Professional Documents
Culture Documents
Contoh Formulir Pelaporan Penggunaan Dana
Contoh Formulir Pelaporan Penggunaan Dana
Contoh Formulir Pelaporan Penggunaan Dana
Cost summary
Construction Type : New Construction
Site Name : Kuala Buya Bridge
Site Location : Lok Bubon, Samatiga, Meulaboh, NAD
Building Unit Type : Summary
Cost Estimate
II EARTHWORKS
1 Excavation m3 130.00 26,520.0 3,447,600.00
2 Backfill m3 52.00 6,300.0 327,600.00
3 Sub Base Class A (incl. compaction and testing) t=160cm m2 257.40 179,826.5 46,287,341.10
4 Sub Base Class B (incl.compaction and testing) t=90cm m2 257.40 77,889.3 20,048,692.95
5 Protection of Excavation (temporary dam and maintenance) ls 1.00 20,000,000.0 20,000,000.00
6 Asphalt pavement m2 210.00 24,400.1 5,124,020.16
95,235,254.21
III STONE MASONRY
1 Rubber Stone m3 - 278,170.0 -
2 Stone Masonry (1:4) m3 43.20 585,480.0 25,292,736.00
3 Finishing of Concrete ( 1:2 ) m3 6.00 15,100.0 90,600.00
4 Lean Concrete (t = 5 cm) m2 31.72 23,100.0 732,732.00
26,116,068.00
V REINFORCED CONCRETE WORKS
1 Foundation Cap m3 1.39 2,808,000.0 3,905,366.40
2 Abutment m3 19.44 3,728,500.0 72,482,040.00
3 Abutment Cap m3 9.50 4,101,350.0 38,962,825.00
4 Concrete of Beam m3 51.60 4,522,600.0 233,366,160.00
5 Oprit/appron m3 3.00 1,309,200.0 3,927,600.00
348,716,391.40
Vi PILlING WORK
1 Furnishing of Pile 250x250x6000 unit 20.00 1,140,487.5 22,809,750.00
2 Pile Driving unit 20.00 300,000.0 6,000,000.00
3 Cut of Pile unit 20.00 20,000.0 400,000.00
28,809,750.00
VII MISCELANEOUS
1 Bearing Pad unit 12.00 390,000.0 4,680,000.00
2 Expansion Joint (complete with joint filler) m' 7.00 13,167,000.0 92,169,000.00
3 GIP Steell Ø 3 inc. (hand rail) m' 62.00 52,000.0 3,224,000.00
100,073,000.00
TOTAL 640,450,463.61
Unit Price Analysis
3 1 m3 membongkar dinding tembok dengan membikin bersih batu merah (An. L4)
1.000 Tukang batu @Rp. 50,000.00 = 50,000.00
0.190 Pekerja @Rp. 30,000.00 = 5,700.00
Sub Total . . = Rp. 55,700.00
Dibulatkan . . = Rp. 55,700.00
4 Pekerjaan bongkar lantai tegel untuk dipergunakan kembali, 10 m2 dengan membongkar lantai l
dengan membikin bersih batu merah dan tegelnya (An. L5)
1.860 Pekerja @Rp. 30,000.00 = 55,800.00
0.200 Mandor @Rp. 45,500.00 = 9,100.00
Sub Total . . = Rp. 64,900.00
Dibulatkan . . = Rp. 64,900.00
D. Pekerjaan Begesting
0.400 m3 Kayu Begesting @Rp. 1,900,000.00 = 760,000.00
4.000 kg Paku @Rp. 9,300.00 = 37,200.00
1.000 Tukang batu @Rp. 50,000.00 = 50,000.00
3.255 Pekerja @Rp. 30,000.00 = 97,650.00
0.200 Mandor @Rp. 45,500.00 = 9,100.00
Sub Total . . = Rp. 953,950.00
Dibulatkan . . = Rp. 953,900.00
36 1 m2 Pintu kaca dan Jendela kaca tebal 5 cm (An. F.2) kaca tidak dihitung.
0.012 m3 Kayu Kamper @Rp. 3,250,000.00 = 39,000.00
1.200 Tukang Kayu @Rp. 50,000.00 = 60,000.00
0.468 Pekerja @Rp. 30,000.00 = 14,040.00
Sub Total . . = Rp. 113,040.00
Dibulatkan . . = Rp. 113,000.00
38 1 m2 Pintu dan Jendela Panil jati tebal 3.5 cm dan 1.1 cm (An. F.4).
0.035 m3 Kayu Jati @Rp. 3,250,000.00 = 113,750.00
3.200 Tukang Kayu @Rp. 50,000.00 = 160,000.00
0.930 Pekerja @Rp. 30,000.00 = 27,900.00
0.150 Mandor @Rp. 45,500.00 = 6,825.00
Sub Total . . = Rp. 308,475.00
Dibulatkan . . = Rp. 308,400.00
48 1m2 Pekerja rangka atap dari Usuk glugu dan reng kamper (An.F16a).
0.003 m3 Reng kayu kamper @Rp. 3,250,000.00 = 9,750.00
2.200 m' Usuk glugu 5/7 @Rp. 3,250.00 = 7,150.00
0.150 kg Paku usuk @Rp. 9,300.00 = 1,395.00
0.100 kg Paku reng @Rp. 9,300.00 = 930.00
0.100 Tukang kayu @Rp. 50,000.00 = 5,000.00
0.010 Pekerja @Rp. 30,000.00 = 300.00
0.003 Mandor @Rp. 45,500.00 = 136.50
Sub Total . . = Rp. 24,661.50
Dibulatkan . . = Rp. 24,600.00
403,700.00
1 m2 Mengecat 3 x = ------------------------ = Rp. 40,370.00
10.00 Dibulatkan 40,300.00
I BAHAN PASIR
1 M.040 Pasir urug / timbun m3 55,000.00
2 M.042 Sirtu / Aggregat kasar m3 55,000.00
3 - Pasir Lokal m3 55,000.00
4 M.041 Pasir beton / pasang m3 85,000.00
5 - Pasir Cor m3 80,000.00
6 M.042.a Aggregat halus m3 53,300.00
7 M.050 Timbunan pilihan m3 60,000.00
8 M.051 Tanah urug m3 35,000.00
II BAHAN BATU
1 M.010 Batu quary 15/20 m3 175,000.00
2 M.020 Batu belah 6 - 10 cm m3 150,000.00
3 M.021 Batu belah 15 - 20 cm m3 175,000.00
4 M.022 Batu pecah 5 - 7 cm m3 175,000.00
5 M.023 Batu pecah 3 - 5 cm m3 225,000.00
6 - Batu gunung belah 15/20 cm m3 175,000.00
7 M.024 Batu pecah 2 - 3 cm m3 348,000.00
8 M.025 Batu pecah 1 - 2 cm m3 85,000.00
9 M.026 Batu pecah 1/2 - 1 cm m3 -
10 - Batu pecah 0.5 / 0.5 cm m3 110,000.00
VI BAHAN KAPUR
1 M.081 Kapur bubuk m3 658,000.00
2 - Kapur gamping kg -
XI BAHAN KAYU
1 - Kayu jati balok 8/12, 6/12 * 2 m' m3 -
2 - Kayu jati papan 2/20 * 2 m' m3 -
3 - Kayu jati usuk 5/7, 4/6 * 2m' m3 -
4 - Kayu jati reng 2/3, 3/5 * 4,5 m' m3 -
5 - Kayu kamper balok 8/15, 8/12, 6/12 *4 m' m3 3,250,000.00
6 - Kayu kamper papan 2/20,3/20,3/30* 4 m' m3 3,250,000.00
7 - Kayu kamper usuk 5/7, 4/6 * 4m' m3 3,250,000.00
8 - Kayu kamper reng 2/3, 3/5 * 4 m' m3 3,250,000.00
9 - Kayu bengkirai balok 8/15, 8/12, 6/12 *4 m' m3 -
10 - Kayu bengkirai papan 2/20,3/20* 4 m' m3 -
11 - Kayu bengkirai usuk 5/7, 4/6 * 4m' m3 -
12 - Kayu meranti balok 8/15, 8/12, 6/12 *4 m' m3 2,500,000.00
13 - Kayu meranti papan 2/20,3/20* 4 m' m3 2,500,000.00
14 - Kayu meranti usuk 5/7, 4/6 * 4m' m3 2,500,000.00
15 - Kayu kruing balok 8/15, 8/12, 6/12 *4 m' m3 1,500,000.00
16 - Kayu kruing papan 2/20,3/20* 4 m' m3 1,500,000.00
17 - Kayu kruing usuk 5/7, 4/6 * 4m' m3 1,500,000.00
18 M.070 Kayu bakar m3 445,000.00
19 M.180 Kayu untuk perancah/bekesting m3 1,900,000.00
20 Ls.21 Dolken dia 15 cm-4 m m3 2,500,000.00
1 2 3 4 7
XII BAHAN PENUTUP ATAP
1 - Genteng kodok bh 5,000.00
2 - Genteng bubungan lokal m' 34,000.00
3 - Genteng vlam pres lokal keping 6,000.00
4 - Rabung Multiroof m' 48,000.00
XX BAHAN SANITAIR
1 - Closet jongkok traso lokal set 90,000.00
2 - Closet jongkok porselin INA set 155,000.00
3 - Closet duduk porselin komplit merk TOTO set 300,000.00
1 2 3 4 7
XXI BAHAN PAKU
1 M.166 Paku kg 9,300.00
2 - Paku reng kg 10,000.00
3 - Paku usuk/kaso kg 10,000.00
4 - Paku triplek kg 10,000.00
5 - Paku seng kg 28,000.00
6 Paku Asbes kg 15,000.00
7 - Paku sekrup gros 216,000.00
a Pondasi
1 pasir urug
2 pondasi batu kali
3 batu kosong
b Tanah (pondasi)
1 Galian tanah
2 Timbunan kembali
c RC ( K 250 )
#REF!
1 Balok sloff 15/15 (atas)
2 Balok Sloof 20/25 (bawah)
1 #REF!
2 Kolom utama 25/25
RC-25/35 #REF!
1 Ring balk 25/35
a tanah 2 Balok Latai 15/15
h
b Wall (batu bata)
c
20 1 Dinding sudut
10 2 Dinding
1 Plesteran trasraam
2 Plesteran
Balok
3.5
25
20 12 Ǿ 12 -10 12 Ǿ 12 -10
70 70
a b C1 C2 h Volume L / each Qty
Tie Beam
0.000 0.0 0.0 M3
0.20 0.25 0.050 391.0 19.6 M3 21.51 150
Console Beam
0.00 0.00 0.000 0.0 0.0 M3
kg Tulangan utama
Sloof
total 32
A - Ǿ 12 0.000113 m2
Berat jenis 7800 kg/m3
Panjang lilitan 1.5
kg 42.322
Kolom praktis 20/20
total 4 each
A - Ǿ 12 0.000113 m2
Berat jenis 7800 kg/m3
Panjang lilitan 189 m2
666.574
20/20
20 240
50
15
160 90
10
20
35 35
15 15 15
225 30 150
50 50
275 50
Rekap Perubahan Anggran Biaya
II EARTHWORKS
1 Excavation m3 130.00 26,520.0
2 Backfill m3 52.00 6,300.0
3 Sub Base Class A (incl. compaction and testing) t=160cm m2 257.40 179,826.5
4 Sub Base Class B (incl.compaction and testing) t=90cm m2 257.40 77,889.3
5 Protection of Excavation (temporary dam and maintenance) ls 1.00 20,000,000.0
6 Asphalt pavement m2 210.00 24,400.1
V MISCELANEOUS
1 Bearing Pad unit 12.00 390,000.0
2 Expansion Joint (complete with joint filler) m' 7.00 13,167,000.0
3 GIP Steell Ø 3 inc. (hand rail) m' 62.00 52,000.0
TOTAL
Keterangan
CCO AWAL (No 1) adalah CCO (perubahan) yang diakibatkan oleh kondisi lapangan pada saat melakukan site eng
RAB setelah Lelang adalah perubahan Anggaran Biaya yang diakibatkan karena perubahan Harga Satuan Material
CCO (No 2,3,4 dst) adalah CCO (perubahan) yang diakibatkan oleh kondisi lapangan pada saat melakukan pekerja
REALISASI adalah biaya riil terakhir yang dihitung setelah konstruksi tersebut dinyatakan selesai.(Umumnya disebu
Data SIM menggunakan RAB(DTPL) , Lelang , Realisasi.
CCO awal
5,000,000.00 1 1 5000000
- 0 0 92800
- 0 0 18800
24,000,000.00 60 60 400000
12,500,000.00 1 1 12500000
41,500,000.00
- 0 0 278170
25,292,736.00 43.2 400000 17280000 43.2 585480
90,600.00 6 6 15100
732,732.00 31.72 31.72 23100
26,116,068.00
4,680,000.00 12 12 390000
92,169,000.00 7 7 13167000
3,224,000.00 62 62 52000
100,073,000.00
611,640,713.61
an pada saat melakukan site engineering
erubahan Harga Satuan Material dan Barang atau perubahanHarga Satuan Pekerjaan sebagai hasil keputusan pemenang dalam Pelelang
gan pada saat melakukan pekerjaan konstruksi.
atakan selesai.(Umumnya disebut CCO terakhir)
CCO awal CCO berjalan
ungkin berubah tergantung lokasi Berubah sesuai kebutuhan lapangan Sama dengan CCO terakhir
oritis tidak berubah Sama dengan kolom 11 Sama dengan kolom 11
5,000,000.00
0.00
0.00
24,000,000.00
12,500,000.00
41,500,000.00
3,447,600.00
327,600.00
46,287,341.10
20,048,692.95
20,000,000.00
5,124,020.16
95,235,254.21
0.00
25,292,736.00 59 400000 23600000 70 400000
90,600.00
732,732.00
26,116,068.00
3,905,366.40
72,482,040.00
38,962,825.00
233,366,160.00
3,927,600.00
348,716,391.40
4,680,000.00
92,169,000.00
3,224,000.00
100,073,000.00
hasil keputusan pemenang dalam Pelelangan.
ma dengan CCO terakhir
ma dengan kolom 11
REALISASI
Sub Total
Rp.
18
28000000
Rekap Perubahan Anggran Biaya
II EARTHWORKS
1 Excavation m3 130.00 26,520.0
2 Backfill m3 52.00 6,300.0
3 Sub Base Class A (incl. compaction and testing) t=160cm m2 257.40 179,826.5
4 Sub Base Class B (incl.compaction and testing) t=90cm m2 257.40 77,889.3
5 Protection of Excavation (temporary dam and maintenance) ls 1.00 20,000,000.0
6 Asphalt pavement m2 210.00 24,400.1
V MISCELANEOUS
1 Bearing Pad unit 12.00 390,000.0
2 Expansion Joint (complete with joint filler) m' 7.00 13,167,000.0
3 GIP Steell Ø 3 inc. (hand rail) m' 62.00 52,000.0
TOTAL
Keterangan
CCO AWAL (No 1) adalah CCO (perubahan) yang diakibatkan oleh kondisi lapangan pada saat melakukan site eng
RAB setelah Lelang adalah perubahan Anggaran Biaya yang diakibatkan karena perubahan Harga Satuan Material
CCO (No 2,3,4 dst) adalah CCO (perubahan) yang diakibatkan oleh kondisi lapangan pada saat melakukan pekerja
REALISASI adalah biaya riil terakhir yang dihitung setelah konstruksi tersebut dinyatakan selesai.(Umumnya disebu
Data SIM menggunakan RAB(DTPL) , Lelang , Realisasi.
CCO awal
5,000,000.00 1 1 5000000
- 0 0 92800
- 0 0 18800
24,000,000.00 60 60 400000
12,500,000.00 1 1 12500000
41,500,000.00
- 0 0 278170
25,292,736.00 43.2 400000 17280000 43.2 585480
90,600.00 6 6 15100
732,732.00 31.72 31.72 23100
26,116,068.00
4,680,000.00 12 12 390000
92,169,000.00 7 7 13167000
3,224,000.00 62 62 52000
100,073,000.00
611,640,713.61
an pada saat melakukan site engineering
erubahan Harga Satuan Material dan Barang atau perubahanHarga Satuan Pekerjaan sebagai hasil keputusan pemenang dalam Pelelang
gan pada saat melakukan pekerjaan konstruksi.
atakan selesai.(Umumnya disebut CCO terakhir)
CCO awal CCO berjalan
ungkin berubah tergantung lokasi Berubah sesuai kebutuhan lapangan Sama dengan CCO terakhir
oritis tidak berubah Sama dengan kolom 11 Sama dengan kolom 11
5,000,000.00
0.00
0.00
24,000,000.00
12,500,000.00
41,500,000.00
3,447,600.00
327,600.00
46,287,341.10
20,048,692.95
20,000,000.00
5,124,020.16
95,235,254.21
0.00
25,292,736.00 59 400000 23600000 70 400000
90,600.00
732,732.00
26,116,068.00
3,905,366.40
72,482,040.00
38,962,825.00
233,366,160.00
3,927,600.00
348,716,391.40
4,680,000.00
92,169,000.00
3,224,000.00
100,073,000.00
hasil keputusan pemenang dalam Pelelangan.
ma dengan CCO terakhir
ma dengan kolom 11
REALISASI
Sub Total
Rp.
18
28000000