BILL OF QUANTITIES FOR PROPOSED ADDITIONS & ALTERATIONS OF EXISTING HOUSE OF

MR.M.D.P.H.MANATHUNGA AT 298/8,1ST MAKEDIN MAWATHA,HABARAKADA ESTATE


,HABARAKADA,HOMAGAMA
BILL OF QUANTITIES FOR PROPOSED ADDITIONS & ALTERATIONS OF EXISTING HOUSE
OF MR.M.D.P.H.MANATHUNGA AT 298/8,1ST MAKEDIN MAWATHA,HABARAKADA ESTATE
,HABARAKADA,HOMAGAMA

GRAND - SUMMARY BOQ Value


BILL NO. 01
SUB STRUCTURE Rs. 903,283.89

BILL NO. 02
GROUND TO FIRST FLOOR LEVEL (Supper Structure) Rs. 3,067,416.98

BILL NO. 04
PLUMBING WORK Rs. 116,575.00

BILL NO. 05
ELECTRICAL WORK Rs. 199,325.00

TOTAL Rs. 4,286,600.87


BILL OF QUANTITIES FOR PROPOSED ADDITIONS & ALTERATIONS OF EXISTING HOUSE OF
MR.M.D.P.H.MANATHUNGA AT 298/8,1ST MAKEDIN MAWATHA,HABARAKADA ESTATE
,HABARAKADA,HOMAGAMA

BILL NO. 1 - SUB STRUCTURE

ITEM DESCRIPTION UNIT QTY. RATE AMOUNT


B - EXCAVATION & EARTH WORKS

B1 Excavation any material other than rock


requiring blasting in pits not exceeding
1000 mm deep commencing at existing ground
level including back filling consolidating
and disposing surplus materials as directed.
a) Column bases. Cube 2.12 6,000.00 12,700.80

b) Foundation treanches. Cube 10.00 6,000.00 60,000.00


c) Stair case bases. Cube 0.60 6,000.00 3,600.00

B2 Consolidated approved dry earth filling under


floors in layers not exceeding 6" thk. watered
well rammed and consolidated. Cube 15.00 7,500.00 112,500.00
Total carried to Summary Rs. 188,800.80
C - CONCRETE WORK

50 mm thk. Grade 15 mass concrete

C1 Under foundation. Sqr 2.15 11,617.00 24,976.55

C2 Under column bases. Sqr 0.32 11,617.00 3,717.44

C3 Under stair case bases. Sqr 0.15 11,617.00 1,742.55

75 mm thk. Grade 15 mass concrete

C4 Ground floor slab. Cube 1.00 45,000.00 45,000.00

Reinforce cement concrete in grade 25,


fill in to form work and well packed
around reinforcement.
C5 Column bases. Cube 2.65 55,000.00 145,750.00

C6 Columns up to D.P.C. level. Cube 0.85 55,000.00 46,750.00

C7 Plinth beams. Cube 3.75 55,000.00 206,250.00

C8 Staircase. Cube Nil 8,050.00 Nil

Tor steel bar reinforcement

Rate shall include for bends, hooks, typing


wires, distance, blocks and ordinary spaces etc.

Y10 - Y25

C9 Column bases Kg. 65.00 365.00 23,725.00

C10 Columns up to D.P.C. level Kg. 52.00 365.00 18,980.00

C11 Plinth beams Kg. 150.00 365.00 54,750.00

C12 Staircase Kg. 60.00 365.00 21,900.00


BILL OF QUANTITIES FOR PROPOSED ADDITIONS & ALTERATIONS OF EXISTING HOUSE OF
MR.M.D.P.H.MANATHUNGA AT 298/8,1ST MAKEDIN MAWATHA,HABARAKADA ESTATE
,HABARAKADA,HOMAGAMA

BILL NO. 1 - SUB STRUCTURE

ITEM DESCRIPTION UNIT QTY. RATE AMOUNT

Mild steel bar reinforcement

C13 In Column. Kg. 10.59 365.00 3,865.35

C14 Plinth beam. Kg. 81.18 365.00 29,630.70

Sawn timber form work

Rate shall inclusive fixing and removing.

C16 Columns up to D.P.C. level Sqr 0.50 18,122.00 9,061.00

C17 Plinth beams Sqr 1.00 18,122.00 18,122.00

Total carried to summary Rs. 654,220.59


D - MASONARY
D1 Random rubble masonary in cement and
sand 1:5 using 6" x 9" broken stone in
foundation. Cube 1.60 35,400.00 56,640.00
Total carried to Summary Rs. 56,640.00

E - DAMP PROOF MEMBRANE


E1 Provide vapour barrier comprising 1000G
plythene on top of compacted and prepared
under floor with 100mm sides & end laps. Sqr 3.15 1,150.00 3,622.50
Total carried to summary Rs. 3,622.50
BILL OF QUANTITIES FOR PROPOSED ADDITIONS & ALTERATIONS OF
EXISTING HOUSE OF MR.M.D.P.H.MANATHUNGA AT 298/8,1ST MAKEDIN
MAWATHA,HABARAKADA ESTATE ,HABARAKADA,HOMAGAMA

BILL NO.1 - SUB STRUCTURE Rs. BOQ Amount

B EXCAVATION & EARTH WORKS Rs. 188,800.80

C CONCRETE WORK Rs. 654,220.59

D MASONARY Rs. 56,640.00

E WATER PROOFING Rs. 3,622.50

Total carried to Grand Summary Rs. 903,283.89


BILL OF QUANTITIES FOR PROPOSED ADDITIONS & ALTERATIONS OF EXISTING
HOUSE OF MR.M.D.P.H.MANATHUNGA AT 298/8,1ST MAKEDIN
MAWATHA,HABARAKADA ESTATE ,HABARAKADA,HOMAGAMA
BILL NO. 2 - GROUND TO FIRST FLOOR LEVEL

ITEM DESCRIPTION UNIT QTY. RATE AMOUNT


Supper Structure

C - CONCRETE WORK
Reinforced cement concrete in
grade 25, fill into formwork and well
packed around Reinforcement.

C1 In slab 125 mm thk. at First floor level. Cube 3.83 55,000.00 210,453.71

C2 In beams at First floor level. Cube 2.50 55,000.00 137,500.00

C3 In columns upto First floor level. Cube 1.24 55,000.00 68,062.50

C4 In Staircase. Cube 1.00 55,000.00 55,000.00

Note:
Rate shall include for bends, hooks, tying wires,
distance blocks and ordinary spacers etc.

C5 In slab at First floor level.


(a) Y10 - Y25 Kg. 1,000.00 350.00 350,000.00

C6 In beams at First floor level Y10 - Y25 Kg. 650.00 350.00 227,500.00

C7 In column upto First floor, Y10 - Y25 Kg. 400.00 350.00 140,000.00

C8 In stair cases, Y10 - Y25 Kg. 85.00 350.00 29,750.00

Mild Steel Bar Reinforcement

C9 In columns, R6 - R10 Kg. 15.00 350.00 5,250.00

C10 In beams at First floor Level R6 - R10 Kg. 68.00 350.00 23,800.00

Form work for RCC work


C11 Vertical sides of columns upto to First floor level. Sqr 6.60 18,122.00 119,605.20

C12 Edges and soffits of First floor slab. Sqr 9.11 18,122.00 165,091.42

C13 Soffits and sides beams, at First floor. Sqr 5.00 18,122.00 90,610.00

C14 Sides and sofit of staircase. Sqr 1.00 20,000.00 20,000.00

Lintels

1:2:4(3/4") cement concrete including


reinforcement & form work
BILL OF QUANTITIES FOR PROPOSED ADDITIONS & ALTERATIONS OF EXISTING
HOUSE OF MR.M.D.P.H.MANATHUNGA AT 298/8,1ST MAKEDIN
MAWATHA,HABARAKADA ESTATE ,HABARAKADA,HOMAGAMA
BILL NO. 2 - GROUND TO FIRST FLOOR LEVEL

ITEM DESCRIPTION UNIT QTY. RATE AMOUNT

C15 225 x 150 mm lintols reinforced with 2 nos


10 mm dia. Tor steel bars & 6 mm
mild steel stirrups at 150 mm centers ft 125.00 1,550.00 193,750.00

C16 -ditto- but 113 x 150 mm lintols m nil 0.00 nil

Total carried to Summary Rs. 1,836,372.83

D - BRICK / BLOCK WORK

Common burnt work bedded and


jointed in 1:5 cement and sand mortar

D1 225 mm tk. external and internal walls Sqr 11.45 48,327.00 553,344.15

Total carried to Summary Rs. 553,344.15

H- DOORS & WINDOWS

All timber for doors should be


in "jack" or approved Class 1 timber.
Frames to be 100 x 75 mm Class I timber framed &
sashes 28 mm thick, timber to be true to sizes
without any defects and complete to working order.

Rates shall include for planning, rebating


& joining including fixing glass
where necessary timber beadings
supplying & fixing all iron mongery
in Dorset or similar Lever locking arrangements
hold fasts, spur stones etc. all complete
as per the detail drawings, specifications &
complete to working order.

arrangements & all the fixtures & accessories


should be approved by the consultants. Taking
actual dimensions of the opening is the
responsibility of the contractor.

Painting on all timber surfaces with one


coat of dye & sanding sealer & 02 coats of
"SAYERLACK" (Local Agent JAT Holding)
exterior or Interior stain & top coat .

All details to be referred as per detail


drawings. etc. fixed complete to approval.

DOORS
BILL OF QUANTITIES FOR PROPOSED ADDITIONS & ALTERATIONS OF EXISTING
HOUSE OF MR.M.D.P.H.MANATHUNGA AT 298/8,1ST MAKEDIN
MAWATHA,HABARAKADA ESTATE ,HABARAKADA,HOMAGAMA
BILL NO. 2 - GROUND TO FIRST FLOOR LEVEL

ITEM DESCRIPTION UNIT QTY. RATE AMOUNT

H1 Supply & fix Door type D2 overall size 3'0" x 8'0",4"x 3" Nos. 1.00 45,000.00 45,000.00
timber framed 1 1/4" single sashed plywood door sash as
per the drawing with necessory fittings & locking
arrengement

H2 Supply & fix Door type D3 overall size 3'0" x 7'0",4"x 3" Nos. 1.00 40,000.00 40,000.00
timber framed 1 1/4" single sashed plywood door sash as
per the drawing with necessory fittings & locking
arrengement

H3 Supply & fix Door type D4 overall size 2'6" x 7'0",4"x 3"
timber framed 1 1/4" single sashed plywood door sash as
per the drawing with necessory fittings & locking
arrengement Nos. 1.00 40,000.00 40,000.00

H4 Allow item for supply & install windows Item 1.00 100,000.00 100,000.00

Total carried to Summary 225,000.00


K - FLOOR FINISHES

Isolated areas, staircase areas, narrow


widths such as returns, reveals jambs
and alike are not measured separately.
All tile edges shall be jointed with miter
joints.
K1 3/4" thick rendering in cement red colour pigments and
sand 1:2 in coloured cement floors
Finished smooth Sqr 10.00 9,100.00 91,000.00
Total carried to Summary 91,000.00
L - WALL AND CEILING FINISHES

Note.
Isolated areas, staircase area, narrow
widths such as returns, reveals jambs
and alike are not are not measured separately.

Internally

16 mm Thick 1:1:5 cement lime and sand


plaster finished smooth with lime putty.

L1 To walls and columns. Sqr 23.00 9,000.00 207,000.00

Externally

16 mm Thick 1:1:5 cement lime


plaster finished semi rough

L3 To walls and columns. m2 17.00 9,100.00 154,700.00

Total carried to Summary 361,700.00


BILL OF QUANTITIES FOR PROPOSED ADDITIONS & ALTERATIONS OF
EXISTING HOUSE OF MR.M.D.P.H.MANATHUNGA AT 298/8,1ST MAKEDIN
MAWATHA,HABARAKADA ESTATE ,HABARAKADA,HOMAGAMA

BILL NO. 2 - GROUND TO FIRST FLOOR LEVEL

Supper Structure Rs. BOQ Amount

C CONCRETE WORK Rs. 1,836,372.83

D BRICK / BLOCK WORK Rs. 553,344.15

H DOORS & WINDOWS Rs. 225,000.00

K FLOOR FINISHES Rs. 91,000.00

L WALL AND CEILING FINISHES Rs. 361,700.00

Total carried to Grand Summary Rs. 3,067,416.98


BILL OF QUANTITIES FOR PROPOSED ADDITIONS & ALTERATIONS OF EXISTING HOUSE OF
MR.M.D.P.H.MANATHUNGA AT 298/8,1ST MAKEDIN MAWATHA,HABARAKADA ESTATE
,HABARAKADA,HOMAGAMA

BILL NO.4 - PLUMBING

Item DESCRIPTION UNIT QTY. RATE AMOUNT


PLUMBING WORK
Note :

Sanitary fixtures and Fittings

Unless otherwise specified all sanitary


fittings and fixtures shall be of American
standard, Toto, or approved equivalent.

All fittings to be completed with water


supply and disposal connections to
working order.
(all fittings supplied by the client)

J-01 Fixing of Pedestal type of water closet coloured


to the Architect's approval, including cistern
accessories such as WC connector, flush pipe, seat
cover approved angle valves and flexible connector
installed. Complete to working to working order. Nos. 1.00 15,000.00 15,000.00

J-03 Fixing of wash basin counter top model


(approx. size 615mm x 415mm) coloured to the
architect's approval with all accessories such as waste
plug, chain approved type plastic bottle trap, angle
valve flexible and Grohe type mixer taps connection
installed. Complete to working Order. Nos. 1.00 7,000.00 7,000.00

J-04 Fixing of chromium plated head shower spray


with control valve including wall mounted tap
installed complete to working order. Nos. 1.00 4,500.00 4,500.00

J-08 Fixing of approved quality hand spray bidet


comprising flexible chromium plated hose, angle
valve and installed to working order. Nos. 1.00 1,500.00 1,500.00

Note :-
Piping shall be measured to the
net length along the center line of
the pipes over all bends, junctions,
tees and the similar pipe fittings
and shall be given in feet. The size
of PVC pipes and specials are
specified by the external dimensions.

All water supply pipes shall be of


UPVC type 1000 with solid welded
of UPVC type 600 with solvent welded joints

The prices to include for screws, nails,


pipes hooks, saddles, brackets
connections nipples and the like
holes, chasing etc. Unless otherwise
specified. Separately should be
deemed to have included in the
relevant items.

priyal2
BILL OF QUANTITIES FOR PROPOSED ADDITIONS & ALTERATIONS OF EXISTING HOUSE OF
MR.M.D.P.H.MANATHUNGA AT 298/8,1ST MAKEDIN MAWATHA,HABARAKADA ESTATE
,HABARAKADA,HOMAGAMA

BILL NO.4 - PLUMBING

Item DESCRIPTION UNIT QTY. RATE AMOUNT


J-18 Supply and fix 1" dia. gate valve. Nos. 1.00 2,600.00 2,600.00

Distribution pipe system as per drawings


laid through ducts, buried and chased in
to walls as indicated from the storage tank.

J-21 40 mm. dia. pipe Mtr. 10.00 525.00 5,250.00

J-22 32 mm. dia. pipe Mtr. 10.00 375.00 3,750.00

J23 25 mm. dia pipes Mtr. 10.00 225.00 2,250.00

J-24 20 mm dia. pipes Mtr. 10.00 200.00 2,000.00

J-25 Pegler or approved quality brass stop valves as


indicated below.

a] 1 1/4" dia. stop valve Nos. 1.00 2,750.00 2,750.00

Internal Drainage
J-26 40 mm dia. waste pipes from wash basins to
outlets, buried & chased in walls. Mtr. 5.00 525.00 2,625.00

J-27 50 mm dia. waste pipes from shower areas,


sinks etc. to the outlets. Mtr. 10.00 625.00 6,250.00

J-28 63 mm dia. waste pipes including bends, tees


and socketted joints. Mtr. 10.00 700.00 7,000.00

J29 UPVC moulded good quality trapped gully fixed


to floor floor slab and finished smooth with neat
cement floating and stainless steel grating cover. Nos. 1.00 1,500.00 1,500.00

J-32 110 dia. UPVC pipes from toilet to manhole laid


through ducts, above floors, and buried as shown
in the drawings. Mtr. 10.00 4,500.00 45,000.00

J-34 Waste water manhole internally 300x300. Built in


75mm thk R.C. walls reinforced with 6 mm dia,
bars, Concrete mix 1:2:4 (20) Nos. nill 3,250.00 nill

J-35 Sewer manhole size internally 600x600 mm depth


exceeding 1m including excavation. Built in 225 mm thk
Brick work in cement and sand 1:5 mortor and 1:3
cement rendering with RC cover slab. Nos. 2.00 3,800.00 7,600.00

J-37 Sewer interceptor man hall size internally 750x600 mm depth


exceeding 1m including excavation. Built in 225 mm thk
Brick work in cement and sand 1:5 mortor and 1:3
cement rendering with RC cover slab. Nos. 1.00 -

J-38 Construction of septic tank internally


2000 mm x900mmx1500 deep in 225mm brick
work in cement mortar 1:5 and internal rendering
1:3 cement plastering and as per details. Item. 1.00 10,000.00
Total Carried to Summery 116,575.00

priyal2
BILL OF QUANTITIES FOR PROPOSED ADDITIONS & ALTERATIONS OF EXISTING
HOUSE OF MR.M.D.P.H.MANATHUNGA AT 298/8,1ST MAKEDIN
MAWATHA,HABARAKADA ESTATE ,HABARAKADA,HOMAGAMA
BILL NO. 5 - ELECTRICAL

Item DESCRIPTION UNIT QTY. RATE AMOUNT


Notes

ELECTRICAL INSTALLATION
FINAL SUB CIRCUIT POINT WIRING

The wiring shall be in full rigid PVC conduits


with the conduit system providing a conti-
nuous and effective means of protection for
the wiring. The conduit system shall be
concealed in the building fabric and where
provided under a roof the conduit shall be
clipped to the roof memebers.

Supply all material and provide final Sub


Circuit point Wiring only for the following
outlets with 1 way Switch,3 Plate Ceiling
Rose,lamp fitting fixing charges with all
materials and excluding the cost of fitting
Wiring shallbe in 1.0mm2 PVC/CU cables + E
as specifiedand as shown in Electrical
Drawings.

Supply all material and provide final Sub


Circuit point Wiring only for the following
outlets with 1 way Switch,3 Plate Ceiling
Rose,lamp fitting fixing charges with all
materials and excluding the cost of fitting
Wiring shallbe in 1.0mm2 PVC/CU cables + E
as specifiedand as shown in Electrical
Drawings.

E-01 Pendant Lamp Nr 4 6,500.00 26,000.00

E-02 Supply all material and provide final Sub


Circuit point wiring only for the following
outlets with one way swith and connector,
lamp fitting fixing charges with all materials
and excluding the cost of fitting wiring shallbe
in 1.0 mm2 PVC/CU cables + E as specified
and as shown in electrical drawings.
a) Wall Lamp Nr 5.00 6,500.00 32,500.00
E-03 Supply all material and provide final Sub
Circuit point wiring only for the following
outlets with two way / intermediate switch
and connector, lamp fitting fixing charges
with all materials and excluding the cost of
fitting wiring shall be in 1.0 mm2 PVC/CU
cable + E as specified and as shown in
electrical drawings.

a) Wall Lamp Nr 8,500.00 0.00


b) Pendant Lamp Nr 8,500.00 0.00

E-05 Supply and install 1mm2 PVC Cable & 5Amp socket Nr 4.00 9,500.00 38,000.00
with all accessories in 230v(including switch & socket)

E-11 MCCB'S

Supply and install TPN 4 Pole adjustable type


MCCB,steel encloser and netural link,
transformer type indicator lamps with all
accessories.

32 Amp Nr 1.00 26,250.00 26,250.00


BILL OF QUANTITIES FOR PROPOSED ADDITIONS & ALTERATIONS OF EXISTING
HOUSE OF MR.M.D.P.H.MANATHUNGA AT 298/8,1ST MAKEDIN
MAWATHA,HABARAKADA ESTATE ,HABARAKADA,HOMAGAMA
BILL NO. 5 - ELECTRICAL

Item DESCRIPTION UNIT QTY. RATE AMOUNT


E-13 DISTRIBUTION BOARDS

Supply and install flush powder coated/or


stove-enamel metal clador all insulated fitted
with

a) 40 Amp SPN 2 Pole isolater,RCCB,4 No. Nr 1.00 55,000.00 55,000.00


MCB's with MCB Distribution Board.

E-15 FEEDER CABLES

Supply all materials and install termination


following PVC/CU feeder cables drawn
through and protect by rigid conduits.

a) 2.5mm2 cable 2 wire and earth 2.5mm2. m 5.0 350.00 1,750.00

b) 6mm2 cable 2 wire and earth 6mm2. m 5.0 450.00 2,250.00

c) 6mm2 cable 4 wire and earth 6mm2. m 5.0 515.00 2,575.00

EARTH

E-16 Supply and install Earth cable, accessories


and heavy duty 50mm dia 1800 mm
G.I. Electrode driven in the ground Nr 1.0 15,000.00 15,000.00

Total carried to Grand Summary Rs. 199,325.00