Professional Documents
Culture Documents
Kaleab Final
Kaleab Final
Kaleab Final
Declaration
I, kaleab worku 4th year Construction technology & management student in Addis
Ababa University EiABC campus declare that this report describe my four month
staying period from October 15/2018 to February 08/2019 in Bamacon
Construction nile source project found at bole japan & all writings in this
document contains things done by myself effort & I approve this by my signature.
Signature: _________________
Date:_____________________
KALEAB WORKU 1
FINAL INTERN REPORT 02/10/2019
Acknowledgment
First of I would like to thank God and his mother Virgin Merry for giving me the
opportunity to exercise. And the EiABC for providing this university industrial
linkage program in order to let us know what the real work environment would
like. During my two months I have been provided with the opportunity to ask
questions and materials and files we would like to refer.
I would like to thank the site engineers and general Forman for their
precious time and their willingness to let us know what we would like to
understand in detail. Moreover I would like to thank the PM Eng. gebre for giving
us his precious time to give us lectures on what we should know and understand
how the office work looks like and what we should do in site inspection as a
CoTM professional.
I will also want to thank my mentor MR Yihenew for giving me this chance,
General Worker ato alemu for answering my questions and brief explanation of
activities on site. And the office engineers Eng. Meron & hiwot for helping us in
questions we had and giving us any supporting files to refer to.
KALEAB WORKU 2
FINAL INTERN REPORT 02/10/2019
KALEAB WORKU 3
FINAL INTERN REPORT 02/10/2019
TITTLE PAGE
1 company profile 8
1.1Introduction 8
1.2 brief history 8
1.3 mission statement 8-9
1.4 services 9
1.5 organizational structure and work flow 9-10
1.6 duties of some staff members 10-12
1.7 past and present performance 12-13
1.8 major items of machinery 13-16
1.9 some projects in hand and completed 17
2 overall internship experience 18
2.1 how I got in to the company 18
2.2 project information 18-19
2.3 the workflow in the site 20
2.4 the section of the company that I have been working 20
2.5 work tasks that I had been performing and its procedures 21
2.5.1 office works 21-24
2.5.2 site works 24
2.5.2.1 earth works 24-27
2.5.2.2 formwork for grade beam 27
2.5.2.3 hard core filling 28
2.5.2.4 floor drain pipe installation 28-29
2.5.2.5 lean concrete work above hard core 30
2.5.2.6water proofing 30-32
2.5.2.7water proofing above DPM of the slab 33
2.5.2.8 reinforcement for grad beams 33
2.5.2.9slab reinforcement placing 33-37
2.5.2.10concrete pouring steps 38-39
2.5.2.11 ditch construction 40
KALEAB WORKU 4
FINAL INTERN REPORT 02/10/2019
TABLE OF CONTENTS
Table of figures
TITTLE PAGE
Fig 1 finished and ongoing projects 17
Fig 2 earth work equipment’s 25
Fig 3 compaction machines and tests 26
Fig 4 block formwork 27
Fig 5 hardcore construction 28
Fig 6 pipe elbows 29
Fig 7 pipe installation 29
Fig 8 lean concrete above hardcore 30
Fig 9 DPM work for beams 32
Fig 10 lean concrete above the DPM and grade beam reinforcement 33
Fig 11 slab reinforcement 34
Fig 12 cube test 36
Fig 13 slump test 37
Fig 14 concrete batching machine and shooter 38
Fig 15 distributing the concrete 39
Fig 16 slab finishing machine 39
Fig 17 starter bars 39
Fig 18 ditch construction 40
Fig 19 column construction 41
Fig 20 stair construction 44
Fig 21 lift formwork 46
Fig 22 ramp construction 47
Fig 23 slab reinforcement 49
Fig 24 perforated pipe laying 50
Fig 25 mat foundation 50
Fig 26 drilling a pile 51
KALEAB WORKU 6
FINAL INTERN REPORT 02/10/2019
List of tables
TITTLE PAGE
Table 1 past and present performance 12-13
Table 2 major items of machinery and equipment’s 13-16
Table 3 contracting parties 19
Table 4 format for takeoff shit 21
Table 5 format for bar schedule 22
Table 6 format for cost breakdown 23
Table 7 format for bill of quantity 23
Table 8 format for payment certificate 24
Table 9 %strength of concrete in different days 35
Table 10 compressive strength of concrete at 7th and 28 days 35-36
Table 11 recommended value of slump for different works 37
KALEAB WORKU 7
FINAL INTERN REPORT 02/10/2019
1, COMPANY PROFILE
1.1 INTRODUCTION
BAMACON Engineering PLC is a share, privately owned construction firm with a reliable
record of accomplishments and a bright prospect that matches its high aspiration. The
following volume is an attempt to profile that track record, the prospect and the aspiration
from its effective operating system springs.
This profile includes:-
Mission statement and brief history of BamaCon Engineering PLC
Its legal status
Its organizational structure and operating systems
Its existing capacity and experience
The inclusion of these elements in the profile, we presume, will give the concerned reader an
insight on the substance of BamaCon Engineering PLC.
1.2 Brief History
Established as a grade VII construction firm in 2005 using the name of the owner and
general manager as Girma Gelaw Building Contractor, BamaCon Engineering registered
with the ministry of infrastructure, has grown to be a very competitive Grade I Building
Contractor with favorable prospects for a role of excellence in the construction industry.
In the twelve years of its growth, the firm has always believed that capacity depends more on
organizational and human resource development than on equipment and finance.
In this belief, the firm has invested a significant portion of its time and money on:
▪ Retaining and developing a highly professional management team.
▪ Training and motivating its technical staff, from the craftsmen to the senior engineers, to
achieve and maintain high standards.
▪ Devising and practicing a modern and effective organizational structure.
▪ Solicit counseling and conduct selected research to assist in strategic planning.
▪ Devising and continuously improving on a system of operation that is guided by written
head office and project guide lines, both of which were the result of the combined efforts
of professionals of high standards.
▪ And the result has been a firm with a work force that can take on any challenge in the
form of a construction job.
With respect to capacity in terms of equipment, while acquisition of major machinery has
been dictated by the need to satisfy the regulatory body’s (ministry of infrastructure’s)
capacity requirements, special emphasis on equipment that are specifically appropriate to
BamaCon Engineering’s own method of construction were also sought and acquired.
Hitherto, financial capacity has always been commensurate to the cash flow requirements of
the projects.
This has been partly due to the firm’s good credit record with clients, insurance companies,
banks and construction material suppliers perhaps the most important creditors to any
construction firm.
Looking back, the path BamaCon Engineering PLC traveled over the last years seems to be a
path of initiation for the competitive challenges of the third millennium.
1.3 Mission statement
KALEAB WORKU 8
FINAL INTERN REPORT 02/10/2019
KALEAB WORKU 9
FINAL INTERN REPORT 02/10/2019
KALEAB WORKU 10
FINAL INTERN REPORT 02/10/2019
Site engineer
The site engineer controls all construction activities on the site starting from the very
beginning. Generally, the site engineer;
Office Engineer
The main responsibility of the office engineers are:-
Prepare material lists for the project and ensuring deployment.
Preparing payment certificates for sub contract works based on actual quantity
executed and Keep records of payments certificates related to the sub contract works.
KALEAB WORKU 11
FINAL INTERN REPORT 02/10/2019
Quantity Surveyor
He is a Surveyor the quantity of materials and prepares a bill of payment for each work item
Executed which is to be checked by the Office engineer and approved by the Project manager
Surveyor
He plays a significant for construction to proceed.
He/she has the responsibility to setting out and the elevation points according to design.
Data Collector
He is responsible to follow up and prepare a report on daily site work items execution.
Report daily data’s to the site engineer
Manage the complains from the site
Prepare monthly report
1.7 Past and Present Performance
The following table summarizes major construction jobs BamaCon Engineering PLC
took over the past four to five years which are relevant to the current job at hand
Table 1
KALEAB WORKU 12
FINAL INTERN REPORT 02/10/2019
(P)
Contract
MIXED-USE BUILDING S
1. Mixed-Use-A.A Ato Alemayehu Tameru 540 days 100 P
2. Mixed-Use –A.A Ato Mesfin Mengesha 730 days 100 P
3. Mixed-Use –A.A OMEDAD PLC 1,095 days 100 P
4. Mixed-Use –A.A NEHCO Trading PLC 720 days 100 P
5. Mixed-Use –A.A Ato Jonny Seifu 730 days 100 P
6. Mixed-Use-A.A Afework Int. Group 540 days 100 P
7. Mixed-Use-A.A Atkilt Tera Mar. Center 1,080 days 89 P
8. Mixed-Use-A.A Dagi PLC 450 days 100 P
9. Mixed-Use-A.A Military Tera Merchants 420 days 100 P
S.Co.
10. Mixed-Use -AA Admas Zemenawi 610 days 93 P
11. Mixed-Use -AA Ato Bahiru Abraham 540 days 100 P
Ethiopian Evangelical 365 days 100 P
12. Mixed-Use -AA Church Mekane
Yesus
13. Mixed-Use -AA Adika tour & Travel 365 days 100 p
14. Mixed-Use -AA Enat Real Estate 730 days 100 p
16. Mixed-Use -AA Emiru & Elizabeth 320 days 100 p
Business
HOTEL BUILDINGS
1. Saromaria Hotel Ato Alemayehu Nigussie 720 days 100 P
3. Hotel –A.A. Ato Habtamu Desta 545 days 100 P
4. Hotel –A.A. Alemgenet Trade & 730 days 57 P
Industry
5. Hotel –A.A. Ato Ayele G/medhin 140 days 100 P
APARTMENT BUILDIN GS
1. Apartment-A.A Ene Tsehaye Zemui 300 days 100 P
2. Apartment -AA AL SAM PLC 570 days 43 P
3. Apartment-AA SACUUR Real Estate 450 days 38 P
PLC
HOSPITAL BUILDING S
1. Hospital-A.A Ato Berhane Dagnew 240 days 100 P
FACTORY BUILDINGS
1. Factory- B IHRAK Int. PLC 240 days 100 P
2. Factory -B STEELY RMI 365 days 100 P
3. Factory -B Kanoria Textile 600 days 100 P
KALEAB WORKU 13
FINAL INTERN REPORT 02/10/2019
OFFICE BUILDINGS
1. G+3 Office Rwanda Embassy 365 days 100 P
SUBSTATION PROJEC TS
1. Shegole Ethiopian Electric Power 180 days 47 SC
Substation Project -CONCO
2. Bako Substation Ethiopian Electric Power 300 days 10 SC
Project – POWER CHINA
1.8 Major Items of Machinery and Equipment
Table 2
Ite Year of
Qt Owner
m Equipment Type Brand Manuf’re Capacity
y ship
No.
A. Vehicles
Toyota, Japan 2008 10 qtl 9 Owned
Toyota, Japan 1986 10 qtl 3 Owned
1. Pickup
Mitsubishi, 2008 10 qtl 3 Owned
Japan
Nissan UD, 2006 14 m3 4 Owned
Japan
Mitsubishi, 2006 14 m3 4 Owned
Japan
IVECO 330-36, 2012 18 m3 3 Owned
2. Dump truck (Double Axle) Italy
IVECO 2012 18 m3 2 Owned
ASTRA, Italy
EURO 2012 18 m3 2 Owned
TRAKKER
Fiat, Italy 1987 10 m3 4 Owned
3. Truck SCANIA 2012 2 Owned
Power, Europe
4. Truck and Trailer (High 2012 4 Owned
Bed)
5. Truck and Trailer (Low VOLVO 2010 2 Owned
Bed)
ISUZU, Japan 2008 30 qtl 2 Owned
6. Medium Truck
ISUZU, Japan 2010 30 qtl 3 Owned
7. Automobile Toyota, Japan 2005 - 5 Owned
KALEAB WORKU 14
FINAL INTERN REPORT 02/10/2019
B. Machineries
1. Tower Crane Simma GT183 , 2002 50m 2 Owned
Italy arm& 6
T
KATO , Japan 1995 10 Ton 3 Owned
2. Mobile Crane
XCMG,China 2008 25 Ton 2 Owned
3. Manitou 2012 2 Owned
4. Dump Truck with Crane 2010 15 Ton 3 Owned
5. Fixed construction Service Ethiopia 2012 1 Ton 35 Owned
lift
5’. Dozer CAT 2008 1 Owned
CAT-DL320 1991 104 Hp 1 Owned
Chain Excavator
6. CAT-DL320 2008 140HP 4 Owned
Bin Ford 1989 5 Ton 1 Owned
CATERPILLA 2013 14 Ton 2 Owned
R
Roller BITELLI DTV 2012 2 Owned
7.
85
2006 10 Ton 1 Owned
BOMAG
2012 14 Ton 2 Owned
Heavenly ZL 2002 5 m3 1 Owned
8. Loader 15C
XGMA 2012 3 m3 2 Owned
Casagrande 2008 2 Owned
9. Hydraulic Crawler Drill B180HD
Bauer C-130 2013 2 Owned
10. Tieback/Micro pile Machine Casagrande C6 2008 4 Owned
OCMER 48 2008 2 Owned
11. Shotcrete Machine MEDIA
2012 2 Owned
12. Grouting Machine 2008 High 3 Owned
Pres.
13. Finisher Power BITELLI BB50 2012 4 Owned
Ite Year of
Qt Owners
m Equipment Type Brand Manuf’r Capacity
y hip
No. e
B. Machineries
KALEAB WORKU 15
FINAL INTERN REPORT 02/10/2019
KALEAB WORKU 16
FINAL INTERN REPORT 02/10/2019
16,500m2
4. Slab Scaffolding Coverage - Owned
Area
Wood 800pcs - Owned
5. I-Beam for Formwork
Aluminum 600pcs - Owned
1000m2
Scaffolding for
6. Steel Coverage - Owned
Plastering
Area
China 2007 15Kva 15 Owned
7. Generator
China 2007 75Kva 1 Owned
Reinforcement bar
8. China 2006 12-24 2 Owned
bending machine,
9. Mechanical HCB China 2007 1000pc/day 2 Owned
making machine,
8000 lit 2 Owned
10. Water tanker 5000 lit 4 Owned
1000 lit 4 Owned
KALEAB WORKU 17
FINAL INTERN REPORT 02/10/2019
Project: - OMEDAD mixed use building Fig 1 Finished and ongoing projects
Location: - bole, olompia
project status: - 100%complited.
KALEAB WORKU 18
FINAL INTERN REPORT 02/10/2019
KALEAB WORKU 19
FINAL INTERN REPORT 02/10/2019
The company is a well-organized one with a lot of educated as well as skilled manpower.
Site man power organization
Site engineer
Office engineer
Intern student
Foremen
Data collector
Consultants
Daily laborers
2.5 Work tasks that I had been performing and procedures followed
KALEAB WORKU 21
FINAL INTERN REPORT 02/10/2019
KALEAB WORKU 22
FINAL INTERN REPORT 02/10/2019
diameter squered
Factor =
162
2. Cost breakdown
▪ Cost breakdown is a process of finding the resources needed to accomplish a certain
task, then to get the total cost of the activity per specified unit.
▪ It includes:-
• Manpower for a specified task
• Material “
• Equipment “
• And other indirect costs
▪ Cost is calculated by taking equipment’s as rental, and 30% overhead costs.
KALEAB WORKU 23
FINAL INTERN REPORT 02/10/2019
▪ The amount of cost for skilled laborers, materials and equipment’s will be added and is
called direct cost. 30% of direct cost is taken to be overhead cost to account employees
at head office and other engineers.
▪ Finally direct cost and overhead cost are summed to give total cost.
▪ The profit is calculated by subtracting total cost from income. The aim of the breakdown
is to know the loss and profit of the company.
Table 6
3. Bill of quantity
▪ It is called bill of quantity. It includes the type of quality, the amount of the quantity, the
rate and the cost.
▪ The rate is the price for a unit amount of quantity which was handed.
▪ The rate is the result of the breakdown, since I did breakdown so I had been taking the
rate from the table of break down that I have been calculated earlier.
Format for bill of quantity Table 7
4. Payment certificate
▪ Payment certificate is a certificate describing the previous payments that the contractor
receives, penalties and the current payment requiests.it includes:-
Retention:-from each cumulative work executed the client take 5% to make the
contractor to repair defects.
50%of the 5% released @ provisional acceptance period.
The remaining 50% is released @ final acceptance period.
Previous payment: - the summation of previously paid amounts.
KALEAB WORKU 24
FINAL INTERN REPORT 02/10/2019
Rebate: - the amount that the contractor discount from each activities.
Advance payment: -amount paid for the contractor for unexecuted works it can be
for starting or if the contractor face financial problem.
Advance repayments: - the contractor will pay the division of advance payment at
each payments.
Materials on sites:-the materials stored in site that the contractor purchased but not
used, if the contractor wants to facilitate the construction he can pay for that.
Liquidated damages :-the amount that the contractor penalized,
Due to delay the penalty is 0.1% of the contract amount per day.
If the liquidated damage reaches 10% the client may terminate the
contractor. Table 8
KALEAB WORKU 25
FINAL INTERN REPORT 02/10/2019
1. Cart away: - Cart away is the disposal of unsuitable or surplus excavation material to an
appropriate site.
It includes stockpiling, loading, transporting, dumping and wheel spreading. At our site,
cart away material not only included excavated soil but also selected material that was
rendered useless due to perched water that was close to the surface, and made the selected
material muddy. This made may cause crack in the grade beam so, they are agreed to
dispose the top filled layer and fill with another selected material.
Problems
When we enter the site at the first time the workers are busy by transporting cart away.
The cart away was transported manually by the daily laborer with the smaller lifts which
is very low productivity.
Recommendations from us:-
1. Why didn’t uses movable crane to transport/remove the cart away from the site?
Their response is there is an obstacle municipal Electric line due to this reason we choose
the manual transportation.
We asked that why they don’t install the electric line underground unless it causes other
problems.
2. The second way is giving the cart away for a group of works other than daily laborers
of the site as a contract by fixing time of completion so it worked it facilitate other works
to be done.
2. Selected excavated fill - Suitable non expansive material approved by the Engineer
for excavation and capable of being compacted to form a stable filling having side slopes as
indicated on drawings or directed by the Engineer.
The selected fill is filled up to 60 cm bellow the floor finish level because, the depth from
the lean concrete to the floor finish level is 60 cm.
Fig 2 Backhoe loader cart away material dump truck dumping selected
material
4. Compaction: - compaction is the process of compressing the filled material to avoid its air
space inside and to increase its resistance to loads.
KALEAB WORKU 26
FINAL INTERN REPORT 02/10/2019
Compaction test
It is also called filed density tests, the objective of test to determine the dry density, wet
density, and OMC of compacted soil on site and to determine the percent of compaction.
In my site we used the Sand cone which is the best one for quality control and acceptance
testing for construction. During this test the soil was excavated through the center hole of the
plate until 15cm depth. Then the sand was replaced in place of the excavated soil. The
excavated soil was burned to know its moisture content. After the test is finished, the tests
give value of;
A. Degree of compaction is determined
B. Moisture content
C. Dry density
Soil test for moisture content test of selecting material procedure:-
KALEAB WORKU 27
FINAL INTERN REPORT 02/10/2019
Lean concrete is used for protecting the reinforcement of the beam from direct contact with
the soil, which helps it from being rusted and also for giving a flatbed for the beam and block
formwork.
In our site one of the new thing is that the form work for the beam is HCB block. Therefore
the lean concrete is wide because it is used as a bed for the block.
After the compaction is finished then we have placed 5cm thick and c-15 lean concrete
with a width of 68cm.this is because the width of the beam is 28cm wide and the total
width of the two side blocks is 20+20cm=40cm,therefore the lean concrete width will be
40cm+28cm=68cm.
KALEAB WORKU 28
FINAL INTERN REPORT 02/10/2019
Fig 4 Center of the beam axis lean concrete for the block formwork block
formwork
2.5.2.3, Hardcore construction
Hardcore is filled after the beam form work is constructed it is used selected stone from the
quarry site up to 30cm thick. But not use the stone gained from the site when they are
digging because of this stone is not strong and suitable since it gets from consolidation of
the soil & it loses their strength.
Its purpose;-
As it is filled in random manner no stone will be vertical up so the ground water flow
down by the sloped placed stone.
To fill the beam area up to slab to avoid direct contact slab and soil.
To support the ground slab.
First fill the larger size of stone and then the top of the stone greater than 30cm was crasher
by using hammer and fill large holes to level & save the concrete usage.
KALEAB WORKU 29
FINAL INTERN REPORT 02/10/2019
KALEAB WORKU 30
FINAL INTERN REPORT 02/10/2019
Fig 7 Using fire to melt the pipe closing the pipe process
2.5.2.5 Lean concrete work above hardcore
The hard core size is 30cm so it drops 5cm from height of the block formwork so we fill the
5cm c-15 lean concrete which is not structural used to strengthen the hardcore and to give
flat surface to install DPM and slab.
The lean concrete work is done by using a wooden purlin 5*3 cm “riga”
C. Water in the soil causes hydrostatic pressure to be exerted underneath basement floors
and walls. This hydrostatic pressure can force water in through cracks, which can cause
major structural damage as well as mold, decay, and other moisture-related problems
o In our site there are 3 membranes.
3, protection boards
It is differ by, it is harder and used for protecting the inner DPM.
Construction mechanisms of DPM
There are two types of water proofing
A, positive side water proofing.
B, negative side water proofing
A, positive side water proofing.
Is a water proofing system that the DPM is plated on the side that the water comes before
passing the structure.
KALEAB WORKU 32
FINAL INTERN REPORT 02/10/2019
When we are at school, we learnt that when we bend a DPM it should not be 90 0 to protect
the DPM from cut so we should use 450cant strip (wooden or other materials).But in our site
there is 900 bending of a membrane for beams why this happens?
The response is;-
▪ The DPM in our site is the new one, which have f.f properties;-
200gm of pollster (mesh) exists in between layers which gives elastic properties not to be
cut, although it is bended, but the older one is only bituminized.
KALEAB WORKU 33
FINAL INTERN REPORT 02/10/2019
Bottom bars
KALEAB WORKU 34
FINAL INTERN REPORT 02/10/2019
The bottom bars overlapped at 1/3 of the effective span of the beam because it is area of
minimum tension.
Fig 10 lean concrete above the DPM reinforcement for the grade beam
KALEAB WORKU 35
FINAL INTERN REPORT 02/10/2019
Problems
Late delivery of concrete
Sometimes the concrete is very workable (more water) which causes; Decrease strength
of concrete and Segregation and flowing through joint of formwork.
▪ For our site cubical molds of size 15cm x 15cm x 15cm are used.
Step 1:-fill the cube with concrete fully
Step 2:-wait for the specified day of 1, 3, 7,14and 28.
The strength of concrete increases with age. Table shows the strength of concrete at
different ages in comparison with the strength at 28 days after casting. Table 9
1 day 16%
3 days 40%
7 days 65%
14 days 90%
28 days 99%
Step 3:- after the above days bring the sample to testing lab and apply the compressive force
then take the point of failure.
Step 4:-then calculate the compressive strength my dividing the failure load with contact
area of the cube.
Compressive Strength of Different Grades of Concrete at 7 and 28 Days Table 10
M15 10 15
M20 13.5 20
M25 17 25
M30 20 30
M35 23.5 35
M40 27 40
KALEAB WORKU 37
FINAL INTERN REPORT 02/10/2019
M45 30 45
fig 12 cube sample taking curing the sample cube tasting macine
b) Slump tests
A slump test is a method used to determine the consistency of concrete.
The consistency, sometimes described in terms of stiffness, generally indicates how much
water has been used in the mix.
The test allows builders and construction crews to get a good sense of how the mixed product
will perform in a variety of settings, and also gives them the opportunity to add either more
powder or more water in order to get the right balance.
Different projects have different specifications when it comes to concrete stiffness, and
testing the results is usually a lot more accurate than simply following prepared instructions
or making informed guesses.
How the Test Is Performed
Step 1:- the mold is shaped more or less like a cone that is missing its pointed end.
Step 2:-1.5 cm diameter metal rod is inserted into the filled cone and pumped up and down
about 25 times, mainly to remove air bubbles and settle the concrete.
KALEAB WORKU 38
FINAL INTERN REPORT 02/10/2019
Step 3:-Anything that is spilling over the top of the mold should be leveled off, and then the
mold is generally removed; without the support from the mold, the concrete slumps down
under its own weight. The amount of slumping is the most important thing.
Step 4:-The rod is then usually placed horizontally over the slumped pile of concrete and
balanced on the empty mold, which most measurers will set nearby. A ruler is used to
measure the distance between the rod and the concrete, which represents the height lost when
the concrete slumped down. This number is the “slump” for that particular batch of concrete.
Rating Specifications
In most cases, a slump of 2.5 to 7.6 cm indicates a very stiff mix and is the most suitable for
commercial work. A stiff mix like this can be really difficult to work with, and ordinarily it
requires a mechanical vibrator to get it to consolidate properly. It generally produces the
hardest and strongest concrete.
A slump of 10.1 to 12.7 cm is generally thought to be the most appropriate for residential
work, and pouring concrete is easier with this amount of slump. This sort of material can
usually be worked by hand, and it still results in strong concrete in most cases.
slump of more than 17.8 cm should not be used at all. In most cases it will be too runny to
set properly, and may lack a lot of the strength and durability people generally expect.
Fig 13 Sample taking by cone road bumping up and down measuring the slump
KALEAB WORKU 39
FINAL INTERN REPORT 02/10/2019
Table 11
10, Concrete pouring steps
▪ Step 1:-First we have to fix our pumping machine.
▪ Step 2:-fix the pumping pipe.
The pumping machine should be in a place where the mixer truck can reach.
When we fix the pumping pipe we can use different junction to connect two pipes and
also benders to change directions.
▪ Step 3:-The other task involved in laying the pipe is elevating the pipe up to some height to
make the concrete pouring easy, this is done by fixing pipe holders (kebelatos) up to 1m
high @ a certain spacing.
In our sites the holders are made of 3 steel bars, which gives better resistance to the
pumping pressure.
▪ Step 4:-Then after start pumping the concrete,
▪ Step 5:-when the concrete reaches the slab vibrators helps to distribute the concrete
through the area and to avoid air space or segregation.
KALEAB WORKU 40
FINAL INTERN REPORT 02/10/2019
KALEAB WORKU 41
FINAL INTERN REPORT 02/10/2019
KALEAB WORKU 42
FINAL INTERN REPORT 02/10/2019
KALEAB WORKU 43
FINAL INTERN REPORT 02/10/2019
Fig 18 Compaction for the ditch reinforcement for ditch finished ditch
2.5.2.12) Work methodologies for concrete column
Column layout work:-In this stage of works the location of columns are determined
practically in field. It is done by laying rope according to grids shown in the drawing and
then mark the location of columns related to rope. This is done for foundation column.
The footing is always poured before the column and contains metal "starter bars" that extend
out of its surface. As their name implies, these starter bars provide a place to fix the rebar or
steel bars that will reinforce the concrete itself.
Column Reinforcement work: After marking the column locations, we then start to place
reinforcement as instructed in the structural drawing. It can be placed by measuring
dimension from the center. For example our column is 40*60 so to place the reinforcement
measure half of 60 or 40 from the center then it gives 30 & 20 respectively then deduct the
spacer from that, so the spacer is 2.5 so the result is (20-2.5=17.5 & 30-2.5=27.5) thus the
reinforcement is placed in (35*55) place of the column from 40*60.
The bars should be tied together by stirrup and according to the drawing.
After stirrups, tie the spacer of the column
Reinforcement inspection as per drawing, lap length, correct lapping guidelines as per code.
Inspection for concrete cover to reinforcement.This is normally described in the drawing like
–C1-12#16 mm⌀ and stirrup-10 mm⌀ @ 100 c/c.that means column C1 will have 12
numbers of 16 mm diameter bar as vertical bar and 10 mm diameter steel should be placed
100 mm center to center as stirrup.
In this case we can determine the lap length by 40*D (where ‘’D’’ is diameter of bar.) As
our supervisor tells to us & from our last year class.
Column formwork: In building, floor height is normally kept 310cm. the slab has beam then
we have to pour concrete up to beam bottom level. Suppose, beam height specified in
drawing is 28cm. So, the casting height of our column will be 292cm. And our formwork
height will be 292cm.
First it must to make a cratury to keep formwork in place and in correct squadra. The cratury
is made from the column dimension.
As we have seen in the reinforcement it is also calculated.
KALEAB WORKU 44
FINAL INTERN REPORT 02/10/2019
our column is 40*60 so to place the cratury measure half of 60 or 40 from the center then it
gives 30 & 20 respectively then add the thickness of plywood which is 2cm. then the cratury
is in space of 32cm & 22cm respectively then to do fully the cratury is done out of or at the
line of 64*44.thenafter the four sides are checked by squadra.
Preparing column form work
Cover the form work by plastic or paint it by wax or olio
Then erect column formwork
The erected form work is attached by nail
Thus after this the formwork is braced by scaffolding known as curevat in its site name.
the diagonal bracings are attached to the ground by a wire.
Working a ladder for up lifting concrete
Finally before casting of concrete check the column alignment.
▪ First check the tumbi (bob) its vertical allignment with the ground. And Check the center to
center dimension with other column which is ligna.
KALEAB WORKU 45
FINAL INTERN REPORT 02/10/2019
wrapped in plastic to prevent it from drying out while it cures. Once it's "cured" completely,
the plastic is removed, and the construction crew can move onto the next phase of the project.
Curing Concrete which is moist cured for 7 days is about 50% stronger than uncured
concrete
2.5.2.13, RETAINING WALLS
▪ Line out the survey of retaining wall on the ground. Excavate the space of survey about 90cm
wide and to the desired depth of 30cm check that the soil's bearing capacity matches the
design specifications. Then Compact and level base laying of C15 lean concrete for the
purpose of reinforcement corrosion.
▪ Install steel reinforcement bars per the construction drawings using cover blocks and spacer
chairs to position them. This is done by deducting the spacer size which is 2.5 cm in one side.
So the formwork work continues after the spacer is placed at the reinforcement.
Check the tumbi (bob) its vertical alignment with the ground.
Working a ladder for up lifting concrete
After inspection, pour the concrete,
As we show in the last page once the concrete has hardened sufficiently, the formwork is
removed. Generally, this process takes 16_24 of hours. Site Engineers also have a variety
of tests they can use to determine whether the concrete is strong enough to remove the
forms. Finally, the concrete is wrapped in plastic to prevent it from drying out while it
cures. Once it's "cured" completely, the plastic is removed, and the construction crew can
move onto the next phase of the project.
Curing Concrete which is moist cured for 7 days is about 50% stronger than uncured
concrete
2.5.2.14, Staircases construction
▪ Stairs are set of steps leading from one floor to another and are provided in building to
afford a means of communication between the various floors.
▪ The primary function of stairs is to provide safe and easy means of travel between floor
levels.
▪ It is a stair with two flights which are connected a rectangular half. During construction
of stair we have to be careful and give more emphasis on the reinforcement detailing.
Step-1: The starting bar was started from the basement floor monolithically to increase
the strength of the concrete stair
Step-2: This we continued to place the scaffolding of the soffit of stair & landing
KALEAB WORKU 46
FINAL INTERN REPORT 02/10/2019
Step-3: This we placed the soffit formwork and landing formwork after this we placed the
reinforcement bar of the stair and landing
Step-4: This we placed the riser formwork along the tread checked by the Squadra &
Tumbi to attained in the correct position and dimension with equal distance
Step-5: The preparation of the riser formwork they casted the rebar with the shape of the
step of stair at the
Step-6: They cast the concrete & dry for two days they remove the riser and stringer
formwork & the soffit formwork was removed after seven days.
Step-7: They cure the concrete after waiting of the formwork was removed for 6 hours
STAIR DESIGN GUIDES: rules that govern the construction of stairs and our site reality
constructed were:-
• Equal rise for every step or landing was satisfied.
• Equal going for every parallel thread was satisfied.
• The going of a thread should not be less than 22 cm for ordinary buildings and 30 cm for
public buildings ours were 28cm it was ok!
• The rise of an ordinary stair should at least be 15 cm and not greater than 22 cm ours
were 17.5cm it was ok!
• At least 200 cm head room measured vertically above the pitch line
Top bar
Scaffoldin
g
Bottom
bar
Soffit
formwork
Rebar connected with floor Distribution Side
bar formwork/Stringer
KALEAB WORKU 47
FINAL INTERN REPORT 02/10/2019
Formwork for
stair
Concrete work for
Fig 20 stair construction stair
initial activity was correctly executed on the site the carpenters were checked the squadra and
tumbi carefully.
Step-1: Our lifts were constructed started equally with the foundation pad with the depth of
230 cm & the pad depth of the lift was 80cm which casted the lifts, the stair & garbage house
as a mat foundation pad.
Step-2: They constructed the retaining wall with in the specified place of the lifts, stair &
garbage house with the same level of the foundation column finished and the retaining walls
had a two types of board I.e. DPM and protective cover in the external wall side of the lift i.e.
the internal DPM was used for protected the water from entering to the lift or stair & the
outer coverage was used as a protection board of the DPM from damage.
Step-3: The reinforcement bar was executed around the wall position of the lift by
overlapping from the initial bar from the foundation shear wall with a proper dimension and
working drawing/ structural drawing ordered/ after the reinforcement bar was placed
Step-4: They placed the scaffolding and crachery around the lift area by keep leveling using
water leveling tool & hand leveling/ goma wuha lik & yeji wuhalik in site name.
Step-5: That placed the formwork/plywood on the crachery with checking of the squadra &
tumbi until the squadra and tumbi was 90o & straight and also checked the diagonal squadra
to place in correct position and braced diagonally to fix stand on
Step-6: This form work was the internal part of formwork and this form work was casted
with the steel scaffolding and diagonal bracing
Step-7: The form work was placed in the correct position the external formwork was
executed by keeping the squadra & tumbi of the internal formwork and external formwork
was supported and braced with the steel bracing RHS also passed door openings of the whole
doors.
Step-8: In order to prepared for the concrete work of the lift to anchored the internal and
external formwork to keeps them in place they were formed hole both sides and this hole was
anchored by tie rod with the outer covering using Conduit for the protection of the tie rod
from contacted with concrete which is used to protect the tie rod from corrosion & rust in
order to reuse for the other work/ activity.
Step-9: After we prepared this activity we cast the concrete using ready mix concrete with a
C-35 concrete grade the casting was using crane which is the site name of Kato.
Step-10: They removed the formwork from the lift after two days of casting period.
Step-11: After they cast the concrete and remove the formwork they also cure for 7 days
some builders on a tight schedule water cure for 3 days as this achieves approximately 80%
of the benefit of water curing for 7 days.
Then the steps were continuing from step four --------------------
KALEAB WORKU 49
FINAL INTERN REPORT 02/10/2019
KALEAB WORKU 50
FINAL INTERN REPORT 02/10/2019
Wires are used to tie main bar and shrinkage and temperature reinforcement
(distribution bar).
Step eight: - After all work is done and checked by the Forman and supervisor
Casting of C-35 ready mix concrete.
The last step is curing of the casted concrete for seven days in order to
maintain the desired strength.
Ramp formwork
with plywood
Ramp reinforcement main and
distribution bar respectively
from bottom
Ramp beam
reinforcement
Punching reinforcement
around the columns used
Z-shaped spacer
bar (kebalito)
KALEAB WORKU 51
FINAL INTERN REPORT 02/10/2019
▪ The material used for this purpose is steel. Vertical stringers have U shaped on the top used
to hold horizontal joists, X shaped on the middle used to resists the buckling of vertical
stringers it is used as inclined bracing. And it do have base plate used fix it on the bottom
slab that scaffolding is erecting.
▪ Step two: -installation of metal horizontal joist with center to center 50cm that used to
support and fix the formwork.
▪ Step three: - installation of formwork …. Formwork is the basic usable material on site,
about 50% of works is done with formwork. It also greatly used on construction projects
(works). It used to mold footing, columns, Beams, slabs etc.
▪ Step four: - As usual the bar man starts to put spacer gap (concrete cover) to create cover
between the formwork and reinforcement bar (main bar)
▪ Step five: -After the step four is done the bar man starts to put the bottom reinforcement bar
(main bar) with ф of 10mm and center to center 100mm then after top reinforcement bar is
reinforced with (1÷3) of the span have different ф of bar around the columns 14mm have
170mm c/c and it have negative bar with same diameter but 140mm c/c when come to
reinforcement bar outside column it has 12 in ф and 800mm top reinforcement ( main) and
170mm (dis) in center to center .
Plywood slab
formwork used
to create flat
KALEAB WORKU 52
FINAL INTERN REPORT 02/10/2019
KALEAB WORKU 53
FINAL INTERN REPORT 02/10/2019
Step 3:- Then place 5cm c-10 lean concrete which is not structural only to avoid direct
contact of the DPM and the ground.
Step 4:- DPM plating is continued after lean concreting.
Step 5:- place 7cm c-10 lean concrete above the DPM to protect the DPM from being
affected by the reinforcement of the mat slab.
Step 6:- place mat mesh with having higher diameter than usual like Ø20&24.
Step 7:- Mat slab reinforcement continued having a depth of 80cm.
Step 8:- Also construction of 2m high mat beam is continued, as it is submerged in the slab
its effective height is 1.2m.
Step 9:-Then the selected fill is to be filled up to the level of the mat beam.
KALEAB WORKU 54
FINAL INTERN REPORT 02/10/2019
As we have discussed above the grouting tube is closed and perforated in the length of
grouting this is for when we pump concrete inside as it is closed it comes back and flow
through the perforation so the grouted length will be filled, in our case it is 6m of the
drilled 13m.
After grouting the concrete we wait for 14 days of curing before post tensioning.
After the grout is cured we start tensioning using the tensioning machine with the extended
strand out of the pile (0.5m).
Then anchor the strands using anchoring plate.
Fig 28 Specific gravity test sound test for aggregate sieves and sieve shaker
The other thing is the batching plant which is consists of many huge bodes starting from
the inlet to the out let.
KALEAB WORKU 56
FINAL INTERN REPORT 02/10/2019
KALEAB WORKU 57
FINAL INTERN REPORT 02/10/2019
If all the above tests show that the strength of the concrete is less than expected mow
there are the following alternatives:-
Demolish the structure
Based on the agreement of the client and the structural engineer the change the
function of that structure, if it is designed for shop its minimum floor live load is
4KN/m2, if we change the function in to residence whose minimum floor live load is
2KN/m2 the structure will hold well.
Reduce the designed service life of the structure,
KALEAB WORKU 58
FINAL INTERN REPORT 02/10/2019
KALEAB WORKU 59
FINAL INTERN REPORT 02/10/2019
KALEAB WORKU 60
FINAL INTERN REPORT 02/10/2019
We told to our PM that there is shortage of protective cloths, then he bring some from
head office.
To be familiar with the site languages I ask all words that they speak and write them
and I try to know all.
To make the site engineer I ask to do tasks and I was trying to show my energy, and
also for the site engineer when he tries to measure some thing or when he do
inspections I asked him to give me his task and I told him If I am not correct he can
correct me.
2.8 Problems in our site
2.8.1Organizational Problems on our sites
There was very repetitive design changes, which creates conflicts between the site engineers
and the consultants and the sub-contractors.
There is no way of evaluation of the productivity of the working staff.
Mal use of workmanships.
There is very shortage of transport down to the basement both for materials and workers.
Low quality of the reinforcement bar it is much rested bar in our site.
The temporary stair shown in the above layout is very dangerous to use it because it is very
weak.
The other problem is that when concrete is arrived the temporary stair is also used as a ramp
for the concrete to slide down which is impossible to use the stair @ that time.
2.8.2 Safety problems in our site
▪ As I discussed earlier there is shortage of safety facilities in our site which makes the workers
not to be concentrated on their task.
We have informed to the project manager that there is shortage of safety wears but up to
we finish our intern there was no delivery.
▪ The stair down to the basement is weakly constructed and dangerous to be used so most of
the time the engineers supervise by being at the ground level which creates quality problems
in the construction.
We had told the project manager to solve this problems by constructing a new safer
temporary stair, and he did it, now it is safer.
2.8.3 Structural problems in our site
At the start of the project they (the designers) assumed that the shoring of piles can be used
as a wall for the basement’s but the shoring is only done for the purpose of retaining the soil
around the site from being collapsed when we are excavating the internal part
But they think that attaching the basement floor slabs to the pile shoring have the following
advantages.
The piles can be used as a wall for the basement floors.
KALEAB WORKU 61
FINAL INTERN REPORT 02/10/2019
When we connect the pile with the basement slab we can create a framed structure. Which
helps the shoring from collapsing towards the building
We save the cost and time of constructing perforated pipe and water proof work for the
retaining wall.
Dis advantages observed
If we connect the slab with the shoring piles first of all it will Couse structural problems
because the temporary structure or the shoring is not structural component of the building, it
is constructed by Ø8 meshed bars.
If we use the shoring as a wall for the basements the ground water that comes from the
retained soil will drop inside the building which will bring structural and it creates bad smell
inside the buildings.
If we connect the shoring with the slab the ditch will be inside the building which is very
dangerous for the basement floor functions.
The causes of the problems
Lack of professionals assigned for the site from the consultants like the hydraulic engineer who
would be in charge of the drainage and water works of the project , if we had hydraulic engineer
He would say that :-
Solutions
Constructing additional shear wall 15cm thick starting from the 3 rd basement
attached to the shooter creep between piles so the ground water outlets will be
provided at far apart and this sheer wall will resist the load of the slab.
Also this solution have the following drawbacks:-
• The solution cand avoid the ditch from being inside the basement parking.
• It needs chessling os the ditch slab to start bars for the sheer wall.
• It involve working in a very narrow place to cast the sheer wall.
KALEAB WORKU 62
FINAL INTERN REPORT 02/10/2019
At a time of concrete casting of the column as shown in the figure it drops around 3m height
from the top of the formwork to the ground. But this scenario leads concrete segregation
because as we have learned from past courses we know that dropping concrete from above
1.5 height isn’t suggested during pouring.
As a solution I have told the site engineer to use a cored formwork at the level of 1.5m to
pour the concrete, then close and fill the remaining from the top of the formwork.
first of all the site work don’t have that much care for the cost of materials for example
They had been construct the permanent formwork with the new expensive plywood with
plating a water proof to it which have no guaranty to stick with the sheer wall.
My recommendation to them was at the design stage we they had to consider the working
space for plating the waterproofs.
There is no need of punching reinforcement around the columns of the ramp because there
are ramp beams that used to transfer the load to column. So if there are beams no need of
punching reinforcement because the bars are purposely put to protect the column from
punching shear. But they used it when ask the structural engineer on the site he told us we
put them just for trial because the next slab will flat no beams so we will have used it by the
time we reinforced the slab.
Again they provide sloppy space on the two side of slab in order to smooth access for the
parking but it is also mall use of places.
Fig 29 Un necessary punching bar around the ramp column slab reinforcement attached
Practical skills
Theoretical knowledge
KALEAB WORKU 63
FINAL INTERN REPORT 02/10/2019
KALEAB WORKU 64
FINAL INTERN REPORT 02/10/2019
The other thing is, when we learn in school we learned that when we plate water proofs
we have to use cant strips to avoid 900 bend of the water proof, but in our site they are
using the new made water proofing which have 200gm of pollster (mesh) exists in
between layers which gives elastic properties not to be cut, although it is bended, but
the older one is only bituminized.
3.3 In terms of improving interpersonal communication skill
Since construction work is a team work by its nature you will face different individuals with
different professions and personality come up together and communicates with each other to
solve different problems and run the whole work, so good interpersonal communication skill
will bring success.
When I started the internship program was not able to know how to deal with people at the
work place that I did not know the way to communicate with different workers so that it was
difficult to me to communicate with the workers.
But afterwards I believe that good relation and communication skill is the key for getting the
experience and knowledge require for the internship program.
Based on this I tried to change my approach to the people at the work place and through time
I was able to saw progress on myself.
Example: - to ask for questions for the foreman’s I helped then in doing tasks like
measuring the works done ,by this method I become very close to our Forman’s
and so I can ask anything new freely.
So as a conclusion I can say that I have got good lesson regarding communication skill while
my stay in the company for the internship program.
3.4 In terms of improving team playing skill
Teams work is the way of success and strength. I learnt that as part of a team, an engineer
should have to works with a positive attitude within a group for the success of a project.
When called upon to lead, an engineer must have good managerial and team playing skill.
Therefore I try to improve my team playing skill in order to be successful engineer.
Confident engineers are able to succeed by gaining the trust of co-workings. Generally
speaking I know that an engineer with good team playing skill has the following qualities.
Demonstrates reliability
Communicates constructively
Listens actively
Functions as an active participant
Shares openly and willingly
KALEAB WORKU 65
FINAL INTERN REPORT 02/10/2019
Punctuality: - means keeping the companies work beginning and ending time and to
complete a given task within the given period.
Office disciplines: - on work place you don’t have to disturb the working atmosphere. For
example abstain from opening loud voice, loud music, songs and things which disturb others
workers mood.
Reliability: - the worker should be qualified for the part he is supposed to be performing.
He/she must have appropriate skill and knowledge for the task assigned.
Honesty: - Regarding this value each worker regardless of its status should abstain from bad
behaviors such as cheating, bias, corruption etc.
Cooperation: - Each worker should interact and cooperate with each other while working.
That is because it is through such system problems could be easily solved.
KALEAB WORKU 66
FINAL INTERN REPORT 02/10/2019
Entrepreneurship is defined as special human talent that helps manage those factors of
production such as labor machinery and capital and takes risks of making loses.
An entrepreneur is required to establish meaningful relationship between activity and
authority which is intimately related to planning function.
Human resource management: - Having a quality worker is a must if one needs to be
productive. Therefore I have been able to understand that taking responsibility for the
safety and well-being of employees in job related activities by providing safety wares like
safety shoes & helmets and insurances one can attain high level of support from them.
Equipment utilization management: - Construction equipment management helps a
person to plan implement and monitor construction equipment’s to: -
Enhance optimum utilization.
Increase efficiency or productivity of inputs to the products of the construction.
Harmonize standards and enhance the quality of work
Financial management: - Wide financial flow is achieved through detailed market
Studies. A Company should also be able to put well qualified and efficient personnel for
preparation of contracts and payments.
During my internship experience I have been able to grasp ideas about human resources
management, equipment utilization and financial flow and also develop self-confidence to
play my strength in believing in myself and taking risks in my future career.
KALEAB WORKU 67
FINAL INTERN REPORT 02/10/2019
other disciplines as much as possible. I am also making the long term friendship with
some of the workers, this made an unforgotten pleasure for me.
4.2 Recommendation
Finally, I want to say something toward and against the company.
Interesting impact of the company:-
The technology they used.
Their speed of work.
Their clarity and quality of work.
Enough accessibility of the construction material.
Their perfect modification of the design when it was found to be necessary.
Respecting of beliefs and attitudes of every worker even their holiday. i.e. there is no
obligatory rule to stand the workers on their task during holiday and when they are sick.
Their good trend of giving works to sub-contractors.
Their very good degree of having modern equipment’s and machines.
Their staffs quality and work ethics.
There timely delivering projects practice.
Recommendation against the company:-
There is no proper schedule and supervision of intern students, I recommend that if they can
have schedule and proper supervision.
The payment for the workers is not that much fair
here is no adequate guarantees for the workers who were damaged during construction
There is shortage of safety wears in the sites, so I recommend that safety should be first.
The payment was not done immediately the workers apply to get it.
There should be a method of evaluating the productivity of the workers to increase their
productivity and to take measure actions.
There were the repetition on the modification of the design which is entails that where was
no serious consultation during designing process. I.e. there was careless during the approval
of such type of unfinished and invalid design.
There was no much interesting communication between the site engineer and the contractor
about the total work flow. i.e there is idea difference between them on some construction
process(environmental idea) which indirectly cause confusion of non- skilled workers.
Recommendation against our campus:-
In me internship period one of the problem for me was there are courses that we have to
cover before we go out to the internship program like :-
Cost management
MS project
KALEAB WORKU 69
FINAL INTERN REPORT 02/10/2019
Construction low
So the above courses should be taken by the students before they join internship.
The other thing is there was a time delay at the start of the internship period, which creates
shortening of the internship period.
So the internship period should be started on time to meet its target.
5. Reference:-
From the scope of my view.
Different documents of bamacon construction and any related materials.
Internet
Handout from construction material l and 2.
Handout from building construction 1and 2.
Specification handouts.
Site supervision handouts.
Scheduling handouts.
HRM handouts.
BATCODA, ACI, EBCS.
KALEAB WORKU 70
FINAL INTERN REPORT 02/10/2019
KALEAB WORKU 71