Agreement Signed Date 3/30/2023

Mechanical Completion
Date 3/15/2026

Mile Stones to be Created

Sl.No Description

As Per Schedule

1 Effective Date of Contract Award

2 Final Completion

3 Completion of Civil Works

4 Mechanical Completion Unit 22

5 Mechanical Completion Unit 21


6 Precomissioning Process Areas

7 Precomissioning Utilities Areas

8 Ready for Loop Check 505,225,215

9 Substation Energised 225,505,215

10 Substation Energised 225,505,215

As Per Payment

1 Labor Camp Ready for 30% Ocuupancy

2 Labor Camp Ready for 60% Ocuupancy


Detailed Schedule Should Comprise the Following:
1 Sequence and Time Span of all activities
2 Critical Path of the Programme
Percentage Progress Curves based on
3 Contrcators Progress weighing system
4 Manpower allocation Programme
5 Equipment allocation Programme
List of Method Statements and Schedule for
6 their Submission
Type of Milestone Date Remarks 1

SM ### 3

FM ### 4

FM ### 5

FM ### 6

FM ### 7
FM ### 8

FM ### 9

FM ### 10

FM ### 11

FM ### 12

13

FM Mobilization to Site of Atleast 800 Persons 14

FM Mobilization to Site of Atleast 1000 Persons 15


General Notes: Scope Of Work

The Subcontractor shall be responsible for producing detail


engineering documents and drawings required for the execution of
the works Sl.No

Schedule for construction activity as per the drawing schedule Inside Battery Limits PE-2
The details of drawings so far issued to be collected from the
concrened Personnel 1

Weightage for the physical proogress to be ensured as the indirect


cost portion payment to be made as per the perccentage of
physical Progress 2
Increase in the scope of Work shall not have any change in the
Project Schedule 3
Incase of any delay by the Contractor the Subcontractor shall not
be entitled to any additional claims 4
The Manhours Required for Each Major Construction Activites to
be calculated Inside Battery Limits PE-2
The List of Suncontractors deliverables to be accquired 1

The Sequence for Supply of Materials and Equipments to be fixed 2

Any change in the Sequence of materials delivery by the contractor


has to be visited and revised schedule has to be submitted. 3
New Prices can be claimed for works not in the price list upon
aggrement between two parties 4
Detailed Schedule to be Submitted within one month of effective
date of contract award Outside Battery Limits

The Contractor's Progress Weighing System to be determined 1

If the rate of Progress is too slow revised program to be submitted


as per the instructions given by the Contractor to complete the
work within the scheduled date of Completion 2
The revised program to be submitted within 5days after the
cotractor has requested for the same 3
4
5
6
7
8

9
10
11

12
Offsite
1
2
3
4
Scope Of Work

Description What falls Within the Various Limits

Inside Battery Limits PE-21

Polymerization

Extrusion

Substatiopn Area and RIE(Remote Instrument Enclosure)

UG & Commom PE-21 Only the Poly Ethylene Processing Units


Falls Within the Inside Battery Limits
Inside Battery Limits PE-22 Area
Polymerization

Extrusion

Substatiopn Area and RIE(Remote Instrument Enclosure)

UG & Commom PE-22

Outside Battery Limits

Main Interconnecting Piperack

Plant/InstrAir/IC4/Demin water/Potable Water

Waste Water/ Sanitary Water/ Cooling Water/ Fire Water


PE Flare Systems
Chemical Storage Building and Raw Catalyst Building Utility and Auxiliary Systems
Utility and Auxiliary Systems
Main EL. Substation/PE OSBL SS/RIE#2
UG and Common Utilites
Bagging Warehouse and Bagging Administration & Exit Gate

Polyethylene Bagging
Loading Area and Other Building
Pond and First Flush Pond

UG and Common Ware House and Pond Area

RLIC Container Port Infrastructure and Building


UG & Common Offsite Port
Electrical Power Switchyard and Substation-132KV(RLF3)
UG & Common Offsite Other