Professional Documents
Culture Documents
SPM Da2 Question PDF
SPM Da2 Question PDF
SPM Da2 Question PDF
1. (a) Identify the critical path for the project with the following details. (b) Draw up a resource table showing
the number of each type of resource needed on each day of the project assuming there is only one system
designer. (c) Suggest the best way of revising the plan to remove resource clashes if any.
Depends
Activity Duration Resource Type
on
A - 2 System Analyst
System
B A 10
Designer
System
C A 2
Designer
D C 2 Software Coder
E C 3 Software Coder
F C 2 Software Coder
G B,D,E,F 4 System Analyst
This study source was downloaded by 100000855851273 from CourseHero.com on 06-19-2023 09:17:35 GMT -05:00
https://www.coursehero.com/file/89125597/SPM-DA2-QUESTIONpdf/
Powered by TCPDF (www.tcpdf.org)