ITP Pressure Vessel

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

Project : Re-Certification of Pressure Vessel

Location : Dayung Station – Sumatera Selatan


Owner : Medco E&P Grissik Ltd.
User : Medco E&P Grissik Ltd.
PI : PT PJ-Tek Mandiri

Code Glossary :
AR : Approval Required M : Monitoring
AI : Actual Inspection R : Review of Document
WI : Witness Inspection V : Verification
Inspection Level
Inspection & Test Inspection
No. VERIFIED DOCUMENT ACCEPTANCE CRITERIA Owner MIGAS
Description Company
Code Code
Code
2.0 Document Review All Document shall be comply Permen ESDM No.32 Tahun 2021
1.1 Manual Book
- Manual Book - Manufacturer Specification P R
Accumulator Unit
1.2 Design Calculation / - Permen ESDM No. 32
Report Reverse - Reverse Engineering Report Tahun 2021 / ASME VIII P R
Engineering Div 1
1.3 Previous Pressure
- Report Pressure Test - API 510 Section 7.7 P R
Test
1.4 - Maintenance Report &
Inspection History - API 510 Section 5.3.5 P R
Record
1.5 As Built Drawing - As Built Drawing - Manufacturer Specification P R
1.6 Report Thickness - Thicness Report - NDE Procedure P V
1.7 NDT MPI Report - MPI Report - NDE Procedure P R
1.8 NDT Personel &
- Personnel Certificate - API 510 Section 4.5.2 R P
Equipment Certificate
- Report of Document
2.0 Document Evaluation - Report of Document Review H H
Review
3.0 External Inspection
3.1 Visual
- Foundation and - API 572 Sec 9.3
Support, Anchor - Visual Inspection Report - API 572 Section 9.3 P V
Quality Manual
- Level Glass,Press. - API 572 Sec 9.3
and Temp. Gauges - Visual Inspection Report - API 572 Section 9.3 P V
Quality Manual
- Shell, Head,
- API 510 Section 5.5.4,
Nozzles, Flanges - Visual Inspection Report P V
Section 5.5.6
Connecting
- Grounding
- Visual Inspection Report - API RP 572 Section 9.3.10 P V
connections
3.2 Coating & Painting - Site documentation report - API 510 Sec 5.5.6 P V
5.0 Foto/Rubbing Name - As built drawing P&ID Site
- API 510 Section 6.2.1.1.a P V
Plate Dokumentation report
- Inspection Report
6.0 Final Evaluation - Inspection Report Document H H
Document
7.0 Reporting
- Permen ESDM No. 32
7.1 Final Inspection Report - Inspection Report AR P
Tahun 2021
- Permen ESDM No. 32
7.2 Certificate of Inspection - Inspection Report ‐ P
Tahun 2021