Professional Documents
Culture Documents
CAPE BMED Option B Bdraw 2019 U2 P2
CAPE BMED Option B Bdraw 2019 U2 P2
CAPE BMED Option B Bdraw 2019 U2 P2
UNIT 2 – Paper 02
2 hours 30 minutes
GENERAL INFORMATION
INSTRUCTIONS TO CANDIDATES
2. Where scales are not stated, the full size should be applied.
4. When first-angle or third-angle is not specified, the choice of projection is left to the
candidate’s discretion, in which case the type of projection used MUST be clearly stated.
5. The candidate should use his/her own judgement to supply any dimensions or other
details not directly shown on the drawings.
7. Each candidate MUST enter his/her school code and registration number in the appropriate
space provided at the bottom of the drawing paper.
SECTION A
1. Figure 1 shows a simply supported beam loaded with two point loads (PLs) and a uniformly
distributed load (UDL).
(b) Produce the shear force diagram (SFD) for the beam, using a graphical method.
[10 marks]
(c) Identify the point where the shear force SF = 0 and calculate the maximum bending moment
(BMmax) corresponding to this point. [6 marks]
Total 20 marks
(a) Produce a reinforcement detail plan of the concrete roof slab for the building in Figure
2 at a scale of 1:20. Use a slab thickness of 150 mm and show the main distribution and
‘over support’ bars along with the bar sizes, type and spacing specifications.
[12 marks]
(b) Produce a section through the slab drawn at a scale of 1:20, showing all details.
[8 marks]
Total 20 marks
SECTION B
3. (a) Name TWO types of Portland cement and, for EACH type named, clearly explain the
situation in which it is suitable for use. [6 marks]
(b) With the aid of a flow chart, explain ONE of the following processes for producing cement:
(c) Table 1 below gives the specifications for the coarse aggregates and fine aggregates to be
used in a mix.
The coarse aggregates are rounded and the mix is of medium workability with an
aggregate cement ratio of 3:8 and a proportion of fine:coarse aggregate of 2:1. Type 1
Portland cement with a specific gravity of 3.15 is to be used. Use the information provided
to design a mix for a total damp aggregate weight of 30 kg and a water cement ratio of
0.4. [8 marks]
Total 20 marks
4. You are the newly appointed site manager for a construction company. Your company is undecided
as to which quarry to choose for the supply of aggregates.
(b) What are the TWO main factors that must be taken into consideration when sampling and
testing aggregates? [2 marks]
(c) Explain the impact that particle shape, surface texture, size and texture classification have
on concrete mix. [6 marks]
(d) Using diagrams where necessary, explain the winning and processing of aggregates.
[8 marks]
Total 20 marks
SECTION C
5. The network shown in Figure 3 represents a section of a project being undertaken by a sub-
contractor. The number of equipment (mixers) required for each activity is also shown in
Figure 3; for example, 2E = 2 equipment. The subcontractor does not want to use more than eight
mixers on the job. However, the main contractor would like the job to be completed in 27 weeks
to phase in his operations.
(a) Produce a bar chart and resource histogram to represent the latest start times for each
activity in Table 2. [12 marks]
TABLE 2: ACTIVITIES
Resources
Activity Duration ES LS Float
Required
A 4 2 0 0 0
B 6 3 4 13 9
D 2 4 4 23 19
C 9 4 4 4 0
F 8 4 10 19 9
E 3 3 10 22 12
G 10 2 13 13 0
J 2 1 13 25 12
H 4 2 23 23 0
(b) Using resource smoothing, schedule the start of each activity so that ONLY eight mixers
are utilized each week. The project should not exceed 27 weeks. [8 marks]
Total 20 marks
6. Develop a line of balance (LOB) for a road project that consists of 20 sections. The target output
rate for the project is three sections per week. A typical working week includes five 8-hour days.
The construction of a single section consists of the following five sequential activities listed in
Table 3.
1 2 3 a b1 b2 c d
A 110 3
B 320 8
C 365 9
D 35 2
E 210 5
Calculate the following and use the answers to complete Table 3 for activities A to E.
(a) Theoretical gang size at the chosen output rate (G) [4 marks]
(b) Actual gang size (Ga) and actual output rate (Ra) [8 marks]
(d) Time from start on first unit to start on last unit (T) [4 marks]
Total 20 marks
END OF TEST
IF YOU FINISH BEFORE TIME IS CALLED, CHECK YOUR WORK ON THIS TEST.
02269020/MJ/CAPE 2019