Rate Build Up Lecture.

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 51

ONLINE SESSION BY QS CHIMA(QS ICON) : YQSF SOUTH EAST ZONE WHATSAPP PLATFORM

RATE ANALYSIS OF CONSTRUCTION WORK ITEMS

+234 703 059 0892: My name is QS. CHIMA Ikechukwu Samuel.


+234 703 059 0892: I am currently in Oyo State and I'm the Assistant General Secretary of
chapter
+234 703 059 0892: Firstly, I will to appreciate the Steering committee of this platform for
giving me the opportunity to lead this session.
+234 703 059 0892: For the next few days, I will be taking you through unit rate analysis
for building works and the likes
+234 703 059 0892: Remember, every one here are still under professional tutelage. If I
make mistaken, please correct me professionally.
+234 703 059 0892: The process of project cost estimation is central to setting up the
foundation for making key decisions, taking initiatives, budgeting activities and controlling
expenditures.
+234 703 059 0892: The necessity of calculating expenses consists in maintaining confidence
and trust that project activities are performed properly and as expected throughout the
entire project life-cycle.
+234 703 059 0892: Logical and reasonable cost estimates will allow the team to make
collaborative effort with a reduced probability of risk occurrence and failure because the
estimators use various efficient methodologies to fight uncertainty, prevent performance
bottlenecks, determine budget and control spending.
+234 703 059 0892: Because of time, let go straight into today business overview of unit rate
for Earthworks
+234 703 059 0892: Earthworks is under section 1.5 of BESMM 4 (Excavation and filling)
+234 703 059 0892: Cost Estimates for building or Engineering works comprises of:

Material cost
Labour cost
Equipment

1
Compiled by: KABEER OLOYEDE MAY 2020.
ONLINE SESSION BY QS CHIMA(QS ICON) : YQSF SOUTH EAST ZONE WHATSAPP PLATFORM

Profit & overhead cost


+234 703 059 0892: Please note: cost of materials, labour and equipment in the calculation
is basically obtainable here in Oyo State. Please update it to your location
+234 703 059 0892: Let Start with top soil excavation.
+234 703 059 0892: Top soil excavation is measured in m2 (see BESMM 4) stating the
average thickness to excavate
+234 703 059 0892: Please note, the output and constant in the calculation of the unit rate
was obtained from NIQS cost data bank @ www.niqsdatabank.org

(1)

+234 703 059 0892: Top soil excavation (m2)

Equipment
Bulldozer = 120,000.00
Low bed (50ton) = 75,000.00
Fuel = 35,000.00
Operator= 5,000.00
Assistant= 2,000.00
total = 237,000.00

Output of D6 Bulldozer per day = 1600m2


Allow 75% efficiency = 1600x0.75 = 1200m2

Therefore:
Cost per m2 = 237,000.00/1200
= 197.50
Add 5% WHT = 9.88
subtotal = 207.38

2
Compiled by: KABEER OLOYEDE MAY 2020.
ONLINE SESSION BY QS CHIMA(QS ICON) : YQSF SOUTH EAST ZONE WHATSAPP PLATFORM

Add 20% p & o = 41.48

Cost/m2 = 248.86
Approximately #250/m2

+234 703 059 0892: Let take questions, comments and observation. Thanks
Kabeer Oloyede: Any consideration for soil of different formation?
Maybe hard strata, other than normal loamy or Sandy area?
+234 703 059 0892: Thanks for that question
+234 703 059 0892: The output provided for Dozer is average output
+234 706 319 0261: Bulldozer=120,000.00 or 12000.00 and is this constant
+234 703 059 0892: 120,000 per day. Thanks
+234 706 319 0261: Low bed (50ton) =75,000:00 is this constant
+234 816 127 0482: Please can you elaborate a bit on that 75% efficiency?
+234 703 059 0892: Low bed is the truck or motor that will carry the dozer to site. 75k is
the cost of to and fro within Ibadan
+234 816 854 3896: Basically the plant can not be 100% efficient Due to the nature because
it can neither be predicted
+254 708 743284: And also the operator, he could answer some phone calls and pause, or
even pause for some puffs, the machine may also require some fuel top up and such
+254 708 743284: Or should the operator's efficiency be considered separately?
+234 703 059 0892: Can we move to Excavation
+234 703 059 0892: What does WHT stand for
+234 703 059 0892: Why is it necessary
+234 703 059 0892: WHT stand for withholding tax
+234 806 981 8812: Good one bro, Thank you for this wonderful presentation.

3
Compiled by: KABEER OLOYEDE MAY 2020.
ONLINE SESSION BY QS CHIMA(QS ICON) : YQSF SOUTH EAST ZONE WHATSAPP PLATFORM

However, I'd like you to include or tell us where you intend to consider VAT allowance in
the estimate?
+234 703 059 0892: A withholding tax is an amount that an employer withholds from
employees’ wages and pays directly to the government
+234 703 059 0892: VAT is to be added at general summary.
+234 806 981 8812: Thanks. It's important as you have told us here because a second option
could be to include it with individual rates.
+254 708 743284: Why is WHT necessary
+234 703 059 0892: This method enables the client or employer to know the actual amount
of VAT in the bill
+234 703 059 0892: A withholding tax is an amount that an employer withholds from
employees’ wages and pays directly to the government
+234 703 059 0892: In every interim certificate, Federal inland revenue do deduct WHT of
5% from the amount due to the contractor
+234 703 059 0892: This amount must be built in into the unit rate.

(2)

+234 703 059 0892: Excavation

+234 703 059 0892: *Laborer basic cost*


General Labour = 2000
Skilled Iabour = 3500
321
Working hour = 8 hours
+234 703 059 0892: Oyo State only
+234 703 059 0892: Excavation (m3)
labour output = 3.5m3/day
General labour = 2000:00
Tools (Digger & Shovel) = 200:00

4
Compiled by: KABEER OLOYEDE MAY 2020.
ONLINE SESSION BY QS CHIMA(QS ICON) : YQSF SOUTH EAST ZONE WHATSAPP PLATFORM

total = 2200:00

Therefore:
Unit rate = 2200.00/3.5
= 628.57
Add 5% WHT = 31.43
subtotal = 660.00
Add 20% p & o = 132.00
Cost/m3 = 792.00
Approximately #800/m3

+234 806 981 8812: In addition, this is one-way government adopt to collect taxes from its
citizens from source instead of going to their individual houses to drive tax. At the end, the
employee is entitled to an evidence of payment which will be presented to government for
tax certificate.

(3)

+234 703 059 0892: Disposal n.e 1.00m from excavation (m3)

General labour output = 5m3/day


General labour = 2000:00
Tools (Digger & Shovel) = 200:00
total = 2200:00

Therefore:
Unit rate = 2200.00/5
= 440.00
Add 5% WHT = 22.00

5
Compiled by: KABEER OLOYEDE MAY 2020.
ONLINE SESSION BY QS CHIMA(QS ICON) : YQSF SOUTH EAST ZONE WHATSAPP PLATFORM

subtotal = 462.00
Add 20% p & o = 92.40
Cost/m3 = 554.40
Approximately #555/m3

(4)
+234 703 059 0892: Backfilling side of excavation (m3)

General labour output = 8m3/day


General labour = 2000:00
Tools (Digger & Shovel) = 200:00
total = 2200:00

Therefore:
Unit rate = 2200.00/8
= 275.00
Add 5% WHT = 13.75
subtotal = 288.75
Add 20% p & o = 57.75
Cost/m3 = 346.50
Approximately #350/m3

(5)
+234 703 059 0892: Next is Imported Filling
+234 706 319 0261: BESSM4 remove backfilling, should back filling still included in the
bill?
+234 703 059 0892: Remember, filling under floor can be either laterite or sand filling.
+234 703 059 0892: It is only Level and compacting that was deemed included in the
excavation

6
Compiled by: KABEER OLOYEDE MAY 2020.
ONLINE SESSION BY QS CHIMA(QS ICON) : YQSF SOUTH EAST ZONE WHATSAPP PLATFORM

+234 703 059 0892: Except in special case where it will be required. That will come under
variation
+234 703 059 0892: BESMM 4 has removed earthworks support
+234 703 059 0892: Laterite earth filling (m3)

Material cost
Note: Laterite is being sold in tonnage and 1m3 of laterite = 1.95ton
Density of laterite varies btw 1095-1350kg/m3
I assume 1300kg/m3
= 1.3tons x 50% = 1.95tons

*Or*
1m3 x 50% / (3.81)
= 1 x 1.5/3.81
=0.39load of 5tons
= 0.39 x 5 = 1.96tons

Let use option 1

Basic cost of laterite here in Ibadan is 15000 per 10tons lorry load
= 1500per tonnage
Therefore:
1.95tons @ 1500 = 2925

Equipment
Compactor (30m3/day at 15,000 (for machine, operator & fueling)
Therefore
Cost per m3 = 15,000/30
500
7
Compiled by: KABEER OLOYEDE MAY 2020.
ONLINE SESSION BY QS CHIMA(QS ICON) : YQSF SOUTH EAST ZONE WHATSAPP PLATFORM

Labour (Spreading & Leveling) = 5m3/day


General Labour = 2000
Shovel & wheelbarrow = 400
Total = 2400
Cost per m3 = 2400/5
480

Summary
Material = 2925
Compactor = 500
Labour = 480
total = 3905.00
Add 5% WHT = 195.25
subtotal = 4100.25
Add 20% p & o = 820.05
Cost/m3 = 4920.30
Approximately #4920/m3

+234 703 059 0892: Then the architect will issue instructions to that effect
+234 703 059 0892: Both the CQS and PQS will agree on fair rate for the item
+234 816 775 0629: Please Sir, this is mechanical method of excavation?

(6)

+234 703 059 0892: Granite hardcore (m3)

8
Compiled by: KABEER OLOYEDE MAY 2020.
ONLINE SESSION BY QS CHIMA(QS ICON) : YQSF SOUTH EAST ZONE WHATSAPP PLATFORM

Material cost
Note: Hardcore is being sold in tonnage and 1m3 of hardcore = 1.76ton
Density of granite 1600kg/m3
Add 10% = 0.16
= 1.76tons
Basic cost of hardcore here in Ibadan is 90,000 per 20 tons lorry load
= 4500per tonnage
Therefore:
1.76tons @ 4500 = 7920

Labour (Laying) = 7m3/day


General Labour = 2000
wheelbarrow = 300
Total = 2300
Cost per m3 = 2300/7
328.57

Summary
Material = 7920
Labour = 328.57
total = 8248.57
Add 5% WHT = 412.42
subtotal = 8660.99
Add 20% p & o = 1732.20
Cost/m3 =10,390.20
Approximately #10,400/m3

9
Compiled by: KABEER OLOYEDE MAY 2020.
ONLINE SESSION BY QS CHIMA(QS ICON) : YQSF SOUTH EAST ZONE WHATSAPP PLATFORM

+234 703 059 0892: Tomorrow I will continue with concrete work, masonry work, DPM,
BRC wire mesh and roof covering
+234 703 059 0892: Thanks
+234 703 059 0892: My name again is Qs. CHIMA Ikechukwu Samuel.
+254 708 743284: And allow me to ask is the rate you get at the end the cost per say one
laborer/plant?
To mean when you divide with the actual project, the price you get is for when you are
using one worker?
+234 703 545 1166: With the ideas developed, so are we to say that;

1)The WHT is deducted from payment due to the contractor and paid directly to
government by the client and VAT is paid to the contractor?
2)WHT should be added to unit rates during tendering, so as to upset the deduction Later.
Thus making ingredients of unit rates Materials, Labour, Plant, WHT, Overhead and
Profit?
3)We can see WHT as tax paid on behalf of the contractor to the government by the client
and VAT as Tax paid directly to the government by the contractor?
4)Does it mean WHT is a subset of VAT? Does it mean one is pay directly while the other is
paid indirectly, and later reconciled to avoid excess taxation?
Is the 5% part of the 7.5%?
5)This shows at the end of the day the client is paying 12.5% of contract value as tax to the
government?
6)A communique for our interactions Will Also Show an effect on our Valuation Summary
such that After arriving at total sum of work done, Retention will have to be deducted,
withholding tax deducted also then VAT added to arrive at payment due to the contractor?

+234 703 059 0892: Without wasting time let start with *WITHHOLDING TAX VS VAT*
+234 703 059 0892: Please note that WHT is different from VAT not only on percentage
variation but also on the mechanic of its concept and application

10
Compiled by: KABEER OLOYEDE MAY 2020.
ONLINE SESSION BY QS CHIMA(QS ICON) : YQSF SOUTH EAST ZONE WHATSAPP PLATFORM

+234 703 059 0892: The WHT system is aimed at tracking down taxpayers and the
incomes which may otherwise not be reported by them.
+234 703 059 0892: When the income on which WHT is deducted at source is finally
brought to the notice of the tax authority and the appropriate tax computed, due credit is
given for the WHT deducted at source on the presentation of the original WHT receipts
through the issuance of credit notes.
+234 703 059 0892: VAT is a different type of tax. VAT is a consumption tax payable on
the goods and services consumed by any person, whether government agencies, business
organizations or individuals.
+234 703 059 0892: The applicable rate for commissions/fees is ten percent (10%) for
limited liability companies, and five percent (5%) for individuals and partnerships.
+234 703 059 0892: Withholding Tax is an advance payment of income tax and the
purpose is to bring the prospective taxpayer to the tax net, thereby widening the income tax
base.
+234 703 059 0892: When the income, which suffered withholding tax as deduction at
source, is finally brought to the notice of the tax authority and appropriate tax is
computed, credit is given for the tax deducted. The taxpayer will be required to pay only
the balance of the tax due (if any). WHT is meant to curb income tax evasion and it is not a
separate tax on its own.
+234 703 059 0892: Withholding taxes are to be paid to FIRS designated collecting banks.
The payment should be accompanied with a schedule showing the following details:
▪️Name of each contractor
▪️Taxpayer Identification Number of each contractor
▪️The gross value of the contract
▪️The amount of tax withheld.

+234 703 059 0892: *Note*


When a Government or her agent advertise a project requesting prospective contractor to
tender. Some conditions are attached which includes the following:

➖Evidence of reg. with CAC

➖ Current Pencom certificate

➖ Current Tax clearance certificate

➖ Three years audited account

11
Compiled by: KABEER OLOYEDE MAY 2020.
ONLINE SESSION BY QS CHIMA(QS ICON) : YQSF SOUTH EAST ZONE WHATSAPP PLATFORM

etc
+234 703 059 0892: Now, before the tax authority can issue Tax clearance certificate, the
contractor will be required to provide audited account of the company, including evidence
of payment of WHT (if any).
This will enable them to compute the actual amount the company will pay for the year.
+234 703 059 0892: From the audited account, the tax authority will know the turnover of
the company, the work executed and amount paid.
+234 703 059 0892: The actual amount paid as *Withholding tax* will now depend on the
company turnover.
+234 703 059 0892: The company and her auditor have to agreed on the project to be
declared in the annual turnover.
+234 703 059 0892: But note that each of the project government or her agent advertised
has a target annual turnover which each prospective contractor must have before
tendering for the project.
+234 703 059 0892: For example, if the instructions to tender stated at least 50millon
annual turnover, only contractor within that range can tender. Some one with 40millio or
less can not tender
+234 703 059 0892: This makes must of the companies to declare a turnover up to the
amount required or beyond for other project of higher turnover.
+234 703 059 0892: The high the numbers of project or contract sum declared, the higher
the company turnover and the company will stand better chance to tender for more
project. Who knows the likely project to be win by the company.
+234 703 059 0892: I tendered for a federal government project here in Ibadan last year
December, our company was disqualified because our turnover was lower than what was
expected
+234 703 059 0892: For the reasons above, I strongly advice all Quantity Surveyors in the
house to sensitize our client (contractor) on the implication of WHT for the development of
the company.
+234 703 059 0892: If a contractor included a project in his turnover, and the unit rate
didn't include WHT, it simply means that he is losing 5% of his profit to government
+234 703 059 0892: For a contractor who is not willing to tender for any governmental or
corporate organization project, he might escape WHT
+234 703 059 0892: On the issue of, *"_if WHT should be included in the general summary
or built-up in the unit rate_"*

12
Compiled by: KABEER OLOYEDE MAY 2020.
ONLINE SESSION BY QS CHIMA(QS ICON) : YQSF SOUTH EAST ZONE WHATSAPP PLATFORM

For Government projects, you can include it in the general summary but for individual
project that will be declared in the turnover, built it into the unit rate where the client will
not have access to it.
+234 703 059 0892: Any questions, clarification or addition to above
+234 703 545 1166: Thanks amiable QS, to clarify this, it means the withholding tax is
deducted at the valuation stage and paid by the client to the govt on behalf of the
contractor?
+234 703 059 0892: Yes, but the contractor must collect evidence of payment to enable him
stand a change for tax clearance certificate
+234 703 545 1166: And this means that to be cleared of tax (tax clearance certificate) the
contractor must have met up with both WHT and VAT
+254 708 743284: In Kenya we only have the VAT of 16%
+234 703 059 0892: Can we continue with *overview of unit rate*?
+234 703 059 0892: Before I continue, I like to speak on percentage *_profit and
overhead_*
+234 703 059 0892: It includes VAT and WHT
+234 703 545 1166: Please Chief we will appreciate the distinctive differences between Wht
and VAT in both administration and usage
+234 703 059 0892: Some state government project also charge 16% for both
+234 703 059 0892: Both are for the benefit of the government. VAT is for the project
While WHT is for the company executing the contract. But to be save from this cost, it is
advisable to factor it into the unit rate
+234 703 545 1166: Invariably both will be paid by the client, thus increasing the client's
tax on the project to 12.5% of the contract sum
+234 703 059 0892: Provided if it was built in the unit rate. No client will be happy that
you are using his money to pay for your company income tax
+234 703 059 0892: Also, on percentage to be included as profit and overhead.

No specific percentage for P&O. It depends on the company pricing policy. Some
companies take 40%, 30%, 25%, 20%, 15% even as low as 7.5%.

13
Compiled by: KABEER OLOYEDE MAY 2020.
ONLINE SESSION BY QS CHIMA(QS ICON) : YQSF SOUTH EAST ZONE WHATSAPP PLATFORM

(7)

+234 703 059 0892: BRC wire mesh come with different sizes per roll. The size varies in
price and covering area.

Pls check the actual specifications in the BOQ before pricing this items.

The prices of some BRC in Ibadan is as follows:


15x2.1x3.5mm = 12k per roll
15x2.1x4.0mm= 14k
15x2.1x5.0mm= 20k
20x2.1x3.5mm= 15k
20x2.1x4.0mm= 18k
25x2.1x4.0mm= 25k
etc
+234 703 059 0892: *BRC Wire mesh (m2)
*Material cost*
Size = 15x2.1x3.5mm at 12000 per rolls

Therefore:
Cost per m2 = 12,000/(15x2.1)
= 380.95
Add 5% waste: 19.05
Total Mat. cost = 400

*Labour* (Cutting & spreading)


Gang size= 1 iron bender & 1 G. Labour
Output = 120m2/gang/day

14
Compiled by: KABEER OLOYEDE MAY 2020.
ONLINE SESSION BY QS CHIMA(QS ICON) : YQSF SOUTH EAST ZONE WHATSAPP PLATFORM

Iron bender = 3500


General Labour = 2000
Total = 5500

Cost per m2= 5500/120


=46.83
Summary
Material = 400
Labour = 45.83
total = 445.83
Add 5% WHT = 22.29
subtotal = 468.12
Add 20% p & o = 93.62
Cost/m2= 561.74
Approximately #560/m2

(8)

+234 703 059 0892: DPM (m2)


*Material cost*
Size = 25x2m at 5000 per rolls (double layer)
Therefore:
Cost per m2 = 5000/(25x2)
= 100
Add 10% waste: 10.00
Total Mat. cost = 110.00

15
Compiled by: KABEER OLOYEDE MAY 2020.
ONLINE SESSION BY QS CHIMA(QS ICON) : YQSF SOUTH EAST ZONE WHATSAPP PLATFORM

Labour (Cutting & spreading)


Output = 150m2/man day
General Labour = 2000
Cost per m2= 2000/150
=13.33

*Summary*
Material = 110
Labour = 13.33
total = 123.33
Add 5% WHT = 6.17
subtotal = 129.50
Add 20% p & o = 25.90
Cost/m2= 155.4
Approximately #155/m2

(9)
+234 703 059 0892: Concrete work (1:2:4) (m3)

*Material needed*
Cement
Sand
Granite
Sum of mix ratio= 1+2+4=7
Vol of conc. = 1m3
Add 40% = 0.4m3
Total = 1.4m3

16
Compiled by: KABEER OLOYEDE MAY 2020.
ONLINE SESSION BY QS CHIMA(QS ICON) : YQSF SOUTH EAST ZONE WHATSAPP PLATFORM

*Cement*
= 1.4m3 x 28.8/(7)
=5.76bags

*Sand*
= 1.4m3 x 2 / (7x3.81)
=0.10loads of 5ton
=0.10 x 5= 0.52tons

*Granite*
= 2 x sand
= 2 x 0.52
= 1.04ton

*Price*
Cement = 2500
Sand = 36,000 (20tons) = 1800/ton
Granite= 90,000 (20tons) = 4500/ton

*Material cost*
Cement: 5.76bag @ 2500 = 14,400
Sand: 0.52ton @ 1800 = 936
Granite: 1.04ton @ 4500 = 4680
Total = 20,016.00

*Equipment*
Conc. Mixer = 15,000/day

17
Compiled by: KABEER OLOYEDE MAY 2020.
ONLINE SESSION BY QS CHIMA(QS ICON) : YQSF SOUTH EAST ZONE WHATSAPP PLATFORM

Poker Vibrator (5000/day)


Fueling= 1500
Renters (wheelbarrow, shovels & head pan) = 3000
Total = 24,500
Output per day = 15m3 (average)
Cost per m3 = 24,500/15
=1,633.33

*Labour* (Placing)
Gang size
1 Mixer operator @ 4000 = 4000
1 poker operator @ 3000 = 3000
2 Bricklayer @ 3500 = 7000
20 General Labor @ 2000 = 40,000
Total = 54,000
Cost per m3 = 54,000/15
= 3600

*Summary*
Material = 21,016
Equipment = 1633.33
Labour = 3600
total = 26,249.33
Add 5% WHT = 1312.47
subtotal = 27,561.80
Add 20% p & o = 5,512.36
Cost/m3 = 33,074.16
Approximately *#33,000/m3*

18
Compiled by: KABEER OLOYEDE MAY 2020.
ONLINE SESSION BY QS CHIMA(QS ICON) : YQSF SOUTH EAST ZONE WHATSAPP PLATFORM

(10)

+234 703 059 0892: *Reinforcement bar (ton)*

Pls note: The price of reinforcement bar varies with size. Rft could be local or imported
(Tigre TMT)
The average cost of the bar in the BOQ will used for the computation of the unit rate or the
cost of Y10 or Y8 which is usually higher due to it's number per tonnage.
For binding wire, 13kg is needed per tonnage. Cost per roll depend on the weight of wire in
a roll.

*Material cost*
Average cost of bar(local) = 207,000
Binding wire: 1 roll (13kg) = 6000
Subtotal = 213,000
Add waste 5%=10,650
Total = 223,650

*Labour* (Cutting & Fixing)


Here in Ibadan, we pay btw 18k to 25k for cutting and fixing of rft per tonnage
Therefore
Labour for cutting & fixing = 22,000

*Summary*
Material = 223,650
Labour = 22,000
total = 245,650
Add 5% WHT = 12,282.50
subtotal = 257,932.50

19
Compiled by: KABEER OLOYEDE MAY 2020.
ONLINE SESSION BY QS CHIMA(QS ICON) : YQSF SOUTH EAST ZONE WHATSAPP PLATFORM

Add 20% p & o = 51,586.50


Cost/ton = 309,519.00
Approximately *#310,000/ton*

To convert to kg, divide by 1000.

Our Online Lecture series on Rate Analysis will commence today by 6pm with QS Chima
(QS Icon)
+234 703 059 0892: Good evening Ladies and Gentlemen.
+234 703 059 0892: Welcome to day 3 of our on going *overview of unit rate*
+234 703 059 0892: I still remain your friend and Colleague QS Chima Ikechukwu Samuel
+234 703 059 0892: From the conversation I have with some students on this platform. I
realized that some students have challenges in *preparation of schedule of materials* for
construction work and *measurement of building and civil engineering works*. I don't
know what the steering committee of this platform want to do about it. @Bolinkz Consults
Nig. pls act on this sir.
+234 703 059 0892: For measurement of building, I have the taking-off on *raft
foundation, and Structural metal work using BESMM 4* I presented last month during
our daily online lockdown lecture organized by YQSF OYO STATE. I don't if I should
share the file
+234 703 059 0892: Someone asked questions in respect to Concrete. Pls if you are using
both sand and stone dust for casting, the average cost of the sand and dust will be use in
computation of the rate.

(11)

+234 703 059 0892: *Blockwork*


Blockwork could be solid filled and hollow in superstructure
+234 703 059 0892: Blockwork (Solid filled) (m2)
225mm blk

20
Compiled by: KABEER OLOYEDE MAY 2020.
ONLINE SESSION BY QS CHIMA(QS ICON) : YQSF SOUTH EAST ZONE WHATSAPP PLATFORM

No of blk/m2 = 10
Vol. of mortar/m2 = 0.024m3/m2
Hollow fill= 0.08m3/m2

*mortar* (1:6)
sum mix ratio = 1+6=7
Vol of mortar = 0.024m3

Cement= 0.024x1.4x28.8/(7)
=0.138bag

Sand= 0.024x1.4x6/(7x3.81)
= 0.008loads of 5tons
= 0.008 x 5= 0.04ton

*Hollow filling* (1:4:8)


sum of ratio = 1+4+8= 13
Vol of concrete = 0.08m3/m2

Cement = 0.08x1.4x28.8/(13)
=0.248bag

Sand = 0.08x1.4x4/(13x3.81)
= 0.09loads of 5ton
=0.09x5 = 0.045ton

Granite = 2 x sand
= 0.045 x 2 = 0.09ton

21
Compiled by: KABEER OLOYEDE MAY 2020.
ONLINE SESSION BY QS CHIMA(QS ICON) : YQSF SOUTH EAST ZONE WHATSAPP PLATFORM

*Note: * 1.4 stand for 40%. 40% of 1 is 1.4 likewise 10% of 1 is 1.1

Materials summary
Cement = 0.138+0.248 = 0.386bag
Sand= 0.04+0.045 = 0.085
Granite = 0.09

*Price*
Block = 180
Cement = 2500
Sand = 36,000 (20tons) = 1800/ton
Granite= 90,000 (20tons) = 4500/ton

*Material cost*
Block: 10no @ 180 = 1800
Cement: 0.386bag @ 2500 = 965
Sand: 0.085ton @ 1800 = 153
Granite: 0.09ton @ 4500 = 405
Total = 3,323.00

*Labour* (laying & hollow blk filling)


Cost = #65/block
Cost/m2 = 65 x 10 = 650
Total = 650.00

*Summary*
Material = 3,323.00

22
Compiled by: KABEER OLOYEDE MAY 2020.
ONLINE SESSION BY QS CHIMA(QS ICON) : YQSF SOUTH EAST ZONE WHATSAPP PLATFORM

Labour = 650.00
total = 3,973.00
Add 5% WHT = 198.65
subtotal = 4,171.65
Add 20% p & o = 834.33
Cost/m2 = 5005.98
Approximately *#5000/m2*

+234 703 059 0892: Here in Ibadan, we lay blk with hollow filling 65 per blk while in
superstructure 35-65 varies with the height of the building.

(12)
+234 703 059 0892: Blockwork (m2) {Non-solid filled}
225mm blk
No of blk/m2 = 10
Vol. of mortar/m2 = 0.024m3

*mortar* (1:6)
sum mix ratio = 1+6=7
Vol of mortar = 0.024m3

Cement= 0.024x1.4x28.8/(7)
=0.138bag

Sand= 0.024x1.4x6/(7x3.81)
= 0.008loads of 5tons
= 0.008 x 5= 0.04ton
*Material cost*

23
Compiled by: KABEER OLOYEDE MAY 2020.
ONLINE SESSION BY QS CHIMA(QS ICON) : YQSF SOUTH EAST ZONE WHATSAPP PLATFORM

Block: 10no @ 180 = 1800


Cement: 0.138bag @ 2500 = 945
Sand: 0.04ton @ 1800 = 72
Total = 2217.00

*Labour* (laying)
Cost = #40/block
Cost/m2 = 40 x 10 = # 400
Total = #400.00

*Summary*
Material = 2217.00
Labour = 400.00
total = 2617.00
Add 5% WHT = 130.85
subtotal = 2747.85
Add 20% p & o = 549.57
Cost/m2 = 3297.42
Approximately *#3300/m2*

+234 703 059 0892: *Note:*


For 150mm (6") block, the volume of mortar per m2 is 0.018m3/m2. This means that in
every square meter of blockwall of 150mm thick contains 0.018m3 of mortar.

(13)
+234 703 059 0892: Let go to roof covering
+234 703 059 0892: Roofing material is of diff type and specifications

24
Compiled by: KABEER OLOYEDE MAY 2020.
ONLINE SESSION BY QS CHIMA(QS ICON) : YQSF SOUTH EAST ZONE WHATSAPP PLATFORM

+234 703 059 0892: *Aluminum roofing sheet*


The price varies with gauge and quality.
+234 703 059 0892: *Aluminum roof covering (m2)*

Note:
Aluminum washer = 100no per pack= 1200/pack
50mm Galva. drive screw (7No/m2) (100pieces/pack= 1250/pack

*Material cost*
Aluminum roof (0.55 gauge): 1m2 @ #1800 = 1800
Washer: 7no @ #12 = #84
Galv. Screw: 7no @ #12.5 = #87.50
Total = #1971.5
Add 10% waste = 197.15
Materials cost = #2168.65

*Labour*
Gang size (2 Carpenter + 1 Labour)
Output/day = 100m2
Carpenter: 2men @ 3500 = 7000
Labour: 1 Labour@ 2000 = 2000
Total = 9000
Cost/m2 = 9000/100
= #90.00

*Summary*
Material = #2168.65
Labour = #90

25
Compiled by: KABEER OLOYEDE MAY 2020.
ONLINE SESSION BY QS CHIMA(QS ICON) : YQSF SOUTH EAST ZONE WHATSAPP PLATFORM

total = #2258.65
Add 5% WHT = 112.93
subtotal = 2371.58
Add 20% p & o = 474.32
Cost/m2 = #2845.89
Approximately *#2850/m2*

(14)

+234 703 059 0892: *Gerald stone coated roof step tiles (m2)*

*Material cost*
Gerald stone coated roof (0.55): 1m2 @ #2800 = #2800
Washer: 7no @ 12 = 84
Galv. Screw: 7no @ 12.5 = 87.50
Total = 2971.5
Add 10% waste = 297.15
Materials cost = 3268.65

*Labour*
Gang size (2 Carpenter + 1 Labour)
Output/day = 65m2

Carpenter: 2men @ 3500 = 7000


Labour: 1 Labour@ 2000 = 2000
Total = 9000
Cost/m2 = 9000 / 65
138.46

26
Compiled by: KABEER OLOYEDE MAY 2020.
ONLINE SESSION BY QS CHIMA(QS ICON) : YQSF SOUTH EAST ZONE WHATSAPP PLATFORM

*Summary*
Material = 3268.65
Labour = 138.46
total = 3407.11
Add 5% WHT = 170.36
subtotal = 3577.47
Add 20% p & o = 715.50
Cost/m2 = 4292.97
Approximately *#4300/m2*

(15)

+234 703 059 0892: *Adex Super 7 asbestos roofing sheet (m2)*

Note:
Size per sheet = 2400 x 1200mm
Cost per sheet = 4500
Cost per m2 = 4500/(1.2x2.4)
=1562.50

*Material cost*
Adex Super 7 roofing sheet: 1m2 @ 1562.50 = 1562.50
Washer: 7no @ 12 = 84
Galv. Screw: 7no @ 12.5 = 87.50
Total = 1734.00
Add 10% waste =86.70
Materials cost = 1820.70

27
Compiled by: KABEER OLOYEDE MAY 2020.
ONLINE SESSION BY QS CHIMA(QS ICON) : YQSF SOUTH EAST ZONE WHATSAPP PLATFORM

*Labour*
Gang size (2 Carpenter + 1 Labour)
Output/day = 55m2
Carpenter: 2men @ 3500 = 7000
Labour: 1 Labour@ 2000 = 2000
Total = 9000
Cost/m2 = 9000 / 55
#163.64

*Summary*
Material = 1820.7
Labour = 163.64
total = 1984.34
Add 5% WHT = 99.22
subtotal = 2083.56
Add 20% p & o = 416.71
Cost/m2 = 2500.27
Approximately *#2500/m2*

+234 703 059 0892: Welcome to day 4 of our online *overview of unit rate analysis for
construction work*
+234 703 059 0892: I still remain that your friend and colleague, QS. Chima Ikechukwu
Samuel.
+234 703 059 0892: Without wasting time, let start.

28
Compiled by: KABEER OLOYEDE MAY 2020.
ONLINE SESSION BY QS CHIMA(QS ICON) : YQSF SOUTH EAST ZONE WHATSAPP PLATFORM

(16)
+234 703 059 0892: *Formwork*
+234 703 059 0892: Unit rate for *formwork* varies depend on the method of
construction, materials and possible no of usage
+234 703 059 0892: No of usage means the number of time to make use of the formwork
before disposing it
+234 703 059 0892: Formwork can be steel, timber (plank) or marine board
+234 703 059 0892: Tonight I will focus on wooden formwork (plank and marine board)
for suspended floor of 3.00m from working floor level

+234 703 059 0892: The diagram above contains names of different members that makes
formwork

29
Compiled by: KABEER OLOYEDE MAY 2020.
ONLINE SESSION BY QS CHIMA(QS ICON) : YQSF SOUTH EAST ZONE WHATSAPP PLATFORM

+234 703 059 0892: *Sheathing* is the platform that will receive the concrete work. It can
steel, wooden plank or marine board
+234 703 059 0892: *Stringer and Joist* connect the sheathing with the shoring. It could
be H-beam for steel formwork or 2" x 3" (50x75mm) hardwood spaced at 600mm for
wooden formwork.
+234 703 059 0892: *Shoring* is the vertical member that transfers the dead load of the
concrete to another floor. It could be Steel pipes for steel formwork or bamboo spaced at
600mm for wooden formwork.
+234 703 059 0892: Tonight I will focus on wooden formwork (plank and marine board)
with 50x75mm hardwood stringer and joist spaced at 600mm centers and Bamboo joist
+234 703 059 0892: I will be considering floor size of 10 x 12m
+234 703 059 0892: *Formwork (wooden plank in suspended slab) (m2)*

Materials needed
Sheathing: wooden plank
Stringer: 2"x3" (50x75mm) wood @ 600mm c/c
Joist: 2"x3" (50x75mm) wood @ 600mm c/c
Shoring: Bamboo

Total floor area: 10x12 = 120m2

Stand length of wood= 3.60m


Stand size of plank= 0.3 x 3.6
Covering area of a plank = 0.3 x 3.6 = 1.08m2

No of plank rqd: 120 / 1.08


=111pieces
Longer length (stringer) = 12m
No of line = (10 / 0.6) + 1 = 18lines

30
Compiled by: KABEER OLOYEDE MAY 2020.
ONLINE SESSION BY QS CHIMA(QS ICON) : YQSF SOUTH EAST ZONE WHATSAPP PLATFORM

Total length of stringer= 12 x 18 = 216m


No of 2x3 wood = 216/3.6 = 60nos

Shorter length (joist) = 10m


No of line = (12 / 0.6) + 1 = 21lines
Total length of Joist = 10 x 21 = 210m
No of 2x3 wood = 210/3.6 = 58no

Shoring (Bamboo)
Average len. of bamboo = 6m
No in a load = 200pieces

No of point for shoring: 18 x 21 = 378points


Assume 3.0m headroom height

Total length of shoring: 378 x 3 = 1137


Nos bamboo rqd: 1137 / 6
= 189 no
Approximately 1load

Nail: 0.25kg per m2


Qty rqd: 0.25kg x 120 = 30kg

Summary
Plank: 111pieces
2x3 wood: 58+60 = 118pieces
Bamboo: 1load
Nail: 30kg

31
Compiled by: KABEER OLOYEDE MAY 2020.
ONLINE SESSION BY QS CHIMA(QS ICON) : YQSF SOUTH EAST ZONE WHATSAPP PLATFORM

Basic price
Plank: 1200
2 x 3 hardwood: 450
Nail (25kg bag) = 6500 = 260/kg
Load of bamboo = 50,000 (200pieces)

*Material cost*
Plank: 111no @ 1200 = 133,200
2x3 hd'wd: 118no @ 450 = 53,100
Nail: 30kg @ 260 = 7800
Bamboo: 1load @ 50,000 = 50,000
Total = 244,100.00
Add 10% waste = 24,410.00
= 268,510.00
Assume 2 usage
Cost of mat. per use = 268,510.00 / 2
= #134,255.00

*Labour*
Output per Carpenter
Fabrication, Installation & dismantling = 7m2 per day
Man day rqd: 120 / 7 = 17days
Carpenter: 17days @ 3500 = 59,500.00

*Summary*
Material = 134,255.00
Labour = 59,500.00

32
Compiled by: KABEER OLOYEDE MAY 2020.
ONLINE SESSION BY QS CHIMA(QS ICON) : YQSF SOUTH EAST ZONE WHATSAPP PLATFORM

total = 193,755.00
Cost/m2 = 193,755.00 / 120
= 1614.63
Add 5% WHT = 80.73
subtotal = 2695.36
Add 20% p & o = 339.07
Cost/m2 = 2034.43
Approximately *#2000/m2*

+234 703 059 0892: *Formwork (marine board in suspended slab) (m2)*

Materials needed
Sheathing: marine board
Stringer: 2"x3" (50x75mm) wood @ 600mm c/c
Joist: 2"x3" (50x75mm) wood @ 600mm c/c
Shoring: Bamboo
Total floor area: 10x12 = 120m2
Standard length of wood= 3.60m
Stand size of marine board = 1.20 x 2.40
Covering area of a plank = 1.2 x 2.4 = 2.88m2

No of board rqd: 120 / 2.88


=42pieces

Longer length (stringer) = 12m


No of line = (10 / 0.6) + 1 = 18lines
Total length of stringer= 12 x 18 = 216m

33
Compiled by: KABEER OLOYEDE MAY 2020.
ONLINE SESSION BY QS CHIMA(QS ICON) : YQSF SOUTH EAST ZONE WHATSAPP PLATFORM

No of 2x3 wood = 216/3.6 = 60no

Shorter length (joist) = 10m


No of line = (12 / 0.6) + 1 = 21lines

Total length of Joist = 10 x 21 = 210m


No of 2x3 wood = 210/3.6 = 58no

Shoring (Bamboo)
Average len. of bamboo = 6m
No in a load = 200pieces
No of point for shoring: 18 x 21 = 378points
Assume 3.0m headroom height
Total len. of shoring: 378 x 3 = 1137
No bamboo rqd: 1137 / 6
= 189 no
Approximately 1load

Nail: 0.25kg per m2


Qty rqd: 0.25kg x 120 = 30kg

Summary
Marine board: 42pieces
2x3 wood: 58+60 = 118pieces
Bamboo: 1load
Nail: 30kg

Basic price

34
Compiled by: KABEER OLOYEDE MAY 2020.
ONLINE SESSION BY QS CHIMA(QS ICON) : YQSF SOUTH EAST ZONE WHATSAPP PLATFORM

Marine board: 8500


2 x 3 hardwood: 450
Nail (25kg bag) = 6500 = 260/kg
Load of bamboo = 50,000 (200pieces)

*Material cost*
Marine board: 42no @ 8500 = 357,000
2x3 hd'wd: 118no @ 450 = 53,100
Nail: 30kg @ 260 = 7800
Bamboo: 1load @ 50,000 = 50,000

Total = 467,900
Add 10% waste = 46,790
= 514,690.00
Assume 2 usage
Cost of mat. per use = 514,6890 / 2
= 257,345

*Labour*
Output per Carpenter
Fabrication, Installation & dismantling = 8m2 per day
Man day rqd: 120 / 8 = 15days
Carpenter: 15days @ 3500 = 52,500.00

*Summary*
Material = 257,345.00
Labour = 52,500.00
total = 309,845.00

35
Compiled by: KABEER OLOYEDE MAY 2020.
ONLINE SESSION BY QS CHIMA(QS ICON) : YQSF SOUTH EAST ZONE WHATSAPP PLATFORM

Cost/m2 = 309,845.00 / 120


= 2582.04
Add 5% WHT = 129.10
subtotal = 2711.14
Add 20% p & o = 542.23
Cost/m2 = 3253.37
Approximately *#3250/m2*

(17)

+234 703 059 0892: *Rendering (m2)*


Thickness of mortar = 15mm
Mix: 1:6
Vol. of mortar/m2 = Area x thickness of mortar
= 1m2 x 0.015m = 0.015m2

*mortar* (1:6)
sum mix ratio = 1+6=7

Cement= 0.015x1.4x28.8/(7)
=0.086bag

Sand= 0.015x1.4x6 /(7x3.81)


= 0.0047loads of 5tons
= 0.0047 x 5= 0.02ton

*Material cost*
Cement: 0.086bag @ 2500 = 225
Sand: 0.02ton @ 1800 = 36
Total = 261

*Labour*
Gang size = 1 bricklayer & 1 Labour
Output/gang/day = 9m2 for wall and 6m2 for beam and column

36
Compiled by: KABEER OLOYEDE MAY 2020.
ONLINE SESSION BY QS CHIMA(QS ICON) : YQSF SOUTH EAST ZONE WHATSAPP PLATFORM

For wall
Bricklayer: 1man @ 3500 = 3500
Labour: 1man @ 2000 = 2000
= 5500

Cost/m2 for wall = 5500 / 9


= 611.11

*Summary*
Material = 261.00
Labour = 611.11
total = 872.10
Add 5% WHT = 43.61
subtotal = 915.71
Add 20% p & o = 183.14
Cost/m2 = 1098.86
Approximately *#1100/m2*

(18)

+234 703 059 0892: *Bed & backing for floor tiles (m2)*
Thickness of bed = 40mm
Mix: 1:6
Vol of mortar = 1m2 x 0.04m = 0.04m2

*mortar* (1:6)
sum mix ratio = 1+6=7

Cement= 0.04x1.4x28.8/(7)
=0.23bag

Sand= 0.04x1.4x6 /(7x3.81)


= 0.013loads of 5tons
= 0.013 x 5= 0.065ton

*Material cost*
Cement: 0.23bag @ 2500 = 575
Sand: 0.065ton @ 1800 = 117

Total = 692

*Labour*

37
Compiled by: KABEER OLOYEDE MAY 2020.
ONLINE SESSION BY QS CHIMA(QS ICON) : YQSF SOUTH EAST ZONE WHATSAPP PLATFORM

Gang size = 1 bricklayer & 1 Labour


Output/gang/day = 20m2

Bricklayer: 1man @ 3500 = 3500


Labour: 1man @ 2000 = 2000
= 5500

Cost/m2 for wall = 5500 / 20


= 275.00

*Summary*
Material = 692.00
Labour = 275.00

total = 967.00
Add 5% WHT = 48.35
subtotal = 1015.35
Add 20% p & o = 203.07

Cost/m2 = 1218.42
Approximately *#1200/m2*

+234 703 545 1166: Pls sir how do u get 1.4 in d calculation of cement
+234 703 059 0892: 40% of 1m3 is same as 1.40
+234 703 059 0892: If I'm to add 40% to 10m2. To save time,
It is 10m2 x 1.40

Pls don't use it, understand examination condition


+234 810 460 1755: To convert dry concrete to wet concrete, shrinkage and waste is added

(19)

+234 703 059 0892: Pls *note* tiles varies in price depend on the size and quality
+234 703 059 0892: *Floor tiles (m2)*

Covering area of white cement = 100m2/bag


Qty rqd/m2: 1 / 100 = 0.01bag

Cement slurry: A bag of cement to cover 10m2


Qty of cement rqd/m2 : 1 / 10 = 0.1bags

*Basic price of material & Labour*

38
Compiled by: KABEER OLOYEDE MAY 2020.
ONLINE SESSION BY QS CHIMA(QS ICON) : YQSF SOUTH EAST ZONE WHATSAPP PLATFORM

Vitrified floor tiles = 2250/m2


White cement (25kg) = 3000
Tiler = 300/m2

*Materials cost*
Tiles : 1m2 @ 2250 = 2250.00
White cement: = 0.01bags @ 3000 = 30.00
Cement slurry: 0.1bag @ 2500 = 250.00
Sub total = 2540.00
Add 10% waste & off cut = 254.00
= 2794.00

*Summary*
Materials cost = 2794.00
Labour = 300.00
total = 3094.00
Add 5% WHT = 154.70
subtotal = 3248.70
Add 20% p & o = 649.74
Cost/m2 = 3898.44
Approximately *#3900/m2*

Kabeer Oloyede: But I think the coverage of tiles as per the bundle depends on the size.
Some are more than 1m2 in a carton
Like 400 × 400 mm. It is about 1.92m2 in a carton.

+234 703 059 0892: Convert the price per carton to m2.
Divide the price per carton by covering area

(20)

+234 703 059 0892: *Hardwood timber roof trusses (m)*

Using 2"x6" (50x150mm) timber

Standard len. of timber = 3.60m


Soligium = 30m2/tin
Nail: 0.045kg/m

Soligium: Qty rqd/m


Surface area/m = 2 x (0.05+0.15)m x 1m

39
Compiled by: KABEER OLOYEDE MAY 2020.
ONLINE SESSION BY QS CHIMA(QS ICON) : YQSF SOUTH EAST ZONE WHATSAPP PLATFORM

= 0.40m2

*Basic price*
2" x6" hardwood = 850
Cost/m = 850 / 3.60 = 236.11

Nail(25kg): 6500 = 260/kg

Soligium = 3000/tin
Cost/m2 = 3000/300
= 100

*Material cost*
Hardwood 2"x6": 1m @ @ 236.11 = 236.11
Nail: 0.045kg @ 260= 11.90
Soligium: 0.4m2 @ 100 = 40

subtotal = 288.01
Add 10% waste = 28.80
Total = 316.81

*Labour* (Cutting & Erecting)

Gang size = 2 carpenter + 1 labour


Output = 35length of wood per day
= 35 x 3.6 = 126m/day

Cost per day


Carpenter: 2men @ 3500 = 7000
Labour: 1man @ 2000 = 2000
Total = 9000
Cost/m = 9000/126
= 71.43

*Summary*
Material = 316.81
Labour = 71.44
total = 388.25
Add 5% WHT = 19.41
subtotal = 407.66
Add 20% p & o = 81.53

Cost/m = 489.19
Approximately *#490/m*

40
Compiled by: KABEER OLOYEDE MAY 2020.
ONLINE SESSION BY QS CHIMA(QS ICON) : YQSF SOUTH EAST ZONE WHATSAPP PLATFORM

(21)
+234 703 059 0892: *Asbestos Ceiling (m2)*
Stand size = 1.2 x 1.2m
Covering area per sheet = 1.2 x 1.2
= 1.44m2

Nail 7no per square meter. A pack contains 100pieces

*Basic price of material & Labour*


Asbestos ceilings = 1450
Cost/m2 = 1250 / 1.44
= 868.06

Tie rod = 6000 (50pieces in bundle)


Price per piece = 6000 / 50
= 120
No rqd/m2 = 1no

Nail = 1200/pack
Cost per nail = 1200 / 100
= 12

*Materials cost*
Asbestos ceilings: 1m2 @ 868.06 = 868.06
Nail: 7o @ 12 = 84
Tie rods: 1no @ 120 = 120
Sub-total = 1072.06
Add 15% waste & off cut = 160.81
= 1232.87

*Labour*
2 carpenters + 1 labour
Output per = 60m2

Cost per m2 = (2x3500) +2000) / 60


150.00

*Summary*
Materials cost = 1232.87
Labour = 150.00
total = 1382.87
Add 5% WHT = 69.14
subtotal = 1452.01
Add 20% p & o = 290.40

41
Compiled by: KABEER OLOYEDE MAY 2020.
ONLINE SESSION BY QS CHIMA(QS ICON) : YQSF SOUTH EAST ZONE WHATSAPP PLATFORM

Cost/m2 = 1742.41
Approximately *#1750/m2*

(22)

+234 703 059 0892: *Suspended Ceiling (m2)*


Covering per pack = 0.6 x 0.6 x 8
=2.88m2
A pack is 600*600mm in 8places.

Nail 7no per square meter. A pack contains 100pieces

*Basic price of materials*


Suspended ceiling = 3000
Cost/m2 = 3000 / 2.88
= 1111.11

Aluminum T shape steel grid & wire suspender = 800/m2

Nail = 1200/pack
Cost per nail = 1200 / 100
= 12

*Materials cost*
Suspended ceilings: 1m2 @ 1111.11 = 1111.11
Nail: 7o @ 12 = 84
Aluminum suspender: 1m2 @ 800 = 800
Sub total = 1995.11
Add 10% waste & off cut = 199.61
= 2195.72

*Labour*
Installation = 300/m2

*Summary*
Materials cost = 2195.72
Labour = 300

total = 2495.72
Add 5% WHT = 124.79
subtotal = 2620.51
Add 20% p & o = 524.10
Cost/m2 = 3144.61
Approximately *#3150/m2*

42
Compiled by: KABEER OLOYEDE MAY 2020.
ONLINE SESSION BY QS CHIMA(QS ICON) : YQSF SOUTH EAST ZONE WHATSAPP PLATFORM

+234 813 309 2457: Sir please WHT 5% and 20% profit and overhead is the same with normal 25%
profit ad overhead
+234 703 059 0892: No
+234 813 309 2457: Please what is the difference sir
+234 703 059 0892: E.g.
100.00
Add 25% = 25
Total = 125

Also,
100
Add wht 5% = 5
105
Add 20% = 21
Total = 126

(23)

+234 703 059 0892: *PVC CEILING (m2)*


No per bundle= 15
Size = 6m x 0.2m
Covering area per bundle = 6 x 0.2 x 15
= 18m2

Nail 10no per square meter. A pack contains 100pieces

*Basic price of material & Labour*


PVC ceilings = 16,000/bundle
Price per m2 = 16,000 / 18
= 888.89

PVC ceilings clip = 200/m2 (assumed)

Nail = 1200/pack
Cost per nail = 1200 / 100
= 12

*Materials cost*
PVC ceilings: 1m2 @ 888.89 = 888.89
Nail: 10no @ 12 = 120
PVC ceiling clips @ 200 = 200
Sub total = 1208.89
Add 15% waste & off cut = 181.33

43
Compiled by: KABEER OLOYEDE MAY 2020.
ONLINE SESSION BY QS CHIMA(QS ICON) : YQSF SOUTH EAST ZONE WHATSAPP PLATFORM

= 1390.22

*Labour*
2 carpenters + 1 labour
Output per = 60m2

Cost per m2 = ((2x3500) +2000) / 60


150.00

*Summary*
Materials cost = 1390.22
Labour = 150.00

total = 1540.22
Add 5% WHT = 77.01
subtotal = 1617.23
Add 20% p & o = 323.45
Cost/m2 = 1940.68
Approximately *#1950/m2*

(24)

+234 703 059 0892: *Gloss Painting (m2)*

Using High Quality paint such as Dulux or other equal

Tin(Gallon) = 4litres
Covering area per litre = 15m2
No of coat = 2coats
Qty of paint rqd/m2 = 1m2 x 2coats x 1.2 /(15m2/Lt
= 0.16lt

*Basic price*
Dulux Emulsion paint: 10,000/tin
Cost per litre = 10,000/4
= 2500

*Material cost*
Paint: 0.16 @ 2500 = 400
Add 15% for tools & others: 60

Total = 460.00

44
Compiled by: KABEER OLOYEDE MAY 2020.
ONLINE SESSION BY QS CHIMA(QS ICON) : YQSF SOUTH EAST ZONE WHATSAPP PLATFORM

*Labour* (Surface preparation & painting)


Output of Painter/day = 25/m2

Cost/m2 = 3500/25
=140

*Summary*
Material = 460
Labour = 140

total = 600.00
Add 5% WHT = 30.00
subtotal = 630.00
Add 20% p & o = 126.00
Cost/m = 756
Approximately *#760/m2*

(25)
+234 703 059 0892: *Emulsion Painting (m2)*

Using High Quality paint such as Dulux or other equal

Drum = 20litres
Covering area per litre = 15m2
No of coat = 2coats
Qty of paint rqd/m2 = 1m2 x 2coats x 1.2 /(15m2/Lt
= 0.16lt

*Basic price*
Dulux Emulsion paint: 34,000/drum
Cost per litre = 34,000/20
= 1700

*Material cost*
Paint: 0.16 @ 1700 = 272.00
Add 15% for tools & others: 40.50
Total = 312.80

*Labour* (Surface preparation & painting)


Output of Painter/day = 30m2

Cost/m2 = 3500/30
166.67

*Summary*

45
Compiled by: KABEER OLOYEDE MAY 2020.
ONLINE SESSION BY QS CHIMA(QS ICON) : YQSF SOUTH EAST ZONE WHATSAPP PLATFORM

Material = 312.80
Labour = 116.67

total = 429.47
Add 5% WHT = 21.47
subtotal = 450.94
Add 20% p & o = 90.29

Cost/m = 541.13

Approximately *#545/m2*

(26)

+234 703 059 0892: *Hardwood Panel door timber (no)*

Supply and fix 900x2100mm high Solid Core Panel door with 1"x10" (25x250mm) hardwood frame,
locks and ironmongery.

Standard length of timber = 3.60m

*Basic price*
0.90 x 2.10 panel door = 15,000
1" x10" hardwood (mansonia) = 2500
Length rqd/ door (0.9*2.1) = 2 length
Lock = 4000
hinges = 450
Nail = 50 (assumed)

*Material cost*
Panel door: 1no @ 15,000 = 15,000
Frame: 2 length @ 2500 = 5,000
Lock: 1no @ 4000 = 4000
Hangers: 1 set @ 450 = 450
Nail: Assumed = 50

subtotal = 24,500.00
Add 5% Tp = 1225.00
Total = 25,725.00

*Labour* (Fabrication of frame & installation)

Cost/door = 3000

46
Compiled by: KABEER OLOYEDE MAY 2020.
ONLINE SESSION BY QS CHIMA(QS ICON) : YQSF SOUTH EAST ZONE WHATSAPP PLATFORM

*Summary*
Material = 25,725.00
Labour = 3000.00
total = 28,725.00
Add WHT 5% = 1436.25
= 30,161.25
Add 20% P&O = 6,032.25
Cost/door = 36,193.50
Approximately *#36,000*

(27)

+234 703 059 0892: *Virony steel door (no)*

Supply and fix 900x2100mm high virony Steel door.

*Basic price*
0.90 x 2.10 virony steel door = 35,000

*Material cost*
Virony steel door = 35,000.00
Add Tp = 1500.00

Total = 36,500.00

*Labour* (Installation)
Cost/door = 4000

*Summary*
Material = 36,500.00
Labour = 4000.00

total = 40,500.00
Add WHT 5% = 2025.00
= 42,525.00
Add 20% P&O = 8505.00
Cost/door = 51,030.00

Approximately *#51,000.00*

47
Compiled by: KABEER OLOYEDE MAY 2020.
ONLINE SESSION BY QS CHIMA(QS ICON) : YQSF SOUTH EAST ZONE WHATSAPP PLATFORM

(28)
+234 703 059 0892: *Aluminum window (no)*

Supply and fix 1200x1200mm high sliding window in Tower Aluminum standard profile with 5mm
tinted glass and flyscreen.

*_Note_*: Tower Aluminum profile could be Tower standard or Tower Economy. Nigerlex is also
very nice profile. Also, cheaper Aluminum profile also available.

*Basic price*
1.20 x 1.20mm Tower standard Aluminum profile Sliding window = 25,000.00

*Material cost*
1.20 x 1.20 sliding window = 25,000.00

*Labour* (Installation)
Cost/window = 3500

*Summary*
Material = 25,000.00
Labour = 3500.00

total = 28,500.00
Add WHT 5% = 1425.00
= 29,925.00
Add 20% P&O = 5,985.00
Cost/window = 35,910.00

Approximately *#36,000.00*

(29)

+234 703 059 0892: *Water closet (no)*

Supply and fix water closet with all accessories.

*Basic price*
WC = 42,000

*Material cost*
WC = 42,000.00
Add Tp = 1500.00

48
Compiled by: KABEER OLOYEDE MAY 2020.
ONLINE SESSION BY QS CHIMA(QS ICON) : YQSF SOUTH EAST ZONE WHATSAPP PLATFORM

Total = 43,500.00

*Labour* (Installation)
Cost/wc= 5000

*Summary*
Material = 43,500.00
Labour = 5000.00
total = 48,500.00
Add WHT 5% = 2425.00
= 50,925.00
Add 20% P&O = 10,185.00
Cost/wc = 61,100.00
Approximately *#61,000.00*

(30)

+234 703 059 0892: *25mm c/w supply ppr pipes (m)*

*Basic price*
25mm c/w pipe = 1250
Standard length= 18ft = 5.4m
Cost/m = 1250/5.4
= 231.48

*Material cost*
25mm diam. pipe = 231.48
Add 15% waste & Accessories = 34.72

Subtotal = 266.20
Add 20% for labour = 53.24

total = 319.44
Add WHT 5% = 15.97
= 335.41
Add 20% P&O = 67.08
Cost/m= 402.49
Approximately *#400.00*

49
Compiled by: KABEER OLOYEDE MAY 2020.
ONLINE SESSION BY QS CHIMA(QS ICON) : YQSF SOUTH EAST ZONE WHATSAPP PLATFORM

(31)
+234 703 059 0892: *2.5mm2 electrical cable (m)*

*Basic price*
2.5mm2 electrical cable = 8,000/roll
Standard length per roll = 100m
*Note* in most cases it usually btw 75-95m per (naija factor)
Cost/m = 8000/75
= 106.67

*Material cost*
2.5mm2 electrical wire = 106.67
Addd 20% waste & Accessories = 21.33

Subtotal = 128.00
Add 20% for labour = 25.60

total = 153.60
Add WHT 5% = 7.68
= 161.28
Add 20% P&O = 32.26
Cost/m= 193.54
Approximately *#195/m*

(32)

+234 703 059 0892: *25mm diameter conduit electrical pipes (m)*

*Basic price*
20mm dia conduit pipe = 3000/bundle
Standard length = 2.6m
No in bundle = 20no
Total length in bundle = 20 x 2.6 = 52m

Cost/m = 3000/52
= 57.69

*Material cost*
20mm dia conduit pipe/m = 57.69
Add 20% waste & Accessories = 11.54

50
Compiled by: KABEER OLOYEDE MAY 2020.
ONLINE SESSION BY QS CHIMA(QS ICON) : YQSF SOUTH EAST ZONE WHATSAPP PLATFORM

Subtotal = 69.23
Add 20% for labour = 13.84

total = 83.08
Add WHT 5% = 4.15
= 87.23
Add 20% P&O = 17.45
Cost/m= 104.68
Approximately *#105/m*

[ Kabeer Oloyede: When calculating the qty of paint required/m2


1m2 x 2 coats x 1.2
What is the 1.2?

+234 703 632 7693: 100/100 + 20/100 = 1 + 0.20 = 1.2. That means 20%increment and should be
allowance for waste and the likes
[5/29, 6:29 AM] +234 703 632 7693: Where 100% is the base qty. Like above it is 2m2 (I.e 1m2 x
2coats)

51
Compiled by: KABEER OLOYEDE MAY 2020.

You might also like