Serial No:

JOB HAZARD ANALYSIS WORK SHEET Revision No:


PTW No:

Job Description: Erection & Dismantling of Scaffolding

Step Description of Task Potential Hazard Consequence Risk Control and/or Recovery Measures
No. Rating
(PEAR)
1 Preparation of PTW  Missing information  Expose worker to C1  Attended PTW training
 Inadequate hazard unexpected hazards  Toolbox meeting prior to start
identification work.
2 Scaffolding Materials  Biological Hazard  Physical injury  Fully aware on the surrounding
Preparation (Poisonous animal) hazards

3 Transfer of Scaffolding  Pinch point  Hand/Finger Injury  Wear hand gloves
Materials from Store to  Fall, Slip & Trip  Physical injury  Be vigilant at pinch point
GCTF  Equipment damage  Identify obstruction, ensure
safety shoes in good condition

4 Erection & of  Hot Weather  Heat stroke, dehydration  Limit time exposure under
Scaffolding  Fall from height  Physical injury direct sun, adequate water
 Falling Object  Equipment damage intake
 Pinch point  Hand/Finger Injury  Wear full body harness
 Barricade the area to limit the
entry of non-authorized
personnel
 Display warning sign
 Secure tools by lanyard
 Full PPE; Helmet, gloves,
safety glass
 Be vigilant at pinch point