of all
investigated whether the estimated voltage reaches the critical involved buses with critical FIDVR. The buses whose voltages
voltage at the critical time or not. This process continues until are estimated lower than the critical voltage at the critical time
the voltages of all buses becomes non-critical. are stored in 𝐶𝐹𝑠 set according to (10) as the buses involved
with critical FIDVR.
𝑙𝑜𝑐 = max (|𝑆𝑀,𝑖 (𝑡𝑐𝑟𝑡 )| − |𝑆𝑀,𝑖 (𝑡0 )|) (3)
𝑖=1,…,𝑁 𝐶𝐹𝑠 = {𝑖||𝑉𝑒𝑠𝑡,𝑖 (𝑡𝑐𝑟𝑡 )| < 𝑉𝑐𝑟𝑡 , 𝑖 = 1, … , 𝑁} (10)
2) LS based on Optimization Algorithm A bus is considered as the LS location where changing its
load current has the greatest effect on the recovery of voltages
The location and amount of LS are obtained through an of all buses in the 𝐶𝐹𝑠 set. Equation (11) is used as an index to
iterative optimization problem in this method. For this purpose, find the LS location. It is possible that the selected bus does not
the matrix equation 𝑉 = 𝑍𝐼 is used at the moment before and have a high penetration of IM load and shedding the load from
after LS according to (4) and (5). The voltages and currents at that bus does not reduce the severity of FIDVR, therefore, the
before and after LS are indicated by 𝑏𝐿𝑆 and 𝑎𝐿𝑆, respectively. factor that causes FIDVR, i.e., the increase in the requested
The effect of shedding 𝑥 percentage from the load of bus 𝑖 is power of IM loads, has also been influenced in location index.
expressed by 𝐼𝑖𝑎𝐿𝑆 = (1 − 𝑥𝑖 )𝐼𝑖𝑏𝐿𝑆 . In this case, the voltages after It is better that 𝐶𝐹𝑠 buses affect in the location index based on
LS can be expressed as a function in terms of the voltages and their importance, therefore, the component of difference
currents before LS, in addition to the amount of LS according between the estimated and critical voltages has also been added
to (6). to this index. In this case, the bus whose voltage has suffered a
𝑉1𝑏𝐿𝑆 𝑍11 ⋯ 𝑍1𝑁 𝐼1𝑏𝐿𝑆 greater drop will have a greater effect in determining the
V𝑏𝐿𝑆 = ZI𝑏𝐿𝑆 →[ ⋮ ]=[ ⋮ ⋮ ⋮ ][ ⋮ ] (4) location of LS.
𝑉𝑁𝑏𝐿𝑆 𝑍𝑁1 ⋯ 𝑍𝑁𝑁 𝐼𝑁𝑏𝐿𝑆
|𝑆𝑀,𝑗 |
|𝑍𝑖,𝑗 | × …
𝑉1𝑎𝐿𝑆 𝑍11 ⋯ 𝑍1𝑁 𝐼1𝑎𝐿𝑆 𝑙𝑜𝑐 = max ( ∑ ∑𝑁
ℎ=1|𝑆𝑀,ℎ | ) (11)
𝑗=1,⋯,𝑁
V 𝑎𝐿𝑆 = ZI𝑎𝐿𝑆 →[ ⋮ ]=[ ⋮ ⋮ ⋮ ][ ⋮ ] (5) 𝑖∈𝐶𝐹𝑠 (𝑉𝑐𝑟𝑡 − |𝑉𝑒𝑠𝑡,𝑖 (𝑡𝑐𝑟𝑡 )|)
𝑉𝑁𝑎𝐿𝑆 𝑍𝑁1 ⋯ 𝑍𝑁𝑁 𝐼𝑁𝑎𝐿𝑆
The bus whose critical FIDVR is most affected by LS from
V 𝑎𝐿𝑆 = ZI𝑏𝐿𝑆 − ZXI𝑏𝐿𝑆 → V 𝑎𝐿𝑆 = V𝑏𝐿𝑆 − ZXI𝑏𝐿𝑆 (6) 𝑙𝑜𝑐 bus is determined by (12). This equation is a sensitivity
The voltages of buses and the currents of loads at the analysis that shows which bus of 𝐶𝐹𝑠 set is more sensitive to
moment before LS are obtained by the voltage estimation changes in the load current of 𝑙𝑜𝑐 bus. After determining the
process, therefore, the optimization problem in (7) and (8) is 𝑀𝐴𝐹 bus, the amount of load is calculated using (13) which its
used in order to obtain the LS variables. The purpose of this shedding from 𝑙𝑜𝑐 bus can control the critical FIDVR of 𝑀𝐴𝐹
optimization problem is to obtain suitable amounts for LS from bus. This method also needs to be repeated several times to
different buses in such a way that the voltages of all buses will reach the final answer, and the results of one execution cannot
recover to a value greater than 𝑉𝑐𝑟𝑡 at time 𝑡𝑐𝑟𝑡 . After solving the eliminate critical FIDVRs due to the made simplifications.
optimization problem, variables 𝑥 that are smaller than a 𝑀𝐴𝐹 = max (|𝑍𝑖,𝑙𝑜𝑐 | × (𝑉𝑐𝑟𝑡 − |𝑉𝑒𝑠𝑡,𝑖 (𝑡𝑐𝑟𝑡 )|)) (12)
minimum value are considered to be zero. Non-zero 𝑥 variables 𝑖∈𝐶𝐹𝑠

are the amount of load that can be shed, and indices of those 𝑥 𝑏𝐿𝑆
𝑉𝑐𝑟𝑡 − |𝑉𝑀𝐴𝐹 |
variables illustrate the location of LS. The linearization of this 𝑛𝐿𝑆 (%) = 𝑏𝐿𝑆
× 100 (13)
|𝑍𝑀𝐴𝐹,𝑙𝑜𝑐 ||𝐼𝑙𝑜𝑐 |
optimization problem to the form of mixed-integer linear
programming has been explained in detail in [12]. B. Critical Conditions and Moments of LS
min 𝑥1 + ⋯ + 𝑥𝑁 (7) Distance relays should be allowed to clear the fault; and LS
𝑥 𝑍 𝐼𝑏𝐿𝑆 (𝑡𝑐𝑟𝑡 ) + ⋯ before the operation of these relays should not be applied. On
|𝑉1𝑏𝐿𝑆 (𝑡𝑐𝑟𝑡 ) − ( 1 11 1 )| ≥ 𝑉𝑐𝑟𝑡 the other hand, the LS methods must shed the loads before the
+𝑥𝑁 𝑍1𝑁 𝐼𝑁𝑏𝐿𝑆 (𝑡𝑐𝑟𝑡 )
⋮ (8) operation of under-voltage (UV) relays, otherwise, these relays
𝑏𝐿𝑆 (𝑡 𝑥1 𝑍𝑁1 𝐼1𝑏𝐿𝑆 (𝑡𝑐𝑟𝑡 ) + ⋯ will disconnect the entire load and equipment from the network.
|𝑉𝑁 𝑐𝑟𝑡 ) − ( )| ≥ 𝑉𝑐𝑟𝑡 Therefore, LS moments should be considered between the
{ +𝑥𝑁 𝑍𝑁𝑁 𝐼𝑁𝑏𝐿𝑆 (𝑡𝑐𝑟𝑡 )
operation times of distance and UV relays.
3) LS based on Sensitivity Analysis The network will have enough time to recover if LS is
applied at the beginning of FIDVR phenomenon because a part
It should be determined that LS from which bus has the of voltage drop will be compensated by the network itself and
greatest effect on the voltage recovery of buses involved with another part by the applied LS. However, most of voltage drop
FIDVR. A relation between the voltages and currents changes must be compensated by the LS and the network will not help
is obtained as (9) by subtracting two voltage matrices in (4) and to increase the voltages if the LS is applied close to the critical
(5).

3
17th International Conference on Protection & Automation
in Power System
Shahid Beheshti University
January 17, 2023 - January 18, 2023

time. It is concluded that less LS is required if it is applied in Second fault: with the occurrence of a two-phase to ground
the early moments of FIDVR occurrence. However, the fault on the line between buses 51 and 58 at the distance of 90%
proposed methods need to spend time to perform calculations from bus 51 at the moment 1 s, the distance relays on buses 58
and send the LS trip signals. The execution time has a direct and 51 sense this fault in their zone 1 and zone 2 with operating
relationship with the speed of processor used in the central unit, times equal to 0.05 s and 0.25 s, respectively. FIDVR
therefore, the advantage of fast LS in the beginning of FIDVR phenomenon occurs in the network after the clearance of this
will be lost if a weak processor is used. The loss of this fault, and the voltages of buses shown in Fig. 2(b) enter the
advantage leads to an increase in the amount of load that can be critical conditions. In such condition, LS is necessary for
shed to deal with critical FIDVRs, therefore, it is better to preventing the interference of FIDVR and UV relays.
specify fixed moments to apply LS. If the real time reaches
these pre-determined moments, the calculated LS up to that A. Results Comparison for Previous and Proposed LS
moment is applied to the network, and the rest of LS Methods
calculations continue assuming they are applied at the next LS UV relays will disconnect 129 and 258 MVA loads fed from
moment. buses with critical FIDVR for the first and second faults.
The previous LS methods are not aware about the effect of Various LS are used to reduce the amount of disconnected load
their applied LS on the voltage recovery; therefore, those through the elimination of FIDVR interference with UV relays.
methods need to monitor the voltages and re-apply LS at the The efficiency of LS methods can be checked in the form of the
next moment if it is necessary. However, the proposed LS amount of load that can be shed, the number of buses which
methods do not need to monitor the voltages after LS due to the their loads should be shed, and the dedicated time for dealing
use of voltage estimation tool. The LS can be applied quickly with critical conditions. The results of proposed methods and
in one LS moment if a high-speed processor is used to perform methods [4] and [8] for the first and second faults are
the calculations. However, the advantage of LS at the early respectively listed in Tables 1 and 2 in order to investigate this
moments of FIDVR cannot be ignored with waiting for matter.
calculations completing if the processor does not have a high The method [4] shed the load using the voltage estimation
ability to perform calculations. Therefore, the total LS will be process based on the straight line, its LS amounts are 10% for
applied to the network in the first moment if all calculations are the first and second moment and 5% for the third one. This
completed until first LS moment, otherwise, a part of LS will method cannot include the network conditions in the
be applied in the first moment and the rest in next moments. calculations due to the fact that its LS amounts are pre-
The important moments for the proposed LS methods including determined, therefore, cannot prevent critical FIDVRs in any of
LS moments, are listed below: faults. After LS according to method [4], bus 83 in the first fault
- 0.25 s after the occurrence of fault: wait for distance relays to and buses 51 and 52 in the second one still remain in the critical
operate in their zone 1 or 2 conditions. The method [8] also identifies critical FIDVR buses
- 0.3 s after the occurrence of fault: start the voltage estimation through voltage estimation process using a straight line, and
process determines the LS amount based on the difference of IMs’
- 0.5 s after the occurrence of fault: the first moment of LS kinetic energy at before and after the fault. Considering that this
- 0.7 s after the occurrence of fault: the second moment of LS method cannot predict the effects of applied LS on the voltage,
- 0.9 s after the occurrence of fault: the third moment of LS the suggested amount for LS is greater than the calculated
- 1 s after the occurrence of fault: the critical time of operation amounts by the proposed methods.
of UV relays The method [8] suggests 40 MVA LS from buses 82, 83,
and 84 for the first fault as it is clear from Table 1, although, the
III. Simulation Results first, second, and third proposed methods by shedding 30, 32,
33 MVA from the bus that LS from it has the highest effect on
The IEEE 118-bus network with 138 and 345 kV voltages the improving the voltages (bus 83) can deal with critical
supplies 2700 MVA loads with the combination of 60% IM FIDVR. The previous methods need to monitor the voltages in
load and 40% static load. The start moment of voltage the next moments and apply new LS if it is necessary. Also, the
estimation is equal to 1.3 s, and LS moments are considered 1.5 results show that the proposed methods suggest LS from less
s, 1.7 s, and 1.9 s. also, the critical time and voltage are 1 s after number of buses compared to the previous ones. The critical
the occurrence of fault and 0.8 pu, respectively. Studies on this conditions of bus 84 is less severe than the others according to
network are carried out considering the following two faults: Fig. 2(a), and there is a possibility that no LS is needed for this
First fault: with the occurrence of a 3-phase fault in 50% bus and its critical FIDVR can be mitigated by LS from the
of the line between buses 82 and 83 at the moment 1 s, the other buses. The methods [4] and [8] do not have the ability to
distance relays on both sides of the line clear the fault at the detect the effect of LS from buses 82 and 83 on the voltage
moment 1.05 s; however, voltage drop during the fault causes recovery of bus 84, therefore, these methods suggest LS from
the occurrence of FIDVR phenomenon. The voltage recovery bus 84 as well. However, the proposed methods do not suggest
in all buses except buses 82, 83 and 84, is such that the voltages LS from bus 84 in addition to bus 82, and the critical FIDVR of
have greater values than 0.8 pu at 1 after the occurrence of fault. these buses can be mitigated by LS from bus 83.
The voltages of buses that have critical FIDVR and require LS Also, methods [4] and [8] are not able to deal with FIDVR
are shown in Fig. 2(a). by applying LS only in one moment according to Table 2, and

4
17th International Conference on Protection & Automation
in Power System
Shahid Beheshti University
January 17, 2023 - January 18, 2023

they also apply LS to buses 50, 53 and 57, which have weak from buses 51, 52, and 58 obtained from the first, second, and
FIDVRs and do not need to LS according to the results of third proposed methods for the second fault. The
proposed methods. The proposed methods avoid FIDVR simultaneously use of network and loads parameters to
interference with UV relays by only applying LS in one LS determine the location and amount of LS is the feature of
moment, and give the operator enough time to make other proposed methods compared to the previous ones. The previous
decisions. As it is clear, the proposed methods have the ability methods have used only the network parameters [4] or only the
to deal with the critical FIDVR by shedding lower load from loads parameters [8] for this purpose, however, the severity of
less number of buses and at less LS moments than other FIDVR is affected by the conditions of network and loads at the
methods. The voltages of network will be greater than the same time.
critical voltage of UV relays by shedding 51, 54, and 60 MVA

B53
B58
B52

2φ-e
B82
B83 B51
Three Phase Short˗Circuit
B57
B84 at 50 % of Line

B50

(a) (b)
Fig. 2. Voltages of FIDVR Involved Buses, (a) for First Fault, (b) for Second Fault

(a) (b)
Fig. 3. Voltage Recovery after Applying Results of Previous and Proposed LS Methods for First fault, (a) Bus 82, (b) Bus 83

(a) (b)
Fig. 4. Voltage Recovery after Applying Results of Previous and Proposed LS Methods for Second fault, (a) Bus 51, (b) Bus 58

5
17th International Conference on Protection & Automation
in Power System
Shahid Beheshti University
January 17, 2023 - January 18, 2023

Table 1. Results Comparison of Previous and Proposed LS Methods for First Fault
First Proposed Second Proposed Third Proposed
Method [4] Method [8]
Method Method Method
10% from bus 82 22% from bus 82
First LS Moment 10% from bus 83 24% from bus 83 70% from bus 83 74% from bus 83 77% from bus 83
10% from bus 84 19% from bus 84
10% from bus 82
Second LS Moment 28% from bus 83 - - -
10% from bus 83
Third LS Moment 5% from bus 83 - - - -
Sum of Loads to be Shed 24 MVA 40 MVA 30 MVA 32 MVA 33 MVA
Remain Critical Buses Bus 83 - - - -

Table 2. Results Comparison of Previous and Proposed LS Methods for Second Fault
First Proposed Second Proposed Third Proposed
Method [4] Method [8]
Method Method Method
10% from bus 50 8% from bus 50
10% from bus 51 12% from bus 51
40% from bus 51 37% from bus 51 51% from bus 51
10% from bus 52 12% from bus 52
First LS Moment 50% from bus 52 56% from bus 52 54% from bus 52
10% from bus 53 12% from bus 53
30% from bus 58 35% from bus 58 35% from bus 58
10% from bus 57 9% from bus 57
10% from bus 58 11% from bus 58
10% from bus 51 17% from bus 51
10% from bus 52 17% from bus 52
Second LS Moment - - -
10% from bus 53 16% from bus 53
10% from bus 58 16% from bus 58
10% from bus 51
33% from bus 51
Third LS Moment 10% from bus 52 - - -
33% from bus 52
10% from bus 58
Sum of Loads to be Shed 49 MVA 84 MVA 51 MVA 54 MVA 60 MVA
Remain Critical Buses Bus 51, Bus 52 - - - -

Table 3. Results Comparison of Proposed LS Methods


First Proposed Method Second Proposed Method Third Proposed Method
First Fault Second Fault First Fault Second Fault First Fault Second Fault
Sum of Loads to be Shed 30 MVA 51 MVA 32 MVA 54 MVA 33 MVA 60 MVA
Total Time Calculation 0.07 s 0.12 s 0.10 s 0.15 s 0.03 s 0.05 s

The restoration of voltages after LS obtained through load that can be shed from the network at the initial moments
different methods are shown in Fig. 3 and 4. It is clear that the of FIDVR occurrence. Better voltage recovery due to LS in the
method [4] could not restore the voltage of bus 83 in the first initial moments of FIDVR compared to the LS in several
fault and the voltage of bus 51 in the second fault to a value moments during this phenomenon can also be recognized in
greater than the critical voltage at the critical time. However, Fig. 4(b). The method [8] shed more load than the proposed
the method [8] and the methods proposed in this paper have methods, however, the voltage recovery obtained from the
succeeded in faster recovering the voltages to prevent the second and third proposed methods are better than method [8].
operation of UV relays during the occurrence of FIDVR. The
method [8] has suggested more amount for LS than the third B. Results Comparison for Proposed LS Methods
proposed method to deal with critical FIDVRs, however, the The first proposed method suggests a lower amount of load
important point in Fig. 3 is the better recovery of voltages after to be shed from the network than the rest of presented methods
applying the results of third proposed method compared to the according to Table 3, however, the performance of this method
voltage recovery resulted from the method [8]. The reason for is highly dependent on the pre-determined LS step. There is a
this issue is related to the faster application of LS in the third possibility of increasing the load suggested to shed if large steps
proposed method. The method [8] shed the load in two are chosen; on the other hand, small steps will increase the
moments, therefore, it can be expected that the amount of load execution time of method. Therefore, this method cannot be
which calculates by this method is greater than the amount of introduced as the most appropriate method among the proposed
methods with certainty. The second method is presented in the

6
17th International Conference on Protection & Automation
in Power System
Shahid Beheshti University
January 17, 2023 - January 18, 2023

form of an optimization problem in order to overcome the larger LS amount than the first method. The third method has
defect of first method. This method suggests a greater amount the best performance in terms of execution time. The operator
than the first method for shedding from the network, also, the can choose one of these three methods based on network
execution time of this method is longer than the first method; conditions and regulatory rules. Choosing the first method for
however, does not have the uncertainty of confusion in implementation leads to less LS in the initial moments of
determining the LS steps unlike the first method. The third LS FIDVR if a high-speed processor is responsible for performing
method can determine the amount and location of LS by the calculations. However, it is recommended to use the third
analyzing the sensitivity of voltages to reduction of load method in order not to lose the advantage of LS in the initial
currents. The execution time of third method is less than other moments of FIDVR if a weak processor is utilized.
proposed ones due to the simplicity of equations extracted for Another important point to be considered in dealing with
this method, however, it is less comprehensive than two other FIDVR is the occurrence of over-voltage phenomenon after
methods, and it offers more load than the other methods to shed shedding the suggested loads. For this reason, load shedding
from the network. and load restoration methods must be simultaneously
LS in the early moments of the FIDVR phenomenon helps implemented.
to restore the voltage faster, therefore, disconnection of the least
amount of load is not the only indicator regarding the optimal V. References
performance of LS method in the discussion of dealing with
FIDVR, and attention should also be paid to the execution time [1] Y. Liu, V. Vittal, “Distribution Side Mitigation Strategy for Fault
of method and the number of moments when the studied Induced Delayed Voltage Recovery”, IEEE PES General Meeting |
method applies LS. In order that the proposed LS methods can Conference & Exposition, USA, 2014.
deal with FIDVR by shedding the load only at the first LS [2] A. Mahari, H. Seyedi, “A fast online load shedding method for
moment, all calculations must be performed in the interval time mitigating FIDVR based on novel stability index”, 21st Iranian
between the start of voltage estimation (0.3 s after the Conference on Electrical Engineering (ICEE), Iran, 2013.
occurrence of fault) and the first moment of LS (0.5 s after the [3] R. Bekhradian, M. Sanaye-Pasand, M. Davarpanah, “Innovative
Load Shedding Scheme to Restore Synchronous Generator Based
occurrence of fault). According to the results listed in Table 3,
Microgrids during FIDVR”, IEEE Transactions on Smart Grid, 2022.
all proposed methods have the ability to deal with the [4] S. M. Halpin, K. A. Harley, R. A. Jones, L. Y. Taylor, “Slope-
interference of FIDVR and UV relays by LS only at the first Permissive Under-Voltage Load Shed Relay for Delayed Voltage
moment because the execution times of these methods are less Recovery Mitigation”, IEEE Transaction on Power system, Volume:
than the time difference between the start moment of voltage 23, Issue: 3, Pages: 1211-1216, 2008.
estimation and the first LS moment. However, it should be [5] H. Yang, N. Li, Z. Sun, D. Huang, D. Yang, G. Cai, “Real-Time
noted that the execution time is not the only time delay expected Adaptive UVLS by Optimized Fuzzy Controllers for Short-Term
in the studies, and other time delays such as data receiving and Voltage Stability Control”, IEEE Transactions on Power Systems,
sending delay through tele-communication channels and the Volume: 37, Issue: 2, pages: 1449-1460, 2022.
[6] A. H. Mohammadi, M. Abedini, M. Sanaye-Pasand, “Novel
operation delay of switches should also be considered.
Relative Slip Based Under-Voltage Load Shedding Protection Scheme
As a conclusion, it is recommended to use the first proposed to Mitigate FIDVR”, IEEE Transactions on Power Delivery, 2022.
method if a high-speed processor is used in the central unit, and [7] D. B. Lusby, “Z Deviation Based Demand Side Control to Reduce
also zero-phase studies are carried out regarding the FIDVR”, Master of Science Thesis, University of Tennessee, 2017.
determination of the appropriate LS step. This method has the [8] H. Bai, V. Ajjarapu, “A novel online load shedding strategy for
ability to deal with critical FIDVRs by shedding lower amount mitigating fault induced delayed voltage recovery”, IEEE Transaction
of loads in case of reducing the execution time of calculation on Power system, Volume: 26, Issue: 1, Pages: 294-304, 2011.
and choosing a small LS step. it will be more appropriate to [9] Y. Du, Q. Huang, R. Huang, T. Yin, J. Tan, W. Yu, X. Li, “Physics-
implement the third LS method in case of using a normal Informed Evolutionary Strategy Based Control for Mitigating Delayed
processor in the central unit. The processor used for extracting Voltage Recovery”, IEEE Transaction on Power system, Volume: 37,
Issue: 5, pages: 3516-3527, 2022.
the results in this study was an average Intel Core i5 processor [10] Q. Li, Y. Xu, C. Ren, “A Hierarchical Data-Driven Method for
with frequency of 2.5 GHz and 8 GB of RAM. Event-based Load Shedding Against Fault-Induced Delayed Voltage
Recovery in Power Systems”, IEEE Transactions on Industrial
IV. Conclusion Informatics, Volume: 17, Issue: 1, Pages: 699-709, 2021.
[11] M. Ghotbi-Maleki, R. M. Chabanloo, H. Javadi, “Load shedding
strategy using online voltage estimation process for mitigating fault-
It is concluded that the proposed methods can shed lower induced delayed voltage recovery in smart networks”, Electric Power
amount of load from less number of buses in the early moments Systems Research, Volume: 214, Part: B, Number: 108899, 2023.
of FIDVR due to the utilization of voltage estimation tool. The [12] M. Ghotbi-Maleki, R. M. Chabanloo, H. Javadi, “MILP-Based
implementation of first method leads to lower LS amount Load Shedding Strategy for Mitigating FIDVR phenomenon in Smart
compared to other proposed methods if an appropriate LS step Networks”, International Journal of Electrical Power & Energy
is selected for the first one. Another difference between the Systems, Volume: 146, Number: 108736, 2023.
proposed methods is their execution times. The first method [13] M. Ghotbi-Maleki, R. M. Chabanloo, H. Javadi, “Load Shedding
requires more time to calculate, however, offers lower LS Method Aimed Fast Voltage Recovery to Prevent Interference of
amounts. The second one does not have the problems associated FIDVR with UV Relays”, IET Generation, Transmission &
Distribution, 2023.
with choosing the appropriate LS step, however, it suggests

You might also like