Work order Maintenance object Maintenance object name

108769 11HAD EVAPORATOR SYSTEM


108770 12HAD EVAPORATOR SYSTEM
108771 13HAD EVAPORATOR SYSTEM
105923 18GML10 PROCESS DRAIN SYS - CONDENSOR PIT
106765 18MAL DRAIN AND VENT SYSTEMS
Description Planned start date Planned end date Status Jobtype
VISUAL INSPECTION ON EVAPORATOR SYSTEM 6/8/2023 9:00 6/8/2023 17:00 INI INS
VISUAL INSPECTION ON EVAPORATOR SYSTEM 6/8/2023 9:00 6/11/2023 17:00 INI INS
VISUAL INSPECTION ON EVAPORATOR SYSTEM 6/8/2023 9:00 6/9/2023 17:00 INI INS
VALVE STEM REGREASING 6M 6/9/2023 9:00 6/9/2023 17:00 INI PM
VALVES STEM REGREASING 6M 6/9/2023 9:00 6/9/2023 17:00 INI PM
Planning Status Planning window IPG P Position key Jobcode Responsible
No 4 11HAD 50 RUN/NO RISK 1.1.03.200
No 4 12HAD 50 RUN/NO RISK 1.1.03.200
No 4 13HAD 50 RUN/NO RISK 1.1.03.200
No 4 18GML10 50 RUN/NO RISK 1.1.03.200
No 4 18MAL 50 RUN/NO RISK 1.1.03.200
Work suppliers Skipped Rel.Delay Abs.Delay Approval status Planned hours Extra WO info
1.1.03.205/1.1.03.214 0 -3% -1 2
1.1.03.204 0 -3% -1 1
1.1.03.208/1.1.03.211 0 -3% -1 4
1.1.03.208/1.1.03.211 0 -1% -2 4
1.1.03.208/1.1.03.211 0 -1% -2 4
Extra WO info2 Extra WO info3 Extra WO info4 Extra WO info5 Rel.Delay Org.Date Abs.Delay Org.Date
-3% -1
-3% -1
-3% -1
-1% -2
-1% -2
Original Start Date Ordered by Finish responsible Guaranty expire date
6/8/2023 MECH SECT
6/8/2023 MECH SECT
6/8/2023 MECH SECT
6/9/2023 MECH SECT
6/9/2023 MECH SECT