Professional Documents
Culture Documents
Pimappe
Pimappe
Abstract
This appendix discusses general site and plot plan layout considerations from the
point of view of an efficient piping installation.
The piping layout practices are mainly applicable to major processing facilities such
as refineries, large gas plants, and large scale commercial chemicals production
facilities. However, the information is applicable to any facility where high-value
processing equipment handling flammable materials is concentrated in close quar-
ters. Included are several checklists that will help design engineers cover the many
considerations a large plant design requires.
Contents Page
general maintenance and plant shutdown work, and provides access for firefighting
equipment. Each facility dictates its own setback dimensions, but usually a
minimum of 5 to 15 feet is used. Platforming designed later may project beyond the
equipment setback line, as it will be elevated.
Some plants are designed without full-length plant setback lines. These plants
provide random width space adequate for servicing and maintaining the equipment,
on an individual basis.
Generally, equipment is set within the bounds of the equipment setback line and
some inner limit such as a pump row aisle. Equipment that occupies little space
between these limits is normally set as close as practical to the inner limit.
It is sometimes advantageous to locate groups of equipment on a common center-
line, when there is no compelling reason to do otherwise (such as when equipment
setback lines take precedence). Locating equipment on a common centerline is a
step toward simplicity. It can reduce susceptibility of errors in coordinate locations
on plot plans, models, drawings and isometric piping details.
Where the equipment edge is near the setback line, it should be moved out or spaced
so that it falls on that line. Lining up equipment on the setback line gives an orderly
appearance or a neat edge to the plant. It is acceptable provided it does not increase
costs.
Where such an arrangement leaves enough space between the setback line and the
equipment for possible future equipment, this potential should be recognized and
the plant arrangement designed accordingly.
Pumps
Always check to be sure that pumps that handle volatile liquids, and are located
under pipeways are located with their liquid ends completely outside the edge of the
pipeway. This may be required if air coolers are located above the pipeway, or if
electrical and instrument conduits and trays are to be located near the pipeway edge.
Very large pumps may require a greater distance from the pipeway edge to the face
of foundation in order to maintain width for crane access under the pipeway. Groups
of pumps should have their face of foundation on a common line facing outward
from the pipeway.
Pumps handling hot liquids are susceptible to cavitation due to flashing of liquid.
This usually dictates that vessels from which they draw suction be elevated to
provide the necessary net positive suction head (NPSH). (See the Pump Manual.)
Give thought to the location of pumps with respect to the equipment they serve.
Locating pumps symmetrically about the centerline (or one pump on the centerline) of
a column handling hot liquid may cause flexibility problems later when the piping is
laid out. Pumps offset from the column centerline allow more piping flexibility.
Walking aisle space between pumps is required for plant operations and for mainte-
nance access for pump, coupling, and motor parts. The minimum clear passageway
between pump foundations or piping is 2 ft-6 in. Spacing of 4 to 5 feet or greater is
not uncommon because of foundations and auxiliary piping occupying grade level
spaces.
Compressors
Compressors must have sufficient walk space all around, and must have crane
access for removal and replacement of heavy parts. Larger compressors usually
require platforms, which makes the overall space allocation greater.
Exchangers
Shell-and-tube exchangers need space for tube bundle removal. They should be
located with the channel end facing outward toward the plant boundary, normally on
the equipment setback line. If tube bundle removal is accomplished with a tube
bundle puller, clearance between adjacent exchangers must be provided.
Stacking exchangers is a way of saving space. More than likely, the unit shown on
the flow diagram (or early P&ID) does not indicate the number of exchangers
comprising the unit. Once the design of these exchangers is complete, many of the
exchangers may have more than one shell. This usually results in some groups of
exchangers becoming stacked without necessarily such stacking having been a
consideration of the initial plot plan. Because of this, investigate exchangers with
heavy duties or large temperature differences for possible multiple units. Normally,
stacking of exchangers is limited to two high for ease of operation and maintenance.
Air coolers are usually located over the pipeway. Make sure they are not “boxed in”
by tall equipment, preventing crane access for tube section removal. Do not use the
space (beneath or around) that has been allocated to air coolers located at grade as
walk-through access to other pieces of equipment.
Hairpin exchangers must have at least enough space to be slid out of their location.
Piping connections should be located on the end away from the plant boundary or
setback line. (This is the opposite of shell-and-tube type exchangers.) Units
comprised of multiple hairpins with shells in series can be stacked nozzle to nozzle
vertically. Hairpin exchangers with shells in parallel are set side by side without
space between the individual units.
Furnaces
Furnaces normally need additional space for tube removal, which requires heavy
equipment such as a mobile crane. A horizontal box furnace with forty-foot tubes
needs more than forty feet for tube removal. Tubes in vertical furnaces can be
removed by pulling them straight up.
Two or more furnaces are usually grouped together to take advantage of centralized
operations or a common stack, (particularly if a very tall stack is required because of
regulations concerning emission of pollutants).
It is not good practice to set furnaces at the end of the plant pipeway. This can make
it difficult to provide flexibility for large hot furnace piping. (See Section 320.)
Due to their inherent hazards, furnaces must be located to provide easy access by
firefighting equipment. The Fire Protection Manual contains a table that estab-
lishes separation distances between furnaces and other equipment. This usually
dictates that furnaces be located at an end or corner of the plant rather than between
equipment. Refer to the Fired Heater and Waste Heat Recovery Manual for further
details on furnace layout.
Access to Plants
Provide access on three sides of a plant with 15-foot minimum width roads. Roads
should have 22 feet minimum overhead clearance. The fourth side of most plants
usually has one or more overhead pipeways. These should be 12 feet high to permit
a hydraulic crane to maneuver under the pipeway for pump and piping maintenance
during shutdowns.
Power Lines
Keep power lines clear of all locations where cranes may be active to allow compli-
ance with applicable state safety orders. Move existing lines if necessary. Consider
placing cable in buried or pipeway-supported conduit rather than on pole lines.
Lighting
Use floodlights rather than individual lights to the extent that adequate lighting is
obtained and first cost is equal. Provide access to floodlights for relamping. Place
individual lights close to or directly over a platform to facilitate relamping.
Plant Shutdown
Provide for a portion of the plant being down, as in many cases a single column or
reactor may be taken out of service without bringing the whole plant down. In
spacing equipment and laying out lines for such cases, consider the fire hazard of
cranes required for maintenance and also the consequences of a mishap while
removing equipment from the area.
Future Expansion
Crowding and consequent high maintenance cost can be avoided by advance plan-
ning for future additions of pumps, lines, exchangers, vessels, etc.
Cooling Towers
Place this unit with its pumps and chemical equipment downwind from a plant. In
colder climates, the mist and condensation produced can be a nuisance.
Control Rooms
Anticipate the preferences of the client in locating control rooms. The client may
sometimes have definite ideas that can cause problems in equipment arrangement.
Control houses should be located in a nonhazardous portion of the plant.
Foundations
Allow space for the buried portion of foundations of tall or heavy pieces of equip-
ment. These foundations can be extensive, especially if piles are not specified.
Spread footings can affect the spacing on your layout. Also consider combining
spread footings in order to save space.
Safety Showers
In compact plants, safety showers with eye washes can be a problem if some
thought has not been given to the space they require. Safety showers can be 30
inches by 60 inches. Generally, both the number and location of safety showers need
approval of the operator. However, the need for them can be anticipated where
hazardous materials such as acid or caustic are part of the process.
Analyzer Buildings
Analyzer shelters require spaces up to 6 feet by 10 feet.
Branch Pipeways
Spacing on the plot plan must take into account locations of branch pipeways to
serve equipment on either side of the main plant pipeway. These branch pipeways
should not be routed over equipment; space should be allowed on the plot plan for
them. However, this does not preclude having them pass over the pump row paral-
leling the main pipeway.
These drawings can be used to provide the basis for the plant piping layout. They
are not intended to solve all piping layout issues. However, they do provide guide-
lines for many typical layout problems.
As an aid to the development of plot layout specifications, several standard forms
are available. They are similar to the above standard drawings, but with spaces to
allow the engineer to insert the dimensions for spacing for the various types of
access and machinery which the project has decided upon. These forms are:
PIM-EF-579 Planning Drawing—Proposed Process Plant—Cross Section—
Equipment and Pumps on Same Side of Pipeway
PIM-EF-580 Planning Drawing—Proposed Process Plant—Cross Section—
Equipment Separated From Pumps by Pipeway
PIM-EF-883 Planning Drawing—Proposed Process Plant—Cross Section—
Two-sided Plant With Air Coolers
E5.3 Communication
Communication between the project engineer and the eventual owner/operator
(client) must remain open, objective, and timely. The following elements are basic
to achieving good communication:
1. Client Representative Responsibilities. Project team members and the client
representative work together to establish the review and approval steps that will
ensure the minimum number of changes after a decision has been made.
2. Description of Project Execution. The client representative should under-
stand the organization, procedures, tools, etc., so he can decide how he partici-
pates in the design effort, where he resides, etc.
3. Early Assignment of Key People. Identify key people early in the planning
phase. This promotes useful communication early enough in the job to estab-
lish definition of facilities. Key people include the Project Manager, Project
Engineer, Drafting Lead, and engineers in charge of P&IDs, piping layout, and
major equipment purchases.
4. Decision Making Process. Describe and schedule the “milestones” necessary
for efficient execution by using the attached Project Planning Chart or other
similar device. This ensures timely participation of the client representative or
his management in basic project decisions.
ments. It is issued to contractors for bidding purposes and serves throughout the
project as the basic design tool. For contractual purposes, it is the definitive docu-
ment for determining plant quality.
Because of its concise treatment of Company design requirements and preferences,
the model specification is useful as a starting point for agreement on plant quality.
Since the model specification includes items which do not apply to all projects, a list
of applicable paragraphs or a tailored version of the specification should be
prepared for each specific job. The document should be limited to the paragraphs
that are technical in nature; portions of the model that deal with administrative
aspects of the job should be dealt with separately from this technical design plan-
ning effort. The specification should then be submitted to the client for comments
and for approval.
On some jobs special techniques, design criteria, approaches, etc., are required.
These peculiarities are not covered in the model specification or in Company
manuals. It is important to define the use of these special techniques at the outset of
the project so that both project members and the client understand their applica-
bility, limitations, and advantages. Such special techniques should be discussed
openly and the approval of all concerned should be gained.
The planning phase starts with project approval and goes up to receipt of final
process designs. The engineering development phase begins with receipt of
process designs and goes through completion of basic design documents (plot plan,
one-line diagrams, P&IDs, paving layout). The drafting development phase starts
with receipt of process designs and goes through approval of the plant model (or
other drawings showing layout concepts and schemes).
The project phase for each item should be reviewed as to both scope and timing in
light of the circumstances surrounding a particular project. This should be done
even though inaccuracies may arise, since the thought process is as valuable as the
final document that emerges.
These phases are time periods in which specific effort is concentrated, but they do
not have rigid start and end points. In the course of most jobs the three phases
overlap. On some jobs the start of the planning phase may have to be delayed until
receipt of process designs. In any event, clear definition of project scope and appro-
priation approval (or management directive) are required before effort is devoted
to any aspect of project work.
While the purpose of the chart is to act as a reminder so that significant items are
not forgotten, it should also be used to identify studies that can be avoided. Many
decisions can be made on the basis of past experience or recent local studies. This
practice is encouraged as an important way to improve design efficiency without
sacrificing quality.
Engineering Questions
The Project Planning Chart also functions as a listing of recurring plant design ques-
tions. Individual items may or may not be applicable, and the list must be screened
to be meaningful for a specific project. The screening should be done with the client
representative, and agreement should be reached as to how any particular item is to
be resolved, whether by study or by arbitrary decision. Add to the list items that
arise from the client review of the model specification. Also, each project has
unusual aspects which need study, and these should be added to the list as necessary.
Site Suitability
Land Purchase (Note 1): Availability of land, size and shape, future
availability.
Site Development (Note 2): Topography, soil conditions, ground water,
piling.
Climate (Note 3): Temperature, rainfall, wind, severe conditions (hurri-
canes, tornados).
Geological Problems (Note 4): Active fault, flood plain.
Additional Tankage (Note 5): Supply change, local requirements.
Character of Area (Note 6): Urban (industrial, commercial, residential);
rural (virgin, farmland, recreational).
Public Services
Utilities (Note 7): Water (sources, quality, quantity); electric power
(purchase, generate, gas).
Communications (Note 8): Telephone, telex, mail.
Fire Protection (Note 9).
Labor Environment
Cities, Towns (Note 10): Distance from site, size.
Labor Availability (Note 11): Construction, refinery operation.
Effect on Local Economy (Note 12).
Business Climate
Local Codes (Note 14): Building requirements, unusual safety
requirements.
Local Zoning (Note 15): Existing, proposed.
Local Taxes (Note 16): Penalties, incentives.
Local Politics (Note 17).
Legal Procedures.
Service Organizations
Local Contractors (Note 20).
Support Facilities (Note 21): Maintenance, repair.
Notes:
1. Finding suitable land at a reasonable price is a first consideration. Enough land
should be acquired initially to allow for future development, or assurance
should be obtained that more will be available at a later time. A reasonably flat
site is needed for process facilities; in addition, there must be room for
construction activities and material storage.
2. Natural drainage is an important early consideration. Crude and product storage
must be located so any released materials flow away from processing facilities.
Soil conditions must be known in order to determine the need for piled founda-
tions. The need for and the availability of imported soil needs early resolution.
3. Climate at the site affects all phases of design, construction, and operations. It
should be understood early since it is a significant factor in deciding on a
particular site.
4. Earthquake activity in an area has an important impact on foundation and
equipment design. The frequency and severity of storms can have a major
impact on drainage system designs.
5. The storage requirements for feedstocks and products need early definition, as
the area for tankfields can be extensive.
6. In determining the overall suitability of a given site, the general characteristics
of the area need consideration. Location near residential or recreational areas
frequently has an effect on design and on operations in the long run.
7. The availability of local public utilities can affect the selection of a new plant
site. New supply lines can be a significant cost. Also quantities available need
to be matched against new plant requirements.
8. Availability of local telephone lines may be a problem if the system is nearly
loaded. Long delays in obtaining service can result.
9. The extent of internal fire protection provided by the plant may be determined
by availability of local fire protection.
10. Pleasant, convenient local communities are particularly important in attracting
a quality labor force to operate new facilities.
11. Consider availability of local labor for construction and operations when
selecting a plant site.
12. Sometimes it is possible to negotiate concessions with government agencies
when new facilities will enhance local economy.
13. A major factor in selecting a plant site is the availability of transportation.
There must be practical forms of transport to bring in construction materials.
When the plant is in operation there must be economical ways to bring in feed-
stocks and supplies and to distribute products generated by the facility.
14. Before final site selection is made, applicable local building codes should be
well understood. Also any special or unusual safety requirements should be
known.
15. Local zoning restrictions enter into the site selection process. If possible, some
insight into possible future changes is useful in making the final decision.
16. In some locations it may be possible to negotiate tax concessions if the area is
interested in attracting new business.
17. The decision to locate a facility at a given site may be influenced by the exist-
ence of strong political factions that could affect construction and operations.
18. Satisfying permit requirements has become a major project activity, often on
the critical path. Maintaining good public relations has become even more
important than in the past.
19. The handling of all potential pollutants that may emanate from new facilities
needs to be considered during site selection. Both the types of potential pollut-
ants and the quantities of each must be addressed.
20. The availability of local contractors to perform work during construction
should be addressed during site selection. If the supply is limited it may be
necessary to import a work force on a temporary basis and perhaps provide
some infrastructure to support them. The long-term availability of local
contractors to support maintenance and miscellaneous construction after the
facility is in operation also should be considered.
21. The availability of local shops and parts supply warehouses needs investigation
from both a construction and an operations standpoint.
22. Locally available material (particularly minor materials such as pipe, valves,
electrical materials, concrete, etc.) provides a site with more flexibility both
during construction and later when the facility goes onstream.
23. Good local community facilities attract and hold people that are the potential
work force for a new installation.
24. One key to the site selection process is the determination of how feedstocks
will be supplied. Product distribution is of equal importance in this study.
Crude oil usually comes in by tanker ship or pipeline, although it sometimes
comes via rail tankcar. A need for water access can have a significant bearing
on site selection, as water terminal facilities are limited in location. Also they
can be very expensive if the plant location is remote.
25. Product distribution is unique to each location. Selection is partially dictated by
existing infrastructure such as product pipelines, railroads, and highway
systems. Also affecting selection is the customer’s ability to receive product.
Most off-plot facilities are affected by the method and size of shipments. For
instance, marine shipments often require much more tankage for finished stock.
Since off-plot requires the largest part of the geographic area of the site, it can
play a significant role in site selection.
Plot Plans
Plant Sizing
Double- or single-sided plant (and other shapes).
Length (controlling elements).
Width (controlling elements).
Height.
P&IDs
Piping Standards
Local Plant Usages. Match and alter standards to suit local plant prac-
tices where possible (usually very little accommodation required).
Critical Piping. Watch services that are hot, hazardous, high pressure,
and/or corrosive. Look closely at the location of critical piping (espe-
cially LPG lines), underground piping, piping in a vibrating service and
piping which includes expansion joints.
Instrument Piping. Piping standards do not cover instrument piping.
Make sure it is compatible. Tubing fittings must be from same manufac-
turer as those currently used in the facility.
Materials Selection
Almost always prepared by the facility’s Materials Specialist or the
Engineering Technology Department’s Materials Group.
Difficult to design for all permutations and special cases. Talk with the
Materials Specialist frequently.
Process Designs
Early Participation. Client and Project Engineers participate—
preferably as early as possible.
Kickoff Meeting. As a minimum, hold an early overall review meeting
with the Client. Be certain critical process considerations are recog-
nized and weighed.
Process changes during the Mechanical Design. Accommodate
changes in the Process Design unless and until they impede the progress
of the Mechanical Design.
Approvals. Obtain review and approval from the Process Designers for
all P&IDs, equipment, designs and Vendor drawings that impact the
Process Design.
Final process P&ID reviews. Hold a joint Client-Engineering-
(Contractor) final process P&ID review just prior to releasing the P&IDs
for procurement and construction.
Capacity Review
Make spot checks on the adequacy of each of the items listed below under the various
conditions of operations, process equipment or utility guarantees notwithstanding:
wash, flush, startup, run, turndown, shutdown, emergency, etc. (Develop rapport with
the Contractor through a mutual understanding of design objectives.)
Pumps and Drivers. NPSH, suction specific speed, head, horsepower,
minimum flow. (Provide additional capacity over and above process
requirements, to allow recirculation—at or above minimum flow—as
necessary.)
Exchangers and Air Coolers. Duties, areas, coolant temperatures, heat
transfer coefficients, fouling factors, motor duties. Size motors so they
will not overload under cold weather conditions with fan blades pitched
for maximum summer cooling. Select fan speeds for noise control.
Columns, Drums, and Vessels. Check residence times for instrumenta-
tion and upsets and reaction times for alarms and shutdowns.
Compressors. Capacity, gas composition and temperature ranges (size
motor to handle density variations), speed, and temperature limits.
Check for capability of run-in on nitrogen, if required.
Furnaces. Duties, heat liberation volumes, flame impingement limita-
tions, flux rates, stack and burner capacities, fuel gas or oil heating
values. (Process Design handles much of this.) Ensure that emissions
comply with Permit to Construct.
Desalters, treaters, filters.
Cooling Towers and Cooling Water Supply System. Cooling towers
should receive exhaustive capacity evaluation by the Contractor.
Chemical addition, quench, and water makeup systems.
Transformer, Motor Control Center Capacity and Sparing. Divide
spared pump and motor loads.
Utility Systems. Steam, air, condensate, BFW, etc. (Use extra care on
condensate systems.)
Control Valves. Review sizing criteria philosophy. Valves must accom-
modate upset conditions and turndown without excessive noise.
Drainage Systems. Size for maximum storm runoff and/or fire loads.
Pipeways. Spare capacity for future.
Instrument Panel. Spare space.
A/C and refrigeration requirements.
Spare underground conduits and MCC slots.
Catalyst Volumes. (Process Design will check).
Plot space for future equipment.
Relief System. Design philosophy. Tabulate and record loads on P&IDs
for all conditions considered.
Operability/Maintenance/Safety
Access. Aisles, ladders, walkways, platforms, stairs. Rigging. Columns,
vessels, (catalyst loading), exchangers, pumps, compressors, furnaces,
reactors, air coolers, filters, machinery, control valves, instrumentation,
electrical, alarms and shutdowns.
Pipeways and Structures. Cross bracing, clearances, pipe stanchion
spacing.
Plot Limit and Piping Manifolds. Location, emergency accessibility,
sizing, and arrangement.
Accessories. Sample, utility, firefighting equipment, removable spools,
blinds, flanges, vents, bleeders, drains, water drawoffs, flush, washout,
steamout, pumpout, lubrication systems.
Lighting.
Elevated Equipment and Instruments. Consider providing stair
access where operator attention is needed once per shift.
Noise, odor, and hazardous chemicals control.
Piping
P&IDs, models, and isometrics.
Accessibility. Operability and maintenance. (Minimize flanges in
hazardous services.)
Piping Standards. Materials, flange facings, type of gaskets, grease
seal valves, unions, pressure seal and welded bonnets.
Pressures and Stresses. Pressures and stresses during upset—power,
cooling, and BFW failure. Pressure surges. Slugging from two-phase
flow or pulsating flow. Snubbers may be required.
Flexibility. Anchors, guides, supports and expansion loops. Avoid
bellows expansion joints. Provide tiebacks for “Dresser coupling” slip
joints.
Safety and fire.
Steam trap schedules and layouts.
Electric or steam tracing. Thermal cement (Thermon).
Insulation. Thickness chart. Stainless steel or aluminum covering.
Flange and manway treatment. Valve blankets. Protection against corro-
sion under insulation.
Hydrotest schedules and procedures.
Pickling. Lube-oil, compressor suctions, etc.
Construction support. An early materials takeoff (and ordering) may
be required for specialty, alloy, or large valves with long delivery times.
Instruments
Control, alarm, and shutdown philosophy. System design philos-
ophy. Fail-safe design.
Control system. Distributed control. Monitoring (data acquisition).
Computer. Programmable logic. Pneumatic vs. electronic instrumenta-
tion; computer compatibility. Spare capacity. Intrinsically safe instru-
ments.
Field vs. house indication and/or recording.
Special installation details. Instrument piping standards. Purge
requirements.
Logic and loop diagrams.
Instrument field locations.
Numbering system, labeling, tagging.
Acceptable instruments and manufacturers (names and model
series). Include approved instruments lists when instruments are
supplied as part of a major equipment package.
Test facilities and procedures for testing all alarms and shutdowns.
Requirements for in-service testing and repair of critical valves and
instruments.
Fire detection devices.
Winterization.
Conduit routing and support.
Process data: specific gravities, viscosities, pressure drops, flow rates.
Safety. Boiler, furnace, reactor, compressor, etc., control systems.
Electrical
Type of system. Power source(s). Generation, transmission, and main
substation. Reliability. Sparing. Automatic load transfer. Transformers,
switchgear, etc.
In-plant power generation. Steam, diesel, gas turbine, cogeneration
facilities, etc.
Facility-wide distribution system.
Large load interaction with existing facility. (Study early.)
Load layout.
One-line diagrams.
Area classification drawings.
Short-circuit study.
Motor starting voltage drop study.
Plant substation. Transformers, switchgear, and MCCs. Layout, sizing
(load shedding), specifications, data sheets, location, conformance to
specifications. Special features: control power, battery backup, heaters,
interlocks, enclosures, etc.
Plant distribution system. Conduit routing and support. Overhead vs.
underground. Piles? Spare conduits for underground banks.
Coordination of protective devices.
Power factor correction. Capacitors. Synchronous motors. Harmonics
study.
Special control systems and wiring diagrams. (Pay particular atten-
tion to the operational functions required of control systems.)
Electrical/instrumentation systems separation. Protection of low
voltage instrumentation systems from transient voltage spikes.
Motor specifications and data sheets. XP, TEFC, WP, chemical
service. Voltage Speed Synchronous, Varispeed. Heaters, winding
temperature monitors, etc.
Emergency and standby power systems. Uninterruptable power
supplies, standby generators, and unit equipment.
Lighting. Spacing, flood, emergency, voltage drop.
Civil
Platforms, stairways, ladders, walkways. Layout, access and imposed
loads on equipment. Spot check critical details: handrails, toe boards,
decking, etc. Maximize use of side step ladders.
Structural. Permitting requirements. Wind and earthquake designs.
Vibration. Fireproofing. Tall stacks. Stanchions in walkways, tripping
hazards, head-knockers, cross bracing, etc.
Plant paving. Layout, extent, shape, drainage and ability to handle
heavy equipment. Concrete vs. asphalt. Pile support? Graveled or
shelled setback areas.
Roads. Clearances, guard posts, guard rails, width, load-carrying design,
truck turning radii.
Underground systems. Conduit banks. Sewers. Interferences. Plan
work to minimize dirt handling.
Drainage Systems. Layout, usage, sealing, and arrangement. Process,
area, sanitary, sample stations, safety showers, analyzers, drinking
fountains, etc. Segregation: oily, storm, chemical, sanitary. Storage
containment.
Control house and buildings. Layout, facilities, plumbing, electrical
systems, lighting, heating, ventilating, and air conditioning, blast-
resistance.
Foundations and piling. Provisions for future expansion. Conform-
ance to specifications. Steel vs. wooden piles.
Soils investigation. Allowable soil bearing pressure vs. piles. Soil
contamination check.
Tankfields and impounding basins.
Site Preparation. Fill availability and hauling costs. Spoil disposal.
Contaminated soils and debris.
Waste treatment facilities. Often a significant civil effort.
Environmental
Air. Dispersion modeling.
Water.
Ground. Leak detection systems.
Flora and Fauna.
Waste. Reduction, treatment, disposal.
Noise Control.
Permits.
Fire Protection
Facility fire systems. Pumping, distribution, looping, emergency
backup. Fire trucks.
Tankfields. Impounding basins. Storage of large volumes of
hydrocarbons.
Access. Facility and in-plant.
Near and in-plant firefighting facilities. Hoses, hydrants, monitors.
Fire water (“First Aid”) systems, foam systems, deluge systems, Halon
systems.
Relief systems. Equipment design temperatures and pressures: design
for operating, upset, startup and shutdown. Consider higher design pres-
sures for equipment handling hazardous materials (e.g., H2S) to prevent
release except under blocked-in fire conditions.
Isolation valving. Provide large block valves for isolation of tanks,
impoundment basins, pumps, and large on-plot hydrocarbon contain-
ment vessels (50 barrels or more). Locate valves where they will be
accessible in an emergency and/or provide remote operation. Identify
with red paint.
Fail-safe design. Determine how each control valve should fail in case
of loss of power: fail closed, fail open, fail in position.
Cooling water system safeguards. To guard against high pressure
exchanger tube ruptures, provide cooling water piping rupture disks.
Also provide for gas venting at the inlet to cooling tower distribution
piping.
Paving and drainage. Design for firefighting loads. Provide sealing and
isolating systems. Drain flammable liquids away from critical equip-
ment to remote impoundment.
Fireproofing. Structures, vessel skirts and saddles, instruments, and
electrical.
Shutdown systems.
Electrical area classification drawings.
Intrinsically safe instrumentation.
Fire alarm systems. Flame and heat detectors (U.V. monitors aimed at
line of pumps). Hydrocarbon vapor detectors. Early warning systems.
Alarms which differentiate between minor and major emergencies.
Blast-resistant control houses. Instrument and computer fire protec-
tion systems.
Conservation
Heat recovery.
Hydraulic (pressure) recovery.
Water, condensate and steam recovery.
Hydrocarbon loss prevention.
Furnace and equipment efficiencies.
Steam turbines vs. electrical drives.
Steam turbines vs. letdown stations.
Air cooler and cooling tower overcooling.
Cooling water fouling.
Variable speed (and 2-speed) motors.
Steam generation.
Cogeneration facilities.
Secondary containment. Leak detection systems.
Utilities
Steam. 15-lb., 150-lb., 400-500-lb., 800-900-lb. Boiler plants. Water
treating. Desuperheating. Steam balances.
Condensate. Recovery systems. Header sizing. Traps vs. control valves.
Process water. Demineralizers. Potable water for safety showers and
drinking.
Boiler blowdown systems.
Quench Water. Chloride-free wash water for hydrotest (for stainless
steel piping and equipment).
Cooling Water. Treating, distribution, blowdown. Cooling water vs. air
cooling.
Closed loop cooling water systems.
Instrument Air. Nonlubricated compressors, dryers, and distribution.
High pressure motive air. Utility air.
Fuel gas. Centralized mix drum, natural gas backup distribution, in-
plant knockout facilities, cleanup facilities, hydrate formation, steam
tracing, and insulation.
Fuel Oil.
Nitrogen, oxygen, CO2, inert gas generation, storage, distribution.
Project Phase
1 2 3
A. General
Layout Considerations
2. Establish location of aboveground off-plot tie-ins (process, utility, relief, chemical lines, X
etc.), underground off-plot tie-ins (sewers, cooling water lines, etc.), and source of electric
power.
9. Establish need for special maintenance facilities (e.g., monorails, catalyst conveyors, etc.— X
see also E. Exchangers, Item 1).
14. Develop plot plan alternatives, including equipment spacing and location requirements. X
Obtain client approval.
Project Phase Key: 1 = Planning 2 = Engineering Development 3 = Drafting Development
Project Phase
1 2 3
Systems Development
15. Review preliminary process designs for possible savings from mechanical standpoint. X
Resolve differences with process engineers.
16. Establish degree of reliability required for plant and various subsystems. X
18. Establish plant operating requirements during power failure, including need for emergency X
power system.
19. Establish plant cleanup requirements and need for special systems and connections. X
Procurement Considerations
25. Establish needs for spare parts that should be ordered at same time as equipment. X
Miscellaneous
27. Develop materials of construction, including determination of need for special work such as X
lab tests, development of fabrication techniques, etc.
29. Review governmental regulations that affect design (including proposed regulations) and X
establish applicable design criteria. Initiate contacts with official agencies and determine
procedures and required schedules for obtaining permits.
B. Utilities
2. Prepare utility balance in sufficient detail to permit selection of types of drivers for all X
significant equipment.
Project Phase Key: 1 = Planning 2 = Engineering Development 3 = Drafting Development
Project Phase
1 2 3
C. Columns and Vessels
D. Tanks
E. Exchangers
4. Determine whether tube bundle extractor will be used and/or requirements for permanent X
handling facilities (davits, monorails, etc.).
F. Furnaces
1. Determine acceptable configuration (if not dictated by process or service) e.g., passing X
arrangement, need for convection section, air preheater, etc.
4. Determine need for soot blowers (consider future soot blowing lanes). X
Project Phase
1 2 3
J. Instruments
5. Determine size, shape, and density of the control panel and need for graphic or semi- X
graphic display.
K. Compressors
L. Piping
3. Establish philosophy for separating utilities from process systems (i.e., drop-out spools, X
double block and bleed, etc.).
4. Establish plot limit philosophy (single block, Hamer blinds, double blocks, etc.). X
M. Structures
3. Determine whether stanchion and structures will be concrete or steel and where bracing is X
allowed.
5. Establish requirements for stairs instead of ladders, including operator walk patterns. X
Project Phase Key: 1 = Planning 2 = Engineering Development 3 = Drafting Development
Project Phase
1 2 3
N. Insulation
1. Establish internal and external insulation requirements, economic thickness, and materials. X
P. Electrical
3. Establish concepts of degree of double ending of substations, separate electrical supply, etc. X
4. Determine extent to which main and spare equipment should be on spare busses. X
5. Establish extent of spare capacity required in switchgear, motor control centers and X
conduit banks.
Q. Foundations
R. Buildings
3. Establish requirements for housing of compressors from a weather shelter and noise X
standpoint.
4. Determine need for auxiliary buildings (tool shed, analyzer sheds, laboratories, etc.). X
S. Miscellaneous
1. Determine method of delivery and quantity as guide to sizing tankage, pumps, etc. X
Project Phase Key: 1 = Planning 2 = Engineering Development 3 = Drafting Development
Project Phase
1 2 3
W. Waste Disposal
1. Establish general waste (including chemicals) disposal scheme and whether systems are X
separate or combined, and how combined.
Z. Noise
1. Determine proper noise specification for the plant locale and client’s willingness to make X
extra expenditures to attain goal.
Project Phase Key: 1 = Planning 2 = Engineering Development 3 = Drafting Development