RESPONSIBLE MATRIX

Item Type Description AMQ ELEEN


1 Engineering Specifications and layout drawings(s) X
Manufacturing documentation: Workshop drawings / Detail and junction (connection)
2 Engineering X
drawings / List of materials (including bolts, nuts, washers,…)
3 Engineering Stock List: Supply list starting from BIM Model. X
4 Engineering BIM Model X
5 Engineering Method Statement, Risk Assessment and Shop Drawing(s) X
6 Engineering Red-marks & As-built Drawings X
1 Documents and Permits Preparation and submission of Method Statement(s) / procedures(s) & Risk Assesment X
2 Documents and Permits Construction Schedule(s) (daily, weekly, monthly, overall) X
3 Documents and Permits Adherence of HSE Management Plan & SubPlans, Procedures and Reports X
4 Documents and Permits SubContractor HSE Requirements documents X
5 Documents and Permits Site Emergency Response Plan X
6 Documents and Permits Manpower and Equipment Mobilisation Plan X
7 Documents and Permits Work permits & NOC's X
8 Documents and Permits Permits, licenses, approvals and passes. (if required) X X
9 Documents and Permits Reports (Daily, Weekly, Monthly and Final) X
10 Documents and Permits Adopt work procedure as per Risk Assessment (RA, MOS) X
11 Documents and Permits As-built Documentation X
12 Documents and Permits Security Pass/Gate Pass for Personnel & Equipment X X
1 Quality QA/QC Plan X
2 Quality ITP (Inspection Test Plan) X
3 Quality Inspection Procedures X
4 Quality Inspection Records - Test Packages X

5 Quality Define and issue a Quality Control Plan, Inspection Program and Daily/Weekly Follow-ups X

Performance of all inspections and tests indicated in this specification and defined in the
Quality Control Program and in the Inspection & Test Plan and applicable codes, standards
6 Quality X
and local regulations. Inspections and Tests will be performed by 3rd party when required in
the ITP.
Issue of documentation related to the compliance with the Quality Control Plan such as
7 Quality Manufacturing dossiers, FAT inspections by 3rd Party, Material Certificates, Inspection X
Reports, Calibration Certificats of Equipments, Performance Tests, etc.
8 Quality Inspection Test Packages and Final Quality Book. X
9 Quality All necessary inspection tools, equipment and material. X
Certificates of Conformity in accordance with international recognized regulations and
10 Quality X
applicable local regulations.
QA/QC team have to be Qualified and approved by EPC. Their attendance full time at site is
11 Quality X
mandatory (QC Manager, QC inspectors and document controller).
1 Supply and Fabrication Supply and Fabrication of Steel Structure (according to approved ITP and legal requirements) X
2 Supply and Fabrication Painting according to technical specification X
3 Supply and Fabrication Supply of the necessary nuts and bolts (bolts, nuts, washers,…) X
4 Supply and Fabrication Supply of the necessary hardwares (bolts, nuts, washers,…) X
Supply and fabrication of steel grating (cutouts and staples are included) including material
5 Supply and Fabrication X
tagging (stencil/stickers/tags)
Supply and fabrication of chequered plate including material tagging (stencil/stickers/tags)
6 Supply and Fabrication X

7 Supply and Fabrication Supply and fabrication of hand rails including material tagging (stencil/stickers/tags) X
8 Supply and Fabrication Supply and fabrication of cat ladders including material tagging (stencil/stickers/tags) X
All components down to small details required to ensure safe and proper operation and
9 Supply and Fabrication X
maintenance of the equipment or required by Codes and Rules applicable.
10 Supply/Fabrication Supply of steel structure leveling grout/concrete X
Supply of the resin/chemical adhesives for the installation of the anchor bolts of the steel
11 Supply/Fabrication X
structure
General: all materials will be approved by AAG. Quality certificate type 3.1 according to EN
12 Supply and Fabrication X
10204 is required
1 Construction Material Construction Materials including wastage disposal in Government Approved Landfill X
2 Construction Material Storage and Testing on Construction Materials X
3 Construction Material Construction Water (if required as per site requirements) X
4 Construction Material Material transportation from AAG warehouse to the site X
1 Construction Equipement Equipment Mobilisation & Demobilisation X
2 Construction Equipement Assembly and Certification by Third Party X
3 Construction Equipement Dismantling, Packaging on Completion X
4 Construction Equipement Survey and Test Equipment (Total Station and etc.) X
5 Construction Equipement Maintenance / Spare Parts / Services X
6 Construction Equipement Diesel and Lubricants X
7 Construction Equipement Supply of electricity and diesel for the works X
8 Construction Equipement Supply of lighting and water for the works X
9 Construction Equipement Supply the materials and Equipment required for the erection activities X
1 Transportation Mobilization of Plan & Equipment to Site X
2 Transportation Mobilisation of Staff to Site X
3 Transportation Daily Transportation Staff X
4 Transportation Demobilisation of Plant & Equipment from Site X
Transport of all material within the scope of the contract (including loading, transport and
5 Transportation X
unloading), including pickup at warehouse
Execution of drilling in the concrete slabs-walls for the installation of the anchor bolts of the
1 Installation X
steel structure (chemical-mechanical)
2 Installation Installation of the anchor bolts of the steel structure (chemical-mechanical) X
3 Installation Steel Structure Erection (according to approved ITP and legal requirements) X
4 Installation Application of steel structure leveling grout/concrete X
5 Installation Application of the resin for the installation of the anchor bolts of the steel structure X
Quality inspections and test reports according to approved ITP (Raw material inspection
6 Installation reports, Visual and Dimensional inspection reports, Destructive and Non Destructives test X
reports, etc.)
Steel Structure: WPQR, WPS, Welder and NDT Qualification are required to be approved by
7 Installation X
3rd part
8 Installation Temporary supports (e.g. wood saddle supports) if needed by erection sequence X
Site adjustment for the positioning of handrails, gratings, checkered plates to avoid clashing
9 Installation with the other existing structures, pipes and other elements (Cutting/ Welding /Drilling / X
Anchoring)
All arrangements required for alignment, including relevant calibrated devices, temporary
10 Installation X
fittings, accessories, etc, are included
1 Construction Provision of Acces Road to Site X
2 Construction Work Area House-Keeping X
3 Construction Site Inspection / Test and Reporting (3rd Party) as required X
4 Construction Removal of all the underground services, facilities and obstacles present X X
5 Construction Survey - Bench Mark near the work site X
6 Construction Survey - Setting out of anchor bolts X
7 Construction Survey - Mounting, tightening and verticality X
8 Construction Final touch up painting including the supply of the material X
9 Construction Supply, installation and removal of any necessary scaffolding X
10 Construction All tools, tackles, special fixures, consumables required for carrying out the works X
11 Construction Supply of equipment, hand tools and power tools X
12 Construction All kind of lifting equipment as per requirement X
Any kind of crane/lifting machinery and equipment’s (such as spreader beams) to place and
13 Construction X
align the structure on its final place
14 Construction Waste water removal X
15 Construction Dumping of unused stock material. Mud included. X
Provision of levelled & well compacted working platform suitable for construction equipment
16 Construction X
manoeuvring
17 Construction General ilumination at working area X
18 Construction Task lighting system and water supply for works X
Provision of levelled & well compacted working platform suitable for construction equipment
1 Earth works X
manoeuvring
1 General Skilled manpower to be mobilized for particular scope of works X
Decent accomodation for Engineering Staff (As per Ministry of Labor & Health
2 General X
Recommendation)
Decent accomodation for Laboures (Employees) (As per Ministry of Labor & Health
3 General X
Recommendation)
4 General Mess Facilities for Laboures (at Site & In Accommodation) X
5 General Sanitation and labour welfare facility on site X
6 General HSE Inductions for workers & other site required trainings X X
7 General Telecomunication X
8 General Office room X
9 General Designated Laydown area for plant, equipment and materials X
10 General Lavatory and Rest Area for Workers at Site (including water for welfare facility) X
1 EHSMS Provision of all requirements of main contractor regarding the HSE activities. X
Jeopardy to life/fatality/endangers conditions/health conditions/loss of limbs due to
2 EHSMS X
unforeseen condition or while performing risky activities
Implementing of HSE subplans & procedures as per the local authority requirements &
3 EHSMS X X
according to Project HSE Management Plan
4 EHSMS Traffic and Security/Patrolling Management (control services) X
Ambulance service & First Aid facilities (AAG is responsible for the service but in no case is it
5 EHSMS free or free and indeterminate use. An usage control will be carried out and it will be X
deducted from the subcontractor monthly certification
Construction Environmental Management Plan & Waste Disposal in Authorized landfill area
6 EHSMS X
through Approved 3rd party supplier
7 EHSMS Daily Work Area House-Keeping maintenance & Weekly mass HK Campaign X
3rd Party Certifications & External training for high potential risk activities (HSE Training
8 EHSMS X
Matrix)