ELEC-001

FACTORY ACCEPTANCE TEST Rev.01

GENERAL DATA
DATE PRODUCTION ORDER WORK ORDER CLIENT NAME

GENERATOR ENGINE
Model Brand
Power Rating KVA Model
Power Rating KW Serial Number
Power Factor Speed (RPM)
Frequency Governor
Phases Sensors Model
Voltage CONTROL PANEL
FLC at PF Brand
ALTERNATOR Model
Brand Serial Number
Model BATTERY CHARGER
Serial Number Brand
Winding Leads Model
Phase Order L1-L2-L3 Serial Number
AVR Type CIRCUIT BREAKER
CT Ratio Brand
BATTERY Model
Brand Rating
Rating Poles
Functional & Protection Tests
Water Level & Leakage Control Panel Wiring Voltage Measurement Overload 110%
Oil Level & Leakage Breaker Adjusted Voltage Within Limit Remote Start Signal
Battery Termination Fuel Leakage Check Over/Under Voltage Cooldown Delay
Belt Tension Exhaust Smoke Leakage Freq. measurement Water Jacket Heater
Radiator Guards Low Oil Pressure Over/Under Freq. Water Level Switch
Alternator Guards High Engine Temp Current Measurement Charging Alternator
AC / DC Connection Fuel Level Functional Overload Alarm Battery voltage meas.
Power Cable Connection Emergency Stop Overcurrent Alarm Battery charger func.
Load Performance Test
Power Duration Freq Volts L1 L2 L3 Temp Oil Battery
Load %
(KW) (min) (Hz) (V) (Amp) (Amp) (Amp) (ºC) (Bar) Voltage
0%
25%
50%
75%
100%
110%
Load test is done with full resistive load (PF=1)

Notes:

We certify that the Generating Set performed normally with no undue signs of stress and the above values were achieved during Load Test.