AQUA 3105

AQUACULTURE ENGINEERING

EMMANUEL M. VERA CRUZ


College of Fisheries
Central Luzon State University

1
Design & Construction of
Freshwater Pond Farms

2
Estimating Earthwork Requirements

(TW + BW) where, TW, top width of dike (m)


 TVDfill = -------------- (hu)(L) BW, bottom width (m)
2 hu, unsettled ht (m)
L, length (m)
TVDfill, Total volume of dike fill (m3)

 TVExcav = Ap (Dc) Ap, ave. area of pond (m)


Dc, ave. depth of cut (m)
TVExcav, Total volume of excavation (m3)
TW
hu

BW Dc

3
Sample Computation
o Given the following, compute for the total volume of dike fill and total
volume of excavation
o 10 m

Pond 1 2 3 4 25 m

1.5 m

1
1.2 m 20 cm
1.5

4
Solution

o TVExcav = 25m (10m)(4)(0.2m) = 200 m3

o BW = 2zh + TW = 2(1.5)(1m) + 1.5m = 4.5 m

o TVDFill = [(1.5m + 4.5m)/2] (1m) (205m) = 615 m3

o Note: Amount of soil excavated (200m3) not


enough for dike construction (615 m3)
5